Professional Documents
Culture Documents
Clean Energy
Decision Support Centre
www.retscreen.net
Worksheets
Energy Model
Load & Network
Equipment Selection
Cost Analysis
Greenhouse Gas Analysis
Financial Summary
Sensitivity & Risk Analysis
Tools
Features
Product Data
Weather Data
Cost Data
Unit Options & Fuel Value Ref.
Language Options
Currency Options
CDM / JI Project Analysis
Version 3.5
Partners
NRCan/CETC - Varennes
English - Anglais
$
Metric units
Imperial units
Project name
Project location
Proposed project
Unit
Estimate
kW
MWh
MWh
Gas turbine
Power load following
30
196
0
kW
kW
MWh
Grid electricity
652
652
1,652
Base
Peak
120%
4.6%
10.6%
100%
80%
60%
40%
100.0%
89.4%
20%
0%
Load
(kW)
kW
Demand
(MWh)
Base
kW
MWh
Gas turbine
165.7
770
Peak
140%
30.4%
69.9%
120%
100%
Not required
$/GJ
kW
kW
MWh
Boiler
Natural gas - GJ
5.000
545.8
545.8
332
65%
kW
MWh
Desiccant
Heating system
233.0
353
80%
60%
40%
100.0%
30.1%
See PDB
1 unit(s)
20%
0%
Load
(kW)
Demand
(MWh)
Base
113.7%
100.0%
150%
100%
50%
0%
Load
(kW)
Demand
(MWh)
Capacity
(kW)
Energy
delivered
(MWh)
Fuel type
Fuel
consumption unit
Natural gas
Electricity
GJ
MWh
6,258
1,652
Total
30
652
682
196
1,652
1,847
Heating
Base load
Peak load
Recovered heat
Natural gas
GJ
1,841
Total
166
546
712
770
332
1,103
Cooling
Base load
Heating system
Total
233
233
353
353
Fuel
consumption
Clean Energy
production credit?
19/12/2005; CHP16-B.xls
RETScreen Load & Network Design - Combined cooling, heating & power project
Heating project
Site conditions
Nearest location for weather data
Heating design temperature
Annual heating degree-days below 18C
Domestic hot water heating base demand
Equivalent degree-days for DHW heating
Equivalent full load hours
Unit
Notes/Range
See Weather Database
-40 to 15 C
Complete Monthly inputs
0% to 25%
0 to 10 C-d/d
Monthly inputs
Month
January
February
March
April
C-d
<18C
896
718
574
299
F-d
<65F
1,613
1,292
1,032
539
Estimate
Minneapolis/St.paul
-23.0
4,221
10%
1.3
2,156
C
C-d
%
C-d/d
h
m
%
5,000
Natural gas - GJ
65%
W/m
MWh
kW
GJ
$/GJ
75.0
809
375.0
4,478
5.000
$
%
kW
MWh
22,390
0%
375.0
809
19/12/2005; CHP16-B.xls
Month
May
June
July
August
C-d
<18C
91
0
0
0
F-d
<65F
165
0
0
0
Month
September
October
November
December
C-d
<18C
65
266
518
794
F-d
<65F
117
479
932
1,430
RETScreen Load & Network Design - Combined cooling, heating & power project
Cooling project
Unit
Site conditions
Nearest location for weather data
Cooling design temperature
Annual cooling degree-days above 10C
Non-weather dependant cooling
Equivalent full load hours
C
C-d
%
h
Notes/Range
See Weather Database
10 to 47 C
Complete Monthly inputs
5% to 30%
Monthly inputs
Month
January
February
March
April
C-d
>10C
0
0
0
0
F-d
>50F
0
0
0
0
Estimate
Minneapolis/St.paul
31.0
1,405
0%
1,722
m
%
5,000
Electricity
300%
W/m
MWh
kW
MWh
$/kWh
41.0
353
205.0
118
0.110
$
%
kW
MWh
12,944
0%
205.0
353
19/12/2005; CHP16-B.xls
Month
May
June
July
August
C-d
>10C
157
311
409
352
F-d
>50F
282
560
737
634
Month
September
October
November
December
C-d
>10C
175
0
0
0
F-d
>50F
315
0
0
0
RETScreen Load & Network Design - Combined cooling, heating & power project
Unit
Power project
Base case power system
Grid type
Central-grid
Month
Ja January
Fe February
Ma March
Ap April
Ma May
Ju June
Ju July
Au August
Se September
Oc October
No November
De December
Power
gross average load
kW
22
22
22
500
500
500
500
500
22
22
22
22
Power
net average
load
kW
22
22
22
500
484
466
457
463
3
22
22
22
Cooling
% time
process
operating
0%
0%
0%
50%
90%
100%
100%
100%
70%
30%
0%
0%
Cooling
average load
kW
0
0
0
0
49
101
129
111
57
0
0
0
Heating
% time
process
operating
0%
0%
40%
100%
100%
100%
100%
100%
100%
100%
100%
30%
Heating
average load
kW
249
192
121
68
29
6
7
7
21
58
112
187
48.0%
740
672
672
Return
100%
205
Return
100%
375
MWh
$/kWh
$
2,022
0.110
222,412 $
Month
January
February
March
April
May
June
July
August
September
October
November
December
Cooling
system
load
kW
0
0
0
0
49
101
129
111
57
0
0
0
Heating
net average
load
kW
249
192
121
68
29
6
7
7
21
58
112
187
Heat
for
cooling
kW
0
0
0
0
41
84
107
92
48
0
0
0
Heating
system
load
kW
249
192
121
68
70
90
114
99
69
58
112
187
652
652
0
0
652
652
205
375
171
546
1,904
0.110
209,469
Proposed case system load characteristics graph
600
500
400
Power
Heating
Cooling
400
Power
Heating
Cooling
300
kW
kW
Power
system
load
kW
21
21
21
485
469
452
443
449
3
21
21
21
500
200
300
200
100
Power
for
cooling
kW
0
0
0
0
0
0
0
0
0
0
0
0
600
0
Jan
Power
net average
load
kW
21
21
21
485
469
452
443
449
3
21
21
21
100
Feb
Mar
%
kW
MWh
Apr
May
Jun
Jul
Aug
Sep
3%
652
1,847
Oct
Nov
0
Jan
Dec
Feb
Mar
Apr
kW
MWh
May
Power
652
1,847
Jun
Jul
Aug
Sep
Oct
Nov
Heating
545.8
1,103
19/12/2005; CHP16-B.xls
Dec
Cooling
205.0
353
kW
%
MWh
Desiccant
Heating system
233.0
120%
Broad
BS20
353
600
500
400
113.7%
300
200
100
1 unit(s)
100.0%
Power
Not required
Jul
Heating
Cooling
Gas turbine
8,300
$/GJ
Single fuel
Natural gas - GJ
5.000
kW
%
MWh
MWh
kJ/kWh
%
GJ/h
kW
30
0%
196
0
Capstone
C30
32,000
70%
1.0
165.7
$/MWh
$/MWh
$/MWh
$/MWh
$/MWh
27.69
110.00
18.00
112.00
112.00
Operating strategy
Full power capacity output
Power load following
Heating load following
Electricity delivered
to load
MWh
196
196
139
95.0%
94.7%
4.6%
10.6%
1 unit(s)
30.4%
Electricity
exported to grid
MWh
53
0
24
Remaining
electricity
required
MWh
1,652
1,652
1,708
19/12/2005; CHP16-B.xls
Heat
recovered
MWh
904
770
904
Remaining
heat
required
MWh
198
332
198
Power
system fuel
MWh
2,213
1,738
1,456
Operating
profit (loss)
$
9,400
8,250
13,490
Efficiency
%
52.1%
55.6%
73.4%
Pre-feasibility analysis
Cost reference
Feasibility analysis
Second currency
Unit
Cost reference
Quantity
None
Unit cost
Canada - 2005
Amount
Relative costs
Sub-total:
$
$
0.0%
Sub-total:
$
$
0.0%
Sub-total:
$
$
0.0%
$
$
$
$
$
$
$
$
$
45,000
45,000
Quantity range
Development
Engineering
Power system
Base load - Gas turbine
Peak load - Grid electricity
Road construction
Transmission line
Substation
Energy efficiency measures
kW
kW
30
652
$
$
1,500
-
project
project
Sub-total:
Heating system
Base load - Gas turbine
Peak load - Boiler
Energy efficiency measures
100.0%
kW
kW
project
165.7
545.8
$
$
$
$
$
$
$
$
kW
project
233.0
$
$
$
$
$
0.0%
$
$
$
$
$
45,000
0.0%
100.0%
Sub-total:
Cooling system
Base load - Desiccant
Energy efficiency measures
See manual
Sub-total:
See manual
0.0%
See manual
%
0.00%
0 month(s)
$
$
45,000
45,000
Sub-total:
Total initial costs
Annual costs (credits)
O&M
Parts & labour
O&M
Contingencies
Unit
project
cost
%
Quantity
196
0.0%
Unit cost
$
$
10
1,956
Sub-total:
Fuel
Natural gas
Electricity
GJ
MWh
8,099
1,652
$
$
5.000
112.000
Sub-total:
Total annual costs
Periodic costs (credits)
Unit
Year
Amount
5% - 40%
3% - 15%
Relative costs
$
$
$
$
1,956
1,956
0.9%
$
$
$
$
40,495
184,975
225,471
227,426
99.1%
100.0%
$
$
$
$
Amount
-
Unit cost
19/12/2005; CHP16-B.xls
Quantity range
10% - 20%
Interval range
RETScreen Greenhouse Gas (GHG) Emission Reduction Analysis - Combined cooling, heating & power project
Settings - Microturbine for Utilities - Minnesota, USA
GHG Analysis
Potential CDM project
Simplified analysis
Standard analysis
Custom analysis
(IPCC 1996)
(IPCC 1996)
Country - region
United States of America (USA)
Fuel type
Coal
GHG emission
factor
(excl. T&D)
tCO2/MWh
0.941
T&D
losses
%
5.0%
GHG emission
factor
tCO2/MWh
0.991
Change in GHG emission factor
-10.0%
GHG emission
tCO2
223
2,003
2,225
Fuel type
Natural gas
Electricity
Total
Fuel mix
%
38.1%
61.9%
100.0%
CO2 emission
factor
kg/GJ
CH4 emission
factor
kg/GJ
N2O emission
factor
kg/GJ
Fuel
consumption
MWh
1,244
2,022
3,266
GHG emission
factor
tCO2/MWh
0.179
0.991
0.681
N2O emission
factor
kg/GJ
Fuel
consumption
MWh
2,250
1,652
3,901
GHG emission
factor
GHG emission
tCO2/MWh
tCO2
0.179
403
0.991
1,636
0.523
2,039
Total
2,039
Proposed case system GHG summary (Combined cooling, heating & power project)
Fuel type
Natural gas
Electricity
Total
Fuel mix
%
57.7%
42.3%
100.0%
CO2 emission
factor
kg/GJ
CH4 emission
factor
kg/GJ
T&D losses
GHG emission reduction summary
Years of
occurrence
yr
1 to 2
Base case
GHG emission
tCO2
2,225
Proposed case
GHG emission
tCO2
2,039
187
tCO2
Gross annual
GHG emission
reduction
tCO2
187
is equivalent to
38.0
GHG credits
transaction fee
%
0%
Net annual
GHG emission
reduction
tCO2
187
19/12/2005; CHP16-B.xls
Financial parameters
General
Fuel cost escalation rate
Inflation rate
Discount rate
Project life
Finance
Incentives and grants
Debt ratio
Debt
Equity
Debt interest rate
Debt term
Debt payments
Annual income
Customer premium income (rebate)
Electricity premium (rebate)
Electricity premium income (rebate)
Heating premium (rebate)
Heating premium income (rebate)
Cooling premium (rebate)
Cooling premium income (rebate)
Customer premium income (rebate)
Capacity
kW
682
712
233
Energy
delivered
MWh
1,847
1,103
353
%
%
%
yr
2.0%
2.0%
10.0%
25
$
%
$
$
%
yr
$/yr
0.0%
45,000
7.00%
10
-
%
%
yr
yes/no
yr
%
$
%
$
%
$
$
End-use
energy rate
$/MWh
110.00
27.69
36.67
30.0%
No
None
95.0%
30.0%
15
No
3
0.0%
0.0%
0.0%
-
MWh
$/MWh
$
%
2.0%
MWh
$/kWh
$
yr
%
0
0.020
10
2.0%
tCO2/yr
tCO2/yr
tCO2
$/tCO2
$
yr
tCO2
%
187
4,671
5.00
21
3,923
2.0%
Fuel cost
$
209,469
22,390
12,944
244,802
End-use
energy rate
$/MWh
117.08
8.35
0.00
Fuel cost
$
216,266
9,204
0
225,471
$
$
$
$
$
$
$
$
45,000
45,000
$
$
$
$
1,956
225,471
227,426
$
$
$
$
$
$
$
$
$
$
244,802
244,802
%
%
%
%
yr
yr
$
$/yr
$/tCO2
41.4%
41.4%
41.4%
41.4%
2.6
2.5
142,999
15,754
4.18
No debt
(84)
After-tax
Cumulative
$
(45,000)
17,724
18,078
18,440
18,808
19,185
19,568
19,960
20,359
20,766
21,181
21,605
22,037
22,478
22,927
23,386
23,854
24,331
24,817
25,314
25,820
26,336
26,863
27,400
27,948
28,507
-
$
(45,000)
(27,276)
(9,198)
9,241
28,050
47,234
66,803
86,762
107,121
127,887
149,069
170,674
192,711
215,189
238,116
261,502
285,356
309,686
334,504
359,817
385,637
411,974
438,837
466,237
494,186
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
522,693
500,000
GHG reduction income
400,000
300,000
200,000
100,000
0
0
10
(100,000)
Year
19/12/2005; CHP16-B.xls
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
RETScreen Sensitivity and Risk Analysis - Combined cooling, heating & power project
Sensitivity analysis for After-tax IRR - equity
After-tax IRR - equity
20%
12
%
Perform analysis on
Sensitivity range
Threshold
-20%
-10%
0%
10%
20%
36,000
-20%
negative
negative
51.2%
120.6%
190.0%
40,500
-10%
negative
negative
45.8%
107.4%
169.1%
Initial costs
45,000
0%
negative
negative
41.4%
96.9%
152.4%
49,500
10%
negative
negative
37.8%
88.2%
138.7%
$
54,000
20%
negative
negative
34.8%
81.1%
127.3%
-20%
-10%
0%
10%
20%
36,000
-20%
179.0%
115.1%
51.2%
negative
negative
40,500
-10%
159.3%
102.5%
45.8%
negative
negative
Initial costs
45,000
0%
143.6%
92.5%
41.4%
negative
negative
49,500
10%
130.7%
84.3%
37.8%
negative
negative
$
54,000
20%
120.0%
77.4%
34.8%
negative
negative
-20%
-10%
0%
10%
20%
36,000
-20%
52.3%
51.8%
51.2%
50.7%
50.1%
40,500
-10%
46.7%
46.2%
45.8%
45.3%
44.8%
Initial costs
45,000
0%
42.3%
41.8%
41.4%
40.9%
40.5%
49,500
10%
38.6%
38.2%
37.8%
37.4%
37.0%
$
54,000
20%
35.5%
35.2%
34.8%
34.4%
34.0%
Value
45,000
1,956
225,471
244,802
Range (+/-)
10%
10%
10%
10%
Minimum
40,500
1,760
202,924
220,322
Maximum
49,500
2,151
248,018
269,283
O&M
$
1,565
1,760
1,956
2,151
2,347
Perform analysis on
Parameter
Initial costs
O&M
Fuel cost - proposed case
Fuel cost - base case
Unit
$
$
$
$
-0.80
-0.60
-0.40
-0.20
0.00
0.20
0.40
0.60
0.80
$
%
$
$
134,999
20%
-12,065
300,486
Frequency
10%
8%
6%
4%
2%
0%
-214,467
-145,041
-75,616
-6,190
63,235
Minimum
132,661
202,087
271,512
Median
340,938
Maximum
10.0%
(12,065)
410,364
134,999
19/12/2005; CHP16-B.xls
10.0%
300,486
Unit conversion
GHG equivalence
Heat rate
Custom 1
Landfill gas
Custom 2
As fired fuel
Custom 3
Unit conversion
Distance
Area
Volume
Weight
Pressure
Temperature
Power (load)
Energy (demand)
Heating value
Emission factor
Load
Unit
Quantity
Unit
Quantity
mi
m
m
kg
bar
C
1.0000
1.0000
1.0000
1,000.0000
1.0000
10.0000
m
ft
ft
t
kPa
F
1,609.3440
10.7639
35.3147
1.0000
100.0000
50.0000
MW
MJ
MJ/kg
kg/GJ
W/m
1.0000
1.0000
10.0000
50.0000
70.0000
RT
Btu
Btu/lb
kg/kWh
Btu/ft
284.3451
947.8171
4,299.2261
0.1800
22.1899
187
tCO2
is equivalent to
159
GHG equivalence
Net annual GHG emission reduction
19/12/2005; CHP16-B.xls