PLATFORM
Engineering
Procurement
Construction
Installation
& Commissioning
Presented by
Mr. Therasap Rattanapat
Concession in Thailand
-Bongkot Field Development (PTTEP)
-Arthit Field Development (PTTEP)
-Erawan Group
-Nang Nuan
-Tantawan
-etc
Drilling Rig
Jack-Up
Tender Rig
Field
Development
Legal and
Contracting
HSE
Schedule and
Planning
Project
Development
Exploration
Drilling
Conceptual
Design
Financing and
Accounting
Detailed
Design
Procurement
Operation
Fabrication
Major
Modification
Load-out,
Transportation,
Installation
Abandonment
Hook-up &
Commissioning
E : Engineering
Engineering Design
Feasibility Study
Conceptual Design
FEED ( Front End Engineering Design)
Detail Engineering
HAZOP
ENGINEERING
Process
Structure
Piping
Mechanical
Electrical
Instrument
42 GA
FSO
E
RT LIN
S EXPO
14
WP4
E
L IN
E L
INE
16
6 C
ON
DE
NS
AT
RISE
KWIN
TO EA
FP
WP3
18
E
L IN
8
1
14
18
WP1
CPP
E
L IN
LIN
LIN
LIN
WP6
QP
WP2
Field
Development
WP5
Riser Platform
(RP)
Wellhead Platform
(WP)
Processing Platform
(PP)
Living Quarter
Platform (LP)
Design condition
Reservoirs
Characteristic of wave
Direction of wind
100 years storm
30 years design life.
80 meters water depth
No seismic.
Receiving facilities
Mercury removal facilities
Gas processing facilities
Condensate processing
facilities
Produced water treatment
and pumping facilities
Glycol
Wellhead
Pipeline
Contactor
Platform
Separator
Wellhead
Platform
Condensate
Stabilization
Wellhead
Platform
FSO
Water
Treatment
QP Facilities Design
Diamond Living Quarters Building
Designed for modular construction with maximaum capacity
of 150 personnel
A Helideck to land a Sikorsky S-61, S-76 or a Eurocopter
EC155 helicopter
Dining/mess facilities designed to accommodate 90
personnel
at one serving
A medical centre
A gymnasium and outdoor recreation facilities (at roof level
just below the Helideck).
A TV/cinema/training room provided to accommodate 80
personnel
QP Facilities Design
TopsideLayout
Three deck levels are envisaged which include a Main
deck, a Mezzanine deck, and a Lower deck.
The LQB shall be installed on the Main deck.
The Central Control Room building will be installed on a
cantilever on the QP.
All other facilities shall be located either on the Mezzanine
deck, Lower deck or in spaces available on the Main Deck.
A single level bridge shall be used to connect the CPP to
the LQ.
QP Facilities Design
Structure Design
Fixed platform 4 legs
Through-leg piles and grouted
annuli
Side-lifting and crane
assisted upending
20 years of sacrificial anodes
FP/T Design
A flare tower, bridge connected to the CPP shall be
provided. The tower will support the flare tips of the HP, LP
and Acid Gas flare systems.
Preliminary flare and dispersion studies have initially set
the bridge length to be 120 m and tower height to be 25 m
above the flare platform deck.
Structure Design
A 3 legged tripod structure
Ungrouted leg piles
15 years of sacrificial anodes
WP Design
3D Design
Approx. weight
(Tons / Each)
6000
15000
QP
Jacket
Topside
800
1500
FP/T
Jacket
Topside
500
500
Bridge (2 bridges)
100
Wellhead ( 6 WH)
Jacket
Topside
1000
1200