Minutes of meeting of Special Plan ( BRGF) held on 01.07.2014


under the chairmanship of Managing Director , SBPDCL
Managing Director reviewed the progress of Special Plan (BRGF)
scheme and found that none of the firm has executed work on
the basis of approved BAR Chart/PERT Network & they are
lagging behind the target.
1.M/s Feedback Infra Ltd. Gurgoan has been appointed PMU for Special plan (BRGF)
scheme. M/s Feedback Infra Ltd. Gurgoan has deployed one PM, two DPM, three
numbers APM and eight numbers of District coordinator till date. MD, SBPDCL
directed to deploy remaining man power as per LOA up to 31st July 2014. The
remaining man power will be selected through interview panel. ESE, Special
Plan(BRGF),OSD(HR&A) and EEE, Special plan(BRGF) will be the members of the
interview panel for selection of experienced persons of power projects.

2. Tender of AB Cable under BRGF Phase-II(Part-C) has been cancelled due to non participation of bidders. MD,SBPDCL directed that LT cabling work is to be done in
theft prone area & with high AT&C loss& HT AB cable may be provided for safety
purpose. It was decided to complete 100% AB cable in LT line in the selected villages.
At the same time, the theft prone areas may also be identified for installation of AB
cable. Whenever, the work of AB cable is taken up, it should be done in the entire LT
line of the DT. The AEE (Projects) and concerned District coordinator were directed to
conduct survey & submit report by 20.07.2014.

3.A bidder meet for discussion of issue related to R&M of LT OH & HT OH Line by AB
cable will be called up to 12th July 2014.

4.Tender for erection of over head line by AB cable will be floated up to 25.07.2014.
5. Work of each cluster was found lagging behind the target, Hence, the Agencies
were directed to submit revised Bar Chart for the work for completion within
prescribed time frame of the LOA.

6.All projects in charge will participate in the next meeting with following reports.
(i) Survey status
(ii) BOQ status
(iii) Status of vendor approval
(iv) Status of inspection call.
(v) Status of GTP approval.
(vi) Progress report.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
(vii) Status of Payment.

7. In Special plan BRGF scheme, the existing 5 MVA power transformers of


identified PSS are to be augmented by 10 MVA power transformers. Released 5 MVA
power transformers will be utilized for augmentation of 3.15 MVA / 1.6MVA Power
transformers.MD SBPDCL has directed to prepare utilization plan for augmented
power transformers.

8.Every

NIT in charge/ concerned PMU in charge should visit his site at least once
in every 10 days and prepare his check list.

9.EEE of every Division

will issue certificate that the work assigned to one agency


is not covered in other scheme.

10.It

was directed to keep two vehicles in BRGF Dept. for field visits. CE(RE) was
directed to obtain formal approval.

(C. L. Prakash)

Chief Engineer (RE)

Memo No:-Date:-

Copy forwarded to M/s Feedback infra Pvt.Ltd. for information &


necessary action.
(C. L. Prakash)

Chief Engineer (RE)


Memo nos.

Date:-

Copy forwarded to Electrical SuperintendingEngineer, Special Plan


(BRGF)/EEE, Special Plan (BRGF)/AEE, Special Plan (BRGF)/AO, Special
Plan (BRGF),SBPDCL,for information and necessary action.

(C. L. Prakash)

Chief Engineer (RE)


Memo No:-Date:-

Copy forwarded to OSD to MD,SBPDCL, Patna for information.

(C. L. Prakash)
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Chief Engineer (RE)


Letter No
From,
C.L.Parkash
Chief Engineer (RE)
To,
M/s Feedback Infra Private Limited,
Energy Division, 15th Floor, Tower 9B,
DLF Cyber City, Phase-III, Gurgaon, Haryana-122 002.
Phone No: +91-124-4169100, Fax Nos.:+91-124-4169155
Email: inquiries@feedbackinfra.com.

Dated-

Sub:- Regarding interview schedule


Ref:- FIPL/PMU/SBPDCL/0407 Dated- 04.07.2014
Sir,
With reference to above this is to inform that, The replacement of key staff in
PMU assignment of SBPDCL. Interview schedule is given below.
Sl.N
Date
Time
os.
1
17.07.2014
3PM To 5PM
2
18.07.2014
3PM To 5PM
3
19.07.2014
3PM To 5PM
Hence you are requested to arrange manpower, as per Clause 5 of LOA whose

qualification as per RFP & LOA.


Yours Faithfully,
(C.L.Prakash)
Chief Engineer (RE)
Memo nos.

Dated

Copy forwarded to ESE. Special Plan (BRGF), OSD (HR&A) and EEE.Special Plan
(BRGF).

(C.L.Prakash)
Chief Engineer(RE)
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Minutes of meeting of Special Plan ( BRGF) Scheme held on


08.07.2014 under the chairmanship of Managing Director ,
SBPDCL
Managing Directorreviewed the progress of Special Plan (BRGF)
scheme and found that none of the firm has executed work on
the basis of approved BAR Chart/PERT Network & they are
lagging behind the target

1.

Districts: Bhagalpur,Banka&Munger NIT NO: 207 (M/s Bajaj


Electricals Limited: Mumbai )

(i). MD, SBPDCL directed the EEE, ESDMunger that Land identification should be
finalised up to 30thJuly 2014
(ii). MD,SBPDCL directed the EEE, ESD Banka that Land acquisition should
completed up to 30thJuly 2014.
(iii).Survey of 11KV line should be completedupto 16th July 2014 of Munger

District.

(iv). Details of target given to agency is asbelow :(a) R&M of PSS- 5nos. in August, and finalise all the R&M work by
September

the end of

(b) 33 KV line 10 Km in July 2014.


(c) 11 KV line - 25 Km in July 2014.

2.Districts:Bhojpur&Buxar NIT NO: 205(M/s Bajaj Electricals


Limited: Mumbai)
(i). BOQ Should be completed on scheduled date, fixed by Director SBPDCL.
(ii). Details of target given to agency is as below:(a) R&M of PSS- 6nos. in August, 6 nos. in September & 6 nos. in October
2014.
(b) 33 KV line 15 Km in July, 25 Km in August 2014.
(c) 11 KV line - 25 Km in July & 50 Km in August 2014.

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

3.

Districts:Patna& Nalanda NIT NO: 206 (M/s East India


Udyoglimited,Ghaziabad )
(i).Details of target given to agency is as below:(a) R&M of PSS- 5nos. in Patna & 5 nos. in Nalanda up to 31st July 2014.

(b) 33 KV line 10 Km in July 2014.


(c) 11 KV line - 50 Km in August 2014.
(ii). MD directed that M/s East India Udyog limited, Ghaziabad
shouldraiseallinspection calls of materials up to 15th July 2014.

4.Districts:Rohtas&Kaimur

NIT NO: 204 (M/s Vijay Electricals

Limited Hyderabad)
(i). MD SBPDCL directed theEEE,Rohtas that NOC of Agrair PSS Should be taken up to
31stjuly 2014.
(ii). Details of target given to agency is as below:(a) R&M of PSS- 6nos. in August, 10 nos. in September & 10 nos. in October
2014 .
(b) 33 KV line 7 Km in July 2014.
(c) 11 KV line - 30 Km in July 2014
(iii). MD SBPDCL was not satisfied with the progress of M/s Vijay Electricals Limited .

5.Districts: Arwal& Aurangabad NIT NO: 203 (M/s Supreme & co.UtkalGlavanizers JV Kolkata)
(i) . Details of target given to agency isas below:(a) R&M of PSS- 3nos. in August 2014.
(b) 33 KV line 10 Km in July, 50 Km in August 2014.
(c) 11 KV line - 10 Km in July 2014.

6.Districts: Gaya,Nawada&Jahanabad NIT NO: 196 (M/s GKC -APL


joint venture,Hydrabad)
(i) . Details of target given to agency isasbelow:South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
(a) R&M of PSS- 5nos. in July 2014.
(b) 33 KV line 20 Km in August 2014.
(c) 11 KV line - 15 Km in July & 15 Km in August 2014.

7. Districts: Lakhisarai,Jamui&Sheikhpura NIT NO: 208 (M/s


Techno Fab gamon Joint Ventures Limited: New Delhi)
(i) . Details of target given to agency isas below:(a) R&M of PSS- 9nos. in July 2014
(b) 33 KV line 15 Km in August 2014
(c) 11 KV line - 30 Km in August 2014

MD SBPDCL directed all the agencies to submit utilization


certificate against mobilization advance.
(C. L. Prakash)
Chief Engineer (RE)
Memo No:Date:Copy forwarded to M/s Feedback infra Pvt.Ltd,M/s GKC-APL Joint Venture,Survey Nos. 9(P),
CII Green Building Lane,Hitech City, Kondapur, Hyderabad- 500084,M/s. SHIRDI SAI ELECTRICALS
LIMITED, 13/82, INDUSTRIALESTATE,KADAPA- 516004,M/s Vijai Electricals Ltd.6-3-648/1&2, off
RajbhavanRoad,Somajiguda, Hyderabad-500082, Andhra Pradesh,M/s Supreme & Co. Pvt. Ltd.-M/S
Utkal Galvanizers Ltd. Joint Venture,53,Justic Chandra,Madhav Road,Kolkata-20,M/s East
IndaiUdyog Ltd.145,G.T.Road,Sahbabad,Ghaziabad , Pin-201005,Uttar Pradesh,M/s Bajaj electricals
Limited,801,10th Floor Rustomjee Aspire,801,10th Floor RustomjeeAspire,Bhanu Shankar YagnikMarg,
Off eastern express highway,Sion (E),Mumbai-400022,
M/s Technofab-Gammon Joint Venture,507,
Eros Apartments, 56, Nehru Place,New Delhi-110019,M/s. Sri Gopikrishna Infrastructure Pvt.
Ltd.Corporate Office: 30/B (8-3-191/162), Vengalrao Nagar, Hyderabad- 500038,M/s SUPREME
VPIL (JV),Ecospace Business Park, Action Area-II, Building Nos.2A, 5th Floor, Unit Nos.501B, New
Town, Rajarhat, Kolkata-700156,for information & necessary action.

(C. L. Prakash)
Chief Engineer (RE)
Memo nos.
Date:Copy forwarded to Electrical Superintending Engineer, Special Plan
(BRGF)/EEE, Special Plan (BRGF)/AEE, Special Plan (BRGF)/AO, Special Plan (BRGF),
SBPDCL, for information and necessary action.
(C. L. Prakash)
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Chief Engineer (RE)


Memo No:Date:Copy forwarded to OSD to MD, SBPDCL, Patna for information.
(C. L. Prakash)
Chief Engineer (RE)

Chief Engineer (RE)

(C. L. Prakash)

Chief Engineer (RE)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Minutes of meeting of Special Plan ( BRGF) Scheme held on


08.07.2014, with Chief Engineer (RE) , SBPDCL
Chief Engineer (RE)reviewed the progress of Special Plan (BRGF)
scheme and found that none of the firm has executed work on
the basis of approved BAR Chart/PERT Network & they are
lagging behind the target

1.

Districts: Patns&Bhojpur NIT- 03 (Phase-II) M/s SupremeVPIL JV


(i). CE(RE) SBPDCL was not satisfied with the progress of M/s Supreme- VPIL
JV
(ii). Agency start the survey work but does not submit survey report
tohisconcern AE Projects.
(iii).Agencyassure that he will submit all GTP Drawing up to 15th august.
(iv). Agency has not taken mobilization advance .

3.

Districts:Patna& Nalanda NIT NO: 206 (M/s East India


Udyoglimited,Ghaziabad )
(i).Agency installed 10 nos. Power Transformer, 7 nos Power transformer in
patna& 3 nos Power transformer in Nalanda details as below.
S.N
o
1
2
3
4
5
6
7
8

Location
Sabbalpur
Mokama
Hathidah
Fatuha
Masaurhi
Barh
Chandi
Ekangarsarai

Qty

Districts
1
1
1
2
1
1
1
1

Patna
Patna
Patna
Patna
Patna
Patna
Nalanda
Nalanda

Date of
Charging
10.05.2014
25.05.2014
24.05.2014
15.05.2014
14.05.2014
10.05.2014
07.05.2014
30.05.2014

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
9

Rajgir

Nalanda

03.06.2014

(ii) . HFL of Parsa Bazar Substation not fixed


(b) 33 KV line 10 Km in July 2014.
(c) 11 KV line - 50 Km in August 2014.
(ii). MD directed that M/s East India Udyog limited, Ghaziabad should
raiseallinspection calls of materials up to 15th July 2014.
(C. L. Prakash)
Chief Engineer (RE)
Memo No:Date:Copy forwarded to M/s Feedback infra Pvt.Ltd,M/s GKC-APL Joint Venture,Survey Nos. 9(P),

CII Green Building Lane,Hitech City, Kondapur, Hyderabad- 500084,M/s. SHIRDI SAI ELECTRICALS
LIMITED, 13/82, INDUSTRIALESTATE,KADAPA- 516004,M/s Vijai Electricals Ltd.6-3-648/1&2, off
RajbhavanRoad,Somajiguda, Hyderabad-500082, Andhra Pradesh,M/s Supreme & Co. Pvt. Ltd.-M/S
Utkal Galvanizers Ltd. Joint Venture,53,Justic Chandra,Madhav Road,Kolkata-20,M/s East
IndaiUdyog Ltd.145,G.T.Road,Sahbabad,Ghaziabad , Pin-201005,Uttar Pradesh,M/s Bajaj electricals
Limited,801,10th Floor Rustomjee Aspire,801,10th Floor RustomjeeAspire,Bhanu Shankar YagnikMarg,
Off eastern express highway,Sion (E),Mumbai-400022,
M/s Technofab-Gammon Joint Venture,507,
Eros Apartments, 56, Nehru Place,New Delhi-110019,M/s. Sri Gopikrishna Infrastructure Pvt.
Ltd.Corporate Office: 30/B (8-3-191/162), Vengalrao Nagar, Hyderabad- 500038,M/s SUPREME
VPIL (JV),Ecospace Business Park, Action Area-II, Building Nos.2A, 5th Floor, Unit Nos.501B, New
Town, Rajarhat, Kolkata-700156,for information & necessary action.

(C. L. Prakash)
Chief Engineer (RE)
Memo nos.
Date:Copy forwarded to Electrical Superintending Engineer, Special Plan
(BRGF)/EEE, Special Plan (BRGF)/AEE, Special Plan (BRGF)/AO, Special Plan (BRGF),
SBPDCL, for information and necessary action.
(C. L. Prakash)
Chief Engineer (RE)
Memo No:Date:Copy forwarded to OSD to MD, SBPDCL, Patna for information.
(C. L. Prakash)
Chief Engineer (RE)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Letter No
DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
M/s Feedback Infra Private Limited,
Energy Division, 15th Floor, Tower 9B,
DLF Cyber City, Phase-III, Gurgaon, Haryana-122 002.
Phone No: +91-124-4169100, Fax Nos.:+91-124-4169155
Email: inquiries@feedbackinfra.com.
Sub:-For information of selected candidate byinterview penal.
Ref:- FIPL/PMU/SBPDCL/1708 Dated- 04.07.2014
Sir,
With reference to above this is to inform that, Interview penal (Mr. Murtaza Halal,
ESE, Special plan BRGF,Mr. A . K Singh OSD HR&A & Mr. ShashiBhushan, EEE, Special
plan BRGF) conducted interview on 19.07.2014& selected fallowing two candidates.
Sl.N
os.
1
2

Name
Dhanesh Chandra Dubey
ArindamMitra

Desiganation
Deputy Project
Manager
Assistant Project
Manager

This is for your information& needful action.

Yours Faithfully,
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
-Sd/(C.L.Prakash)
Chief Engineer (RE)
Memo nos.

Dated

Copy forwarded to ESE. Special Plan (BRGF), OSD (HR&A) and EEE.Special Plan
(BRGF).

(C.L.Prakash)
Chief Engineer (RE)

Officers tour program for the month of August, under special


plan BRGF
Sl.Nos.

Name of officer's

Designation

Date of visit

District to be reviewed

Mr. Shashibhushan

EEE, BRGF

08.08.2014

Gaya

Mr. Ashishkumarjha

AEE,BRGF

09.08.2014

Nalanda

Mr. Murtazahelal

ESE, BRGF

11.08.2014

Rohtas

Mr. Suresh prasadmondal

AEE,BRGF

12.08.2014

Bhagalpur

Mr. Suresh prasadmondal

AEE,BRGF

13.08.2014

Banka

Mr. Shashibhushan

EEE, BRGF

14.08.2014

Buxar

Mr. Murtazahelal

ESE, BRGF

16.06.2014

Kaimur

Mr. Abhishek raj

AEE,BRGF

19.08.2014

Lakhisarai

Mr. Suresh prasadmondal

AEE,BRGF

20.08.2014

Munger

10

Mr. Ashishkumarjha

AEE,BRGF

21.08.2014

Nawada

11

Miss. Kusumkumari

EEE, BRGF

22.08.2014

Bhojpur

12

Mr. Abhishek raj

AEE,BRGF

25.08.2014

jamui

13

Mr. Abhishek raj

AEE,BRGF

27.08.2014

Sheikpura

14

Mr. Murtazahelal

ESE, BRGF

28.08.2014

Aurangabad, Arwal

15

Mr. Ashishkumarjha

AEE,BRGF

29.08.2014

Patna(Fatuha, Barh)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
16

Mr. Shashibhushan

EEE, BRGF

30.08.2014

Jehanabad

The above officers are directed to visit their respective Districts and review in details
ofSpecial plan (BRGF) Project with site visit. They will visit agencys office, agencys store,
manpower deployed, status of work, sight visit of on going works with JEE & AEE Projects and
bring detail report. All the issues with agency & related to work will also be sorted out.
Details of Civil Contractors deployed , their name & mobile nos. to be taken & reviewed.

(C. L. Prakash)
Chief Engineer (RE)
Memo No:-

Date:-

Copy forwarded to Director projects, ESE. Special Plan (BRGF), OSD (MD) and all
officersof special plan BRGF
(C.L.Prakash)
Chief Engineer (RE)

Minutes of meeting of Special Plan ( BRGF) held on 04.08.2014


under the chairmanship of Managing Director , SBPDCL at 6: 30
pm
1.

To identify 25 nos, of weakest line of each circle that can be conshueled by project.

2.

Capacity Augmentation

3.

Inter Department coordination of O & M and projects by both Directors.

4.

Details of projects to be gr at PSS level and 33 KV level.

5.

Tour program to be made &priority to be given worst performing area, at least one
person from each department should go in field in worst performing area.

6.

Tour plan to be submitted by Wednesday (06/06/2014) 5 : 30 pm.

7.

Last 1-1/2 years minutes of meeting & compliance of previous meeting should be with
in 7 days.

8.

Land Issue daily reporting from 05/08/2014.

9.

Freezing of all reporting format , report should be sent with comments from higher
officers.
Meter readings/ O&M of only LTIS
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Minutes of meeting of Special Plan ( BRGF) held on 06.08.2014


under the chairmanship of Managing Director , SBPDCL
11
am1

M/s Supreme- VIPL Mumbai ( NIT- 02) Patna, Bhojpur

Poor performance letter to agency by MD SBPDCL for non- performance

2.Districts:Rohtas&Kaimur
Limited Hyderabad)

NIT NO: 204 (M/s Vijay Electricals

(i). Daily report format send to all AEE/JEE Projects.


(ii). Details of gang involved in field by the agency district wise
(iii). Inspection of store & site work executed by agency to be done by AEE /
JEE Projects daily.
(iv).To talk to ESE / Supply daily regarding projects.
(v). Scope of work of each project & what work is to be done is to be provided
to all ESE/ Supply. Priority will be defined .
(vi).Weekly meeting to be done by all ESES of RGGVY, BRGF and RAPDRP
Project will AEE & JEE Project along with agency. Proceedings of meeting &its
compliance to MD on each Saturday.
(vii).Date of meeting to be fixed.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
(viii).In charge at HQ will attend that meeting.
(ix). Standard format of meeting with target & achievement.

3. Districts: Arwal& Aurangabad NIT NO: 203 (M/s Supreme &


co.-UtkalGlavanizers JV Kolkata)
(i). Inspection call of to be done by agency with C&R Panel & CT PT .

4.Districts: Gaya,Nawada&Jahanabad NIT NO: 196 (M/s GKC -APL


joint venture,Hydrabad)
Civil contractor of R & M work to be providedDistrictwise by the agency. Write a letter to
agency.

5. Feedback PMU
Meeting with M/s Feedback infra PMU regarding its work & manpower deploymentwho
should be effective.

(C. L. Prakash)
Chief Engineer (RE)
Memo No:-

Date:-

Copy forwarded to M/s Feedback infra Pvt. Ltd, M/s GKC-APL Joint Venture,Survey Nos.
9(P), CII Green Building Lane, Hitech City, Kondapur, Hyderabad- 500084,M/s Vijai
Electricals Ltd. 6-3-648/1&2, off Rajbhavan Road, Somajiguda, Hyderabad-500082, Andhra
Pradesh, M/s Supreme & Co. Pvt. Ltd.-M/S Utkal Galvanizers Ltd. Joint
Venture,53,Justic Chandra,Madhav Road,Kolkata-20,, M/s SUPREME VPIL
(JV),Ecospace Business Park, Action Area-II, Building Nos.2A, 5th Floor, Unit Nos.501B, New
Town, Rajarhat, Kolkata-700156,for information & necessary action.

(C. L. Prakash)
Chief Engineer (RE)
Memo nos.
Date:Copy forwarded to Electrical Superintending Engineer, Special Plan
(BRGF)/EEE, Special Plan (BRGF)/AEE, Special Plan (BRGF)/AO, Special Plan (BRGF),
SBPDCL, for information and necessary action.
(C. L. Prakash)
Chief Engineer (RE)
Memo No:Date:Copy forwarded to OSD to MD, SBPDCL, Patna for information.
(C. L. Prakash)
Chief Engineer (RE)
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Letter No
DatedSouth Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
From,
C.L.Parkash
Chief Engineer (RE)
To,
M/s GKC-APL Joint Venture, Survey Nos.9(P), CII Green Building Lane, Hitech City,
Kondapur, Hyderabad- 500084
_____________________________________________________________
M/s Supreme & Co. Pvt. Ltd.-M/S Utkal Galvanizers Ltd. Joint Venture,
53,JusticChandra,Madhav Road,
Kolkata-20
_____________________________________________________________
M/s Vijai Electricals Ltd. 6-3-648/1&2, off Rajbhavan Road, Somajiguda,
Hyderabad-500082, Andhra Pradesh.
_____________________________________________________________
M/s Bajaj electricals Limited, 801,10th Floor Rustomjee Aspire, 801,10th Floor Rustomjee Aspire,
Bhanu Shankar YagnikMarg, Off eastern express highway,Sion (E), Mumbai-400022
______________________________________________________________
M/s East IndaiUdyog Ltd. 145,G.T.Road,Sahbabad,Ghaziabad ,
Pin-201005,Uttar Pradesh
______________________________________________________________
M/s Technofab-Gammon Joint Venture, 507, Eros Apartments, 56, Nehru Place,
New Delhi-110019
________________________________________________________________
M/s. SHIRDI SAI ELECTRICALS LIMITED,13/82, INDUSTRIALESTATE ,
KADAPA- 516004
________________________________________________________________
M/s. Sri Gopikrishna Infrastructure Pvt. Ltd. Corporate Office: 30/B (8-3-191/162), Vengalrao Nagar,
Hyderabad- 500038
________________________________________________________________
M/s SUPREME VPIL (JV), Ecospace Business Park, Action Area-II, Building Nos.2A,
5th Floor, Unit Nos.501B, New Town, Rajarhat,Kolkata-700156
_________________________________________________________________

Sub:-Regarding Painting of Pole under special plan (BRGF) Phase-I & Phase-II.
Sir
With reference to above subject, it is directed to paint upper most part (90 cm) of each PSC/
Rail pole with blue colour so that it may be distinguished from other schemes.

Yours Faithfully,
(C.L.Prakash)
Chief Engineer (RE)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
Memo nos.

Dated

Copy forwarded toAllElectrical Superintending Engineer/All Electrical Executive


Engineer / All Assistant Electrical Engineer Projects, SBPDCL Patna for information &
needful action.

(C.L.Prakash)
Chief Engineer (RE)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
Letter No:-S-XIII/BRGF-FEEDBACK-DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
M/s Feedback Infra Private Limited,
Energy Division, 15th Floor, Tower 9B,
DLF Cyber City, Phase-III, Gurgaon, Haryana-122 002.
Phone No: +91-124-4169100, Fax Nos.:+91-124-4169155
Email: inquiries@feedbackinfra.com.

Sub:- Regarding interview schedule


Ref:- FIPL/PMU/SBPDCL/3107 Dated- 31.07.2014
Sir,
With reference to above this is to inform that, The replacement of key staff in
PMU assignment of SBPDCL. Interview schedule is given below.
Sl.N
Date
Time
os.
1
19.08.2014
3PM To 5PM
Hence you are requested to arrange manpower, as per Clause 5 of LOA whose

qualification as per RFP & LOA. Interview is Scheduled for One DPM, One APM and
Five District Coordinators.
Yours Faithfully,
Sd/(C.L.Prakash)
Chief Engineer (RE)
Memo nos.

Dated

Copy forwarded to ESE. Special Plan (BRGF)/ OSD (HR&A) / EEE. Special Plan
(BRGF).SBPDCL Patna for information & needful action
(C.L.Prakash)
Chief Engineer (RE)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Letter No
DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
M/s Feedback Infra Private Limited,
Energy Division, 15th Floor, Tower 9B,
DLF Cyber City, Phase-III, Gurgaon, Haryana-122 002.
Phone No: +91-124-4169100, Fax Nos.:+91-124-4169155
Email: inquiries@feedbackinfra.com
------------------------------------------------------------------------------------The Louis Berger Group,
inc.B.3-6,sector-32
Gurgoan, Haryana-122001.
Phone Nos. +91-124-4044750
Email: india@louisberger.com
Sub:-Meeting with PMU,PMC of all Projects.
Ref:- FIPL/PMU/SBPDCL/3107 Dated- 31.07.2014
S-XIII-RE/NIT-PMS-1025/213/651 dated:- 29.11.2013
Sir,
With reference to above, it is to inform that there is a meeting with PMU of all
Projects by MD SBPDCL on 21.08.2014 at 4:00 pm.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
You are requested to attend meeting with preparation positively.

Yours Faithfully,
Sd/(C.L.Prakash)
Chief Engineer (RE)
Memo nos.

Dated

Copy forwarded to ESE. Special Plan (BRGF/ EEE. Special Plan (BRGF).SBPDCL
Patna for information.

(C.L.Prakash)
Chief Engineer (RE)

Letter No
DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
M/s GKC-APL Joint Venture,
Survey Nos.9(P), CII Green Building
Lane, Hitech City,
Kondapur, Hyderabad- 500084

Sub:-Regarding weekly review meeting of non Performing agency.


Sir,

As per your approved BAR Chart, your work progress is very slow and unsatisfactory. In the lastreview
meeting , it was found that important Electrical equipments are not yet reached at site which is affecting
the progress of work.
Neither the R&M works nor the new works has been started yet which result very slow and unsatisfactory
performance of work.
So, you are requested to be present in the weekly review meeting on dated 20.08.2014 at
11.30
HRS in the office chamber of MD SBPDCL with all reports positively.
Yours Faithfully,

(C.L.Prakash)
Chief Engineer (RE)

Letter No
DatedFrom,
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
C.L.Parkash
Chief Engineer (RE)
To,
M/s Supreme & Co. Pvt. Ltd.-M/S Utkal Galvanizers Ltd.
Joint Venture, 53,JusticChandra,Madhav Road,
Kolkata-20

Sub:-Regarding weekly review meeting of non Performing agency.


Sir,

As per your approved BAR Chart, your work progress is very slow and unsatisfactory. In the lastreview
meeting , it was found that important Electrical equipments are not yet reached at site which is affecting
the progress of work.
Neither the R&M works nor the new works has been started yet which result very slow and unsatisfactory
performance of work.
So, you are requested to be present in the weekly review meeting on dated 20.08.2014 at
11.30 HRS in the office chamber of MD SBPDCL with all reports positively.
Yours Faithfully,

(C.L.Prakash)
Chief Engineer (RE)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
Letter No
DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
M/s Vijai Electricals Ltd.
6-3-648/1&2, off Rajbhavan Road,
Somajiguda, Hyderabad-500082,
Andhra Pradesh.

Sub:-Regarding weekly review meeting of non Performing agency.


Sir,

As per your approved BAR Chart, your work progress is very slow and unsatisfactory. In the lastreview
meeting , it was found that important Electrical equipments are not yet reached at site which is affecting
the progress of work.
Neither the R&M works nor the new works has been started yet which result very slow and unsatisfactory
performance of work.
So, you are requested to be present in the weekly review meeting on dated 20.08.2014 at
11.30 HRS in the office chamber of MD SBPDCL with all reports positively.
Yours Faithfully,

(C.L.Prakash)
Chief Engineer (RE)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Letter No
DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
M/s SUPREME VPIL (JV),
Ecospace Business Park, Action Area-II,
Building Nos.2A,5th Floor, Unit Nos.501B,
New Town, Rajarhat,
Kolkata-700156

Sub:-Regarding weekly review meeting of non Performing agency.


Sir,

As per your approved BAR Chart, your work progress is very slow and unsatisfactory. In the lastreview
meeting , it was found that important Electrical equipments are not yet reached at site which is affecting
the progress of work.
Neither the R&M works nor the new works has been started yet which result very slow and unsatisfactory
performance of work.
So, you are requested to be present in the weekly review meeting on dated 20.08.2014 at
11.30
HRS in the office chamber of MD SBPDCL with all reports positively.
Yours Faithfully,

(C.L.Prakash)
Chief Engineer (RE)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Authorisation latter
Dated:- 19.08.2014
To
West Bengal Minorities Development &Finance Corporation
Amber,DD-27/E, Sector 1
Salt Lake City
Kolkata-700064
Subject:-Authorisation letter
Dear sir
I Murtaza Halal, here by authorise my father-in-law Mr.ManzoorAhsan Ansari
to attend the lottery for allotment of flat at ARFNA housing project on my
behalf. I also authoriseMr.ManzoorAhsan Ansari to represent, sign, deliver and
receive any documents on my behalf.
The signature of Mr.ManzoorAhsanAnsar is attested below.

Thanking you
Yours Faithfully
Mr.ManzoorAhsan Ansari

(MurtazaHelal)
Attested
Flat Nos. J/4
SAPANA APPARTMENT
PHASE VI
MurtazaHelal
NAYATOLA,BIHAR
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
PATNA-800004

Letter No
DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
M/s Supreme & Co. Pvt. Ltd.-M/S Utkal Galvanizers Ltd.
Joint Venture, 53,JusticChandra,Madhav Road,
Kolkata-20

sub:- Regarding Review meeting with Director Projects SBPDCL on 21.08.2014 at


5.00 PM regarding progress of work
under Special Plan (BRGF) Phase-I.
Sir,
As per the above subject, it is to inform that a review meeting is arranged in the
conference
room in the Headquarter at 5.00 PM on 2l.08.2014 regarding progress of work
under Special plan
(BRGF).
so, you are directed to be present in the aforesaid meeting positively.
Yours Faithfully

Yours Faithfully,

(C.L.Prakash)
Chief Engineer (RE)
Memo nos.

Dated

Copy forwarded to ESE. Special Plan (BRGF/ EEE. Special Plan (BRGF).SBPDCL
Patna for information.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

(C.L.Prakash)
Chief Engineer (RE)

Letter No
DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
M/s Vijai Electricals Ltd.
6-3-648/1&2, off Rajbhavan Road,
Somajiguda, Hyderabad-500082,
Andhra Pradesh.

sub:- Regarding Review meeting with Director Projects SBPDCL on 21.08.2014 at


5.00 PM regarding progress of work
under Special Plan (BRGF) Phase-I.
Sir,
As per the above subject, it is to inform that a review meeting is arranged in the
conference
room in the Headquarter at 5.00 PM on 2l.08.2014 regarding progress of work
under Special plan
(BRGF).
so, you are directed to be present in the aforesaid meeting positively.
Yours Faithfully

Yours Faithfully,

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
(C.L.Prakash)
Chief Engineer (RE)
Memo nos.

Dated

Copy forwarded to ESE. Special Plan (BRGF/ EEE. Special Plan (BRGF).SBPDCL
Patna for information.

(C.L.Prakash)
Chief Engineer (RE)

Letter No
DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
M/s GKC-APL Joint Venture,
Survey Nos.9(P), CII Green Building
Lane, Hitech City,
Kondapur, Hyderabad- 500084

sub:- Regarding Review meeting with Director Projects SBPDCL on 21.08.2014 at


5.00 PM regarding progress of work
under Special Plan (BRGF) Phase-I.
Sir,
As per the above subject, it is to inform that a review meeting is arranged in the
conference
room in the Headquarter at 5.00 PM on 2l.08.2014 regarding progress of work
under Special plan
(BRGF).
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
so, you are directed to be present in the aforesaid meeting positively.
Yours Faithfully

Yours Faithfully,

(C.L.Prakash)
Chief Engineer (RE)
Memo nos.

Dated

Copy forwarded to ESE. Special Plan (BRGF/ EEE. Special Plan (BRGF).SBPDCL
Patna for information.

(C.L.Prakash)
Chief Engineer (RE)

Letter No
DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
M/s Bajaj electricals Limited,
801,10th Floor Rustomjee Aspire,
801,10th Floor Rustomjee Aspire,
Bhanu Shankar YagnikMarg, Off eastern express highway,Sion (E),
Mumbai-400022

sub:- Regarding Review meeting with Director Projects SBPDCL on 21.08.2014 at


5.00 PM regarding progress of work
under Special Plan (BRGF) Phase-I.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
Sir,
As per the above subject, it is to inform that a review meeting is arranged in the
conference
room in the Headquarter at 5.00 PM on 2l.08.2014 regarding progress of work
under Special plan
(BRGF).
so, you are directed to be present in the aforesaid meeting positively.
Yours Faithfully

Yours Faithfully,

(C.L.Prakash)
Chief Engineer (RE)

Memo nos.

Dated

Copy forwarded to ESE. Special Plan (BRGF/ EEE. Special Plan (BRGF).SBPDCL
Patna for information.

(C.L.Prakash)
Chief Engineer (RE)

Letter No
DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
M/s East IndaiUdyog Ltd. 145,
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
G.T.Road, Sahbabad,Ghaziabad ,
Uttar Pradesh-201005,

sub:- Regarding Review meeting with Director Projects SBPDCL on 21.08.2014 at


5.00 PM regarding progress of work
under Special Plan (BRGF) Phase-I.
Sir,
As per the above subject, it is to inform that a review meeting is arranged in the
conference
room in the Headquarter at 5.00 PM on 2l.08.2014 regarding progress of work
under Special plan
(BRGF).
so, you are directed to be present in the aforesaid meeting positively.

Yours Faithfully,

(C.L.Prakash)
Chief Engineer (RE)

Memo nos.

Dated

Copy forwarded to ESE. Special Plan (BRGF/ EEE. Special Plan (BRGF).SBPDCL
Patna for information.

(C.L.Prakash)
Chief Engineer (RE)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
Letter No
DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
M/s Technofab-Gammon Joint Venture,
507, Eros Apartments, 56, Nehru Place,
New Delhi-110019

sub:- Regarding Review meeting with Director Projects SBPDCL on 21.08.2014 at


5.00 PM regarding progress of work
under Special Plan (BRGF) Phase-I.
Sir,
As per the above subject, it is to inform that a review meeting is arranged in the
conference
room in the Headquarter at 5.00 PM on 2l.08.2014 regarding progress of work
under Special plan
(BRGF).
so, you are directed to be present in the aforesaid meeting positively.

Yours Faithfully,

(C.L.Prakash)
Chief Engineer (RE)
Memo nos.

Dated

Copy forwarded to ESE. Special Plan (BRGF/ EEE. Special Plan (BRGF).SBPDCL
Patna for information.

(C.L.Prakash)
Chief Engineer (RE)
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

It is reported By inspection cell that you all are issuing the Dispatch
instruction without informing
Inspection cell
It is directed to all AEE Special Plan (BRGF) that before issuing the Dispatch
instruction, certify the inspection report from Inspection cell for record.

Minutes of meeting held by CMD,BSPHCL of all the


Ongoing Projects of SBPDCL & NBPDCL with all the
agencies and concerned officers on 23.08.2014.
M/s East India Udyog Ltd.
SBPDCL

NBPDCL

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Special Plan (BRGF) Phase-I


Phase-INalanda& Patna
Siwan&Gopalgang

Special Plan (BRGF)


Saran,

State Plan- Jehanabad


Special Plan (BRGF) Phase-I:CMD directed that in next meeting Head of the company should be present with physical
progress of all the Projects under taken by the firm.
The survey work & freezing of BOQ should be on time .
Mechanism of monthly review in each week & minutes of meeting of each week &its action
taken is not proper. The meeting should not be mechanical review rather it should be with
purpose and its achievement. On 5th august MD/ North held review
meeting of Special
plan(BRGF) and the agency was not present. Showcase of the firm was not proper and its
reply was yet to come.
Monthly review of next month with head of the agency. The review should be on roster wise
with review of North is Monday & South is Tuesday . The site Project Manager should also be
present in the review.
CMD directed that supplementary agreement should be executed by all agency which should
have milestones defined for completion of project with incentive clause. If an schedule date
of completion the agency fails to achieve 80% of awarded work , the firm should be debarred
from all future projects of BSPHCL & its subsidiary Co. aperies till the completion of projects
CMD expressed displeasure regarding slow progress of work by the firm & why action was
taken against the form for non progress of work as per approved bar chart. The agency
should complete the work by NOV-2014.
State plan:- Civil work of PSS is in final stage. Schedule time of completion on 06.08.2014 &
this is extended up to 15.10.2014. The time extension should be given with proper clause.
The firm should complete all the three PSS at Sagarpur,Dharaut, &Bhadsora
By
15.10.2014.CMD directed the firm to come up with full preparation in next meeting.
Dharaut PSS:- Agency asked for time extension due to damage road. & it should be given.
On the scale of 10the firm does not stand at 3. The company should be desamed.
Special plan (BRGF):As per approved bar chart the firm should have completed the R&M work By 18.06.2014 and
new work to be completed by 18.09.2014.
Survey & BOQ freezing work completed on 22.08.2014 to headquarter which is to be
approved as yet.
CMD expressed displeasure on this matter and wanted the file for investigation .
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
CMD directed that for all future project preliminary work of freezing of BOQ survey etc.
should be done before hand for smooth take off of project.

M/s Bajaj Electricals


SBPDCL
Special Plan (BRGF)Phase-I
(BRGF)Phase-I

NBPDCL
Special Plan

Banka, Bhagalpu, MungerSamastipur&Begusarai


BhojpurBuxarDurbhanga&Madhubani
RGGVYRGGVY
BhojpurKishanganj&Purnia
CMD reviewed Work under Bhojpur Districts:Bajaj electricals Ltd representative stated that they have completed the survey work,
18% pole erection work completed and completed works of 3 villages chanda,
Panchwan&Pithari in Bahara&Piro Blocks.
CMD directed director Project to visit Bhojpur on 26.08.2014 and inspect the work of villages
completed ongoing works of PSS at agiaon, udwantnager and charpokhari PSS.
The firm requested for time extension due to delay regarding installation of 63 KVA
transformer instead of 25 KVA for which the firm has already given in writing.
CMD was of the view to give the time extension till December 2015 / Jan 2016.
CMD directed for formation of variation committee to finalize the variation & its meeting
should be held every fifteen Days. If holiday taken on next day to materialize the case
variations.
CMD expressed displeasure regarding slow progress & listed the agency as non performer&
should be defamed from up comingBRGFtender.

RGGVY-NBPDCL Kishangang District:The agency representative stated that 8 villages have been electrified and their progress of
work is 10%. They e that there DI was not issued last 30 days.
CMD directed for agenda regarding inspection of level-2 & level-3 items as raised by the
firm.
The firm also wanted in writing for waived of inspection of level-3 item.
CMD directed to agency to be present at kishangang for details review on 26.10.2014
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
The agency was on the scale of 10 at 4.
Supplementary agreement to be executed & the firm should be debarred.
SBPDCL-Bhagalpur, Banka ,&munger / BRGF Phase-I
The agency raised queries about land filling where new PSS is to be built. They stated
regarding land filling at Dogachi up to 6 feet at Bhagalpur District.
CMD directed to execute all the filling works at SOR of PWD. The company should done its at
own cost for early completion of project.
CMD expressed displeasure at the slow progress of work by Bajaj Electrical LTD & directed in
next meeting the owner of the company should be present.

M/s A2Z MES Ltd.


SBPDCL

NBPDCL

ADB funded Project


Project

ADB funded

Ara&BuxartownBettiah&Motihari
Samastipur&Bagusarai
Bettiah&Motihari :CMD Expressed displeasure and firm was at its worst in Bettiah in terms of performance. No
representative of Bettiah&Motihari was present.
CMD called for meeting with A@Z 28.08.2014(Thursday)

Arrah&Buxar- SBPDCL
CMD expressed displeasure for non completion of the project as yet Show cause to be issued
& remove for non performance.
CE/ Planning was directed to investigate the work of A@Z of urban area with team of
Director Projects.
A2Z should complete the work by 30 th September 2014 & meeting to be held with A2Z on
28.08.2014 (Thursday)
The firm raised the issue of ROW problem to completion of 33KV NEW Line FromDumroan to
Industrial PSS. THE firm had intimated CE/ Planning on 15.05.2014regarding the position at
Zaso village in Buxardistict.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

M/s GKC-APL JV
SBPDCL

NBPDCL

Special Plan BRGF Phase-1


R-APDRP-Part-B
Gaya, Jehanabad&NawadaDerbhanga&Madhubani
RGGVYSiwan
BRGF Phase-1 Gaya, Jehanabad& Nawada
The firm raised the issue regarding variation of materials in R&M of PSS for which CT PT &
Panels are not incorporated.CMD directed to resolve it through variation committee for all the
project SBPDCL & NBPDCL.
The firm raised the issue regarding pending approval of civil work level from 16.05.2014,CMD
Directed to investigate the reasons for its pendency.
The firm was of the project district wise by the CMD.
Gaya-30.11.2014, Nawada- 31.01.2014 &Jehanabad-31.01.2014.
This time extension should be given with 10% deductions. Executed Supplementary
agreement & debar.

RGGVY Siwan:CMD directed to CE/RE/NBPDCL to visit Siwan district on 26.08 2014(Tuesday) and should
submit detail review report of the progress of work of entire district.
Supplementary agreement to be drafted by Sunday by both companies of North & south.

R-APDRP Parts- Daurbhanga&MadhubaniCMD review the R-APDRP works at Duarbhanga on 25.08.2014(Monday)


CMD expressed displeasure at the non-performances of the work by the agency formed it as
worst company. If no improvement head of agency to be called in next meeting.

M/s ECI Engineering & Construction Co. Ltd.


SBPDCL

NBPDCL

RGGVY- Rohtas

RGGVY- RohtasSouth Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
The firm inform that work has been completed in 10 villages of Rohtas districts.
CMD directed ESE/ Special Plan (BRGF) to Cary out inspection of the villages under two
teams. One headed by ESE(BRGF) & other by ESE/Rohtas with magistrate provided by DM &
submit report by 27.08.2014.
Owner of ECI should come in next review meeting.

M/s Supreme & Co. Kolkata.


SBPDCL

NBPDCL

Special Plan BRGF Phase-1


Arwal& Aurangabad
CMD directed to call the head of company on 28.08.2014 at 3.00 PM on scheduled

M/s Supreme VPIL.


SBPDCL

NBPDCL

CMD directed the agency to complete the survey work by 31.08.2014 and freeze all the
quantity by next meeting. If the work is not complete deduct penalty.

M/s Godrej
SBPDCL

NBPDCL

The firm inform that their work is to be completed by January 2015 & 40 % materials are at
sight.
CMD expressed displeasure at the non-performances of the work at purnea will review
26.08.2014 & physically verify the work. Siwan&Gopalganf................................

M/s Vijai Electricals Ltd.


SBPDCL

NBPDCL

Special Plan BRGF Phase-1


BRGF Phase-1
Rohtas&Kaimur

Special Plan

Muzaffarpur, Vaishali, Sitamarhi,


East Champaran& West

champaran
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
RGGVY- Arraria
The firm inform that they have completed 110 villages & 40 villages is to be taken over.
CMD directed to ESE/Purniacheak at least 10 villages with .................. & will be revived on
26.08.2014.
BRGF- Arwal& Aurangabad
The firm .............. For extension of time for BRGF works &called for extension upto
31.12.2014 for R&M work & 31.03.2014 for new work.
CMD allowed extension upto 31.12.2014 as per terms & conditions.
The firm raise the issue of Railway crossing & 12 nos of places, one 33 KV line river crossing
to be built on .........which is 390 meter wide , about concreting of rail poles instead of 1:2:4
while in LOA ,it is 1:4:8 and regarding size of control room of new PSS . CMD Director for
meeting with GM Railways before10-09-2014 to take up all the issue related to railways and
rest of the issues to be resolved by CE/RE and CE/BRGF/North and by the variation
committee.
The firm also raised issue of special drawing approval for baraPSS at muzzafarpur due to
pond on 1 site .approval to be given by CE.
M/s

JyotiInfrastructure Ltd.

SBPDCL

NBPDCL

RGGVY

RGGBY-

SekhpuraKhagaria:CMD Raised Issue regarding termination of .................................to firm in fifth month by


CE/RE but the firm was not terminated yet in Khagaria and PSS was to be built out of which
only two is complete .
CMD Director to call meeting with the firm on 28-08-2014 at 4.30 p.m. and expressed
displeasure regarding the agencys work and categories as worst performer.
CMD Directed EEE/ Khagaria to inspect the quality of work done by agency at PSS with
magistrate . EEE/ Project will also be there. CMD called for review of work of Shyama power
and supreme separately .
CMD also directed EEE/STF/Rajiv Ranjan to go to Betiah and inspect for ..................of 33
KV/ line of Siktah.

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Letter No
DatedFrom,
C.L.Parkash
Chief Engineer (RE)
To,
M/s GKC-APL Joint Venture, Survey Nos.9(P), CII Green Building Lane, Hitech City,
Kondapur, Hyderabad- 500084
_____________________________________________________________
M/s Supreme & Co. Pvt. Ltd.-M/S Utkal Galvanizers Ltd. Joint Venture,
53,JusticChandra,Madhav Road,
Kolkata-20
_____________________________________________________________
M/s Vijai Electricals Ltd. 6-3-648/1&2, off Rajbhavan Road, Somajiguda,
Hyderabad-500082, Andhra Pradesh.
_____________________________________________________________
M/s Bajaj electricals Limited, 801,10th Floor Rustomjee Aspire, 801,10th Floor Rustomjee Aspire,
Bhanu Shankar YagnikMarg, Off eastern express highway,Sion (E), Mumbai-400022
______________________________________________________________
M/s East IndaiUdyog Ltd. 145, G.T.Road, Sahbabad,Ghaziabad ,
Pin-201005,Uttar Pradesh
______________________________________________________________
M/s Technofab-Gammon Joint Venture, 507, Eros Apartments, 56, Nehru Place,
New Delhi-110019
________________________________________________________________
M/s. SHIRDI SAI ELECTRICALS LIMITED,13/82, INDUSTRIALESTATE ,
KADAPA- 516004
________________________________________________________________
M/s. Sri Gopikrishna Infrastructure Pvt. Ltd. Corporate Office: 30/B (8-3-191/162), Vengalrao Nagar,
Hyderabad- 500038
________________________________________________________________
M/s SUPREME VPIL (JV), Ecospace Business Park, Action Area-II, Building Nos.2A,
5th Floor, Unit Nos.501B, New Town, Rajarhat, Kolkata-700156
_________________________________________________________________

Sub:-Regarding Review meeting with MD ,SBPDCL on 12.09.2014 at 10 am regarding


progress of work under special plan (BRGF) Phase-I & Phase-II.
Sir

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
As per above subject, it is to inform you that a review meeting is to be heald under
chairmanship of MD in the conference hall in headquarter at 10 am on 12.09.2014 regarding
progress of work under special plan (BRGF) Phase-I & Phase-II.

Yours Faithfully,
(P.K. Govil)
Chief Engineer Project-I

Memo nos.

Dated

Copy forwarded to All Electrical Superintending Engineer/All Electrical Executive


Engineer / All Assistant Electrical Engineer Projects, SBPDCL Patna for information &
needful action.
(P.K. Govil)
Chief Engineer Project-I

Letter No
DatedFrom,
(P.K. Govil)
Chief Engineer Project-I
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
To,
M/s GKC-APL Joint Venture, Survey Nos.9(P), CII Green Building Lane, Hitech City,
Kondapur, Hyderabad- 500084
_____________________________________________________________
M/s Supreme & Co. Pvt. Ltd.-M/S Utkal Galvanizers Ltd. Joint Venture,
53,JusticChandra,Madhav Road,
Kolkata-20
_____________________________________________________________
M/s Vijai Electricals Ltd. 6-3-648/1&2, off Rajbhavan Road, Somajiguda,
Hyderabad-500082, Andhra Pradesh.
_____________________________________________________________
M/s Bajaj electricals Limited, 801,10th Floor Rustomjee Aspire, 801,10th Floor Rustomjee Aspire,
Bhanu Shankar YagnikMarg, Off eastern express highway,Sion (E), Mumbai-400022
______________________________________________________________
M/s East IndaiUdyog Ltd. 145, G.T.Road, Sahbabad,Ghaziabad ,
Pin-201005,Uttar Pradesh
______________________________________________________________
M/s Technofab-Gammon Joint Venture, 507, Eros Apartments, 56, Nehru Place,
New Delhi-110019
________________________________________________________________
M/s. SHIRDI SAI ELECTRICALS LIMITED,13/82, INDUSTRIALESTATE ,
KADAPA- 516004
________________________________________________________________
M/s. Sri Gopikrishna Infrastructure Pvt. Ltd. Corporate Office: 30/B (8-3-191/162), Vengalrao Nagar,
Hyderabad- 500038
________________________________________________________________
M/s SUPREME VPIL (JV), Ecospace Business Park, Action Area-II, Building Nos.2A,
5th Floor, Unit Nos.501B, New Town, Rajarhat, Kolkata-700156
_________________________________________________________________

Sub:-Regarding unsatisfactory Progress& submission of load center analysis .


Sir,

As per your approved BAR Chart, your work progress is very slow and unsatisfactory. In the lastreview
meeting , it was found that important Electrical equipments are not yet reached at site which is affecting
the progress of work.
Neither the R&M works nor the new works has been started yet which result very slow and unsatisfactory
performance of work.
This is also inform you that as per LOA/Clause:-1-X, before start of the work, detailed Survey is to be
carried out by your firm for identification of weak areas before starting work & submit plan for all the
works relatedtostrengthening/Augmentation of Distribution Network tobe taken up under the scope of
awarded work.
The details of analysis and survey should also include single line diagram of existing network, its voltage
regulation at different load centres and proposed distribution infrastructure along with its voltage
regulation after completion of work.After specific approval on this stage, the work will be taken up.
It is directed to you expedite your supply rate of materials as well as erection activity .
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
Yours Faithfully,
-Sd/
(P.K. Govil)
Chief Engineer Project-I

Memo nos.

Dated

Copy forwarded to All Electrical Superintending Engineer/All Electrical Executive


Engineer / All Assistant Electrical Engineer Projects, SBPDCL Patna for information &
needful action.
(P.K. Govil)
Chief Engineer Project-I

Minutes of meeting of Special Plan ( BRGF) held on 12.09.2014


under the chairmanship of Chief Engineer(Project-I) , SBPDCL at
11.00 AM

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Districts: Bhojpur&Buxar (NIT NO:205) AND


Bhagalpur,Banka&Munger(NIT NO: 207) (M/s Bajaj Electricals
Limited: Mumbai )

Agency raised the issue regarding land of New PSS at PratapsagarofBuxar& Nehru
colonyofBankadistricts. They wanted in writing to start the work at new PSS.

It was informed by the Agency that rate of Control & Relay Panel& CT PT is not given
in schedule of R&M of PSS.
Estimate of Boundary wall & Control room extension is not not finalized yet of NIT
207.
In LOA volume of concreting of Rail Pole in 11KV Line is 0.26 cu meter with
concreting ratio 1:4:8.
Agency requested to finalize the rate of concreting ratio 1:2:4 per cubic meter.
It was informed by the Agency that Land filling of Dogacchi PSS of Bhagalpur district
is not possible.

2. Districts: Lakhisarai,Jamui&Sheikhpura NIT NO: 208 (M/s


Techno Fab gamon Joint Ventures Limited: New Delhi)
It was inform by the agency, there is no provision of land filling in LOA.
3. Districts: Arwal& Aurangabad NIT NO: 203 (M/s Supreme &
co.-UtkalGlavanizers JV Kolkata)
It was requestby agency that expedite

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Letter No
DatedFrom,
Director (Project), SBPDCL
To,
M/s SUPREME VPIL (JV),
Ecospace Business Park, Action Area-II,
Building Nos.2A,5th Floor, Unit Nos.501B,
New Town,Rajarhat, Kolkata-700156

Subject:- Unsatisfactory progress of work under Special Plan (BRGF)


Phase-II in Patna &Bhojpur District.
Ref:- (i) NIT nos.-03/PR/SBPDCL/2014
Dear Sir
The Schedule of work involved against NIT NO- 03/PR/SBPDCL/2014are
reviewed on thebasis of approved BAR CHART/PERT NETWORK.It was
found that your work Progress is not as perapproved BAR CIHART/PERT
NETWORK. Details of poor performance areas are given below:
1. Your survey report is not received to this office till date.
2. You have to submit 100% GTP & Drawing to this office by 25
September 2014. But you haven'tsubmitted the above as yet which is
alarming considering the paucity of time.
3. Also you have to start supply of materials from August 2014. But till
date the progress is nil.
4. You, have not submitted inspection call of materialsandall matching
materials.Considering the time-period of work.your progress as per BAR
CHART' (provided by you)isunsatisfactory and target seems difficult to
achieve in specified time period. Since it is a time bound project of 18
months, hence youare warned to speed up your work in order to achieve
target within specified time.
This is also inform you that as per LOA/Clause:-1-X, before start of the
work, detailed Survey is to be carried out by your firm for identification of
weak areas before starting work & submit plan for all the works related
to strengthening/Augmentation of Distribution Network to be taken up
under the scope of awarded work.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

The details of analysis and survey should also include single line diagram
of existing network, its voltage regulation at different load centres
and proposed distribution infrastructure along with its voltage regulation
after completion of work. After specific approval on this stage, the work
will be taken up.It is directed to you expedite the supply of materials as
well as erection activity.
Yours Faithfully,
Sd/Director (Project), SBPDCL
Memo Nos.
Dated
Copy forwarded to OSD to CMD, BSPHCL/OSD to MD, SBPDCL for
information.

Director
(Project), SBPDCL

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Letter No

Dated-

From,
Director (Project), SBPDCL
To,
M/s. Sri Gopikrishna Infrastructure Pvt. Ltd.
Corporate Office: 30/B (8-3-191/162),
Vengalrao Nagar, Hyderabad- 500038
Subject:- Unsatisfactory progress of work under Special Plan (BRGF) Phase-II
in Patna &Bhojpur District .
Ref:- (i) NIT nos.-02/PR/SBPDCL/2014
Dear Sir
This is also inform you that as per LOA/Clause (1-X), before start of the work,
detailed Survey is to be carried out by your firm for identification of weak areas
before starting work & submit plan for all the works related to
strengthening/Augmentation of Distribution Network to be taken up under the
scope of awarded work.
The details of analysis and survey should also include single line diagram of
existing network, its voltage regulation at different load centres and proposed
distribution infrastructure along with its voltage regulation after completion of
work. After specific approval on this stage, the work will be taken up.It is
directed to you expedite the supply of materials as well as erection activity &

the work stated above.

Yours Faithfully,
Sd/-

Director (Project), SBPDCL


South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Memo Nos.
Dated
Copy forwarded to OSD to CMD, BSPHCL/OSD to MD, SBPDCL for
information.
Director (Project), SBPDCL

Letter No
DatedFrom,
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Director (Project), SBPDCL


To,
M/s. SHIRDI SAI ELECTRICALS LIMITED,
13/82, INDUSTRIALESTATE ,
KADAPA- 516004

Subject:- Unsatisfactory progress of work under Special Plan (BRGF)


Phase-II in Patna &Bhojpur District .
Ref:- (i) NIT nos.-04/PR/SBPDCL/2014
Dear Sir
The Schedule of work involved against NIT NO- 04/PR/SBPDCL/2014 are
reviewed on the basis of approved BAR CHART/PERT NETWORK. It was
found that your work Progress is not as per approved BAR CIHART/PERT
NETWORK. Details of poor performance areas are given below:
1. Your survey report is not received to this office till date.
2. Also you have to start supply of materials from September 2014. But
till date the progress is nil.
3. You have not submitted inspection call of materials and all matching
materials. Considering the time-period of work.your progress as per BAR
CHART' (provided by you) is unsatisfactory and target seems difficult to
achieve in specified time period. Since it is a time bound project of 18
months, hence you are warned to speed up your work in order to achieve
target within specified time.
This is also inform you that as per LOA/Clause:-1-X, before start of the
work, detailed Survey is to be carried out by your firm for identification of
weak areas before starting work & submit plan for all the works related
to strengthening/Augmentation of Distribution Network to be taken up
under the scope of awarded work.
The details of analysis and survey should also include single line diagram
of existing network, its voltage regulation at different load centres
and proposed distribution infrastructure along with its voltage regulation
after completion of work. After specific approval on this stage, the work
will be taken up.It is directed to expedite supply of materials as well as
erection activity & the work stated above.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Yours Faithfully,
Sd/Director (Project), SBPDCL
Memo Nos.
Dated
Copy forwarded to OSD to CMD, BSPHCL/OSD to MD, SBPDCL for
information.

Director (Project), SBPDCL

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Minutes of the review meeting held by CMD, BSP(H)CL of all on-going


projects under SBPDCL with the working Agencies, Consultants (PMU/PIU)
and officers of field & HQ on 18.11.2014.
_________________________________________________________________________
_

Presentation was made by STF team in which it was shown in details the
defect in erection work of different agencies and poor civil work being

carried out by the agencies.


It was directed that jointing sleeves to be used in stringing of conductor at

joints and turn table to be used for handling of conductors.


Regular field visit should be done by Project officers & officers at

Headquarter to monitor work as per work program submitted by agencies.


Most of the agencies have not submitted work programs.
All R&M work to be completed by 31.12.14 by all the agencies of BRGF,

Phase-I scheme.
M/S East Indias Civil Work is poor quality & it should be checked.
Road department will not object if the poles are erected at ROW edge.
All agencies should submit work program & it should be clarified in minutes

by YES/NOS.
Action should be taken against observation made by PMU/PME/Third Party.
DI to be issued by EEE of concerned projects at Headquarter.
CMD directed to carry out the project work on time with quality. All officers

at head quarter should carry out field visit.


ESE of concerned circle, EEE/ Projects, AEE/Projects & JEE/ Projects should
report about performance of agencies. If not performing then report for
termination. Working of agencies should be in full mode with quality on top
priority.

Memo No:-

Date:-

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
Copy forwarded to M/s Feedback infra Pvt. Ltd, M/s GKC-APL Joint Venture,Survey
Nos. 9(P), CII Green Building Lane, Hitech City, Kondapur, Hyderabad- 500084, M/s.
SHIRDI SAI ELECTRICALS LIMITED, 13/82, INDUSTRIALESTATE,KADAPA- 516004,
M/s Vijai Electricals Ltd. 6-3-648/1&2, off Rajbhavan Road, Somajiguda,
Hyderabad-500082, Andhra Pradesh, M/s Supreme & Co. Pvt. Ltd.-M/S Utkal
Galvanizers Ltd. Joint Venture,53,Justic Chandra,Madhav Road,Kolkata20,M/s East IndaiUdyog Ltd. 145,G.T.Road,Sahbabad,Ghaziabad ,
Pinth
201005,Uttar Pradesh, M/s Bajaj electricals Limited, 801,10 Floor Rustomjee
Aspire, 801,10th Floor Rustomjee Aspire, Bhanu Shankar YagnikMarg, Off eastern
express highway, ion (E),Mumbai-400022,
M/s
Technofab-Gammon
Joint
Venture, 507, Eros Apartments, 56, Nehru Place, New Delhi-110019, M/s. Sri
Gopikrishna Infrastructure Pvt. Ltd.Corporate Office: 30/B (8-3-191/162),
Vengalrao Nagar, Hyderabad- 500038, M/s SUPREME VPIL (JV),Ecospace
Business Park, Action Area-II, Building Nos.2A, 5th Floor, Unit Nos.501B, New Town,
Rajarhat, Kolkata-700156,for information & necessary action.
(N.K.P. Sinha)
Director(Project)
Memo nos.
Date:Copy forwarded to Electrical Superintending Engineer, Special Plan
(BRGF)/EEE, Special Plan (BRGF)/AEE, Special Plan (BRGF)/AO, Special Plan (BRGF),
SBPDCL, for information and necessary action.
(N.K.P. Sinha)
Director(Project)
Memo No:Date:Copy forwarded to OSD to MD, SBPDCL, Patna for information.
(N.K.P. Sinha)
Director(Project)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Minutes of the review meeting held by CMD, BSP(H)CL of all on-going


projects under SBPDCL with the working Agencies, Consultants (PMU/PIU)
and officers of field & HQ on 18.11.2014.
_________________________________________________________________________
_
1.Districts: Gaya,Nawada&Jahanabad NIT NO: 196 (M/s GKC -APL
joint venture,Hydrabad)
The firm has to complete R&M work of PSS till end of December 2014,
but R&M work of not a single PSS completed in all respect till date. No
stringing work started in 11 KV & 33 KV line till date. The firm has
committed that R&M work of PSS will be completed in all
respectsupto 31st January 2015.
Target date for completion of new PSS is given below :Sl. Nos.

Name of PSS

(i)

33/11 KV DakhaniJehanabad PSS

June. 2015

(ii)

33/11 KV Majhwe PSS

July. 2015

(iii)

Target date of completion

33/11 KV Maya bigha PSS

July. 2015

(A) The firm has committed following regarding completion of 33 KV Line


as detailed below.
(i) December 2014- 10 KM
(ii) January 2015-

14.5 KM

(iii) February 2015 - 11.5 KM


(iv) March

2015 -

11.8 KM

(B) The firm has committed following regarding completion of 11 KV Line


as detailed below.
(i) December 2014- 8 KM
(ii) January 2015(iii) February 2015(iv) March

2015-

31.53 KM
16.9 KM
6.46 KM

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

The firm has further committed that all works related to construction of
new 11 KV Line will be completed upto June 2015.
2.Districts:Rohtas&Kaimur
Limited Hyderabad)

NIT NO: 204 (M/s Vijay Electricals

The firm has to complete R&M work of PSS till end of December 2014,
but R&M work of not a single PSS completed in all respect till date.
(A) The firm has committed following regarding completion of 11 KV Line
as detailed below.
(i) December 2014- 40 KM
(ii) January 2015-

77 KM

(iii) February 2015- 80 KM


Balance 53 Km of 11 KV Line will be completed after finalizing the land
for new PSS and getting railway crossing clearance.
(B) The firm has committed following regarding completion of 33 KV Line
as detailed below.
(i) January 2015-

7.5 KM

Balance 73.95 Km of 33 KV Line will be completed after finalizing the


land for new PSS and getting railway crossing clearance.
(C ) The firm has committed following regarding completion of R&M work
(i) December 2014- 4 Nos.
(ii) January 2015(iii) February 2015(iv) March 2015-

15 Nos.
15 Nos.
5 Nos

3. Districts: Bhagalpur,Banka&Munger NIT NO: 207 (M/s Bajaj


Electricals Limited: Mumbai )
The firm has to complete R&M work of PSS till end of December, but R&M
work of not a single PSS completed in all respect till date. No
stringing work has been started in 11 KV & 33 KV line till date.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Target date for completion of new 33/11 KV Shankarpur PSS is 31 st march


2015
(A) The firm has committed following regarding completion of 11 KV Line
as detailed below.
(i)

December 2014- 17 KM

(ii) January 2015(iii) February 2015-

87 KM
122 KM

4. Districts:Bhojpur&Buxar NIT NO: 205(M/s Bajaj Electricals


Limited: Mumbai)
The firm has to complete all R&M work of PSS till end of December, but
R&M work of not a single PSS completed in all respect till date. No
stringing work has been started in 11 KV & 33 KV line till date.
Target date for completion of new 33/11 KV Pratapsagar PSS is
31.05.2015
(A) The firm has committed following regarding completion of 33 KV Line
as detailed below.
(i) January 2015(ii) February 2015-

5.63 KM
43.37 KM

(B) The firm has committed following regarding completion of 11 KV Line


as detailed below.
(i)

December 2014- 26.5 KM

(ii) January 2015(iii) February 2015-

36.12 KM
25.47 KM

5.Districts:Patna& Nalanda NIT NO: 206 (M/s East India


Udyoglimited,Ghaziabad )
The firm has to complete all R&M work of PSS till end of December, but
R&M work of not a single PSS completed in all respect till date.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Target date for completion of new 33/11 KV Parsa Bazar PSS is


31.03.2015
(A)The firm has committed following regarding completion of 33 KV Line
as detailed below.
(i) December 2014 10 KM
(ii) January 2015-

19.5 KM

(B) The firm has committed following regarding completion of 11 KV Line


as detailed below.
(i)

December 2014- 16 KM

(ii) January 2015(iii) February 2015-

50.25 KM
63.1 KM

(C ) the firm has committed following regarding completion of R&M work


(i) December 2014- 12 Nos.
(ii) January 2015-

36 Nos.

6.Districts: Arwal& Aurangabad NIT NO: 203 (M/s Supreme & co.UtkalGlavanizers JV Kolkata)
The firm has to complete all R&M work of PSS till end of December, but
R&M work of not a single PSS completed in all respect till date. No
stringing work has been started in 11 KV & 33 KV line till date.
Matching materials for R&M and new 11 KV & 33 KV line is not
present at site.
Target date for completion of new 33/11 KV GT Road PSS is 31 st march
2015
The firm has committed for completion of 11 KV Line as detailed below.
(i)

December 2014- 17 KM

(ii) January 2015(iii) February 2015-

87 KM
122 KM

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

7. Districts: Lakhisarai,Jamui&Sheikhpura NIT NO: 208 (M/s


Techno Fab gamon Joint Ventures Limited: New Delhi)
The firm has to complete all R&M work of PSS till end of December, but
R&M work of not a single PSS completed in all respect till date. No
stringing work has been started in 11 KV & 33 KV line till date.
Target date for completion of new 33/11 KV Parsa Bazar PSS is
31.04.2015
(A)The firm has committed for completion of 33 KV Line as detailed
below.
(i) December 2014 07 KM
(ii) January 2015(iii) February 2015 (iv) March 2015(v) April 2015-

13 KM
20 KM
20 KM
30 KM

(B) The firm has committed following regarding completion of 11 KV Line


as detailed below..
(i)

December 2014- 15 KM

(ii) January 2015(iii) February 2015(iv) March 2015(v) April 2015-

30 KM
40KM
40 KM
62 KM

(C ) The firm has committed following regarding completion of R&M work


related to PSS
(i) December 2014- 09 Nos.
(ii) January 2015-

8 Nos.

(iii) February 2015- 9 Nos.


Memo No:Date:Copy forwarded to M/s Feedback infra Pvt. Ltd, M/s GKC-APL Joint Venture,Survey
Nos. 9(P), CII Green Building Lane, Hitech City, Kondapur, Hyderabad- 500084, M/s.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
SHIRDI SAI ELECTRICALS LIMITED, 13/82, INDUSTRIALESTATE,KADAPA- 516004,
M/s Vijai Electricals Ltd. 6-3-648/1&2, off Rajbhavan Road, Somajiguda,
Hyderabad-500082, Andhra Pradesh, M/s Supreme & Co. Pvt. Ltd.-M/S Utkal
Galvanizers Ltd. Joint Venture,53,Justic Chandra,Madhav Road,Kolkata20,M/s East IndaiUdyog Ltd. 145,G.T.Road,Sahbabad,Ghaziabad ,
Pinth
201005,Uttar Pradesh, M/s Bajaj electricals Limited, 801,10 Floor Rustomjee
Aspire, 801,10th Floor Rustomjee Aspire, Bhanu Shankar YagnikMarg, Off eastern
express highway, ion (E),Mumbai-400022,
M/s
Technofab-Gammon
Joint
Venture, 507, Eros Apartments, 56, Nehru Place, New Delhi-110019, M/s. Sri
Gopikrishna Infrastructure Pvt. Ltd.Corporate Office: 30/B (8-3-191/162),
Vengalrao Nagar, Hyderabad- 500038, M/s SUPREME VPIL (JV),Ecospace
Business Park, Action Area-II, Building Nos.2A, 5th Floor, Unit Nos.501B, New Town,
Rajarhat, Kolkata-700156,for information & necessary action.
(N.K.P. Sinha)
Director(Project)
Memo nos.
Date:Copy forwarded to Electrical Superintending Engineer, Special Plan
(BRGF)/EEE, Special Plan (BRGF)/AEE, Special Plan (BRGF)/AO, Special Plan (BRGF),
SBPDCL, for information and necessary action.
(N.K.P. Sinha)
Director(Project)
Memo No:Date:Copy forwarded to OSD to MD, SBPDCL, Patna for information.
(N.K.P. Sinha)

Director(Project)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Minutes of meeting of Special Plan (BRGF) Scheme held


on 31.03.2015 under the chairmanship of Managing
Director, SBPDCL
1. Districts: Gaya,Nawada&Jehanabad NIT NO: 196 (M/s GKC -APL joint
venture,Hydrabad)
(i) The firm raised the issue regarding civil estimation for cable trench in some
of Exiting PSS in Gaya Districts.EEE (Project), Gaya committed that civil
estimation will be made available to firm up to 5th April-2015.
(ii) The firm requested to clarify rates for construction of New Control room to
be constructed under R&M head under BRGF Scheme. MD, SBPDCL directed
to carry out the above said as per approved rate of BSPHCL. Civil as well as
electrical estimation is already circulates to all turnkey agencies of BRGF
Phase-I and all ESE/all EEE (Project).
(iii) The firm raised issue regarding non-utilization of procured VCBs.EEE
(Project),Gaya/Jehanabad/Nawada has been directed to finalize the scope
of VCB.
(iv) Details of target given to agency is as below:(a) New PSS at Majhwe&Mayabigha, Nawada District May2015
(b)New PSS at Dakshini, Jehanabad,Jehanabad District-April-2015
(c) 33 KV line 48 Ckm in May 2015.
(d) 11 KV line 42.42 Ckm in April 2015&133.96 Ckm in May 2015.
(e) R&M of PSS- 15nos. PSSup to 15th April 2015& balance 24 nos. PSS up to 24 th
May-2015(Expect work associated with extension
of existing control
room/construction of new control room at existing PSS).

2. Districts: Arwal& Aurangabad NIT NO: 203 (M/s Supreme &


co.-UtkalGlavanizers JV Kolkata)
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
I.
II.
III.
IV.
V.
(a)

Managing Director was disappointed on slow progress of work & directed


to issue notice to firm for slow progress.
The firm has committed for completion of R&M Works for existing PSS by
end of April 2015 except work allotted for extension of existing control
room and construction of new control room required.
MD, SBPDCL directed the EEE (Project), Arwal& Aurangabad to regularly
monitor the progress of work as per target committed by agency.
EEE (Project), Aurangabad raised issue of non-compliances of 24 nos. of
SOR to agency. Agency committed to submit all compliance report by 8 th of
April2015 after rectification
Details of target given to agency areas below:New PSS at GT Road ,BIADA,Aurangabad -April-2015

(b)33 KV line 60Ckm in April 2015.


(c) 11 KV line 42Ckm in April 2015.
(d) R&M of PSS- 18nos. in April 2015. (Expect work associated with
extension
of existing control room/construction of new control room at existing
PSS).

3.Districts:Rohtas&Kaimur

NIT NO: 204 (M/s Vijai Electricals

Limited Hyderabad)
(i).M/S Vijai Electricals Limited, Hyderabad was directed to rectify discrepancies observed
in newly
installed VCB at Bada,Takiya&Bikramganj PSS under R&M work by 05 th
April, 2015 & rectify all issues
raised during inspection of sites by EEE(Project)
th
Rohtas/ Kaimur up to 10 April, 2015.

(ii) Managing Director instructed to clear payment of all pending bills of M/s Vijai Electricals ltd up
to 06th April, 2015
(iii) MD, SBPDCL directed to ESE (Project-I) to personally monitor the issue of land availability at
New PSS S.P. Jain &Agrair.
(iv)Details of target given to agency is as below:(a) R&M of PSS- 39Nos existing PSS by end of April, 2015. (Expect work
associated with extension
of existing control room/construction of new
control room at existing PSS).
(b) 33 KV line 35CKm by 31st April, 2015 and 75% Pole pitching will be
completed in April2015
(c)11 KV line 120 Ckm by 31st April, 2015.

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

4.Districts:Bhojpur &Buxar NIT NO: 205(M/s Bajaj Electricals


Limited: Mumbai)
(i)Details of target given to agency is as below:(a) 11 KV line 56 CKmin April, 2015& rest will be completed in May 2015.
(b) 33 KV line-Completed in all respect 15 May 2015.
(c) R & M of PSS-24 nos. Existing PSS by 10th April-2015(Expect work
associated with extension
of existing control room/construction of new
control room at existing PSS).
(d) New PSS Pratapsagar-May 2015.
5.

Districts:Patna& Nalanda NIT NO: 206 (M/s East India


UdyogLimited,Ghaziabad )
(i)

Details of target given to agency is as below:-

(a) R&M of PSS- 48 nos. by end of April, 2015 except extension work.
(b) New PSS Parsa Bazar, Patna up to end of April, 2015

6.

Districts: Bhagalpur,Banka&Munger NIT NO: 207 (M/s Bajaj


Electricals Limited: Mumbai )

(i) EEE (Project), Bhagalpur/Banka raised issue of non-proper installation of AB Switch


under R&M
work. Agency committed to rectify this issue.
(ii)It was instructed to EEE (Project), Bhagalpur/ Banka/Munger to made available
civil estimate for

extension of control room under R&M head.

(iii) Details of target given to agency is as below:(a) R&M of PSS- Completion of total work by end of April,2015.
(b) New PSSShankarpur PSS by April 2015 & Nehru Colony PSS, Banka by May
2015.

7. Districts: Lakhisarai,Jamui&Sheikhpura NIT NO: 208 (M/s


Techno Fab Gammon Joint Ventures Limited: New Delhi)
(i)Required quantity of Pole is more than LOA Quantity. ESE (Project-I) is
directed to visit
Jamui,Shekhpura&Lakhisarai and resolve the issue.
(ii)Firm has informed that station transformer is not available at 33/11 KV PSS
Katari,Berma and
onama. MD, SBPDCL directed to EEE (Project) to
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
complete the work with the help of supply
unit.Target date for the work in
th
10 April 2015.
(iii)ACDB & DCDB is also not available at 33/11 KV PSS
Katari,Berma&Onama,MD,SBPDCL directed to allow ACDB & DCDB for those
PSS though variation Committee.
(iv) Details of target given to agency are as below:(a)R&M of PSS- 11 nos. by end of April,2015 and remaining 15 nos. up to
May,2015.
(b)11 KV line 60Ckm by end of April2015, 90Ckm in May 2015 & rest in June 2015
(c)33 KV line - 45Ckm by end of April2015.
(d)New PSS Khairma up to end of May 2015.

8. Turnkey Contractors of BRGF Phase-II raise issue for overlapping of work with other
ongoing Project.MD directed to call co-ordination meeting of EEE (Supply),EEE
(Project),Agencies district wise and resolve issue up to 10th April 2015.
9. M/S Feedback Infra Pvt. Ltd., Gurgaon
(i) EEE (Project), Arwal/Banka/Sheikhpura raised issue of non-deployment of
district co-ordinator at their respective sites.EEE(Project),Nalanda has
informed that appointed district Co-ordinator is not available at Nalanda.
District Co-ordinator at Gaya District is under notice period. It was directed
to M/s Feedback Infra to ensure availability of district co-ordinatior at all
these sites by 10th April, 2015.
(ii) It was directed to M/S Feedback Infra to e-mail progress reports to
concerned agency and EEE (Projects) one day before scheduled meeting to
avoid any ambiguity during meeting.
(iii) Also it was instructed to M/S Feedback to include all targets& date of
completion decided during PPT presentation of next scheduled meeting.

(N.K.P.Sinha)
Director(Project)
Memo nos.
Date:Copy forwarded to M/s Feedback infra Pvt. Ltd, M/s GKC-APL Joint
Venture,Survey Nos.
9(P), CII Green Building Lane, Hitech City, Kondapur,
Hyderabad- 500084, M/s. SHIRDI SAI ELECTRICALS LIMITED, 13/82,
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
INDUSTRIALESTATE,KADAPA- 516004, M/s Vijai Electricals Ltd. 6-3-648/1&2, off
Rajbhavan Road, Somajiguda, Hyderabad-500082, Andhra Pradesh, M/s Supreme &
Co. Pvt. Ltd.-M/S Utkal Galvanizers Ltd. Joint Venture,53,Justic
Chandra,Madhav
Road,Kolkata-20,M/s
East
IndaiUdyog
Ltd.
145,G.T.Road,Sahbabad,Ghaziabad ,
Pin-201005,Uttar Pradesh, M/s Bajaj
electricals Limited, 801,10th Floor Rustomjee Aspire, 801,10 th Floor Rustomjee
Aspire, Bhanu Shankar YagnikMarg, Off eastern express highway, ion (E),Mumbai400022,
M/s Technofab-Gammon Joint Venture, 507, Eros Apartments, 56,
Nehru Place, New Delhi-110019, M/s. Sri Gopikrishna Infrastructure Pvt.
Ltd.Corporate Office: 30/B (8-3-191/162), Vengalrao Nagar, Hyderabad- 500038, M/s
SUPREME VPIL (JV),Ecospace Business Park, Action Area-II, Building Nos.2A, 5th
Floor, Unit Nos.501B, New Town, Rajarhat, Kolkata-700156,for information &
necessary action.

(N.K.P.Sinha)
Director(Project)

Memo no:Date:Copy forwarded to all Electrical Superintending Engineer, Electric Supply


Circle/all EEE (Project), for information and needful action.
(N.K.P.Sinha)
Director(Project)
Memo No: Date:Copy forwarded to Director (Project), SBPDCL, Patna for information.
(N.K.P.Sinha)
Director(Project)
Memo No: Date:Copy forwarded to OSD to MD, SBPDCL, Patna for information.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
(N.K.P.Sinha)
Director(Project)

Minutes of meeting of Special Plan (BRGF) Scheme held


on 17.04.2015 under the chairmanship of Managing
Director, SBPDCL
1. Districts: Gaya,Nawada & Jehanabad NIT NO: 196 (M/s GKC -APL joint
venture,Hydrabad)
(i)Details of target given to agency are as follows:(a)

New PSS- Dakshini Jehanabad : 15th May,2015


Mayabigha, Nawada : 31st May, 2015
Majhwe, Nawada
: 31st May, 2015
(b) 33 KV line 12 Ckm. stringing & erection of 551 nos. of rail
poles up to 30th April, 2015.
(c) 11 KV line 20 Ckm. Stringing & erection of 351 nos. rail pole &
352 nos. PSC pole up to 30th April, 2015.
(d)R&M of PSS- R&M work of all PSS by 15th May in all respect.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

2. Districts: Arwal& Aurangabad NIT NO: 203(M/s Supreme & co.-Utkal


Glavanizers JV Kolkata)
(i)MD SBPDCL instructed to issue Show- Cause notice to all
concerned SBPDCL officer
for delay in marking layout for
construction of new control room & extension of existing control
room and also directed to complete work of layout marking within
seven days i.e. before 24.04.2015
(ii)Agency committed to achieve target given for 33 KV & 11 KV line
during last MD meeting held on 31.03.2015.
Details of target given to agency are as follows:(a) New PSS: - To complete work in all respect by end of April, 2015.
(b) 33 KV line: - To complete stringing of 60 Ckm line till end of
April, 2015 and balance stringing work to be completed by end
of May, 2015.
(c) 11 KV line To complete 42 Ckm. stringing of line till end of
April, 2015.
(d) R&M of PSS- To complete R&M work of electrical works of
switchyard of 11 nos. PSS by end of April, 2015.

3. Districts:Rohtas&Kaimur NIT NO: 204 (M/s Vijai Electricals


Limited Hyderabad)
(i) MD, SBPDCL instructed to CE (Civil) to check all civil estimates
related to extension of control room of R&M work by 21.04.2015.
(ii) Agency was directed to submit compliance of 40 nos. of
pending SOR within a week. EEE/Project will report the matter to
H.Q. regarding its compliance.
(iii) Details of target given to agency are as follows:(a) R&M of PSS- To complete R&M work of 26 nos. PSS till end of
April, 2015 and
Rest by 10th May, 2015.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

(b) 33 KV line To complete erection of 737 nos. rail poles and 15


Ckm stringing work till end of April, 2015.
(c) 11 KV line To complete stringing of 120 Ckm line.
4.Districts: Bhojpur &Buxar NIT NO: 205(M/s Bajaj Electricals
Limited: Mumbai)
(i)Details of target given to agency are as follows:
(a) 33 KV line- To complete erection of all 1340 nos. poles and
stringing of 72 Ckm.
line up to 15 th May,2015.
(b) 11 KV line Stringing of 56 ckm. line to be completed up to
April,2015 and
balance 42 Ckm line will be completed in May, 2015
(c) R & M of PSS- All 24 nos. PSS to be handed over by end of
April, 2015.
(d) New PSS (Pratapsagar)- To be completed in all respect by
May,2015.
5. Districts:Patna& Nalanda NIT NO: 206 (M/s East India Udyog
Limited,Ghaziabad )
(i) MD, SBPDCL directed to collect all details regarding issues
related to NHAI and get it resolved.
(ii) Details of target given to agency are as follows:(a) R&M of PSS- To complete R&M work of 20 nos. PSS by April
2015, 15 nos. by May, 2015 and balance work up to June, 2015.
(b) 33 KV Line: - To erect 660 nos. rail poles and stringing of 23.3
CKm line by April, 2015 and stringing of balance line by end of
May, 2015.
(c) 11 KV Line: - To erect 1183 nos. poles and 44.27 Ckm. stringing
by April, 2015.
(d) New PSS Parsabazar new PSS to be completed in all respect by
15th May, 2015.

6.

Districts: Bhagalpur,Banka&Munger NIT NO: 207 (M/s Bajaj


Electricals Limited: Mumbai )
(i) MD, SBPDCL directed ESE/Bhagalpur & ESE/Munger &
EEE(projects) to submit estimate of civil work to CE (Civil) up to
20th Apr, 2015.CE (Civil) will give approval by 24 th April, 2015.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

(ii) MD, SBPDCL instructed to resolve issue of railway line


crossing by 10th May, 2015. EEE(Project) and agency will ensure
it.
(Iii) Details of target given to agency are as follows:(a) R&M of PSS- To complete R&M work of 09 nos. PSS by 30 th April
2015 and
balance work up to 31st May, 2015.
(b) New PSS Shankarpur PSS by 15th May, 2015 & Nehru Colony
PSS, Banka by 15th
June, 2015.
(c) 33 KV Line- To erect 578 nos. rail poles by end of April, 2015.
(d) 11 KV Line- To achieve 58 Ckm. stringing by end of April,
2015.

7. Districts: Lakhisarai,Jamui&Sheikhpura NIT NO: 208 (M/s


Techno Fab Gammon Joint Ventures Limited: New Delhi) .
(i) MD, SBPDCL instructed to make available battery & battery
charger to agency. ESE/Munger will ensure it.
(ii MD, SBPDCL directed to provide layout for construction of new
control room & extension of control room at Jamui by 18 th April, 2015
and at Lakhisarai & Sheikhpura by 20th April, 2015. Agency was
directed to start work immediately after layout.
(iv) Details of target given to agency are as follows:(a) R&M of PSS-.R&M work of 11 nos. of PSS must be completed in
April, 2015.
(b) 11 KV line Erection of 2087 nos. poles and stringing of 60 Ckm.
line is to be completed by end of April, 2015.
(c) 33 KV line Erection of 1433 nos. rail poles and stringing of 35
Ckm. line is to be completed by end of April, 2015.
(d)New PSS To complete by end of May, 2015.
8. Districts: Nalanda, Nawada & Banka NIT NO: 02 (M/S
Gopikrishna Infrastructure Pvt Ltd.)

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

(i) MD, SBPDCL directed to finalize the scope of work of Nalanda


district. If scope is not available then to transfer it to Nawada & Banka
districts.
(ii) Agency requested for 25 nos. DT in Nalanda and 25 nos. DT in
Nawada district on loan basis. E.S.E, E.S.C Biharshariff was directed to
make available distribution transformer on loan basis and all 50
distribution transformers to be energised by April, 2015.
(iii)Agency was directed to accelerate works and meet target as per
approved BAR CHART/PERT Network till end of May, 2015.Weekly
progress to be monitored & work should be expedited to match with
approved BAR chart/PERT network.
(iv) Details of target given to agency are as follows:(a) 33 KV Line- To achieve 05 Ckm stringing by April, 2015 end.
(b ) 11 KV Line- To achieve 10 Ckm. Stringing of Dog conductor,, 10
Ckm of rabbit conductor and 25 Ckm of Weasel conductor by
April,2015 end.
9. Districts: Patna & Bhojpur NIT NO: 03 (M/s Supreme-VPIL JV.)
(I)MD, SBPDCL expressed displeasure about slow progress in both
districts and directed to issue notice to agency to improve their work
& match with approved BAR chart/ PERT network in next three
weeks or else their BG of mobilization advance will be invoked.
(ii)It was directed to agency by the MD, SBPDCL to submit detail plan
for supply & erection for Patna & Bhojpur districts separately on weekly
basis.
(iii) Details of target given to agency are as follows:(a)

33 KV Line- To achieve 15 Ckm stringing.

10. Districts: Gaya & Rohtas NIT NO: 04 (M/s Shirdi Sai
Electricals Ltd. Hyderabed.
(i) Work progress of firm is very unsatisfactory and MD, SBPDCL
directed to issue notice to agency to improve their work & match with
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

approved BAR chart/PERT network in next three weeks or else their BG


of mobilization advance will be invoked.
(ii) Details of target given to agency are as follows:(a) 33 KV Line- 10 Ckm stringing by April, 2015.
(b) 11 KV Line- To erect 2198 nos. pole by end of April, 2015 and
stringing of 24.2 Ckm by end of April, 2015.
(c) LT Line- To achieve 100 Ckm. stringing by end of April, 2015.
(d) R&M of DSS- To complete R&M of 200 nos. DSS by end of April,
2015.
11. A notice may be issued to all three agencies of BRGF Phase-II to
submit load flow analysis by 15 May, 2015.The work of all three agencies
will be monitored weekly for upto three weeks and if progress is not
found satisfactory, BG to be invoked against mobilization advance
12. The progress of BRGF project will be reviewed by MD, SBPDCL on
every Tuesday and the progress of work will be monitored as per the
given target of the month. The agency should show progress of work
accordingly.
13. MD, SBPDCL directed that in future awards of works the agency will
have to open separate account for mobilization advance provided to
them & monthly utilization of accounting to be done.
14.MD,SBPDCL instructed to complete the layout work of new control
room building & extension work within a week under R&M of PSS work
for BRGF phase-I project. Also the construction work should start
immediately. The SBD documents also to be checked & this clause to be
inserted.
15. CE (Civil) will ensure that all pending estimates for approval are
cleared.

(N.K.P.Sinha)
Director (Project)
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
Memo nos.
Date:Copy forwarded to M/s Feedback infra Pvt. Ltd, M/s GKC-APL Joint
Venture,Survey Nos.
9(P), CII Green Building Lane, Hitech City, Kondapur,
Hyderabad- 500084, M/s. SHIRDI SAI ELECTRICALS LIMITED, 13/82,
INDUSTRIALESTATE,KADAPA- 516004, M/s Vijai Electricals Ltd. 6-3-648/1&2, off
Rajbhavan Road, Somajiguda, Hyderabad-500082, Andhra Pradesh, M/s Supreme &
Co. Pvt. Ltd.-M/S Utkal Galvanizers Ltd. Joint Venture,53,Justic
Chandra,Madhav
Road,Kolkata-20,M/s
East
IndaiUdyog
Ltd.
145,G.T.Road,Sahbabad,Ghaziabad ,
Pin-201005,Uttar Pradesh, M/s Bajaj
electricals Limited, 801,10th Floor Rustomjee Aspire, 801,10 th Floor Rustomjee
Aspire, Bhanu Shankar YagnikMarg, Off eastern express highway, ion (E),Mumbai400022,
M/s Technofab-Gammon Joint Venture, 507, Eros Apartments, 56,
Nehru Place, New Delhi-110019, M/s. Sri Gopikrishna Infrastructure Pvt.
Ltd.Corporate Office: 30/B (8-3-191/162), Vengalrao Nagar, Hyderabad- 500038, M/s
SUPREME VPIL (JV),Ecospace Business Park, Action Area-II, Building Nos.2A, 5th
Floor, Unit Nos.501B, New Town, Rajarhat, Kolkata-700156,for information &
necessary action.

(N.K.P.Sinha)
Director (Project)
Memo no:Date:Copy forwarded to all Electrical Superintending Engineer, Electric Supply
Circle/all EEE (Project), for information and needful action.
(N.K.P.Sinha)
Director (Project)
Memo No: Date:Copy forwarded to Director (Project), SBPDCL, Patna for information.
(N.K.P.Sinha)
Director (Project)
Memo No: Date:South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)
Copy forwarded to OSD to MD, SBPDCL, Patna for information.
(N.K.P.Sinha)
Director (Project)

Minutes of the review meeting held by CMD, BSP(H)CL of


all on-going projects under SBPDCL with the working
Agencies, Consultants (PMU/PIU) and officers of field
& HQ on 18.11.2014.
Managing Director reviewed the progress of Special Plan (BRGF)
scheme and found that none of the firm has executed work on
the basis of approved BAR Chart/PERT Network & are lagging
behind the target.
1. Districts: Gaya, Nawada & Jehanabad NIT NO: 196 (M/s GKC -APL joint
venture,Hydrabad)
(i)EEE Jehanabad raised issue of action not being taken by agency for rectification of
improper concreting of poles for which SOR has already been given. MD,
SBPDCL warned agencies that quality shall not be compromised at any cost
anywhere and directed M/s GKC APL JV to resolve issue at priority.
(ii)MD, SBPDCL expressed displeasure for very slow progress and instructed M/s
GKC APL JV to deploy 6-7 new gangs by 22nd May, 2015.
(i)Details of target given to agency are as follows:(b)

New PSS- Dakshini Jehanabad

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

Mayabigha, Nawada : All erection works by 15th


June,2015 and ready to charge by 30th June,2015.
Majhwe, Nawada
: All erection works by 15th
June,2015 and ready to charge by 30th June,2015.
(b) R&M of PSS To complete 28 nos. PSS by 30th May, 2015 and
remaining 11 nos. PSS by 15th June, 2015.
(c) 33 KV Line
(d)11 KV Line2. Districts: Arwal& Aurangabad NIT NO: 203(M/s Supreme & co.-Utkal
Glavanizers JV Kolkata)
(i)EEE Aurangabad raised issue of improper concreting in stay
support and poor workmanship in stringing. MD directed to recheck
concreting of stay supports and to lodge FIR against subcontractors of agency if concreting not found in stay supports.
(iii) Details of target given to agency are as follows:-

(a) New PSS: - To complete GT Road New PSS by 30th May, 2015 and
all associated lines by 15th June, 2015.
(b) 33 KV line: - To complete 70 Ckm. stringing by 31 st May, 2015.
(c) 11 KV line : To complete 50 Ckm. stringing by 31 st May, 2015.
(d) R&M of PSS- To complete 05 nos. PSS in all respect by 30 th
May, 2015 all 18 nos. PSS by 15th June, 2015.

3. Districts:Rohtas&Kaimur NIT NO: 204 (M/s Vijai Electricals


Limited Hyderabad)
(i) EEE Rohtas raised issue of improper grounding of 02 nos.
augmented 10 MVA PTR and 33&11KV VCB. Agency committed to
get it resolved by 23.05.2015.
(ii)EEE Rohtas raised issue of pole tilting in Sanjauli to Bazipur
feeder of 2.87 Ckm length containing 75 poles. Agency committed
to resolve issue by end of May, 2015.

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

(iii)EEE Kaimur raised issue of conductor twisting in Bhabhua Old


to Devimandir feeder of 1.65 Ckm and poor quality of civil work in
new control room .Agency committed to resolve issue.
(iv) Details of target given to agency are as follows:(a) R&M of PSS- To handover 15 nos. PSS by 30 th May, 2015 and
handover of additional 11 nos. PSS by 15 th June, 2015. All 39 nos.
PSS by end of July, 2015.
(b) 33 KV line 15 Ckm. stringing by 30th May, 2015 and
additional 15 Ckm. stringing by 15th June, 2015.
(c) 11 KV line- To complete 113.6 Ckm stringing up to 30 th May
2015 and 143.62 Ckm by 15th June,2015.
4.Districts: Bhojpur &Buxar NIT NO: 205(M/s Bajaj Electricals
Limited: Mumbai)
(i) EEE Bhojpur raised issue of conductor twisting in Bihiya and Piro.
Agency committed to replace conductor.
(i)Details of target given to agency are as follows:
(a) New PSS: - To complete all Electrical & Civil works at
Pratapsagar PSS by 31st May,2015 and redy to charge by 10th
June,2015.
(b) R & M of PSS- 20 nos. PSS by 31 st May,2015 and remaining 04
nos. by 2nd week of June,2015.
(d) 33 KV Line:5. Districts:Patna& Nalanda NIT NO: 206 (M/s East India Udyog
Limited,Ghaziabad )
(i)
(ii) Details of target given to agency are as follows:(a)New PSS: - To complete Parsa Bazar PSS by 31 st May, 2015.
(b)R&M of PSS: - To handover 31 nos. PSS by 31st May, 2015.
(c) 33 KV Line: - To charge Punpun New Pss to Dharayechak feeder
by 05th June,2015 and remaining 33 KV feeders by 30th June,2015.
(d) 11 KV Line: - 26 Ckm. by 31st May, 2015.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

(e) Extension of Control room: - To complete all works by 30 th June,


2015.No request for further extension of date shall be entertained

6.

Districts: Bhagalpur,Banka&Munger NIT NO: 207 (M/s Bajaj


Electricals Limited: Mumbai )
(i)
(ii)

(Iii) Details of target given to agency are as follows:(a) New PSS: - Shankerpur PSS by 15th June, 2015.
Nehru colony PSS by 20th June, 2015.
(b) R&M of PSS: - To handover 10 nos. PSS by 31st May, 2015 and
remaining 08 nos. up to 15th June, 2015.
(c) 33 KV Line- To complete all feeders by June,2015.
(d)11 KV Line:7. Districts: Lakhisarai,Jamui&Sheikhpura NIT NO: 208 (M/s
Techno Fab Gammon Joint Ventures Limited: New Delhi) .
(i)
(ii)
(iv) Details of target given to agency are as follows:(a) New PSS: - To complete Khairma New PSS by 15 th June, 2015.
(b) 11 KV line All 11 KV feeders associated with Khairma PSS by
15th June,2015.
(c) 33 KV line To complete stringing of 34 Ckm. lines by 30 th May
and balance by end of June 2015.
(d)R&M of PSS - To complete R&M of 12 no. PSS by end of this
month
(e) Extension of Control room:- To complete extension of control
room by end of July,2015 and new control room by end of
June,2015.

South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

8. Districts: Nalanda, Nawada & Banka NIT NO: 02 (M/S


Gopikrishna Infrastructure Pvt Ltd.)
(i)
(ii)
(iii)

(iv) Details of target given to agency are as follows:(a) 33 KV Line(b ) 11 KV Line9. Districts: Patna & Bhojpur NIT NO: 03 (M/s Supreme-VPIL JV.)
(I)
(ii)
(iii) Details of target given to agency are as follows:i.

33 KV Line-

10. Districts: Gaya & Rohtas NIT NO: 04 (M/s Shirdi Sai
Electricals Ltd. Hyderabed.
Details of target given to agency are as follows:(a) New PSS: - Matrain
Natwar
(a) 33 KV Line- 15 Ckm.
(b) 11 KV Line- 20 Ckm.
(c )LT Line- 25 Ckm
(d)R&M of DSS
(e) New DTR- 100 KVA:
200 KVA:
(f)R&M of 11 KV: - 50 Ckm.
(g) DT Augmentation: - 63 to 100 KVA:
100 to 200 KVA:
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

(N.K.P.Sinha)
Director (Project)
Memo nos.
Date:Copy forwarded to M/s Feedback infra Pvt. Ltd, M/s GKC-APL Joint
Venture,Survey Nos.
9(P), CII Green Building Lane, Hitech City, Kondapur,
Hyderabad- 500084, M/s. SHIRDI SAI ELECTRICALS LIMITED, 13/82,
INDUSTRIALESTATE,KADAPA- 516004, M/s Vijai Electricals Ltd. 6-3-648/1&2, off
Rajbhavan Road, Somajiguda, Hyderabad-500082, Andhra Pradesh, M/s Supreme &
Co. Pvt. Ltd.-M/S Utkal Galvanizers Ltd. Joint Venture,53,Justic
Chandra,Madhav
Road,Kolkata-20,M/s
East
IndaiUdyog
Ltd.
145,G.T.Road,Sahbabad,Ghaziabad ,
Pin-201005,Uttar Pradesh, M/s Bajaj
electricals Limited, 801,10th Floor Rustomjee Aspire, 801,10 th Floor Rustomjee
Aspire, Bhanu Shankar YagnikMarg, Off eastern express highway, ion (E),Mumbai400022,
M/s Technofab-Gammon Joint Venture, 507, Eros Apartments, 56,
Nehru Place, New Delhi-110019, M/s. Sri Gopikrishna Infrastructure Pvt.
Ltd.Corporate Office: 30/B (8-3-191/162), Vengalrao Nagar, Hyderabad- 500038, M/s
SUPREME VPIL (JV),Ecospace Business Park, Action Area-II, Building Nos.2A, 5th
Floor, Unit Nos.501B, New Town, Rajarhat, Kolkata-700156,for information &
necessary action.

(N.K.P.Sinha)
Director (Project)
Memo no:Date:Copy forwarded to all Electrical Superintending Engineer, Electric Supply
Circle/all EEE (Project), for information and needful action.
(N.K.P.Sinha)
Director (Project)
Memo No: Date:Copy forwarded to Director (Project), SBPDCL, Patna for information.
South Bihar Power Distribution Co. Ltd.; VidyutBhawan, Bailey Road, Patna 21.
E-mail-esebrgf.sbpdcl@gmail.com; Contact Nos. : - 7763814004

SOUTH BIHAR POWER DISTRIBUTION COMPANY LIMITED


Registered Office: VidyutBhawan, Bailey Road, Patna 21.
A Govt. Of Bihar Undertaking
CIN-U40109BR2012SGC018890
(Rural Electrification Department)

(N.K.P.Sinha)
Director (Project)
Memo No: Date:Copy forwarded to OSD to MD, SBPDCL, Patna for information.
(N.K.P.Sinha)
Director (Project)