You are on page 1of 28

Pearl GTL

Project
Shell Project No: HP-3000-QAT
Project Document Number: T- 4.250.896

Purchase Order Number:

2MH127

Tag/Item Number(s):

N/A

Unit(s):

ASU

PCWBS:

LINDE ENGINEERING

Contractor Project No :
Project Rev.: C

Page 2 of 26

5887

QATAR SHELL GTL PROJECT (PEARL)


C2 AIR SEPARATION UNITS CONSTRUCTION

18.05.2008

Company Comments Incorporated

AG

EE

AG

CCI

23.03.2008

Ready For Construction

BR

UA

ZG

RFC

28.02.2008

Ready For Construction

BR

UA

ZG

RFC

29.11.2007

Issued for Company Comments

UA

MC

ZG

ICC

22.11.2007

Issued for Review

BR

AU/MC

ZG

IFR

20.11.2007

Issued for Internal Review

BR

AU/MC

ZG

IIR

Date

Description

GAMA
Rev.
No.

Project
Rev
No.

Prepared Checked Approved


By
By
By
ORIGINATOR

Status

Document Title:

LINDE ENGINEERING AG

METHOD STATEMENT FOR STRUCTURAL STEEL


ASSEMBLY AND ERECTION
Document No.

Contractor

Gama Qatar Co. W. L. L.

LOC470
GAM

MTS

MEC

GTL

001

Org.
Code

Doc.
Type

Disc.
Code

Geogr.
Area

Seq.
No

Rev.
No

Project Document Number: T- 4.250.896

Vendor Code

Rev No: C

Q A T A R

Doc. Title

Doc No

METHOD STATEMENT FOR STRUCTURAL STEEL ASSEMBLY &


ERECTION

GAM-MTS-MEC-GTL-001 Rev. F

Date:

18.05.08

TABLE OF CONTENTS
1.

PURPOSE _____________________________________________________________________5

2.

SCOPE ________________________________________________________________________5

3.

HSSE _________________________________________________________________________5

4.

REFERENCES _________________________________________________________________5

5.

DEFINITIONS _________________________________________________________________6

6.

RESPONSIBILITY ______________________________________________________________7

7.

6.1.

SITE MANAGER _________________________________________________________________ 7

6.2.

CONSTRUCTION MANAGER _____________________________________________________ 7

6.3.

EQUIPMENT MANAGER _________________________________________________________ 7

6.4.

SITE ENGINEER_________________________________________________________________ 7

6.5.

SITE SUPERVISOR/FOREMAN____________________________________________________ 7

6.6.

QC ENGINEER __________________________________________________________________ 7

6.7.

QC INSPECTOR _________________________________________________________________ 7

6.8.

HSSE MANAGER ________________________________________________________________ 7

6.9.

HSE OFFICER ___________________________________________________________________ 7

PROCEDURE __________________________________________________________________8
7.1.

PLANT AND EQUIPMENT ________________________________________________________ 8

7.2.

WORKFORCE ___________________________________________________________________ 8

7.3.

MATERIALS ____________________________________________________________________ 9

7.4.

SITE PLANNING AND PREPARATION _____________________________________________ 9

7.5.

WORK METHODOLOGY _________________________________________________________ 9

8.

QUALITY ASSURANCE_________________________________________________________12

9.

ATTACHMENTS_______________________________________________________________13

TYPICAL ERECTION OF COLUMNS IN PIPE RACK PHASE 1 _________________________13


JSA______________________________________________________________________________13

T-4.250.896 Rev. C

Page 4 of 26

Q A T A R

Doc. Title

Doc No

METHOD STATEMENT FOR STRUCTURAL STEEL ASSEMBLY &


ERECTION

GAM-MTS-MEC-GTL-001 Rev. F

Date:

18.05.08

1. PURPOSE
The purpose of this method statement is to outline the general requirements & precautionary
measures which will be taken into consideration for the structural steel assembly & erection
works for C2 ASU Pearl GTL Project by GAMA Qatar.

2. SCOPE
This method statement identifies the general steps, arrangements & precautions for the
structural steel assembly & erection works at the C2 ASU Pearl GTL Project site.

3. HSSE
All works shall be in compliance with the State of Qatar laws and regulations, Ras Laffan
Industrial City and International standards, codes, Linde Engineering AG and QSGTL and/or its
PMC requirements and instructions.
In addition all employees and Gama subcontractor employees on site will have through Linde
Engineering AG Site Safety Induction and Gama Qatar Safety induction for site safety, health,
environmental and security prior to work activities. Other training courses will be attended as
required by Linde Engineering AG and QSGTL and/or its PMC as required.
At a minimum a Risk Assessment will have been prepared by the Risk Assessment Team
(RAT) ranking the hazards associated with project works and control measures to be taken to
mitigate the hazards to an acceptable level.
Each work scope or task will have a completed and approved Job Safety Analysis (JSA)
identifying the potential hazards and control measures that will be implemented to protect
people and environment. Supervisor as the basis of conducting his daily Pre-Task meeting and
his weekly TSTI will use the JSA.
In addition to the above, employees conducting survey works will wear required PPE and
highly visible vest where traffic or other hazards may exist. For additional safety requirements
for a particular or specific task please refer to the JSA prepared for that task.

4. REFERENCES

T.4.115-071

:Fabrication & Assembly of Steel Structure

DEP 34.28.00.31

:Steel Structures (Amendment T-13.376.359)

T-4.219.611

:HSSE Plan

T-4.234.542

:Project Quality Plan

SSPC-SP14/NACE No. 8:Industrial Blast Cleaning

T-4.250.896 Rev. C

Page 5 of 26

Q A T A R

Doc. Title

Doc No

METHOD STATEMENT FOR STRUCTURAL STEEL ASSEMBLY &


ERECTION

GAM-MTS-MEC-GTL-001 Rev. F

Date:

18.05.08

T-4.250.917

:ITP For Structural Steel

34-00-01-30

:Minimum Requirements For Structural Design &


Engineering

GZ00-C-SY2005.013

: Metal Works and Fencing.

T-4.250.907

: Procedure for Structural Steel.

T-13.376.369 Rev-K

: Structural Steel Work General Notes and


Abbreviations.

T.4.250.545

: Procedure for Grouting

T.4.129.859

: Lifting Procedure (General)

T.4.129.868

: Work at height Scaffolding

5. DEFINITIONS
COMPANY

QSGTL and/or its PMC

CONTRACTOR

Linde Engineering AG

SUB CONTRACTOR

Gama Qatar

PROJECT

QSGTL Pearl Plant C2 ASU Construction Works

QA/QC

QUALITY ASSURANCE/QUALITY CONTROL

QCE

QUALITY CONTROL ENGINEER

QCI

QUALITY CONTROL INSPECTOR

CM

CONSTRUCTION MANAGER

T-4.250.896 Rev. C

Page 6 of 26

Q A T A R

Doc. Title

Doc No

METHOD STATEMENT FOR STRUCTURAL STEEL ASSEMBLY &


ERECTION

GAM-MTS-MEC-GTL-001 Rev. F

Date:

18.05.08

6. RESPONSIBILITY
6.1.

SITE MANAGER

The site manager will provide inputs to the project execution plan to ensure that lifting
strategies & philosophy are addressed.

6.2.

CONSTRUCTION MANAGER

The construction manager is responsible for the overall management of the project
construction team to ensure that safe and effective operations are conducted and
properly documented.

6.3.

EQUIPMENT MANAGER

The equipment manager will be responsible for the transporting equipments availability
and good order.

6.4.

SITE ENGINEER

Shall report to Construction Manager.


Shall be responsible for planning, execution and implementation of all site activities
related to this procedure.

6.5.

SITE SUPERVISOR/FOREMAN

Shall report to Site Engineer.


Shall be responsible for execution of construction activity.
Shall also prepare daily site construction records.

6.6.

QC ENGINEER

Shall report to Manager (QA/QC) and shall be responsible for overall implementation,
monitoring and control of QC activities.

6.7.

QC INSPECTOR

Shall report to QC Engineer


Shall be responsible for attending all Inspection Stages as required by ITP.
Shall be responsible of performing all checks and shall prepare necessary Inspection
Reports.

6.8.

HSSE MANAGER

Shall report to Project Manager and shall be responsible for over all control and
inspection of HSSE issues.

6.9.

HSE OFFICER

Shall report to HSE Manager.


Shall be responsible for all safety aspects for this procedure.

T-4.250.896 Rev. C

Page 7 of 26

Q A T A R

Doc. Title

Doc No

METHOD STATEMENT FOR STRUCTURAL STEEL ASSEMBLY &


ERECTION

GAM-MTS-MEC-GTL-001 Rev. F

Date:

18.05.08

7. PROCEDURE
7.1.

PLANT AND EQUIPMENT

7.2.

Boom Truck or Hiab Min. capacity 3 ton.


Fork Lift
Articulated Man lift
Trailer
Crane Lifting studies for above 10 ton shall be presented, according to the
availability and size of the cranes.
Gas cutting Torch
Grinding Machine
Welding Machine
Diesel Generator
Air Compressor
Air actuated tools
Hand tools
Electrical tools

WORKFORCE

Work force allocation shall be done based on quantum of job involved. So as to finish the
job within stipulated period with the required quality and safety.

Site Engineer
Rigger
Survey Team
Safety Officer
Painter
Supervisor/Foreman
Operators
Drivers
Laborer

a) Erection Crews
Crane operator
Rigger
Scaffolder
Fitter
Foreman
Banks Man
Helper

T-4.250.896 Rev. C

Page 8 of 26

Q A T A R

Doc. Title

Doc No

METHOD STATEMENT FOR STRUCTURAL STEEL ASSEMBLY &


ERECTION

GAM-MTS-MEC-GTL-001 Rev. F

Date:

18.05.08

b) Bolt Tightening Crews


Bolt Tighteners
c) Material Handling Crew
crane operator
rigger
helper

7.3.

MATERIALS

Structural-Steel Materials
All Steel Material should confirm to;
EN 10025, ASTM A 36, JIS 3101 SS 400
BS 5950 Part 1, 2 Min Requirement Structural Steel

7.4.

SITE PLANNING AND PREPARATION


Necessary work permit shall be taken before starting the job. The job will be
carried out as per approved RFC drawing and specification.

7.5.

WORK METHODOLOGY

7.5.1 STRUCTURAL STEEL FABRICATION AND ERECTION


A. Fabrication
Structural steel will be fabricated according to the approved RFC drawings &
Standard drawing if any.
1. Fabrication will be done with exposed surfaces smooth, square, and free of
surface blemishes including pitting, rust, scale, sea, marks, roller marks, rolled
trade names, and roughness.
2. Blemishes should be removed by filling or grinding or by welding and grinding,
before cleaning, treating and shop priming.
3. Fabrication tolerances shall conforming to BS 5950-1 & 2.
4. Man Lock Hole (holes for fixing ladder support) shall be drilled as per Drawing
T.13.376.379 Rev G and the same to be used to tie off safety harness.
B. Thermal Cutting
Heavy sections and thick plates will be preheated prior to cutting as required by
Specification AWS code. The same will ground smooth to remove all serrations.

T-4.250.896 Rev. C

Page 9 of 26

Q A T A R

Doc. Title

Doc No

METHOD STATEMENT FOR STRUCTURAL STEEL ASSEMBLY &


ERECTION

GAM-MTS-MEC-GTL-001 Rev. F

Date:

18.05.08

C. Bolt Holes

Standard bolt holes will be drilled, or punched perpendicular to metal


surfaces.
Holes will be provided required for securing other work to structural steel and
for passage of other work through steel framing members.
All holes for high strength bolts shall be drilled.
Holes shall be clear of burrs or rough edges and countersunk when required.
The diameter of all holes shall not exceed the diameter of bolts by more than
1mm for bolts 12mm, 2mm for bolts 16 to 24mm and 3mm for bolts 27mm
and larger.
All threaded portion each bolt shall project beyond the nut by at least 3
threads.

D. Finishing
Ends of members and any other supports will be accurately finished.
E. Welding

Welding procedure Specification, Welder Qualification, Quality of welders,


tolerances etc. shall be complied with AWS D1.1 / ASME Section IX.
Weld size, fabrication sequence, and equipment used for exposed structural
steel will be verified to limit distortions within allowable tolerances.
Defects that would be visible in the finished work shall be ground out, filled
with welding material, and ground flush prior to finishing. Grind welds smooth
where indicated. Welds shall be neat, complete and free of voids, flush finish,
and not ground. NDE requirements if applicable shall be performed.
All welding shall be performed in an area protected from adverse weather
conditions, rain, wind dust and sand with tents.
Welding procedures shall identify material, weld geometry, tolerances, and
Welding process, and preheat temperature, welding position to be used and
welding consumable.
All welders and welding operators shall be qualified by tests for welding
structural shapes, pipe and plates to meet to the requirement of welding
codes.
Spills of zinc based paint on structural steel causes the material to
disintegrate during welding. Have the welding areas be cleaned properly and
free from paint spills. (FSI Ref. # Q3b-13.0)

F. Surface Preparation
Surface preparation will be done as per MS for Painting and Repair Works
T.4.250.900

T-4.250.896 Rev. C

Page 10 of 26

Q A T A R

Doc. Title

Doc No

METHOD STATEMENT FOR STRUCTURAL STEEL ASSEMBLY &


ERECTION

GAM-MTS-MEC-GTL-001 Rev. F

Date:

18.05.08

G. Galvanizing
Spray galvanize paint shall be applied on damaged areas using Paint System as
per the Painting and coating of new equipment. (DEP 30.48.00.31)
H. Grouting
Grouting shall be done on equipment and steel structure foundation with
approved materials as per specifications and MS for Grouting T.4.234.076.All
structural steel frame will be aligned/plumb accepted by contractor before start of
Grouting Works.
I. Pre Assembly:

Work permit will be taken for pre assembly works.


Pre assembly will be done at site/yard on leveled ground surface.
Pre assembly size will be determined based on transportation and capacity
of crane, the lifting procedure T.4.129.859 will be followed strictly.
All the preassembled structure will be tightened as per MS for bolt
tightening T.4.250.857 and torqued with calibrated Torque wrench and
recorded in GAM-QCR-QAC-GTL-041
Over all safety precautions will be taken care for assembly activities.

J. Handling and Storage

All materials shall be stored well clear of the ground with erection marks are
clearly visible on skids or timbers. These supports shall be spaced so that no
damage results from deflection. Stacking of components more than three
pieces high is not permitted.
Steel work components shall be handled and stored in such a manner as to
minimize the risk of surface abrasion and damage.
Fasteners and small fittings shall be stored in dry conditions.
Steel work shall be stored so that erection marks are clearly visible.

7.5.2 Execution
Elevation of concrete and masonry-bearing surfaces and location of anchor rods,
bearing plates, and other embedment will be verified with steel erector present, for
compliance with requirements. Temporary shores, guys, braces, and other supports
will be provided during erection to keep structural steel secure, plumb, and in
alignment against temporary construction loads. Temporary supports will be removed
when permanent structural steel, connections, and bracing are in place, unless
otherwise indicated. Temporary shoring supporting composite deck construction will
not be removed until cast-in-place concrete has attained its design compressive
strength.

T-4.250.896 Rev. C

Page 11 of 26

Q A T A R

Doc. Title

Doc No

METHOD STATEMENT FOR STRUCTURAL STEEL ASSEMBLY &


ERECTION

GAM-MTS-MEC-GTL-001 Rev. F

Date:

18.05.08

7.5.3 Erection
Work permit will be taken before commencement of the Structural steel erection
activities.
Training for all personnel for working at height will be provided. All personnel shall
use Man Lock Hole to tie off safety harness.
All plant and equipment shall be suitable, and of sufficient capacity to complete
erection of steel work.
All plant and equipment shall conform to the statutory regulations and
requirements applicable to construction, plant and lifting devices. Test certificates
for such items as slings and D shackles etc. shall be available for inspection.
Gama shall ensure that no part of the structure permanently distorted by stacking
of materials or temporary erection loads during the erection process.
No equipment shall be supported from the frame until correct position and
alignment has been obtained and the structure is securely connected and grouted
to its foundations.
Column base plates shall be set and shimmed to the correct positions and
elevations as shown on the drawings.
The erection of structural steel shall not commence until shims and anchors have
obtained sufficient strength to adequately support all the loads imposed upon them
including any due to the erection operation.
All steel shall be plumb and level.
During erection, temporary bracing and guys shall be used to maintain structural
stability as necessary. (Ref. Attachment)
Concrete and masonry-bearing surfaces of bond reducing material will clean and
roughened surfaces prior to setting base and bearing plates. Bottom surface of
base and bearing plates will be clean.
Alignment and adjustment of various members forming part of complete frame of
structure will be done before permanently fastening. Before assembly, bearing
surfaces and other surfaces that will be in permanent contact with members will be
properly cleaned. All steel members will be cleaned before start of erection.
Individual members of structure will be leveled and plumbed.
Erection bolts on welded, architecturally exposed structural steel will be removed;
holes should be filled with plug welds and ground smooth at exposed surfaces.
For all Lifts above 10 MT single unit ,prior approval will be taken for Rigging plans.
Bolt Tightening Shall be done as per Method statement T.4.250.897

8. QUALITY ASSURANCE
A Quality Assurance System shall be operated conforming to related standards.
Controls and checks shall be established and documented through relevant
T-4.250.907(QCP), T-4.250.917(ITP) and QCRs.

T-4.250.896 Rev. C

Page 12 of 26

Q A T A R

Doc. Title

Doc No

METHOD STATEMENT FOR STRUCTURAL STEEL ASSEMBLY &


ERECTION

GAM-MTS-MEC-GTL-001 Rev. F

Date:

18.05.08

9. ATTACHMENTS
TYPICAL ERECTION OF COLUMNS IN PIPE RACK PHASE 1
JSA

T-4.250.896 Rev. C

Page 13 of 26

Q A T A R

T-4.250.896 Rev. C

Doc. Title

Doc No

METHOD STATEMENT FOR STRUCTURAL STEEL ASSEMBLY &


ERECTION

GAM-MTS-MEC-GTL-001 Rev. F

Date:

18.05.08

Page 14 of 26

Q A T A R
JSA Number: T.4.250.896

JOB SAFETY ANALYSIS FORM


NEW

Page No: 15 of 26

REVISED

Job being analysed: METHOD STATEMENT FOR STRUCTURAL STEEL ASSEMBLY AND ERECTION
JSA Members: Mr. Syd Osborne, Mr. Atila Gun
Department/Section doing JSA: HSSE & Construction
Job Performers: Mr. Aitla Gun
General job requirements / Common Personnal Protective
Signature
Normal Approvals:
Name
Date
Equipment.
JSA by:
Mr. Atila GUN
18.05.08
1. The following Personal Protective Equipment shall be
18.05.08 worn while erecting structural steel at C2 ASU PEARL GTL
PROJECT: Approved coveralls, safety glasses, safety
Additional Approvals (Determined by Job Supervisor in correlation with LINDE HSSE Manager).
helmet, safety steel toe shoes, gloves and safety harness.
Signature
Name
Date
Job Supervisor:

Mr. Ihsan POLAT

Discipline Superindent LINDE


HSSE Representative LINDE
2. Permit To Work.

OTHERS (List Below):

Approval required for hazardous work detailed in the LINDE work permit procedure.
Changing conditions and emergency procedures: Stop work. Switch of equipment.Supervisor directs personnel to nearest and safest muster point considering wind direction. Supervisor counts all employees. Missing
employees are reported to LINDE HSSE Dept. When all clear is given check with LINDE HSSE before returning to work.
EMERGENCY TELEPHONE NO.

RLIC:
LINDE HSSE MANAGER:

474 88 88
583 40 72

Note: 1) If any of the tasks involves biological, physical or chemical hazards, then The LINDE Industrial Hygienist must also approve the work.
2) Use additional sheets as necessary.
3) Details on safety (PPE,Hazard etc) and environmental requirements can be found in LINDE and Shell Safety and Environment Procedures.

Page 15 of 26

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T.4.250.896

Q A T A R

SCOPE : Steel Structure Assembly and


Erection

Initial Risk
ITEM

ACTIVITY

HAZARD / POTENTIAL
CONSEQUENCES

Pre-Assembly of 1.1
Frames at ground
level.

Residual Risk

CURRENT
CONTROLS

RISK
RANK

Slip,trip and fall hazards.

1.1.1

LOW

1.1.2
1.1.3

1.2

Improper use of hand


tools during assembly of
frame.

1.2.1
1.2.2
1.2.3
C

LOW
1.2.4
1.2.5

1.3

1.4

Fall of materials from


dunnage or support.

LOW

1.1.1.2

Man Lock Holes are provided


A
to tie off Lan Yards while
working at heights.

1.2.1.1

All tools shall be inspected


prior to use. Use the right tool
for the job.

1.2.1.2

The weight, size and type of


tool should be selected to fit
the job at hand.

MED

Keep the structural steel as


low as possible to the
ground.

LOW

LOW

1.3.1.1

1.4.1

Ensure workers hand shall be away


from the connecting pieces of
materials.
Ensure employee has appropriate
hand protection.

1.4.1.1

1.4.2

Remove any unecessary


materials.

Ensure correct cribbing of dunnage.


Ensure support can withstand
maximum intended weight/load.

LOW

1.1.1.1

1.3.1
LOW 1.3.2

Hand injury.
C

Work area shall be properly


maintained, all equipment and
materials must be properly stored.
Housekeeping shall be done daily at
the end of the days work.
Material storage areas shall be
identified, stored properly, barricaded
& secured.
Ensure employee has appropriate
hand protection.
Do not use wrenches if the jaws are
sprung.
Operate tools according to
manufacturers instruction.
Perform mechanical tools maintenance
regularly.
Cheater bar are not allowed to be uses
as an extension for tightening bolts.

ADDITIONAL
CONTROLS

Discuss in TSTI.

Page 16 of 26

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T.4.250.896

Q A T A R

SCOPE : Steel Structure Assembly and


Erection

Initial Risk
ITEM

ACTIVITY
Lifting of
assembled
structural frame.

HAZARD / POTENTIAL
CONSEQUENCES
2.1

Residual Risk

CURRENT
CONTROLS

RISK
RANK

Dropped loads.

2.1.1

2.1.2

2.1.3
2.1.4
2.1.5
MED
2.1.6
2.1.7

2.1.8
2.1.9
2.2

Overturning machines

2.2.1

LOW 2.2.2

2.2.3
2.3

Attempting to lift
unknown weigth

2.3.1
B

MED

2.3.2
2.3.3

ADDITIONAL
CONTROLS

Ensure that crane operator is certified 2.1.1.1


by Third party, valid certificates and
driver's licenses.
Ensure that all lifting gear/lifting tackle 2.1.1.2
is properly inspected and color coded
as per color code chart.

All equipment, slinging,


hooks, pin, shackles shall be
Third party certified.
Rigger shall be 100% visible
& clearly relay the information
to the crane operator.

Third party crane inspections.


Competent Riggers.
Daily crane inspections.
Tag lines are to be used to control
loads.
Barricade the working area with sign
boards indicating crane lifting is in
progress to prevent unauthorized
entry.
Ensure that no materials are on the
assembled materials.
Ensure pre lift check to be conducted
prior to lift.
Only work on level solid ground use
out riggers with adequate support
pads.
Ensure all lifts will be controlled and
supervised by supervisor/competent
person.
Safe Working Load displayed.

Ensure all lifts will be


controlled and supervised by
a supervisor/competent
person.

2.1.1.3

2.2.1.1

Load chart should be available in the 2.3.1.1


operators cabin at all times.
Display of SWL, radius of working
indication.
Ensure automatic safe load indicator is 2.3.3.1
working.

Ensure the machine shall be


traveled to the most suitable
position for the job to be
carried out before any
slewing takes place.

LOW

LOW

LOW

Provision of lifting plan if


there are critical.

Test before use.

Page 17 of 26

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T.4.250.896

Q A T A R

SCOPE : Steel Structure Assembly and


Erection

Initial Risk
ITEM

ACTIVITY

HAZARD / POTENTIAL
CONSEQUENCES

2.4

MED

2.3.4
2.4.1

MED 2.4.2

Sub-standard cranes

2.5.1
B

2.6

RANK

Unqualified crane
drivers/operators.
B

2.5

Residual Risk

CURRENT
CONTROLS

RISK

MED 2.5.2
2.5.3

Improper rigging method

2.6.1
2.6.2
C

2.7

MED 2.6.3

Underrated
slings/hooks/shackles.

2.7.1
2.7.2
C

MED
2.7.3

2.8

People/material struck
by swinging loads/crane
in motion.

2.8.1
2.8.2
B

MED
2.8.3
2.8.4

Use of out riggers and/or counter


weights.
Ensure to have a valid certificates for
drivers/operators.
Competence checks for drivers /
operators.

ADDITIONAL
CONTROLS

2.4.1.1

Use only cranes less than 10 years


2.5.1.1
old.
Ensure to have Third Party Inspection.
Ensure to have a valid certificates
checks.
Competence checks registered riggers 2.6.1.1
clearly identified.
Ensure to have a list of competent
2.6.1.2
persons maintained.
Contractor supervisor to constantly
monitor rigger performance.

Ensure to know the weight of load.


2.7.1.1.
Ensure all lifting equipment shall be
inspected and approved by third party
and certified prior to use on site.
Safe Work Load should be display.
2.8.1.1
Keep away personnel from lifting
/moving area.
2.8.1.2
Rigger and crane operator must be
certified by third party as being
competent.
Tag lines shall be attached to control 2.8.1.3
the loads.
Personnel shall not work directly below
suspended load.

4 LOW

Only drivers/operator with


Qatar license & certified
operator inducted and trained A
personnel are allowed to
work on site.
Crane shall be inspected and
approved by third party and
A
certified prior to use on
respective site.
Ensure competent rigger
oversees all lifting
operations.
Rigger shall be 100% visible
A
to the crane operator &
clearly relay the information
to the crane operator and
Refer MS for Lifting, Ref T4.234.084
Ensure all lifting gear brought
into the site shall be clearly
identified by means of a
A
name plate, supplied by a
manufacturer, as to SWL &
serial no.
Ensure that nobody on the
way of the crane.
Barricade and secure the
working area with high
visibility warning signs.
Assign competent banks
man to control passerby.

LOW

LOW

LOW

LOW

LOW

Page 18 of 26

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T.4.250.896

Q A T A R

SCOPE : Steel Structure Assembly and


Erection

Initial Risk
ITEM

ACTIVITY

HAZARD / POTENTIAL
CONSEQUENCES
2.9

Residual Risk

CURRENT
CONTROLS

RISK
RANK

Equipment failure due to


mechanical problem.

2.9.1
2.9.2
B

2.10

Setting up of lifted 3.1


frames at anchor
bolts foundation.
3.2

3.3

Possible collapse of
assembled frame due to
severe twisting.
Pinch point injuries
tightening of nuts to the
anchor bolts.
Muscle strain or sprain
while positioning of
frames into anchor bolts.

MED

2.10.1
B

MED

2.10.2
3.1.1

LOW

3.1.2
3.2.1

LOW

3.2.2
3.2.3
3.3.1

Caught in between
column base plate &
foundation.

3.3.2
B

Initial bolts
tightening.

4.1

4.1.1

Pinch point .
B

Ensure to have inspection of all


2.9.1.1
equipment prior to use on site.
Inspection shall be carried out by a
competent person who has detailed
knowledge of the type of machine he is
to examine.
Ensure permanent bracings are
installed and bolt tightened.
Ensure center of gravity of the frame
being lifted.
Ensure that all hand tools are in good
condition.
Ensure qualified/ competent employee
to carry out the task.
Ensure employee use proper lifting
techniques i.e. lift with their legs not
their back.
Use the "Buddy System" get help.
Break the job down into manageable
portions.
Only authorized & skilled worker for
the task.
Ensure workers not to hold base plate.

2.10.1.1 Ensure two tag lines are


controlling the load.

3.1.1.1

3.2.1.1

3.3.1.1

LOW

4.1.2
4.1.3

Supervisor shall ensure that work will


be supervised as per work Method
Statement. Ref.T-4.250.896
Ensure that all hand tools are in good 4.1.1.1
condition.
Ensure qualified/ competent employee
to carry out the task.
Ensure not to use extentsion handles.

LOW

LOW

LOW

LOW

LOW

LOW

Ensure after inspection to


generate report specifying
any repairs, renewals which
he considers are necessary if A
the equipment is to continue
to be used with safety.

Discuss in TSTI.

Discuss in TSTI.

Discuss in TSTI.

LOW
3.3.3

ADDITIONAL
CONTROLS

Tools to be checked and


certified and colour coded
prior to use.

Page 19 of 26

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T.4.250.896

Q A T A R

SCOPE : Steel Structure Assembly and


Erection

Initial Risk
ITEM

ACTIVITY

HAZARD / POTENTIAL
CONSEQUENCES

Hook-up of
5.1
temporary support
stability concrete
blocks.
5.2

Installation of
6.1
temporary support
for frame stability.
6.2

5.1.1

7.1
Assembling
purloins between
columns &
diagonals prior for
tirfors, sling
removal.

LOW
5.2.1

LOW

6.1.1
LOW 6.1.2

Hand injury.

Back injury due to


manual handling.

5.2.2

6.2.1
B

RANK

Hand injury.

Personnel injury from


poor body position.

Residual Risk

CURRENT
CONTROLS

RISK

LOW 6.2.2
6.2.3

Fall of personnel.

7.1.1

MED
7.1.2

7.2

7.3

Tools/materials fall
hazard.

7.2.1
B

LOW

Lifeline failure.

7.2.2
7.3.1

MED

7.3.2

ADDITIONAL
CONTROLS

Ensure employee has appropriate


hand protection.

5.1.1.1

Warn employees of pinch or crush


points.
Two tag lines shall be attached to
control the loads.

5.2.1.1

Discuss in TSTI.
Ensure employee has appropriate
hand protection.
Ensure employee use proper lifting
techniques i.e. lift with their legs not
their back.
Use the "Buddy System" get help.
Provisions for mechanical equipment
i.e. trolley, fork lift etc..

6.2.1.1

All employees shall wear inspected full 7.1.1.1


body harness fitted with twin lanyards
with shock absorbers, each lanyard
shall be fitted with dual action selflocking safety hook to allow for 100%
Tie-off.
Ensure that all employees working at
height are properly trained.
Ensure bolts/nuts are contained in
7.2.1.1
bolts bags.
Tools shall be tied with retaining rope
attached to the body harness.
Ensure lifeline has a design
7.3.1.1
calculation/Engineering design.
Ensure lifeline can withstand load
impact.

LOW

LOW

LOW

LOW

LOW

LOW

LOW

Discuss in TSTI.

Discuss in TSTI.

Break the job down into


manageable portions.

Discuss working at height


hazards at daily TSTI.
Provided Man Lock hole for
tie off Land Yard.

Barricade and secure the


working area with signboard.

Lifeline should be inspected


prior to its use by a
competent personnel.

Page 20 of 26

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T.4.250.896

Q A T A R

SCOPE : Steel Structure Assembly and


Erection

Initial Risk
ITEM

ACTIVITY

HAZARD / POTENTIAL
CONSEQUENCES

Removal of slings. 8.1

Residual Risk

CURRENT
CONTROLS

RISK
RANK

Fall of personnel, while


working on slings.

8.1.1

MED
8.1.2

Alignment of
9.1
structural columns.

Possible fall down of


frame.

9.1.1
9.1.2

9.1.3
B

9.2

Slip, trip and fall


hazards.

MED

9.2.1

LOW 9.2.2
9.2.3

All employees shall wear inspected full 8.1.1.1


body harness fitted with twin lanyards
with shock absorbers, each lanyard
shall be fitted with dual action selflocking safety hook to allow for 100%
Tie-off.
Ensure that all employees working at
height are properly trained.
9.1.1.1
Tie-back to prevent frame from any
deflection and fall.
Supervisor shall ensure that work will
be supervised at all times as per work 9.1.1.2
Method Statement.
Method statement detailing the
proposed erection schemes will be
produced. These method statements
will identify hazardous site features
and other aspects likely to impair safe
erection. These proposed methods for
ensuring the stability of the framework
and its component will also be
addressed.
Area shall be properly maintained with 9.2.1.1
all equipment and materials to be
properly stored and picked up.
Housekeeping shall be on going and
picked up at the end of the day.
Material storage areas shall be
identified and properly barricaded.

ADDITIONAL
CONTROLS

LOW

LOW

LOW

Discuss working at height


hazards daily in TSTI.

Barricade and secure the


area to prevent unauthorized
entry.
Provide competent banks
man to control passerby.

Remove any unnecessary


materials.

Page 21 of 26

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T.4.250.896

Q A T A R

SCOPE : Steel Structure Assembly and


Erection

Initial Risk
ITEM

10

ACTIVITY

HAZARD / POTENTIAL
CONSEQUENCES

Final tightening of 10.1


bolts using electric
& mechanical
wrench.

Residual Risk

CURRENT
CONTROLS

RISK
RANK

Electric shock.

10.1.1
10.1.2
B

MED
10.1.3

10.2

Hand & Finger injuries.


C

10.3

Slip, Trip & Fall from


same level due to
cluttered area.

Ensure employee wear suitable gloves


when using mechanical torque wrench.

10.2.2

Only qualified & trained employee will


carry out the task.
Housekeeping shall be a priority, walk 10.3.1.1 Keep cables, materials, tools
neatly organized.
and work areas shall be kept free of
materials.
Remove any unnecessary materials.

Roof installation.

11.1

LOW

Dropped materials.

11.1.1

LOW

LOW

MED

LOW

10.3.2
11

10.1.1.1 Ensure all electrical


Insulate yourself from work and
equipment were properly
ground.
grounded and built with
Ensure tools/equipment are of correct
ELCB at their source.
type, size and they are in good
10.1.1.2 Dont touch electrically live
condition and inspected and color
parts with skin or wet
coded.
clothing.
Ensure good electrical connection.

10.2.1

10.3.1
C

ADDITIONAL
CONTROLS

HIGH

11.1.2

11.1.3

Install barricades "exclusion zone" with 11.1.1.1 Remove any unnecessary


materials.
sign boards indicating roofing works in
progress to prevent unauthorized
entry.
11.1.1.2 Provision of Watchman with
All materials shall be safety lowered
whistle & vest to control
from one level to the next either by
people from barricaded area.
hand-to-hand or by securely attaching
a rope and hauling.
Tools shall be tied by a retaining rope
attached to the harness.

Page 22 of 26

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T.4.250.896

Q A T A R

SCOPE : Steel Structure Assembly and


Erection

Initial Risk
ITEM

ACTIVITY

HAZARD / POTENTIAL
CONSEQUENCES
11.2

RANK

Wind hazard.

Residual Risk

CURRENT
CONTROLS

RISK

11.2.1

100 % fall protection system.

11.2.2

Monitor wind speed using


Anemometer. Crane operations should
be stopped at greater than 25 knots.

LOW 11.2.3

Lifting work must be stopped during


strong wind as per crane
manufacturers recommendations.
Ensure all roofing sheets to be
secured on the ground and on the roof.

11.2.4

11.3

11.4

12

Sliding installation. 12.1

Unprotected edges or
openings.

11.3.1
C

HIGH

MED

Lifeline failure.

11.3.2
11.4.1

Dropped materials.

12.1.1

HIGH

12.1.2

12.1.3

ADDITIONAL
CONTROLS

LOW

MED

LOW

MED

11.2.1.1 Employees should be aware


of the affect of weather
conditions on the operation.

11.3.1.1 Ensure that all employees


working at height are
properly trained with proper
TSTI.
11.4.1.1 Lifeline should be inspected
prior to its use and erected
by a competent person.
Install barricades "exclusion zone" with 12.1.1.1 Remove any unnecessary
materials.
sign boards indicating sliding works in
12.1.1.2 Discuss in daily TSTI.
progress to prevent unauthorized
entry.
All materials shall be safety lowered
from one level to the next either by
hand-to-hand or by securely attaching
a rope and hauling.
Tools shall be tied by a retaining rope
attached to the harness.
Full body harness and lanyards shall
be inspected & color code or tagged.
Harness and safety line when work is
greater than 1.5 meters.
Ensure lifeline has a design
calculation/Engineering design.

Page 23 of 26

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T.4.250.896

Q A T A R

SCOPE : Steel Structure Assembly and


Erection

Initial Risk
ITEM

ACTIVITY

HAZARD / POTENTIAL
CONSEQUENCES
12.2

Residual Risk

CURRENT
CONTROLS

RISK
RANK

Wind hazard

12.2.1
12.2.2

LOW

12.2.3

12.2.4

12.3

Poor illumination/ No
lights

12.3.2

Employees shall wear clear lens safety


glasses.
All access should be cleared of all
materials.
Lighting shall be set up to prevent
shadows.
Lighting shall be set up in such a way
that it does not blind employees.

12.3.4
12.3.5
12.3.6

12.4

12.5

Personnel injury from


poor body position.

12.4.1
B

LOW

Fall of personnel, while


working at heights.

12.4.2
12.5.1

Lifting work must be stopped during


strong wind as per crane
manufacturers recommendations.
Ensure all roofing sheets to be
secured on the ground and on the roof.
Provide suitable area flood lighting to 12.3.1.1 Refer to Lighting Plan.
ensure the workers have sufficient light 12.3.1.2 Obtained Extended Work
Hours/Night Work Request
to allow accurate depth perception with
with prior approval.
elimination of shadows.

LOW

MED
12.5.2

LOW

LOW

LOW

LOW

100 % personal fall protection system. 12.2.1.1 Employees should be aware


of the affect of weather
conditions on the operation.
Monitor wind speed using
Anemometer. Crane operations should
be stopped at greater than 25 knots.

12.3.1

12.3.3
B

ADDITIONAL
CONTROLS

Provide adequate lighting ( Light


Towers or Flood Lights) around the
work fronts, access roads and welfare
facilities.
Warn employees of pinch or crush
12.4.1.1 Discuss in daily TSTI.
points.
Two tag lines shall be attached to
control the loads.
All employees shall wear inspected full 12.5.1.1 Discuss working at height
hazards at daily TSTI.
body harness fitted with twin lanyards
Provided Man Lock hole, to
with shock absorbers, each lanyard
tie off Land yard.
shall be fitted with dual action selflocking safety hook for 100% Tie-off.
Ensure 100% fall protection.

Page 24 of 26

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T.4.250.896

Q A T A R

SCOPE : Steel Structure Assembly and


Erection

Initial Risk
ITEM

13

ACTIVITY
Using of Manlift.

HAZARD / POTENTIAL
CONSEQUENCES
13.1

Residual Risk

CURRENT
CONTROLS

RISK
RANK

Mechanical breakdown.

13.1.1

13.1.2
B

LOW

13.1.3
13.1.4

13.1.5
13.2

Improper use of
equipment.

13.2.1

LOW

13.2.2
13.2.3

13.3

Untrained personnel.

13.3.1

13.3.2
B

LOW
13.3.3
13.3.4

ADDITIONAL
CONTROLS

13.1.1.1 Ensure equipment to be


Equipment shall be serviced,
provided with controls of the
maintained and inspected as per set
Dead man type, which only
maintenance and inspection program.
allow movement of the
Ensure E-Stop is in place through the
machine to take place whilst
control system.
they are actually being
Perform equipment daily check prior to
operated. Dead man controls
use.
automatically return to the
Supervisor shall ensure that work will
neutral position.
be properly supervised as per Work
Method statement.
Ensure an emergency stop should be
provided on the platform control panel.
Manlift shall not be used as cranes or 13.2.1.1 Ensure all equipments are
inspected / approved & color
jacks unless they have specifically
coded.
been designed for this purpose by their
manufacturers.
Leaning out of the platform shall be
avoided.
Color coded inspected sticker should
be available on the equipment.
Ensure platforms must only be used by 13.3.1.1 Ensure supervisor who will
using manlift should be
authorized personnel who have been
particularly aware of the
trained in the operation of the type of
hazards which may be
platform in use.
encountered while using
Initial training should cover operating
these machines and of the
principles, machine controls and
precautions which may be
environmental conditions, which are
taken to eliminate or
likely to be encountered.
minimize there hazards.
Training and practice in the type of
work to be undertaken is essential.
Ensure that equipment operator is
certified by Third party, valid
certificates.

LOW

LOW

LOW

Page 25 of 26

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T.4.250.896

Q A T A R

SCOPE : Steel Structure Assembly and


Erection

Initial Risk
ITEM

ACTIVITY

HAZARD / POTENTIAL
CONSEQUENCES
13.4

Residual Risk

CURRENT
CONTROLS

RISK
RANK

Fall of personnel.

13.4.1

MED
13.4.2

13.5

Overturning of
machines.

13.5.1

13.5.2

MED

13.5.3

13.5.4

13.6

Vehicle movement.

13.6.1
B

LOW

13.6.2

ADDITIONAL
CONTROLS

13.4.1.1 Discuss working at height


Safety harness shall be provided for
hazards at daily TSTI.
the use of all personnel working from
13.4.1.2 Supervisor shall ensure that
mobile work platforms so that in the
work will be properly
event of any advertent movement of
supervised at all times as per
the platform they are working from,
work Method Statement.
they will not be thrown from it.
Provided Man Lock hole/live
Boxes, hop-ups or ladders shall never
wire to tie off Land yard.
be used to gain additional height or
reach from the platform of manlift
machine/ work platform.
Ensure no excessive force is used by 13.5.1.1 When a manlift needs to
work in confined area, an
the operator on the platform, by
approval for the operation
introducing an element or side load.
shall be obtained.
13.5.1.2 Considered the effects of
The outriggers or stabilizers, when
acceleration and
fitted, shall be fully extended and in
deceleration.
position, before the platform or boom
is raised.
The platform shall not be overloaded
exceeding the regulated Safe Working
Load.
Ensure the machine shall be placed to 13.5.4.1 Ensure the boom to be well
within the limits of control.
the most suitable position for the job to
be carried out before any slewing
takes place. Slewing the boom to the
extent that causes the machine to
overturned shall be avoided.
13.6.1.1 Barricade and secure the
Ensure all vehicle movement to be
working area with sign
guided by competent banks men with
boards to prevent
High visibility vests.
unauthorized entry.
Ensure that each piece of equipment is
fitted with an automatic reverse alarm
and beacon or strobe light.

MED

LOW

LOW

Page 26 of 26

You might also like