Professional Documents
Culture Documents
Pursuant to Section 43 (f) of Republic Act No. 9136, otherwise known as the
Electric Power Industry Reform Act of 2001 (EPIRA), Rule 7 and Rule 15 Section
5(a) of its Implementing Rules and Regulations (IRR), the Distribution Services and
Open Access Rules (DSOAR) and Section 20 (b) of Commonwealth Act No. 146, as
amended, the Energy Regulatory Commission (ERC) hereby promulgates the
following Rules for Approval of Regulated Entities’ Capital Expenditure Projects.
ARTICLE I
GENERAL PROVISIONS
1.1 Objectives
1.1.1 To provide the Regulated Entities with a uniform system for filing
applications for the approval of capital expenditure projects;
1.1.2 To ensure that projects are timely, appropriate, necessary and cost-
efficient;
1.1.3 To ensure that proposed capital projects are consistent with the
Distribution Development Plan (DDP), the Philippine Grid Code (PGC),
the Philippine Distribution Code (PDC), and other relevant government
issuances; and
These Rules shall apply to all Regulated Entities, including but not limited to
the following:
High Voltage (HV) Lines A voltage level exceeding 34.5kV up to 230 kV.
Generally, lines on this level are considered either
subtransmission line needed for connection to
transmission network or a primary distribution
circuits that satisfy the (n-1) reliability criterion.
Low Voltage (LV) Lines A voltage level not exceeding 1000 volts.
Generally, lines on this level are radial in
configuration and the (n-1) reliability criteria are not
considered.
Medium Voltage (MV) Lines A voltage level exceeding one (1) kV up to 34.5 kV.
Generally, lines on this level are radial in
configuration and the (n-1) reliability criteria are not
considered.
Philippine Grid Code (PGC) The set of basic rules, requirements, procedures,
and standards to ensure the safe, reliable, secured
and efficient operation, maintenance, and
development of the high-voltage backbone
Transmission System and its related facilities.
ARTICLE II
Regulated Entities’ capital assets are divided into two (2) categories, namely:
(1) regulated distribution assets; and (2) distribution connections assets. The
regulated distribution assets are further divided into two subcategories,
namely (a) distribution plant assets or network assets; and (b) general plant
assets or non-network assets.
Office Supplies - this represents the cost of postage, stationery and all
other office supplies on hand.
Those are facilities which may be bypassed or removed from the network
without affecting any customer except those that are directly connected to it.
The planning periods over which future load growth can be allowed for shall
not exceed the following:
a) Fifteen (15) years for high voltage (HV) lines or subtransmission lines,
substations (excluding transformers), primary distribution circuits and
points of connection to a transmission network;
c) Five (5) years for medium voltage (MV) and low voltage (LV) distribution,
and other network assets.
c) The age of the electrical supply facilities, both at the beginning and the
end of the period. Particular attention must be given to the percentage of
the facilities which are or will be beyond their useful life; and,
a) Safety;
c) Power Quality;
a) Subtransmission Development;
• Acquisition (of TransCo Subtransmission Lines);
• Refurbishment (of acquired TransCo Subtransmission Lines);
and
• Reinforcement (to meet capacity and reliability criteria).
b) Substation Project;
• Uprating (of capacity of existing substation); and
• New (substation in new location).
ARTICLE III
A Regulated Entity shall submit its proposed five (5) year capital expenditure
program in accordance with the prescribed groupings and schedule. The
grouping and schedule is appended as Annex “A” and is hereby made an
integral part of this Rule. Succeeding CAPEX applications shall be filed by
DUs, depending on their groupings, on the first (1st) quarter or third (3rd)
quarter of the year before the start of the next 5-year period CAPEX
application.
A Regulated Entity shall submit to ERC its capital expenditure program for a
period of five (5) years. The periodic filing of these proposed capital
expenditure projects shall be made for review and approval of the ERC.
Proposed capital projects must be categorized in accordance with Article II.
This expenditure program also includes the capital projects that form part of
the system loss reduction program.
The five (5) year capital expenditure program shall be consistent with the five
(5) year rolling DDP submitted by the Regulated Entity to the DOE.
The application for the approval of the five (5) year capital expenditure
program shall be verified by an authorized representative of the Regulated
Entity, which has to present either a Board Resolution or Secretary's
Certificate to show proof of his / her designation as a representative of the
Board of Directors and shall be filed with the ERC together with properly
labeled three (3) hard copies and three (3) electronic copies. The capital
expenditure program shall be accompanied by the following documents:
3.2.1.15 Approval to secure loans sourced from NEA may be filed together
with the CAPEX application.
If a Force Majeure or Fortuitous event, as the case may be, occurs, the
affected Regulated Entity shall seek the ERC’s confirmation of the
implementation of capital expenditure projects arising from such event.
To seek the ERC’s confirmation, the affected Regulated Entity must give the
ERC a Force Majeure or Fortuitous Event Notice within three (3) months from
4
See Annex B – Templates.
the occurrence of the Force Majeure or Fortuitous Event and must specify the
following:
The affected Regulated Entity shall file a formal application within thirty (30)
days from the submission of the Force Majeure or Fortuitous Event Notice
and shall be decided by the ERC within sixty (60) days from the time the
applicant formally offers its evidence. The formal application shall be
supported by documents indicating the following:
a) Project Description;
b) Justifications or Benefits to be delivered;
c) Estimated Project Costs;
d) Project Financing Plan; and
e) Project Schedule.
a) Project Description;
b) Justifications or Benefits to be delivered;
c) Estimated Project Costs;
d) Project Financing Plan; and
e) Project Schedule.
3.5 Unplanned Capital Expenditure
These are expenditure projects that may occur at any given period which may
be resulting from unexpected significant new load that will be connected to the
Distribution System. A Regulated Entity shall file a formal application prior to
the start of implementation of such projects and shall be supported by
documents similar to the usual requirements of network asset capital
expenditures.
These are expenditures that may occur at any given period which may be
resulting from the implementation of national government policies and
initiatives and/or implementation of local government development programs.
A Regulated
Entity shall file a formal application sixty (60) days from the start of
implementation of such projects and shall be supported by documents
indicating the following:
a) Project Description;
b) Justifications or Benefits to be delivered;
c) Estimated Project Costs;
d) Project Financing Plan; and
e) Project Schedule.
ARTICLE IV
Before accepting the application for filing, the ERC’s Docket Section may first
refer applicant or its representative to the appropriate Service of the ERC for a
pre-filing conference to inquire into the completeness of the supporting
documents attached to the application.
The application may be rejected due to non-payment of the required filing fee
as docketing requirement. Rejection of such application is not a bar to the re-
filing of the same with the ERC.
The ERC may conduct an ocular inspection before the hearing without
prejudice to the conduct of additional inspection, if necessary, to verify/clarify
any issue or information pertaining to the proposed capital projects.
During the review and evaluation, the ERC may request additional information
from the Regulated Entity on issues that it requires more clarification
pertaining to their capital expenditure program.
Failure on the part of the Regulated Entity to submit any of the required
detail/information within the prescribed period from receipt of an Order shall
be a ground for the denial of the application.
Any application for the approval of any capital expenditure project shall be
decided by the ERC within ninety (90) days from the time the case was
declared submitted for resolution.
The ERC may refer to the DMC or engage the services of a consultant at a
reasonable cost, in the evaluation of any Capital Projects application
submitted to it for approval. The concerned Regulated Entity shall be charged
an amount equivalent to the expenses incurred by the ERC in engaging the
services of the consultant, and said expenses, shall be recovered by the
concerned Regulated Entity as part of the capital expenditure of the project
being evaluated.
Payment of permit fee shall be on an annual basis. The amount of permit fee
to be paid shall correspond to the estimated cash flow per year of the project.
The first of the series of payments shall be made fifteen (15) days from receipt
of the Decision approving the application. The succeeding annual payments
shall be paid every 15th day of January of the pertinent year.
Should an approved CAPEX project be re-filed for any reason, only the cost
that was not subjected to permit fee shall be paid.
All ECs shall bear the regulatory cost/s associated with the implementation of
this Rules, including but not limited to, cost attendant to the public hearings in
the EC’s localities.
ARTICLE V
A Regulated Entity shall submit the results of the competitive bidding which
shall include proposals and purchase orders, the as-built drawings and bill of
materials and the actual cost incurred in the implementation of the planned
capital expenditure projects not later than the 30th of January of the
succeeding year.
The current DDP shall also be submitted annually not later than the 30 th of
April for monitoring of the planned capital expenditure projects of a Regulated
Entity.
A Regulated Entity must also notify the ERC, in writing, if any expenditure for
a Capital Project forecasted to be undertaken in the five (5) year capital
expenditure program as approved by the ERC, has not been substantially
undertaken within twelve (12) months from the time it was so forecasted to be
undertaken. The written report shall state the reason/s for such deferment and
the updated status of the said deferred capital projects, i.e., if the projects will
be deferred indefinitely or will it be included in the next filing of CAPEX
application.
The ERC may conduct site inspections anytime without notice to the
Regulated Entity to verify and monitor the progress of the proposed capital
projects being implemented. The Regulated Entity shall provide the ERC
inspection team of the project records, documents, any variation order and
relevant reports necessary in the assessment of the capital expenditure
programs undertaken, in accordance with the prescribed format.
ARTICLE VI
FINAL PROVISIONS
Subsequent
No.
Deadline of Filing of
Group of Initial CAPEX
CAPEX Period CAPEX and
(Region) EC Plan Coverage
Submission every 5-years
s
thereafter
CARAGA, 1st Quarter of
18 May 2010 2010 – 2012 3 years
X and X1 2012
rd
3 Quarter of
1 & CAR 11 June 2010 2010 – 2012 3 years
2012
st
1 Quarter of
II 7 July 2010 2010 – 2013 4 years
2013
rd
3 Quarter of
III 14 August 2010 2010 – 2013 4 years
2013
st
1 Quarter of
IV 13 Sept. 2010 2010 – 2014 5 years
2014
rd
3 Quarter of
V 11 Oct. 2010 2010 – 2014 5 years
2014
st
1 Quarter of
VI 10 Nov. 2010 2011 – 2015 5years
2015
rd
3 Quarter of
VII 10 Dec. 2010 2011 – 2015 5 years
2015
st
1 Quarter of
VIII 12 Jan. 2011 2011 – 2016 5 years
2016
ARMM,
3rd Quarter of
IX, XII & 15 Feb. 2011 2011 – 2016 5 years
2016
OFFGRID
Capital projects which have already been included in the applicant’s rate
base, as approved by the ERC, or those that were already filed for evaluation,
or those that were already filed for inclusion in the rate base and presently
being evaluated by the ERC shall be excluded from the application of these
Rules.
Capital projects that are not included in any ERC approved CAPEX projects
but within the initial CAPEX Plan Coverage/Period (such as 3, 4 or 5 years)
shall also be filed within the prescribed deadline.
Any rule or regulation inconsistent with the provisions of these Rules is hereby
repealed and modified accordingly.
6.5 Effectivity
ZENAIDA G. CRUZ-DUCUT
Chairperson
A. NETWORK CAPEX
ANNEXES TEMPLATES
Problem
Description
Project Ideas (Solutions) Classification
Alternative 1
Alternative 2
Alternative 3
:
:
Alternative n
Problem
Description
Project Project System Performance
Alternative Description Without Project With Project
Alternative 1
Alternative 2
Alternative 3
:
:
Alternative n
Problem
Description
Project
Project Description Present Worth
Alternative
Alternative 1
Alternative 2
Alternative 3
:
:
Alternative n
Problem
Description
Project
Project Description NPV B/C IRR
Alternative
Alternative 1
Alternative 2
Alternative 3
:
:
Alternative n
Area to be
Energized
Project
Project Description Present Worth
Alternative
Alternative 1
Alternative 2
Alternative 3
:
:
Alternative n
Investment Funds from Rates Subsidy Requirements
VII. OTHER CAPEX REQUIREMENTS
a. Distribution Transformers
Total
Total
Total
d. Metering Equipment
Total
VIII. PROJECT COST ESTIMATES
Total
Estimated cash-flow / Year (Capital Outlay):
2010 2011 2012 2013 2014