Professional Documents
Culture Documents
technology for
Meri-Pori
To meet increasing electricity demand Finland is building a 560 MWe power
station known as Meri-Pori. Once complete, it will be one of the world's cleanest
and most efficient coal-fired power plants. The project which is being funded by
Imatran Voima Oy (IVO) and Teollisuuden Voima Oy (TVO), is scheduled for
completion in late 1993.
Kevin Dodman
inland needs more generating
capacity, to meet an expected
3 0 0 0 M W g r o w t h in e n e r g y
demand during the period up to the
year 2000. Of this 3000 MW, it is
anticipated that 1500 MW will need
to be base load capacity, while the
rest will only be needed during the
winter months.
T o help m e e t t h i s d e m a n d a
new 5 6 0 MWe c o a l - f i r e d plant
called Meri-Pori is being built, near
the town of Pori, 250 km north-west
of H e l s i n k i in F i n l a n d . T h e n e w
plant will use an advanced design
of s t e a m t u r b i n e t o a c h i e v e an
overall efficiency of 43.5 per cent.
It has been designed for base
load o p e r a t i o n a n d will have an
annual output of 3.6 TWh. A combination of l o w - N O burners a n d a
flue gas cleaning plant will result in
emissions that will be within t h e
recently determined regulatory limits of 7 0 m g / M J f o r N O , 1 4 0
mg/MJ for S 0 and 20 mg/MJ for
particulates.
March 1993
C o m m i s s i o n i n g is s c h e d u l e d for
s u m m e r 1993, w i t h c o m m e r c i a l
operation to follow in November.
Power will be fed into the local 400
kV grid.
Figure 1. T h e
Meri-Pori
power station
will be one of
the world's
c l e a n e s t and
most efficient
coal-fired
power plants
19
Plant c o n s t r u c t i o n
appeenranta
Figure 3.
Meri-Pori
during
construction
Figure 2 . T h e
plant is
situated near
the town of
Pori, 250 km
north-west of
Helsinki
Varch 1993
21
March 1993
ic p r e c i p i t a t o r s for dust
r e m o v a l . T h e s e will be
dual-chamber, four-field
systems and after passing t h r o u g h t h e m , t h e
dust content of t h e flue
gas will be a mximum of
100 m g / n m (wet).
A p r o p o r t i o n of t h e
remaining particulate
m a t t e r will be r e m o v e d
during
the desulphurization
process, after which the particulate
content will be no more than 50
m g / n m (wet), which is equivalent
to 20 mg/MJ.
Overall, 99.5 per cent of the fly
ash in the flue gas stream will be
removed. This will be around 150
000 t/yr and it will be held in two
silos, each with a volume of 3000
m , prior to being recycled either
for use in the construction industry,
or for disposal in a landfill site.
3
Figure 4.
Additional
coal delivery
equipment
h a s been
added to the
existing
facilities that
dellver coal
to the
Tahkoluoto
power plant
Boiler
Figure 5. T h e
desulphurization p r o c e s s
Figure 6. T h e
boiler is fitted
with 30 HTNR
burners, six at
e a c h burner
level
Steam turbine
Selective catalytic
reduction
1000C
800C
Economizer
1200C
Completion of
combustin
Overfire
air
CO+ I2 O2
Secondary
Fuel
and
primary
air
a i r
Fuel
gases
380C
CO2
Tertiary air
NO
Nh
N2 + O2
Fuelj<
nitrogen
\ N
000
000
0000c
000
0000/
Nitrogen
water
2NO
S<N2
Ammonium
feed
Ammonium +
nitrogen
oxides +
catalyst
140-C
Figure 8.
Reduction of
nitrogen
oxides at
Meri-Pori
Machine bases
NH injection
grid
ReheaterSuper
After air
ports
LowNO burners
Fumace
Air
heater
Figure 9. T h e
boiler
supplied by
Tampella
Power is a
Benson oncethrough
design which
will burn
pulverized
coal, with oil
u s e d for
start-up
25
Control system
Coal
transport
system
=Jtomation
Burner and sootblower automation (acting as a subcontractor to
the boiler supplier)
i Auxiliary switchgear automation
It includes two different bus sys"s; the CS275 bus and the sysm coupling bus, both of which
nave r e d u n d a n t s t r u c t u r e s . T h e
s y s t e m c o u p l i n g b u s is u s e d t o
nnect all t h e process stations
t need data exchange, such as
rxotection signis and interlocking
signis.
The C S 2 7 5 bus c o n n e c t s the
AS 220 EA automation systems,
ttie O S 2 5 6 - 6 operating systems,
t r e Simatic S5 programmable logic
: o n t r o l l e r s fitted to t h e auxiliary
ooiler plant and the water treatment
plant, the workstations for system
- a i n t e n a n c e , and the information
system (process computer).
Both main systems (boiler and
ine) and the auxiliary systems
sulphurization, coal transport,
_c) h a v e t h e i r o w n b u s e s a n d
rating systems. The two buses
r
1993
.
Absolute f x point, bearing
I 9 casing/outer casing
V anchored on foundation
Control room
Inner
"casing
^Outer
casing
_ Rotor
train
Figure 11.
Thermal
expansin of
the s t e a m
turbine train
Figure 12.
T h e power
plant control
room
27
Schematic diagram
Schematic diagram
HT-NR BURNER
MERI PORI
FINLANDIA
560 MWe
Coal and
prlmary air
Tertiary
air
A.
B.
C.
D.
Fame
stabilizing ring
Key
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Coal yard
Coal conveyor
Coal silo
Coal feeder
Coal mili
Coal burners
Forced-draught fan
Mill-airfan
Air preheater
Ammonia supply
NOx catalyst
Electrostatic precipitator
Induced-draught fan
Desulphurization absorber
Absorbent circulation
Demisters
Flue gas reheater
Stack
Gypsum dewatering
Effluent
Process Water
Limestone silo
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
Gypsum silo
Ash silo
Main condnsate pump
Low-pressure preheater
Feed-water tank (FW)
Turbine driven FW-pump
High-pressure preheater
Economiser
Evaporator
Superheater
HP turbine
Reheater
IP-turbine
LP-turbine
Condenser
Cooling water pump
Turbogenerator
Main transformen
Control room
Boiler house
Turbine hall
Switch yard