Professional Documents
Culture Documents
High Voltage
Electrical Apparatus
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
1|Page
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
2|Page
Contents
SECTION 1 DEFINITIONS .................................................................................................................................................. 11
SECTION 2 TRAINING, AUTHORISATION & DUTIES ......................................................................................................... 16
2.1 TRAINING .............................................................................................................................................................. 16
2.1.2HIGH VOLTAGE OPERATOR ............................................................................................................................. 16
2.1.3AUTHORISED RECIPIENT ................................................................................................................................. 16
2.1.4 AUTHORISED TESTER...................................................................................................................................... 16
2.1.5 AUTHORISED TO ENTER SUBSTATIONS, SWITCHROOMS & TRANSFORMER ENCLOSURES........................... 16
2.1.6 AUTHORISED TO OPERATE A CABLE SPIKING GUN ........................................................................................ 16
2.1.7 RESCUE AND RESUSCITATION ........................................................................................................................ 16
2.2 AUTHORISATION ................................................................................................................................................... 17
2.2.1 AUTHORISATION OF PERSONNEL .................................................................................................................. 17
2.2.2 AUTHORISATION OFFICER .............................................................................................................................. 17
2.2.3 HV SPECIALIST: HIGH VOLTAGE CONTROLLER ............................................................................................... 17
2.2.4 SENIOR HIGH VOLTAGE ELECTRICAL OPERATOR ........................................................................................... 17
2.2.5 HIGH VOLTAGE ELECTRICAL OPERATOR ........................................................................................................ 17
2.2.6 RESTRICTED HIGH VOLTAGE ELECTRICAL OPERATOR .................................................................................... 18
2.2.7 LOW VOLTAGE ELECTRICAL OPERATOR ......................................................................................................... 18
2.2.8 AUTHORISED RECIPIENT................................................................................................................................. 18
2.2.9 AUTHORISED TESTER...................................................................................................................................... 18
2.2.10 AUTHORISATION CERTIFICATES ................................................................................................................... 18
2.3 DUTIES ................................................................................................................................................................... 18
2.3.1 HV SPECIALIST: HIGH VOLTAGE CONTROLLER ............................................................................................... 18
2.3.2 HV SAFETY TRAINING AND COMPLIANCE OFFICER ........................................................................................ 19
2.3.3 SENIOR HIGH VOLTAGE ELECTRICAL OPERATOR ........................................................................................... 19
2.3.4 HIGH VOLTAGE ELECTRICAL OPERATOR ........................................................................................................ 20
2.3.5 RESTRICTED HIGH VOLTAGE ELECTRICAL OPERATOR .................................................................................... 20
2.3.6 LOW VOLTAGE ELECTRICAL OPERATOR ......................................................................................................... 20
2.3.7 AUTHORISED RECIPIENT................................................................................................................................. 20
2.3.8 AUTHORISED TESTER...................................................................................................................................... 20
2.3.9 AUTHORISED TO ENTER SUBSTATIONS, SWITCHROOMS & TRANSFORMER ENCLOSURES........................... 20
2.3.10 PERSON AUTHORISED TO OPERATE A CABLE SPIKING GUN ........................................................................ 20
SECTION 3 ELECTRICAL PERMITS & FORMS .................................................................................................................... 20
3.1 PERMITS AND FORMS IN USE AT BAC ............................................................................................................... 20
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
3|Page
4|Page
5|Page
3.11.18 .................................................................................................................................................................... 33
3.11.19 .................................................................................................................................................................... 33
3.11.20 .................................................................................................................................................................... 33
3.11.21 .................................................................................................................................................................... 33
3.11.22 .................................................................................................................................................................... 33
3.11.24 .................................................................................................................................................................... 33
3.11.25 .................................................................................................................................................................... 33
3.11.26 .................................................................................................................................................................... 33
3.11.27 .................................................................................................................................................................... 33
3.11.28 .................................................................................................................................................................... 33
3.11.29 .................................................................................................................................................................... 34
3.11.30 .................................................................................................................................................................... 34
3.11.31 .................................................................................................................................................................... 34
3.11.32 .................................................................................................................................................................... 34
3.12.1 RE-COMMISSIONING .................................................................................................................................... 34
3.13 PRE COMMISSION CHECK LIST ............................................................................................................................ 35
3.13.1 STANDARD ................................................................................................................................................... 35
3.13.2 PROCEDURE ................................................................................................................................................. 35
SECTION 4 SUBSTATIONS, SWITCHROOMS, TRANSFORMER ENCLOSURES & HV CABLE TUNNELS ............................... 35
4.1 ENTRY .................................................................................................................................................................... 35
4.1.1 AUTHORISED PERSON SUBSTATION ENTRY ................................................................................................... 35
4.1.2 UNAUTHORISED PERSON SUBSTATION ENTRY .............................................................................................. 35
4.1.4 NOTIFICATION OF VISIT .................................................................................................................................. 35
4.1.5 DURATION OF VISIT........................................................................................................................................ 35
4.1.6 REQUIREMENTS ............................................................................................................................................. 35
4.1.7 WORKING IN A SUBSTATION, SWITCHROOM, TX ENCLOSURE or HV CABLE TUNNEL .................................. 36
4.1.8 VISITING A SUBSTATION, SWITCHROOM OR TX ENCLOSURE OR HV CABLE TUNNEL ................................... 36
4.2 MINIMUM PPE AND CLOTHING REQUIREMENTS ................................................................................................. 36
4.2.1 PURPOSE ........................................................................................................................................................ 36
4.2.2 GENERAL ........................................................................................................................................................ 36
4.2.3 CLOTHING REQUIREMENTS............................................................................................................................ 37
4.2.4 PERSONNEL NOT UNDERTAKING WORK (VISITING) ...................................................................................... 37
4.2.5 PERSONNEL UNDERTAKING WORK (OTHER THAN ELECTRICAL) ................................................................... 37
4.2.6 PERSONNEL UNDERTAKING ELECTRICAL WORK ............................................................................................ 37
4.2.7 PERSONNEL CARRYING OUT ELECTRICAL SWITCHING OPERATIONS ............................................................. 37
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
6|Page
7|Page
TABLE 4.................................................................................................................................................................... 44
4.7 ELECTRICAL POWER SYSTEM ACCESS........................................................................................................................ 44
4.7.1 GENERAL ........................................................................................................................................................ 44
4.7.2 PLANNED WORK............................................................................................................................................. 44
4.7.3 UNPLANNED (EMERGENCY) WORK................................................................................................................ 45
4.8 SUBSTATION MAINTENANCE, INSPECTIONS & AUDITING ........................................................................................ 45
4.8.1 GENERAL ........................................................................................................................................................ 45
4.8.2 MAINTENANCE ............................................................................................................................................... 45
4.8.3 INSPECTION .................................................................................................................................................... 45
4.8.4 SIX MONTHLY INSPECTIONS ........................................................................................................................... 45
4.8.5 AUDITING ....................................................................................................................................................... 46
4.9 HIGH ENERGY LOW VOLTAGE ................................................................................................................................... 46
4.9.1 GENERAL ........................................................................................................................................................ 46
4.9.2 PLANNING & RISK ASSESSMENT .................................................................................................................... 46
4.9.3 WORK ON LIVE SWITCHBOARDS .................................................................................................................... 47
4.9.4 WORK ON DE-ENERGISED SWITCHBOARDS ................................................................................................... 47
4.9.5 LIVE TESTING .................................................................................................................................................. 47
4.10 ELECTRICAL HAZARDS ............................................................................................................................................. 47
4.11 SECURITY ................................................................................................................................................................. 48
4.11.1 KEYS .............................................................................................................................................................. 48
4.11.2 WORK IN SUBSTATIONS, SWITCHROOMS & TRANSFORMER ENCLOSURES ................................................ 48
SECTION 5 SWITCHING OPERATIONS.............................................................................................................................. 48
5.1 SAFE OPERATING IN SUBSTATIONS....................................................................................................................... 48
5.1.1 INTRODUCTION .............................................................................................................................................. 48
5.1.2 PRINCIPLES ..................................................................................................................................................... 49
5.1.3 COMMUNICATION ............................................................................................................................................. 49
5.1.3.1 PURPOSE ..................................................................................................................................................... 49
5.1.3.2 GENERAL ..................................................................................................................................................... 49
5.1.3.3 REQUIREMENTS OF HV CONTROLLERS AND OPERATORS .......................................................................... 49
5.1.4 ELECTRICAL OPERATOR SAFETY & OPERATIONAL EQUIPMENT ............................................................................ 50
5.1.4.1 PURPOSE ..................................................................................................................................................... 50
5.1.4.2 CARE OF EQUIPMENT.................................................................................................................................. 50
5.1.4.3 STORAGE ..................................................................................................................................................... 51
5.1.5 INSPECTION PRIOR TO USE .................................................................................................................................... 51
5.1.5.1 GLOVES........................................................................................................................................................ 51
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
8|Page
9|Page
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
10 | P a g e
11 | P a g e
definition of isolated.
Competent
Having the skills, knowledge and attributes a person needs to complete a task.
Conductor a wire
Cable or form of metal designed for carrying electrical current.
De-energised
Not connected to any source of electrical supply but not necessarily isolated.
Discharged
Having been connected to the general mass of earth in such a manner as to remove
any residual energy in a conductor.
Directed
Do achieve a desired result.
EAP
Electrical Access Permit
Earthed
Directly connected to the general mass of earth so as to ensure and maintain
The effective dissipation of electrical energy.
Earthing Device
An approved device used for the earthing of conductors.
Electrical Apparatus
Any electrical equipment, including overhead lines and underground cables, the
conductors of which are live or can be made live.
Energised
Connected to a source of electrical supply (see live).
Exposed Conductor
An electrical conductor, approach to which is not prevented by a BAL Basic Level of
Insulation of rigid material or by a Fixed and Earthed Barrier
High Voltage
A nominal voltage exceeding 1000V AC or exceeding 1500V DC.
HV High Voltage Safe Access Procedures
Procedures in place incorporating the Electrical Safety Act and Regulation Qld 2002 and
work in or near Live Parts Code Of Practice 2010
High Voltage Customer
Any user of electricity connected at high voltage to the Electrical Power System.
High Energy Low Voltage
Shall be taken to mean any main switch board directly fed from a distribution
transformer, or any LV interconnectors.
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
12 | P a g e
Instructed Person
A person adequately advised or supervised by an authorised person to enable them in High Voltage
enclosures ie HV Substations.
Insulated Mobile Plant mobile plant
Approved and tested for carrying out work on or near electrical apparatus.
Insulated
Separated from adjoining conducting material by a non-conducting
substance which provides resistance to the passage of current, or to disruptive
discharges through or over the surface of the substance at the operating
voltage, and to mitigate the danger of electric shock or injurious leakage of
current.
Insulating Stick
A stick approved and tested for carrying out operating, earthing on live electrical HV
apparatus.
Isolated
Disconnected from all possible sources of electrical supply by means
that prevent the apparatus from being unintentionally energised and separated by a
distance appropriate to the voltage and the insulating medium and that are assessed
as a suitable step in the Switching Sheet for access purposes.
Live
Energised or subject to hazardous induced or capacitive voltages. i.e. a
potential difference exists.
Live Work
All work performed on components of electrical apparatus not isolated, proved deenergised and earthed.
Low Voltage
A nominal voltage exceeding 50V AC /120V DC but not exceeding
1000V AC/1500V DC.
LV
Low Voltage
Mobile Plant
Cranes, elevating work platforms, tip trucks or similar plant, any
equipment fitted with a jib or boom and any device capable of raising or
lowering a load. Mobile Plant can only be considered as a vehicle when in the
normal travelling mode and not in the working mode when determining safe approach
distances.
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
13 | P a g e
14 | P a g e
The minimum distance that shall be maintained by an Untrained Person as laid out in
the Electrical Safety Regulation Qld 2002 schedule 2.
Safe Approach Distance for Mobile Plant Operated by Ordinary Persons
The minimum distance that shall be maintained between mobile plant (including
its load, controlling ropes and any other accessories) and electrical apparatus,
when such plant is operated by an ordinary person. This safe approach
distance is not associated with performing electrical work on an electricity
network.
Safe Approach Distance for Instructed or Authorised Persons
The minimum distance that shall be maintained by an Instructed or Authorised Person
when performing works that requires that person to approach electrical apparatus. An
appropriate hazard and risk assessment shall be completed for work at these distances.
Safe Approach Distance for Mobile Plant Operated by Instructed or Authorised Persons
The minimum distance that shall be maintained between mobile plant (including its load, controlling
ropes and any other accessories) and electrical apparatus when such plant is operated by an
instructed or authorised person an appropriate hazard and risk assessment shall be completed for
work at these distances. When performing work that requires that person to approach electrical
apparatus at a distance less than the safe approach distance for instructed or authorised persons
defined above.
Safe Approach Distance Special Limit for an Authorised Person Only
The minimum distance that shall be maintained by an Authorised Person when
performing work that requires that person to approach electrical apparatus at a
distance less than the safe approach distance for instructed or authorised persons defined above.
Safety Observer
A person with sufficient knowledge of the task being performed and competent for the duty of
observing and warning against unsafe approach to electrical apparatus.
Testing
TIC
Tester In Charge
Vehicle
A truck (non-tipping), car, utility or other general purpose conveyance
used for the carriage of persons or goods. (See also mobile plant).
Vicinity a situation where it is unlikely that a person, vehicle or mobile plant will,
either directly or through any conducting medium, come within the relevant safe
approach distances.
V/A Authority
To Work in the Vicinity of Electrical Apparatus
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
15 | P a g e
16 | P a g e
immediate treatment of electrical injury shall be prominently displayed in workshops normally used
by electrical personnel, substations, switchrooms, and enclosures throughout the worksites in
general. Electrical rescue kits can be used for the release of victims from both HV and LV apparatus.
Only appropriately trained personnel should use the rescue kits.
2.2 AUTHORISATION
2.2.1 AUTHORISATION OF PERSONNEL
All personnel involved with the operation of, or work upon the electrical power
system controlled by BAC shall hold the appropriate authorisations and permits. These
authorisations shall be subject to the approval and site authorisation of the BAC Electrical Inspector
or their delegate.
2.2.2 AUTHORISATION OFFICER
The Electrical Inspector or an approved delegate will sign all authorisations.
All authorisations shall be reviewed periodically and any authorisations that are no longer required
shall be withdrawn.
2.2.3 HV SPECIALIST: HIGH VOLTAGE CONTROLLER
Before being authorised to perform the duties of the HV controller the person
Shall have appropriate knowledge and skills base required to satisfactorily fulfil a supervisory role
within BAC. This should include appropriate WHS training, have satisfactorily completed an initial HV
electrical operator training course and have a good working knowledge of the Brisbane Airport HV
and LV electrical systems and a comprehensive knowledge of the BAC network and/or; Have been
trained as a HV electrical operator and demonstrated competence in the skills and knowledge
required of a senior HV electrical operator.
2.2.4 SENIOR HIGH VOLTAGE ELECTRICAL OPERATOR
Before being authorised to perform the duties of a senior HV electrical operator, the person shall
have satisfactorily completed an initial HV electrical operator training course and is deemed by the
Electrical Services Asset Manager, to have reached a high level of understanding of the HV and LV
electrical systems to be able to perform the duties of a senior HV electrical operator. This knowledge
shall include, but not be limited to;
Protection philosophies
Awareness of the impact and consequences of any switching
Testing of protection systems
Operation of plant and equipment
Comprehensive knowledge of the Brisbane Airport BAC procedures.
2.2.5 HIGH VOLTAGE ELECTRICAL OPERATOR
Before being authorised to perform the duties of an HV operator the person
shall have satisfactorily completed an initial HV electrical operator training
course and is deemed by the Electrical Services Asset Manager to have reached a level of
understanding of the BAC HV and LV electrical system to perform the duties of an HV electrical
operator.
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
17 | P a g e
18 | P a g e
Ensure all up to date HV electrical drawings are available and displayed in the appropriate
substations, switchrooms and enclosures
Ensure the correct labels are fitted to all electrical apparatus & protection circuits
Approval of all work on, and in the vicinity of, the interconnected HV and LV electrical
system and assets
Approval of all LV work external to the 415V switchrooms that could have
an effect on
a)Loading
b) Essential/ Non-Essential supplies
Ensure all authorised persons and HV operators are advised of all changes to system
conditions and SOPs
Update all SOPs
Control, audit and oversee all HV & LV maintenance under the control of
the AES HV section
Plan all access requirements to the HV & LV system under the control of
the AES HV section
In conjunction with the HV safety training and compliance officer review
and approve any changes to the SAPs on a periodic basis
General security of all HV assets
Assess all HV electrical operators for authorisation
Assess all HV operators for operational authority level increases
Ensure all HV operators & authorised personnel switch & work in a safe
manner as per all HV procedures
Coordinate & facilitate all HV electrical projects & rectify project defects
Approve & plan all system outage
19 | P a g e
20 | P a g e
21 | P a g e
22 | P a g e
The work to be done may require the issuing of one or more of the following permits.
1. Electrical Access Permit (EAP)
2. Test Permit (TP)
3. Authority to work in the vicinity of electrical apparatus (V/A)
4. Personal safety and service clearance
5. Statement of condition of apparatus / plant (SWITCHING SHEET)
3.5.1 PRIOR TO ISSUE EAP
The electrical operator shall consult with the RIC to ensure
Isolations and Earthing performed meet all requirements as per the work
schedule
Barriers meet all safety considerations while allowing the work party to
carry out their work
All other requirements to be listed on the permit will be adequate for the
work to be carried out
All recipients are authorised or placed in the charge of an authorised recipient
3.5.2 AT THE ISSUE OF AN EAP
At the issue of the EAP the electrical operator shall ensure an Authorised Recipient is in attendance
(when possible) at the issue of the permit then clearly and accurately
Describe all the isolations carried out
Describe all earthing carried out
Indicate the position of all work party earths required
Indicate any earths that can be safely removed during the currency of the
Permit i.e. working earths only.
Describe all notes and special requirements listed on the permit
Warn the work party of all adjacent alive apparatus
Indicate any requirements of other permits involved with this permit
Indicate the position of all barriers and signs
Ensure that all isolations and earthing should be shown to the work party where practicable.
23 | P a g e
Can you remain clear of all live apparatus while working under the terms of the permit?
If the answers to the questions are correct, the issue of the permit can proceed.
If any doubt exists both the electrical operator and RIC or TIC shall seek clarification from the HV
controller. The RIC signs on to accept the permit. All members of the work party sign on the permit.
3.5.4 WORK PARTY RESPONSIBILITIES UNDER EAP
The RIC shall ensure
All members of the work party follow the extent of work and safety procedures as detailed
on the permit/s
That no member of the work party approaches or commences work on the apparatus until
instructed by the RIC
All work party earths that are required are applied before work commences
If the permit conditions need to be altered due to the progress of the work the electrical operator is
immediately contacted, work ceases and if the isolations require changing, then the permit is
cancelled and a new one issued or if the permit can be extended without altering the existing
isolations, the electrical operator endorses the permit and re issues it to the work party
The original copy of the permit is retained on site.
All members who sign on the permit sign off the permit
Any member of the work party who temporarily leaves the work site reports back to the RIC
before approaching the apparatus and restarting work
All work party earths and any other earths requested by the operator are removed at the
completion of the work
Any testing is carried out safely and all members of the work party are protected at all times
It is preferable that a detailed verbal report is given to the electrical operator at the
cancellation of the permit after conclusion of all work
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
24 | P a g e
The HV controller shall be satisfied that every effort has been made to locate the absent
recipient/s and that they will not be able to return to the site and approach the apparatus
that was under EAP
The HV controller shall ensure the absent recipient/s are advised that they have been signed
off the EAP
The HV controller shall instruct the RIC, in the presence of the electrical operator, to sign off
for the absent recipient/s
The RIC shall sign his own name at each absent recipient/s cancellation position on the EAP
The RIC shall then sign off the EAP
The electrical operator shall then cancel the EAP
NOTES
1. At any time the HV controller shall be the responsible Authority
3.5.6 CANCELLATION
The electrical operator shall ensure (preferably in conjunction with the RIC that
All personnel who signed on are signed off the relevant permit/s
All work equipment is removed
All barriers and boards are removed
All Personnel Safety and Service Clearance forms are provided
The apparatus is in a serviceable condition
All earths attached by the work party are removed
That the original copy of the permit is signed off
That the duplicate copy (when applicable) of the permit is signed off
The electrical operator shall then sign, print his/her name fill in the day, date and time.
These details shall be recorded in the substation log book
The completed permit/s are forwarded to the HV controllers office
3.5.7 TRANSFER OF EAPs
The existing RIC completes Section .G of the EAP
3.5.7.1 RIC PRESENT AT TRANSFER
The New RIC completes Section .G of the EAP
3.5.7.1.1 A CURRENT RECIPIENT IS TO TAKE OVER THE EAP
The existing RIC signs off in Section .E of the EAP
3.5.4.12 A NEW RIC NOT SIGNED ONTO THE EXISTING EAP IS TO BE SIGNED ON
The existing RIC or HV operator acting with the RIC.S knowledge issues the EAP to the new
Recipient and he signs on the EAP in Section .D ..
The existing RIC completes Section .G of the EAP.
The New RIC completes Section .G of the EAP
The existing RIC signs off in Section .E of the EAP
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
25 | P a g e
26 | P a g e
3.6.6 CANCELLATION
The electrical operator shall cancel the TP.
3.7 ISSUE AND CANCELLATION OF TPs
TPs shall only be issued and cancelled by approved electrical operators authorised in writing
by the AES manager or his / her deputy.
The HV TPs shall be issued when the work to be done requires: Testing of apparatus at
voltages considered to be harmful to humans.
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
27 | P a g e
28 | P a g e
The instructions that the work party shall observe are to be completed
For example
a) Safe approach distances to be observed at all times
b) Hand tools only to be used (e.g. excavation)
c) Everything shall be carried below shoulder height
d) The location of any mobile plant while working
e) The direction of movement of mobile plant while working
f) If a safety observer is required
g) Means of access to the specific area
h) Any other instructions deemed necessary
3.8.1 PRIOR TO ISSUE
The electrical operator shall consult with the recipient to ensure that
The proposed work is the same as stated in the application
The equipment to be used is as stated in the application
The precautions taken will be adequate for the work to be carried out.
The conditions stated on the permit will allow the work to be carried out safely
No electrical equipment or other assets will be damaged while the work is carried out
Safe approach distances to electrical equipment can be maintained
The recipient of the permit will be able to adequately and safely supervise the members of
the work party
3.8.2 SIGNING ON
Before the recipient accepts the V/A the electrical operator will ensure that the recipient
Understands the requirements of the permit
Understands the conditions of the permit.
Is satisfied with the precautions taken
Can maintain safe approach distances to adjacent alive apparatus while working under this
permit.
Can remain clear of other assets while carrying out the work
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
29 | P a g e
Can suitably instruct other members of the work party on the conditions and requirements
of the permit
3.8.3 ISSUE
The V/A shall be signed by the electrical operator at the completion of the issue
3.8.4 ACCEPTANCE
The recipient shall complete the acceptance of the authority including the time and date received
3.8.5 RELINQUISHMENT
The recipient shall complete the relinquishment of the V/A including the time and date relinquished
3.8.6 CANCELLATION
The operator shall cancel the V/A
NOTE:
When a V/A is issued in conjunction with an EAP or SFT, the V/A is issued after the EAP or SFT issue
and cancelled before the EAP or SFT cancellation.
3.9 PERSONNEL SAFETY AND SERVICE CLEARANCE
The following shall be printed clearly and accurately on the clearance form.
3.9.1 PART 1
3.9.2 PART 2
All work party members shall sign onto this clearance when instructed by the person in charge of
construction. The person in charge of construction shall complete the section stating the work still to
be completed, if further work is required before commissioning, including time, day and date.
3.9.3 PART 3
a) The person in charge of construction shall complete this section when all work is completed
including time, day and date.
bi) Completed by the tester in charge after the SFT is cancelled if the testing is satisfactory, including
time, day and date.
bii) Completed by the operator or tester after all on load tests have been satisfactorily completed,
including time, day and date.
c) Completed by the operator after the apparatus is placed into service, including time, day and date.
30 | P a g e
3.10.1 PROCEDURE
NOTE:
The issue and cancellation of all EAPs or SFTs should be recorded
on the bottom section of the SWITCHING SHEET.
3.11 THE USE OF ELECTRICAL PERMITS
3.11.1
All EAPs shall be issued to an RIC and at least one other person who is authorised to receive EAPs
(Authorised Recipient).
3.11.2
An issuer of an EAP shall not be the RIC but may sign on the EAP as a recipient.
3.11.3
An authorised recipient can sign onto an EAP as long as the person;
Understands the electrical apparatus covered by the EAP
Understands the limits of the EAP
Is satisfied with the precautions taken
Is aware of the adjacent alive apparatus
Can remain clear of the adjacent alive apparatus while working under the terms of the EAP
3.11.4
A non authorised person (NAR) may be signed onto an EAP as long as the person understands;
The instructions given on what approach is permitted to the electrical apparatus
The instructions given on what activity is permitted to be taken in relation to the electrical
apparatus
They agree to the continuous and dedicated supervision of a nominated authorised recipient
3.11.5
For electrical work an authorised recipient can only be in direct charge of one non-authorised
recipient and a Recipient in Charge cannot be in direct charge of any non-authorised recipients
3.11.6
For mechanical work an EAP can be issued to an authorised Recipient in Charge on his own who can
be in direct charge of any number of non-authorised recipients. No electrical work or the application
or removal of earths can be performed under any circumstances.
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
31 | P a g e
3.11.7
An EAP can be transferred once to a new RIC.
3.11.8
Access to any apparatus that requires HV isolation shall be carried out under the EAP procedure.
Access to any high Energy Low voltage apparatus shall be carried out under the EAP procedure.
NOTE:
An EAP is not required to change the tap position on an isolated transformer where the tapping
switch is on the side of a transformer with exposed connections or is an external switch on a sealed
transformer.
3.11.9
When more than one EAP is on issue on the same apparatus, then, those documents shall be
cross-referenced.
3.11.10
Amendments to Part A of the EAP can be made providing there is not a requirement to alter existing
isolation points and both the RIC and electrical operator are in agreement that safety is not
compromised. Any amendment requiring a change in an isolation point requires the original permit
to be cancelled and a new EAP to be issued. Any alterations that are required for an SFT shall require
the original SFT to be cancelled and a new SFT to be issued.
3.11.11
Additional recipients can be signed onto an EAP or SFT by the RIC or TIC respectively or by HV
operator acting with their permission.
3.11.12
An EAP can be issued to a single authorised recipient when the recipient is performing a supervisory
role and the EAP on the apparatus is issued as a safety precaution for other work in the vicinity of
that apparatus i.e. mechanical work (See 3.9.6)
Note:
No electrical work can be performed on that apparatus or earths applied or removed.
3.11.13
Any authorised person can recommend to the RIC or TIC that a recipient of an EAP or TP be excluded
from the EAP or TP if that recipient is considered to be acting in an unsafe manner.
3.11.14
Following a temporary cessation of work or an absence from the work site the recipient of an EAP or
TP shall report to the RIC or TIC before approaching the apparatus under EAP or TP.
3.11.15
TPs shall be issued when, for the purposes of testing, it is necessary to work on electrical apparatus
in such a manner that the prescribed procedure relating to an EAP shall be waived in order that the
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
32 | P a g e
electrical apparatus may be made alive at, HV or at a voltage or a current considered hazardous,
from either normal or test sources. (This does not include meggering).
3.11.16
All TPs shall be issued to a TIC and at least one other person who is authorised to receive TPs.
3.11.17
An TP and an EAP shall not be on issue on the same electrical apparatus simultaneously.
3.11.18
Only one TP shall be issued on the same apparatus at any time.
3.11.19
A TP shall not be signed off and reinstated at a later date. When all recipients have signed off, the TP
shall be cancelled by the electrical operator. If an TP is required on the same apparatus at a later
time a new TP shall be issued.
3.11.20
Disconnection and reconnection can be carried out under an TP.
3.11.21
No apparatus will be Hi-Pot Tested on site without an TP.
3.11.22
Non-authorised persons may be signed onto an TP under the supervision of an authorised person.
3.11.23
A TP shall not be transferred.
3.11.24
The same conditions as those that apply to EAPs described above under electrical work shall apply.
3.11.25
A TP cannot be issued to a lone tester or a tester cannot work alone under a TP.
3.11.26
A missing recipient shall be signed off as per the procedure for an EAP.
3.11.27
A V/A is to be issued to a recipient who shall then fully instruct the work group on the task to be
carried out.
3.11.28
A V/A is to consider all safety aspects of the tasks to be performed.
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
33 | P a g e
For example,
Excavation
Use of cranes mobile plant
Limits of approach
Earthing of plant
Notices and barriers
Limiting of access
Use of tools
Any other aspect that influences the safety of the work task shall be considered.
3.11.29
A V/A shall be issued after the issue of an EAP or TP and cancelled before the cancellation of the EAP
or TP.
3.11.30
When a V/A is issued in conjunction with another access authority then both documents shall be
cross-referenced.
3.11.31
A V/A can only be on issue for a maximum of 30 days.
3.11.32
A SWITCHING SHEET/OA shall be issued or received when any isolations and earthing take place at
the points of supply involving an interface with power supply authority.
3.12 OUT OF COMMISSION
HV electrical apparatus may be declared .out of commission when:
Disconnected from all sources of supply by the physical removal of sufficient conductor to
provide a break of a length appropriate to the voltage and the insulating medium and where
applicable, prevented from rotation by a prime mover.
A written statement on an .out of commission form declares that the apparatus is out of
commission. The form is completed by the contractor carrying out the work, given to the HV
operator and forwarded to the HV controller, after the work is completed to establish this
condition, and the EAP or SFT is cancelled. The .out of commission form shall accurately
describe the apparatus, the isolations carried out and the condition of the all the relevant
auxiliary equipment (eg control circuits).
Out of commission apparatus may be approached and worked upon without the issue of an
EAP provided the limits of approach to adjacent
HV apparatus are not infringed during the performance of the work
Any testing of out of commission apparatus that, if that apparatus was in service, would
require the issue of an SFT shall be carried out under an SFT. The apparatus shall be recommissioned and an SFT issued.
The work party is responsible for the correct identification of the out of commission
apparatus.
3.12.1 RE-COMMISSIONING
A HV clearance form shall be raised whenever the out of commission apparatus needs to be
returned to service and the original out of commission form completed in the bottom section.
All HV and Pilot cables shall be capped and sealed in an approved manner.
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
34 | P a g e
These forms shall be completed by the electrical operator prior to activation of the
substation.
The completed forms are to be forwarded to the HV controller.
4.1.6 REQUIREMENTS
The substation shall not, under any circumstances be used as a thoroughfare or storeroom.
All pedestrian exit/entry doors are to be secured in the open position Substation security is
to be maintained at all times
Substation exit/entry doors are to be locked when no one is in attendance At least one
mobile phone is to be on site at all times
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
35 | P a g e
The substation, switchroom or transformer enclosure name, location and building number is
to be noted in case of an emergency
If there is any arcing, strange noise or burning smell noticed the area is to be immediately
evacuated, doors locked closed and the Electrical Inspector immediately notified. In the
absence or unavailability of the Electrical Inspector the on call Electrical person notified.
All work inside/around substations, switchrooms or transformer enclosures that are
designated .security restricted areas require an appropriate ASIC pass which is to be
displayed at all times
Any visitor accompanying an ASIC pass holder shall at all times display an extended visitors
card or visitor pass
If any circuit breaker or switch is accidentally operated the Electrical Inspector shall be
immediately notified. In the absence or unavailability of the Electrical Inspector the on call
Electrical person notified.
The Electrical Inspector the on call Electrical person notified, is to be notified at the end of
each days work and the completion of the task
The substation, transformer enclosure or switchroom is to be left in a clean and tidy
condition at the end of the task and all entry/exit doors locked closed
Switchboards that are not under permit shall not have any liquid cleaning agents applied to
them
No person is to be under the influence of alcohol or drugs
Permission to enter a substation, transformer enclosure or switchroom shall be obtained
from an authorised BAC representative
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
36 | P a g e
37 | P a g e
Additional protective layers of clothing such as overalls, 100% wool jumper or flame
retardant switching coats
Hard hat (AS1800:1998 and AS 1801:1997)
Face Shield, if determined necessary after a risk assessment, when switching non fault
contained apparatus for example
High Voltage insulating gloves (AS 2225) rated for the voltage present
Eye Protection (AS 1336:1997 and AS 1337:1992)
Safety shoes or boots (AS2210:1994)
Hearing protection, if determined necessary after a risk assessment, when generators are
running for example
38 | P a g e
39 | P a g e
4.3.3.2.GENERAL USES
To be placed to restrict all personnel from entering the area within the
boundary of the barrier, except personnel signed onto a TP on that
particular apparatus.
4.3.3.2.2 RULES
40 | P a g e
41 | P a g e
42 | P a g e
43 | P a g e
3. An appropriate hazard & risk assessment shall be completed for work at these approach
distances.
44 | P a g e
is involved the applicant shall arrange an AWP and notify the customers of the interruption date and
duration. This information shall be included on the OA.
The HV controller shall be notified of any changes to the interruption time prior to the planned
outage taking place. All switching and associated duties shall be carried out in accordance with these
SAPs.
45 | P a g e
46 | P a g e
last alternative. Every effort will be made to de-energise the switchboard. An LV rescue kit shall be
on the work site and set up. Suitable safety apparel shall be worn such as PPE as per work in the
vicinity of HV apparatus. Barriers and signs shall be used, where practicable, to indicate to work
parties the condition of the apparatus.
4.9.3 WORK ON LIVE SWITCHBOARDS
An extensive risk assessment shall be carried out before any live work is performed. Any
persons undertaking work on live electrical equipment shall be skilled and competent in the
work to be carried out
A safety observer shall be used when working on or close to live electrical equipment
Suitable safety apparel shall be worn, i.e. Clothing as per work in the vicinity of or on HV
apparatus, hard hat, safety boots, eye protection.
Only tools and equipment approved and appropriate for the work to be carried out shall be
used.
Suitable insulating barriers shall be used where possible Barriers and signs shall be in place
to prevent all non-essential personnel from entering the area
An extensive briefing of the work party and safety observer by the HV controller or his
representative shall be performed before any work is carried out.
The appropriate rescue kit shall be provided and set up
4.9.4 WORK ON DE-ENERGISED SWITCHBOARDS
An extensive risk assessment shall be carried out before any live work is performed.
A safety observer shall be used when working close to other live electrical equipment.
Suitable safety apparel shall be worn, i.e. Clothing as per work in the vicinity of or on HV
apparatus.
Hardhat, safety boots or shoes, suitable eye protection.
Only tools and equipment approved and appropriate for the work to be carried out shall be
used.
Barriers and signs shall be in place to prevent all non-essential personnel
from entering the area
An EAP shall be issued
The apparatus shall be tested, earthed or bonded as appropriate
The appropriate rescue kit shall be provided
The following areas are defined as high energy LV:
The bus way system
Switchboards directly connected to a distribution transformers
Switchboards in the customers LV switch rooms.
4.9.5 LIVE TESTING
A risk assessment shall be carried out before any live testing is performed.
Any person performing live testing shall be suitably trained and authorised for that work. Suitable
insulating barriers shall be used where appropriate.
47 | P a g e
tunnels and cable pits under the control of HV. The hazards listed herein are the known hazards that
exist at Brisbane Airport and may not be the only hazards present.
Electrocution.
Electric Arc Flash.
Burns
Percussion.
Physical Injury.
Resultant Fires
Explosion
These locations are known to have the potential to expose personnel to the hazards listed above
HV substations.
LV switch rooms
Transformer enclosures.
HV and LV cable pits
Any point where HV & LV cables are being or have been exposed
4.11 SECURITY
Security of substations, switchrooms and transformer enclosures is the responsibility of the HV
controller. All access doors of HV substations, switchrooms and transformer enclosures shall be
locked when they are unattended.
4.11.1 KEYS
Only authorised persons shall be issued with keys to substations, switchrooms and transformer
enclosures. The issue of keys is the responsibility of the Electrical Inspector.
4.11.2 WORK IN SUBSTATIONS, SWITCHROOMS & TRANSFORMER ENCLOSURES
ENCLOSURES
When work is being performed all persons in the work party shall ensure the security of substations,
switchrooms and transformer enclosures is maintained preventing unauthorised access. Supervision
of open or unlocked access doors or access points that have been established shall be maintained at
all times.
When the work is temporarily suspended, all substation, switchroom and transformer enclosure
access doors or established access points, shall be locked or secured as appropriate. The erection of
suitable barriers and signs shall be carried out as per operational procedures or where necessary.
48 | P a g e
1. No personnel, other than the electrical operators or safety observer involved in the switching
operations, shall be in any substation when switching and earthing is being carried out
2. The second electrical operator or observer shall remain well clear as each operation is carried out.
3. If the HV or LV operation requires the simultaneous attention of two electrical operators, i.e. hand
application of earths and earthing at CB positions, then a safety observer shall be in place outside the
substation.
4. All access doors/gates to substations shall be restrained in the open position in a manner that
precludes accidental closure.
5. All access ways and emergency exit paths shall be clear.
6. Whenever possible suspect apparatus shall be energised from a remote switching point.
5.1.2 PRINCIPLES
Only authorised persons shall undertake switching and associated duties on HV and High Energy LV
apparatus. Electrical operators whose training, duties and instructions cover the particular apparatus
shall perform switching and associated duties on HV and High Energy LV apparatus. The available
information regarding circuit conditions shall be considered prior to any switching operations being
performed. No apparatus shall be operated if it is inappropriate for the duty to be performed. No
apparatus shall be operated outside the manufacturers ratings. Verification of the correct operation
of all switchgear after each switching operation shall be confirmed where possible.
An electrical operator shall be protected in an approved manner from electric shock when operating
switchgear using a metal handle.
An electrical operator shall avoid contact, if possible, with earth conductive equipment when
operating electrical switchgear. All apparatus shall be referred to by nameplate description. All
communications shall be clear and definite and repeated back word for word to avoid
misunderstanding. All defective apparatus shall be reported and tagged.
5.1.3 COMMUNICATION
5.1.3.1 PURPOSE
The purpose of this procedure is to ensure incidents and accidents do not occur when personnel are
engaged in electrical work at Brisbane Airport.
5.1.3.2 GENERAL
Communication is the process of sending and receiving signals between people that conveys
meaningful information. Effective communication is mandatory when working with HV and LV
power systems. Switching errors have been made in the other power system networks due to
poor communication techniques.
5.1.3.3 REQUIREMENTS OF HV CONTROLLERS AND OPERATORS
All communications relating to the operation of, or access to, electrical apparatus shall be clear and
definite. Apparatus shall be referred to by nameplate wording with sufficient detail to give positive
identification. Verbal instructions and statements shall be confirmed by repeating back to avoid
misunderstanding. Switching directions shall be communicated word for word, as written on the
Switching sheet, by the HV operator or observer in possession of the SASI to the HV operator
performing the switching. The HV operator performing the switching shall repeat back, word for
word as written on the SASI, the direction given before the switching step is performed and after the
switching step is completed. The HV operator or observer in possession of the SASI shall check this
communication against the SASI and verify the operation has been successfully completed by stating,
.That is correct. The same procedure shall be followed in all switching communications between HV
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
49 | P a g e
operators, the supply company and other HV authoritys operational personnel. No HV operator shall
perform any switching if there is any doubt as to the direction received.
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
50 | P a g e
5.1.4.3 STORAGE
Keep all equipment in designated storage facilities
Store rubber mat flat
Store gloves correctly
Check tags and padlocks are stored correctly
Check barriers and signs are stored correctly
Check HV operating sticks are stored correctly
Check earth and short circuits are stored correctly
51 | P a g e
Check for any general damage, do not use if the damage may affect the safe use of the equipment
5.1.10 EARTH SWITCH TRUCKS
Check for any general damage, do not use if the damage may affect the safe use of the equipment
Check that the contacts are undamaged, do not use equipment the has damaged contacts Check
that the contacts are clean, do not use equipment that has dirty contacts
Report any damaged or unserviceable equipment to the HV compliance officer
Report any equipment that has passed its test date to the HV compliance officer
Operator safety equipment replacement is through the HV compliance officer
5.2 MODIEWARK
5.2.1 DESCRIPTION
A Modiewark is an approved proximity testing device to be used for testing HV and LV apparatus in
the energised state or the de-energised state prior to discharging and earthing.
The general Modiewark Testers will provide reliable voltage indication as to the state of the
apparatus up to 66kV. The SP.150 Modiewark Spout Tester model is designed for testing in spouts up
to & including 33kV. The activation voltage on the 240V setting is within the range of 28-50V. Three
size .C batteries power the Modiewark. They are located in the removable stem. The batteries are
inserted into the removable stem with the positive terminal towards the head of the tester. Regular
checks should be carried out on the condition of the batteries. Turning the Modiewark off
immediately after use will prolong battery life. The Modiewark Spout Tester model has a detachable
150 mm. grey spout. If the spout is removed from the Modiewark Tester, the Tester will not operate.
This is a safety precaution so that the tester cannot be used without the pressure tested grey spout
in place. Modiewarks are available in a number of models. The earlier models, when turned to the
test position, require a live source, or an induced charge test to prove the Modiewark is working. The
Modiewark may beep only, or beep and a red light will illuminate to prove the
Modiewark is functioning correctly. The later models will beep when turned on and a red light will
illuminate. With both types, when the apparatus being tested is alive, the beep will become a
continuous sound.
5.2.2 USE
A Modiewark is to be tested at a time interval not exceeding twelve months.
This test is a calibration test for all models. The Modiewark Spout Testers specifically designed for
testing in bus or cable spouts, will also require a pressure test to be carried out on the detachable
spout.
A Modiewark should not be brought into contact with electrical apparatus. If a
Modiewark is accidentally brought into contact with electrical apparatus it shall not simultaneously
be brought into contact with earthed or non-approved insulated apparatus. A Modiewark is designed
for fitting to an approved, tested
HV operating stick using a Taplin multipurpose or rising sun head. Attachments are available to allow
the Modiewark to be attached to HV operating sticks.
These attachments allow for testing at both horizontal and vertical CB spout positions as well as any
exposed apparatus. The testing at spout positions should be carried out with the SP 150 Modiewark
specifically designed for that purpose and can be inserted into the bus or cable spouts if induction is
present that effects the Modiewark indication when it is external to the spouts. It is preferable that
where possible the Modiewark remains outside the bus or cable spouts by using the appropriate
voltage setting. Under no circumstances shall the Modiewark be held directly in a hand when testing
HV apparatus. A protective storage bag is available and should be used to protect the
Modiewark.
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
52 | P a g e
5.2.3 PROCEDURE
Turn the selector switch to 240V, which is the self-test mode. This is an acceptable instrument test,
or select the appropriate voltage and test on a known source
Then on the appropriate voltage and test for dead
The apparatus to be earthed is tested on all phases
Test the Modiewark again against known live voltage source
The apparatus is then discharged on all phases, where possible, and earthed
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
53 | P a g e
NOTE
The insulated connecting cable is not HV insulated and care should be taken not to allow that cable
to come into contact with the electrical apparatus or earth when carrying out the test.
The HV operator shall not handle the live line sticks above the grip handles or indicated mark on
each stick at all times while either one of the live line sticks are in contact with the electrical
apparatus.
5.4.3 TAGS
5.4.3.1 PRIMARY ISOLATIONS
A DNOB tag shall be used on all primary isolation points
5.4.3.2 SECONDARY ISOLATIONS
A DNOB tag shall be used on all secondary isolation points
5.4.4 LOCKS
5.4.4.1 EARTH SWITCHES
A specifically keyed HV operator lock independent of any other operating lock shall be fitted to all
earth switches and they shall be locked in the open position.
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
54 | P a g e
5.5 EARTHING
5.5.1 APPLICATION
For the HV electrical system at Brisbane Airport and for all works that require earthing by or for the
supply and other HV authorities.
5.5.2 RESPONSIBILITY
The electrical operator and the work party have the responsibility to comply with this earthing
procedure.
5.5.3 GENERAL
All HV and LV apparatus that requires HV Switching for access shall be earthed. Earthing shall, where
practicable, be between the work party and all points of supply and at the site of the work. All earths applied by
an electrical operator are operational earths and can only be removed by the work party with the permission of
an electrical operator. All earths applied by the work party are work party earths and the work party is
responsible for removing these earths prior to the cancellation of the electrical permit. The electrical operator
is responsible for the attachment of the first earth to electrical apparatus except where an earth cannot be
applied prior to the permit issue. Where earths at the points of supply can be applied by the electrical operator
prior to the permit issue, this shall be done. At least one earth shall, where practicable, be attached prior to the
EAP or SFT issue.
55 | P a g e
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
56 | P a g e
57 | P a g e
5.6.3 RECORDING
The HV controller shall record all in the appropriate register
5.6.4 DEFECT RECTIFICATION
Each defect shall be reported to the maintenance contractor, in writing (Email) indicating
1. The Substation involved
2. The nature of the defect
3. The urgency of the repair
The maintenance contractor shall advise the HV controller of the proposed rectification date and
submit a works application. If the repair is urgent a verbal application shall suffice.
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
58 | P a g e
59 | P a g e
8. Simple disconnection and reconnection of electrical apparatus can be carried out under an SFT
If new or repaired electrical apparatus cannot be energised from a remote switch or via a CB, then
operator safety is paramount, and the electrical apparatus shall be Hi-Pot tested by an authorised
tester under SFT procedures, before being energised by the operator.
6.3 SOAK TEST
A soak test is where the apparatus is energised on no load for a nominal 24 hr period before being
declared fit for service.
6.4 TESTING OF UNDERGROUND HIGH VOLTAGE CABLES
Cable manufacturers suggest that D.C Hi-Pot testing of previously energised or new XLPE and paper
lead type cables significantly decreases the life expectancy of that cable.
6.4.1 TYPES OF CABLE TESTS
1. INSULATION TEST MEGGER
2. SOAK TEST
3. 5kV
4. DC HI-POT TEST
5. VLF AC HIPOT TEST
(Paper/Lead cables only)
The preferred AC pressure test is a Very Low Frequency (VLF) test (Refer
IEEE400.2) at 2-3 times the rated voltage.
6.4.2 TEST GUIDELINES
6.4.2.1 TABLE No. 1 XLPE CABLE STATUS OPTION TEST # VOLTAGE
Old or new previously energised
(Includes adding new to old & to
paper / lead)
11kV phase to phase
13kV phase to earth
New
11kV phase to earth
19kV phase to earth
6.4.2.2 TABLE No. 2 PAPER / LEAD CABLE STATUS OPTION TEST # VOLTAGE
11kV phase to phase
New or existing
13kV phase to earth
17.5kV phase to phase
30kV phase to phase
6.4.3 TESTING PROCEDURE
1. Authorised testers, working under the terms of an SFT, shall carry out all
HV testing
2. All HV cables shall be meggered after fault repairs and before new cables are commissioned
3. Megger testing can be carried out under an EAP or SFT
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
60 | P a g e
4. Cables that have been de-energised or not placed into service after testing for a period exceeding
24 hrs shall be meggered before being energised and be soak tested if possible.
5. Cables that have been de-energised or not placed into service after testing for a period exceeding
48 hrs shall be Hi-Pot tested before being energised, or be meggered and soak tested.
6. Transformer HV cables do not need to be tested when they have been deenergised for the above
periods if the cable can be visually inspected for its entire length.
Eg: at a kiosk substation.
7. In all cases (where practical) the route of the cable should be inspected for any visual damage
prior to the cable being energised
8. Test No.1 is only applicable if the cable can be energised remotely via a three phase switch with
protection tripping, or at any point where a CB can energise the cable
9. Simple disconnection and reconnection of HV cables can be carried out under SFT
If a new or repaired HV cable cannot be energised from a remote switch or via a
CB, then operator safety is paramount, and the HV cables shall be Hi-Pot tested by an authorised
tester under SFT procedures, before being energised by the operator.
November 2012
Safe Access Procedure High Voltage - Airport Facilities - Electrical
61 | P a g e