Professional Documents
Culture Documents
Abstract
Recent studies have shown the X-bar control chart with variable sampling interval detects shifts
in the process mean faster than the traditional X-barchart.These studies are usually based on the
assumption that the process data are independently and normally distributed. However, many
situations in practice violate these assumptions. In this study, a methodology is developed to
economically design a variable sampling interval X-barcontrol chart that takes into consideration
correlated non-normal sample data. An example is provided to illustrate the solution procedure.
A sensitivity analysis on the input parameters (i.e., the cost and the process parameters) is
performed taking into account the non-normality and the correlation on the optimal design of the
chart.
Keywords: X-bar control chart; Economic design; Variable sampling interval; Non-normality;
Correlated process data; Genetic algorithms
Corresponding author
sampling interval ( h ), and the control limits width ( k ). Shewhart considered these parameters
fixed, however recent studies have shown that varying the sampling interval (VSI), the sample
size (VSS), the sampling interval jointly with the sample size (VSSI), or all design parameters at
the same time, including k , (VP) reduce the detection time of process changes (see for example,
Reynolds et al., 1988; Baxley, 1996; Prabhu et al., 1993,1994; Costa, 1994, 1997, 1999). Further,
a survey of studies on VSR charts is presented in Tagaras (1998).
Duncan (1956) proposed the first economic model to determine the optimal values of n ,
h , and k of an X chart. Since then, the economical design of control charts has received
increasing attention in the literature (e.g., Montgomery, 1980; Vance, 1983; Woodall, 1986;
Pignatiello and Tsai, 1988; Niaki et al. 2010). The usual approach in an economical design is to
develop a cost model for a special type of industrial process, and then derive the optimal
parameters by minimizing the expected cost per unit of time.While Duncans (1956) and Chius
(1975) models for the economic design of control charts have been widely studied in practice, in
the former the process remains in operation during the period of search for the assignable cause
and in the latter the process is ceased.
In the design process of the Shewhart X control chart, one assumes the measurements
(observations) within the subgroups are independently and normally distributed. However, these
assumptions may not hold in many practices. For example, when a production process consists of
2
multiple but similar units on a single part, such as several cavities on a single casting, multiple
pins on an integrated circuit chip, or multiple contact pads on a single machine mount, the
collected measurements within a subgroup are usually correlated (Grant and Leavenworth 1988).
Neuhardt (1987) considered the effect of correlation within a subgroup on the performances of
control charts. Yang and Hancock (1990) employed Neuhardts idea to conduct simulation
studies to specify the effect of correlated data on the performances of X , R, S and S2 charts. Liu
et al. (2002) used the correlation model of Yang and Hancock (1990) to develop a minimum-loss
design of fixed sample size and sampling interval (FSI) charts for correlated data. Chen and
Chiou (2005) combined Yang and Hancocks correlation model (1990) with the cost model of
Bai and Lee (1998) to make the economic design of the VSI charts for correlated data. Recently,
Chen et al. (2007) incorporated the Yang Hancocks correlation model (1990) with the cost
model of Costa (2001) to develop an economic design of the VSSI charts for correlated data.
If the size of subgroups (sample size) is large enough, the statistic X is approximately
normal based on the central limit theorem. However, when a control chart is applied to monitor
the process, unfortunately the sample size is usually not sufficiently large due to the sampling
cost. As a result, due to non-normality, the traditional method of designing the control chart may
decrease the ability of detecting assignable causes. Yourstone and Zimmer (1992) considered the
Burr distribution to represent the non-normal distributions and statistically designed the X chart.
Chen (2004) presented the economic design of VSI X control charts for non-normal data. Lin
and Chou (2005) employed the Burr distribution to design both symmetric and asymmetric-limit
VSSI X chart under non-normality. Recently, Lin and Chou (2007) studied the effect of nonnormality on the performances of adaptive X control charts (i.e., variable sample size, sampling
intervals, and and/or action limit coefficients) and concluded the VP X control chart is more
3
effective than the other adaptive charts in detecting small process mean shifts under non-normal
process data.
In this research, the economic model of the VSI X chart for correlated non-normal
process data is developed using Burr distribution and the correlation model presented in Yang
and Hancock (1990). The FSI and VSI schemes are compared in terms of the long-run expected
cost per hour and statistical performances for various levels of correlation.
The remainder of the paper are as follows. In the next section, the concept of the VSI
control charts is briefly discussed. The Burr distribution representing the various types of nonnormal distributions is introduced in section 3. The economic model based on the Burr
distribution that works under correlated process data is developed in section 4. A solution
method to find the optimal values of the design parameters of an asymmetric VSI X chart is
presented in section 5. Sensitivity analysis on the process parameters and correlation coefficients
are conducted in section 6. Finally, conclusions make up the last section.
the control limit width) the process is considered in-control and the next sample is taken in a
fixed interval of h1 time. Otherwise, a signal is sent to inform the operator to search for an
assignable cause. This control chart is said to operate in a fixed sample-size ( n ) and fixed
sampling interval (h1 ) (FSI) condition.
When the VSI scheme is in use, the waiting time h until the next sampling point is a
function of the current x value. In other words, if x I i ; i 1, 2 , then h hi where
I 1 0 k '1
, 0 k ' 2
, 0 k 1
0 k 2
n
n
n
n
I 2 0 k ' 2
, 0 k 2
n
n
(1)
with 0 k 2 k 1 , 0 k 2' k 1' , and h2 h1 0 . According to Chen (2004), the slight cost savings
offered by the VSI schemes with more than two sampling interval sizes does not justify their use.
As an example, Fig. 1 depicts a VSI X chart using two interval lengths of h1 and h2 .
The sample means in Fig.1 are plotted against the time on the horizontal axis. The first
sample mean falls within I 2 , so the next sampling interval is h2 . The second one falls within I 1 ,
which is close to the control limits. Hence, a shorter sampling interval is adopted to take the third
sample and so on.
The way the VSI X control charts work can improve the detection ability of FSI charts
by shortening the length of time until a signal is occurred. Nonetheless, the complexity will
increase when the number of divided areas becomes large. Further, traditional symmetric VSI
charts can be easily obtained by setting k 1 k '1 .
k
1
F y 1 y c
y0
y <0
F y 1
1 Max 0, y
c
f y
cky c 1
1 y c
y 0
(2)
Burr (1942) tabulated the first two moments (given in a Table numbered 2) and the
coefficients of skewness and kurtosis (given in another Table numbered 3) for the family of the
Burr distribution. These tables allow users to make a standardized transformation between the
variable of the Burr distribution (Y ) and any other random variable ( X ) when they have the
same coefficients of skewness and kurtosis. The standardized transformation between Y and
X is defined as follows:
X X Y M
Sx
S
(3)
Where S and M are the sample mean and standard deviation of the Burr distribution,
respectively and X and S x are the sample mean and standard deviation of the data set (as a
random variable).
Different combinations of the parameters c 1 and k 1 can cover an extensive range of
skewness and kurtosis coefficients of various probability density functions (e.g., Normal,
Gamma, Beta, etc.). For instance, when c = 4.8621 and k = 6.3412, the Burr distribution
approximates the normal distribution (Yourstone and Zimmer 1992). Further, the first four
moments of the empirical distribution can be used to determine c and k . Burr (1967) used this
distribution to study the impact of non-normality on constant coefficients of the X and R control
charts. Tsai (1990) employed the Burr distribution to design the probabilistic tolerance for a
subsystem. Yourstone and Zimmer (1992) used the Burr distribution to design the control limits
of X control charts for non-normal data. Chou et al. (2000) employed the Burr distribution for
the economic design of X charts under the presence of non-normal process data.
The economic design of the VSI X control chart is developed employing a cost function
and searching for the optimal design parameters that minimizes the cost function during a
production cycle. The derivation of the cost function comes in the next subsection.
In the derivation of the cost function, the process is initially assumed in-control 0 .
The process will then be disturbed by a single assignable cause that makes a shift of in the
mean (i.e., the out-of-control process mean becomes 0 ),where is the magnitude of
the shift. After the shift, the process remains out-of-control until the assignable cause is removed.
The inter-arrival time of the assignable cause is assumed to follow an exponential distribution
with a mean of 1 .
For monitoring purposes, a sample of size n is taken at each sampling point. If the
calculated sample mean falls inside the two control limits, its position inside the control region
will be used to specify the next sampling point; making sampling interval variable. If the sample
mean goes beyond the two control limits, the process is ceased and a search starts to find a
possible assignable cause and if necessary to adjust the process.
As in Chen (2004), the length of a production cycle is the time between the instant the
process starts in control to the time the process is stopped for adjustments. Fig. 2 shows a
production cycle (T ) that is divided into four intervals including the in-control period (T1 ) , the
out-of-control period (T 2 ) , the searching period due to a false alarm (T 3 ) , and the period for
identifying and correcting the assignable cause (T 4 ) .
Cycle
Process mean
Start
Shift
Cycle
ends
Assignable
First Sample
afterprocess
meanshift
Out-of-control
Detected
Assignable
Cause
Cause
The individual periods are now illustrated before they are grouped together.
(T1 ) : Based on the assumptions the expected length of the in-control period is 1 .
(T 2 ) : Let A be the length of the sampling interval in which an assignable cause occurs,
and Y be the time interval between sample points just prior to the occurrence of the assignable
cause and the occurrence itself (see Fig. 2). Then, Reynolds et al. (1988) showed that
m
E T 2 E A E Y S 1 1 h j P1 j
(4)
J 1
Where S 1 represents the expected number of samples required to detect the assignable cause and
P1 j represents the conditional probability that X falls within I j , given that X falls inside the
two control limits when 0 . Moreover, the number of samples in detecting the
assignable cause can be modeled by a geometric distribution with parameter q1 , (i.e., S 1 1 q1 ),
where q1 is the probability of detecting an assignable cause in a sample. Reynolds et al. (1988)
also assumed that the probability of the length of A being h j is
m
h P
Pr(A h j ) h j P0 j
j 1
(5)
0j
Where P0 j is the conditional probability that X falls within I j , given that X falls inside the
control limits when 0 . Then from the result of Duncan (1956), the conditional expected
value of Y given A h j is
E Y A h j
1 h j 1 e
1e
h j
h j
(6)
Therefore, the expected length of the out-of control period is reached using (4)(6) as:
E T 2
j 1 h j P0 j
m
P0 j h j h j 1 e
j 1
1e
h j
h j
1 1 h j P1 j
(7)
j 1
(T 3 ) : Let S 0 be the expected number of samples in the in-control state. Then, Bai and
Lee (1998) showed that
S0
j 1
P0 j e
m
j 1
h j
P0 j e
h j
P
j 1
0j
1 e
h j
(8)
t 1q 0S 0
where q 0 is the false alarm rate and that an average of t 1 hours is spent if the signal is a false
alarm.
10
(T 4 ) : The time to identify and correct the assignable cause following an action signal is
assumed a constant t 2 .
Thus, the expected length of a production cycle can be aggregately represented by
E (T ) E (T1 T 2 T 3 T 4 )
1
m
j 1
h j P0 j
P0 j h j h j 1 e
j 1
1e
h j
h j
1 1 h j P1 j t 1q 0S 0 t 2
(10)
j 1
The expected cost of a production cycle includes (a) the cost of false alarms; (b) the cost
of detecting and eliminating the assignable cause; (c) the cost associated with production in the
out-of-control condition; and (d) the cost of sampling and testing. Defining c1 the average search
cost of a false signal, c 2 the average cost to discover the assignable cause and adjust the process
to in-control state, c 3 the hourly cost associated with production in an out-of-control state, c 4 the
fixed sampling cost for each sample, and c 5 the variable cost of sampling and testing in each
sample, the expected cost of a production cycle, E (C ) , becomes:
E (C ) c1 q 0S 0 c 2 c 3 E T 2 c 4 c 5 n S 0 S 1
(11)
The aim of the economic design of a VSI X control chart with generalized control limits
is to determine the appropriate values of design parameters n , k 1 , k 2 , k '1 , k '2 , h1 , h2 such that
the expected cost per hour, ECT , given in (12) is minimized
ECT
E (C ) c1 q 0S 0 c 2 c 3 E T 2 c 4 c 5 n S 0 S 1
1
E (T )
E T t q S t
1 0
(12)
Note that ECT is a function of both the process and the cost parameters.
Since the objective of this research is to develop an economical design of the VSI X
control chart under correlated non-normal process data, in the next section, correlated data is first
11
considered. Then we take advantage of the Burr distribution to model non-normal data in section
4.3. These modeling can help determine the values of P0 j and P1 j used in (12).
X [X 1 , X 2 ,..., X n ]T following
multivariate
normal
distribution
N (, V ) ,
where
V 2 R , where R {rij ; i 1,..., n , j 1,..., n } is the correlation matrix, the sample mean X
can be shown to be normally distributed with mean and variance as follows:
E(X )
V(X )
(13)
1 n 1
n
(14)
Where
ij
i#j
n n 1
(15)
The mean and variance of X are still valid even if the measurements are not normally
distributed.
Now, let O 0 and O1 be the conditional probabilities that any sample mean X falls outside
the control limits, given that the process is in control ( 0 ) and out of control ( 0 ),
respectively. The conditional probabilities O 0 and O1 are also called the false alarm rate and the
12
failure-detection power of a control chart, respectively. Then by denoting the upper and the
lower control limits of the X chart by UCL and LCL , respectively, we have
UCL 0 k 1
LCL 0 k 1'
(16)
O 0 1 Pr LCL X UCL 0
Pr X UCL 0 Pr X LCL 0
O 0 Pr
X 0
n 1 n 1
Pr
X 0
k1
k 1
1 n 1
'
n 1 n 1
1 n 1
(17)
Similarly O1 becomes
O1 =1 Pr LCL X UCL 0
k ' n
X 0
k1 n
1
1 Pr
1 n 1
n
1 n 1
(18)
The skewness and kurtosis coefficients of the sample mean X (based on a sample of size
n ) according to Dodge and Rousson (1999) are, respectively,
3 X
3
n
, 4 X =
4 3
n
+3
(19)
13
In which 3 and 4 denote the skewness and kurtosis coefficients of the random variable
X (modeling the population). Using the values of 3 (X ) and 4 (X ) and the tables of the Burr
distribution (1942), one can obtain the values of M , S , c , and k for the distribution with
skewness and kurtosis values close to the 3 (X ) and 4 (X ) through the interpolation.
Now, using the Burr transformation given in (2) and (3), expressions for O 0 , O1 , P0 j ,
P0 m , P1 j , and P1m are derived in the equations A.1 to A.6 of the appendix, respectively.
An examination of the probability components in (12) reveals that finding the optimal
values of the parameters n * , k 1* , k 2* , k 1'* , k 2' * , h1* , h2* of the VSI X chart using a conventional
optimization method is not simple. As a result, to describe the nature of the solutions obtained
for the economic design of the VSI X control chart under correlated non-normal process data, a
numerical example is provided and a parameter-tuned genetic algorithm (GA) is developed to
search for a near optimal solution. The numerical example is borrowed from Chou et al. (2002)
and is modified to demonstrate the methodology. In this example, the input based on the
historical data is:
1.05E
8.40E
V
7.80E
6.90E
deviation are computed x 0.5 and S x 0.001 , respectively. For a given sample size, in order
to calculate the probabilities Pij and ultimately ECT we first find the skewness and kurtosis
using Equation
(19). Next, using the Burr (1942) Tables II and III the values of M , S , c , and k that correspond
to 3 X and 4 X are obtained using interpolation. Finally, equations (A.1)-(A.6) are used to
determine the probabilities P0 j , P0 m , P1 j , and P1m that are required to evaluate ECT in (12). The
solution procedure is carried out using a parameter-tuned GA to obtain the near optimal values of
n , k
*
*
1
the integer sample size n , decimal coding is applied. The initial population contains 40 feasible
chromosomes that are randomly generated. The fitness value of each solution in the initial
population is evaluated by ECT in (12) and the chromosome with the lowest cost replaces the
one with the highest cost. The best 20% of the chromosomes are the survivors for the next
generation. For the crossover operation, among the second 20% of the chromosomes, the parents
are selected using the Rolette-Wheel method, in which the crossover point is randomly selected
and the crossover operation on the parents are performed with the probability of 0.5. In this step,
if a gene does not satisfy its corresponding constraints, its value is transformed to an acceptable
15
value within the range uniformly. Moreover, the mutation is performed with a probability of 0.3.
These steps are continued until the stopping condition, 1500 generations, is achieved.
By employing the proposed GA on the economic designs of both the FSI and VSI X-bar
charts, the near optimal solutions along with the minimum costs are obtained as given in Table
(1). As shown in this table, the cost function ETC of Equation (12) gives a minimum of $4.748
if the sample size, the sampling interval, and the control limit coefficient are fixed (FSI).
However, a minimum cost of $3.335 is obtained when the sample size and the control limit
coefficient are fixed and the sampling intervals change (VSI), resulting in 29.76% cost savings.
Table (1): The optimal designs of the FSI and VSI X-Bar control chart
X-Bar
h1
FSI
0.520
VSI
0.010
h2
k1
k2
2.457
1.361
k 1'
k 2'
2.796
ETC
% decrease
4.748
3.335
29.76
In the operations of the GA,the quality of the solution obtained depends on the setting of
its control parameters: the population size (PS), the crossover probability (CP), the mutation rate
(MR), and the generation number (GN) (Chen 2006). In order to find the optimal setting of these
parameters, an orthogonal array experiment is performed on three different levels of the
parameters. Based on three replicates and the smaller-the-better criterion on the signal-to-noise
ratio, the optimal combination level of the control parameters is obtained as PS=40, CP=0.5,
MR=0.3, GN=1500.
16
6. Sensitivity analyses
In this section, a sensitivity analysis is conducted to understand how typical the given
numerical example is and to explore the effect of the model parameters on the solution of the
proposed economic design of the VSI X control chart under correlated non-normal process data.
Since the chart is designed without knowing the shift direction, the optimization should
consider the overall better performance taking into account process mean increases and process
mean decreases. As a result, different cost parameter settings are considered for each of which
the near optimal solution of the economic model of both the FSI and VSI X-Bar control chart
along with its expected cost per hour is obtained for positive and negative mean shifts in Tables
(2) and (3), respectively. In these tables, is the false alarm risk. Further, similar to the tables
given in Chen (2004), we set k 1' k 2' ; for 0 (and k 1 k 2 ; for 0 ) and added them to
the constraints in the optimization model. By this way, the chart is designed without lower
(upper) limits in case of increase (decrease) in the process mean. Moreover, a constraint in the
optimization model was added to avoid false alarm risks of bigger that 0.05, and another
constraint was added to avoid h1 smaller than 0.01.
While previous research works (Bai and Lee 1998, Chen 2004, Chen and Chiou 2005,
and Chen et al. 2007) only considered positive mean shifts, a careful examination of the results
in Table (3) reveals that the optimal sample size of "one" has been obtained in all cases in which
negative mean shifts are considered. Based on Equations (A.2)-(A.6), this means the correlation
should not have any effect on the probabilities obtained to reach the near optimal solution.
Moreover, Table (4) summarizes the performances of the economic design of X control charts
for process data with different levels of correlation coefficients and Table (5) shows the
percentage reductions in cost obtained using the VSI X-Bar chart.
17
The results given in Tables (2) and (5) reveal the following findings:
1. For positive mean shifts, the expected cost per hour of the VSI control schemes are
consistently smaller than that of the FSI control scheme over the 15 parameter
combination sets.
2. Compared with the FSI schemes, in most cases the corresponding VSI scheme tends to
operate with a larger upper control limit ( k 1 ) and the same (or sometimes smaller)
sample size.
3. The percent reduction in ECT is reduced when small or intermediate mean shifts ( = 0.5
or 1) are encountered.
4. The percentage reduction in ECT is significantly increased due to higher searching cost
(involving c1 and c 2 ), lower sampling cost (involving c 4 and c 5 ), when the production
cost in the out-of-control state is large and when is small. Other parameters such as t 1
and t 2 do not significantly affect the ECT.
5. In most cases, false alarm rate () of the X control chart for the VSI scheme is smaller
than the FSI scheme.
Further, the results in Tables (3) and (5) indicate the following
1- For negative mean shifts, the expected cost per hour of the VSI control schemes are
consistently smaller than that of the FSI control scheme over the 15 parameter
combination sets.
2- The percent reduction in ECT is significantly increased when the mean shifts are = -0.5
or -1.
18
3- The percentage reduction in ECT is increased due to lower searching cost (involving c1
and c 2 ), lower sampling cost (involving c 4 and c 5 ), and when is small. Other
parameters such as t 1 and t 2 do not significantly affect the ECT
From Table (4), several findings can be spelled out as follows:
1. As the measurements in the sample are positively or negatively correlated, both VSI and
FSI charts for highly correlated data require less frequent sampling with small sample
size and narrow width of the control limits.
2. Monitoring the process data by the VSI chart results in an evident improvement in
ECT when a high positive correlation is considered. On the contrary, when the
measurements in the sample are negatively correlated, the obvious improvement only
sounds to be the case for intermediatehighly correlated data
0.5 0.8.
3. The sample sizes taken in VSI schemes are slightly smaller than the corresponding one in
the FSI scheme.
4. As compared with the FSI charts, the VSI chart takes the next sample more slowly for
positively correlated data and more quickly for the most of negatively correlated data.
5. In this study, the percentages of the cost reduction with c 2 , k 4 , and different
values of (Table 4) are consistently more significant than the corresponding
percentages of the cost reduction (Table 3) obtained by Chen and Chiou (2005), where
the process data is distributed normality.
It should be noted that when 0 the expected cost per hour obtained for the FSI and VSI
charts are 2.398 and 2.163, respectively. These figures are similar to the ones in Chen (2004), in
which he obtained them as 2.440 and 2.145, respectively. The difference is due to different
19
computer codes written to solve the problem. In fact, while Chen (2004) employed the
EVOLVER coding to solve the problem, we solved the problem in MATLAB environment.
In this paper, we first took advantages of the Bai and Lees (1998 ) cost model, the Yang
and Hancocks (1990 ) correlation model, along with the Burr distribution modeling of nonnormal data to develop the economic design of the VSI X-Bar control chart for monitoring the
mean of correlated non-normal process data. An illustrative example to demonstrate the
application of the proposed methodology was then provided and comparisons were made
between the FSI and VSI schemes in terms of the expected cost per hour. To do this a parametertuned genetic algorithm was developed to search for the near optimal solution of the economic
designs. Sensitivity analyses were next carried to determine the influences of the input
parameters on the solutions of the economic design. Based on the results in the sensitivity
analyses, we have the following findings:
1. Over the 15 different combination sets of the model parameters indicated for positive
mean shifts given in Chen and Chiou (2005) the average percentage reduction in the
expected cost per hour ( ECT ) of the VSI scheme under correlated non-normal process
data is about 26.76%, which is more than that for correlated normal process data.
2. For positive mean shifts, the improvements in the VSI scheme in terms of ECT become
evident when the average wasted costs associated with false alarms and the detection and
elimination of the assignable cause after a true alarm are large. Moreover, when the
sampling cost is low, the improvement is also important for both positive and negative
mean shifts.
20
3. When the sample measurements are correlated, the improvement in ECT is apparent for
process data with a high degree of positive correlation or with an intermediatehigh
degree of negative correlation.
4. As compared with the FSI charts, the VSI chart takes the next sample more slowly for
positively correlated data and more quickly for the most of negatively correlated data.
5. For monitoring the correlated data, the FSI and VSI chart use a smaller sample than that
for monitoring uncorrelated data.
6. In most cases, false alarm rate () of the X control chart for the VSI scheme is smaller
than the FSI scheme.
While a single assignable cause was assumed throughout this research, it would be
interesting to conduct a research on the optimal design of VSI X control charts to monitor
correlated non-normal process data under the consideration of multiple assignable causes in the
future.
8. Acknowledgement
The authors are thankful for constructive comments of the reviewers that helped better
presentation of this paper.
21
Table 2. The optimum design of FSI and VSI X charts for positive mean shifts under the Burr distributions ( c 2 and k 4 )
FSI
No
t1
t2
c1
c2
c3
c4
c5
h1
k1
k'1
ECT
h1
h2
k1
k2
k'1
k'2
ECT
0.01
0.1
0.3
10
30
100
0.5
0.1
0.9438
2.4560
2.8659
0.0500
2.6952
0.0103
1.3600
2.9815
0.3796
1.8453
1.8453
0.0120
1.8038
0.05
0.1
0.3
10
30
100
0.5
0.1
0.4644
2.4624
2.8732
0.0496
6.6443
0.0101
0.6327
2.6656
0.3989
2.9600
2.9600
0.0179
4.9277
0.01
0.1
0.3
10
30
10
0.5
0.1
3.2542
2.4561
2.6753
0.0500
1.0331
0.0101
4.7090
2.8331
0.3844
2.0326
2.0326
0.0145
0.7752
0.01
0.1
0.3
10
30
1000
0.5
0.1
0.3115
2.4560
2.6526
0.0500
7.8436
0.0100
0.4641
2.6538
0.3879
2.2658
2.2658
0.0182
5.2736
0.01
0.1
0.3
25
75
100
0.5
0.1
1.2166
2.4596
2.6683
0.0498
3.7817
0.0103
1.5817
3.0000
0.3704
2.8698
2.8698
0.0117
2.4090
0.01
0.5
1.5
10
30
100
0.5
0.1
0.9626
2.4569
2.8347
0.0499
2.6102
0.0101
1.4578
2.9281
0.3749
2.7379
2.7379
0.0128
1.7727
0.01
0.1
2.1
10
210
100
0.5
0.1
1.0957
2.4559
2.7048
0.0500
4.3896
0.0100
1.4379
2.9699
0.3717
2.6024
2.6024
0.0122
3.5173
0.01
0.1
0.3
100
0.5
0.1
0.7160
2.4584
2.8515
0.0499
1.9395
0.0118
1.2941
1.8632
0.4692
1.7030
1.7030
0.0499
1.3475
0.01
0.1
0.3
10
30
100
0.1
2.1940
2.4562
2.8601
0.0500
5.5069
0.0101
3.7610
1.8617
0.4794
2.0574
2.0574
0.0500
4.1687
10
0.01
0.1
0.3
10
30
100
0.5
1.1107
1.8614
2.7378
0.0500
3.7594
0.0110
2.1792
2.5370
0.4040
2.0408
2.0408
0.0211
2.5344
11
0.01
0.1
0.3
10
30
100
0.5
0.1
0.5202
2.4572
2.7956
0.0499
4.7479
0.0102
1.3613
2.4563
0.0004
2.6219
2.6219
0.0500
3.3351
12
0.01
0.1
0.3
10
30
20
0.5
0.1
1.2372
2.4560
2.7481
0.0500
2.2451
0.0102
3.1640
2.4570
0.0018
2.9970
2.9970
0.0499
1.6415
13
0.05
0.1
0.3
10
30
100
0.5
0.1
0.2405
2.4561
2.8830
0.0500
10.9347
0.0100
0.7009
2.4565
0.0009
2.9828
2.9828
0.0500
8.1413
14
0.01
0.5
0.1
0.3
10
30
100
0.5
0.1
0.3430
1.8616
2.1894
0.0500
6.6988
0.0106
0.7823
2.4581
0.0001
2.8878
2.8878
0.0499
5.6334
15
0.01
0.5
0.1
0.3
10
30
0.5
0.1
2.0035
2.4560
2.6434
0.0500
1.5727
0.0105
3.9988
2.4559
0.0009
2.9479
2.9479
0.0500
1.3989
0.77
22
VSI
Table 3. The optimum design of FSI and VSI X charts for negative mean shifts under the Burr distributions ( c 2 and k 4 )
FSI
No
t1
t2
c1
c2
c3
c4
c5
h1
k1
k'1
ECT
h1
h2
k1
k2
k'1
k'2
ECT
0.01
0.1
0.3
10
30
100
0.5
0.1
0.9000
2.9988
1.5996
0.0137
1.9121
0.0100
1.0260
2.9997
2.9997
1.6585
1.1122
0.0118
1.8202
0.05
0.1
0.3
10
30
100
0.5
0.1
0.3933
2.9998
1.5963
0.0139
4.9941
0.0100
0.4954
2.9957
2.9957
1.6559
1.0701
0.0119
4.8011
0.01
0.1
0.3
10
30
10
0.5
0.1
2.9803
2.9995
1.6009
0.0137
0.7974
0.0104
3.3745
2.9995
2.9995
1.6585
1.1139
0.0118
0.7701
0.01
0.1
0.3
10
30
1000
0.5
0.1
0.2558
2.9994
1.6137
0.0131
5.4336
0.0100
0.3256
2.9975
2.9975
1.6606
1.0979
0.0118
5.1187
0.01
0.1
0.3
25
75
100
0.5
0.1
1.0320
2.9997
1.6352
0.0123
2.5528
0.0107
1.1484
2.9989
2.9989
1.6688
1.1110
0.0118
2.4391
0.01
0.5
1.5
10
30
100
0.5
0.1
0.9013
3.0000
1.5963
0.0139
1.8783
0.0137
1.0344
2.9971
2.9971
1.6546
1.1041
0.0119
1.7904
0.01
0.1
2.1
10
210
100
0.5
0.1
0.9144
2.9995
1.5990
0.0138
3.6248
0.0116
1.0439
2.9994
2.9994
1.6579
1.1055
0.0119
3.5358
0.01
0.1
0.3
100
0.5
0.1
0.9599
2.9996
1.3325
0.0499
1.4305
0.5122
1.0320
2.9983
2.9983
1.3328
0.8591
0.0499
1.4126
0.01
0.1
0.3
10
30
100
0.1
2.7436
2.9999
1.3322
0.0500
4.3864
1.5009
2.9897
2.9937
2.9937
1.3326
0.9011
0.0500
4.3394
10
0.01
0.1
0.3
10
30
100
0.5
1.4055
2.9986
1.5178
0.0201
2.6823
0.0114
1.5800
2.9999
2.9999
1.6303
1.1062
0.0125
2.5792
11
0.01
0.1
0.3
10
30
100
0.5
0.1
0.6331
2.9996
1.4686
0.0260
2.9988
0.0105
0.9782
2.9993
2.9993
1.5558
0.5244
0.0166
2.7255
12
0.01
0.1
0.3
10
30
20
0.5
0.1
1.4326
2.9996
1.4688
0.0259
1.4881
0.0105
2.0278
2.9986
2.9986
1.5594
0.6150
0.0163
1.3705
13
0.05
0.1
0.3
10
30
100
0.5
0.1
0.3142
2.9999
1.4364
0.0306
7.3119
0.0101
0.3615
2.9997
2.9997
1.5470
0.6871
0.0173
6.7761
14
0.01
0.5
0.1
0.3
10
30
100
0.5
0.1
0.5109
2.9984
1.3325
0.0499
4.4881
0.0109
0.9183
2.9988
2.9988
1.3555
0.3117
0.0451
4.2459
15
0.01
0.5
0.1
0.3
10
30
0.5
0.1
2.5710
2.9983
1.3331
0.0498
1.1636
0.0113
4.0903
2.9918
2.9918
1.3354
0.4842
0.0494
1.1204
0.77
23
VSI
Table 4. Effect of correlation coefficients on the optimal design of the FSI and VSI X charts under the Burr distributions ( c 2 and k 4 )
FSI
VSI
h1
k1
k'1
ECT
h1
h2
k1
k2
k'1
k'2
ECT
0.9
0.42696
2.54506
2.96068
0.04997
4.93567
0.01000
1.14443
1.86145
0.00106
1.68205
1.68205
0.04997
3.36725
31.77724
0.8
0.53618
2.47706
2.81296
0.04997
4.77219
0.01068
1.18143
1.86118
0.00113
1.98587
1.98587
0.04999
3.36713
29.44267
0.7
0.54953
2.41360
2.68994
0.04963
4.69388
0.01023
1.12432
2.48025
0.00245
2.93573
2.93573
0.04609
3.34272
28.78554
0.6
0.62383
2.71990
2.99961
0.04997
4.53213
0.01057
1.49458
2.34295
0.00492
2.92305
2.92305
0.04955
3.18791
29.65975
0.5
0.62306
2.58229
2.99907
0.04999
4.36052
0.01026
1.65146
2.58918
0.00052
2.99608
2.99608
0.04963
3.07956
29.37639
0.4
0.69670
2.72072
2.99993
0.04982
4.19957
0.01101
1.65987
2.56365
0.00098
2.92944
2.92944
0.04388
2.94890
29.78085
0.3
0.70525
2.48929
2.99993
0.04998
3.91435
0.01047
1.60831
2.58609
0.00396
2.79143
2.79143
0.03563
2.80881
28.24321
0.2
0.91768
2.39362
2.99997
0.04985
3.54721
0.01022
1.77758
2.84457
0.00388
2.99874
2.99874
0.02411
2.62885
25.88951
0.1
1.45073
2.38232
2.99533
0.04986
3.01286
0.01013
1.70928
2.78880
0.31280
2.84947
2.84947
0.01873
2.42983
19.35140
11
1.86872
1.91101
2.80768
0.03639
2.39795
0.01222
1.72507
2.66818
0.85559
2.99931
2.99931
0.00947
2.16310
9.79352
-0.1
1.65198
1.67679
1.92691
0.00423
1.93348
0.01001
1.57608
2.24190
1.27358
1.90720
1.90720
0.00173
1.88589
2.46151
-0.2
1.43798
1.37049
1.08825
0.00521
1.74940
0.01005
1.41908
1.82256
1.23673
2.66754
2.32316
0.00079
1.71984
1.68937
-0.3
1.36257
1.31588
2.31656
0.00080
1.63784
0.01116
1.35429
1.51731
1.29000
1.72271
1.72271
0.00025
1.63485
0.18278
-0.4
1.36355
1.08033
1.38650
0.01966
1.75917
0.01073
1.29067
1.64592
0.85457
2.52335
2.52335
0.00235
1.61942
7.94401
-0.5
0.92253
1.30626
2.57480
0.04990
2.85462
0.01018
1.57398
1.99290
0.18527
2.55298
2.55298
0.01172
1.98012
30.63450
-0.6
1.03912
1.16751
2.51285
0.04999
2.56525
0.01061
1.43037
1.87324
0.30548
1.53344
1.53344
0.00941
1.86062
27.46810
-0.7
1.21410
1.01146
2.99077
0.04995
2.24150
0.01016
1.37357
1.72249
0.43533
2.10534
2.10534
0.00711
1.73396
22.64305
-0.8
1.36156
0.88854
2.17417
0.04076
1.91192
0.01023
1.28667
1.53854
0.59497
2.44292
2.44292
0.00453
1.61081
15.74925
-0.9
1.25857
0.90606
1.36369
0.01091
1.58033
0.01007
1.19620
1.29985
0.81036
1.48247
1.48247
0.00164
1.50857
4.54048
Fixed cost parameters: =0.01, =1, t1=0.1, t2= 0.3, c1= 10, c2=30, c3=100, c4=0.5, c5=0.1
24
Table (5): Cost Reductions when instead of FSI, the VSI X-Bar chart is employed
Percentages of Cost Reduction
No.
33.074
4.806
25.836
3.863
24.962
3.419
32.766
5.797
36.298
4.456
32.086
4.682
19.872
2.454
30.522
1.251
24.300
1.073
10
32.585
3.844
11
29.758
9.112
12
26.883
7.906
13
25.546
7.329
14
15.905
5.396
15
11.050
3.714
25
References
Bai, D.S., Lee, K.T. (1998). An economic design of variable sampling interval X control
chart. International Journal of Production Economics 54: 57-64.
Baxley Jr., R.V. (1996). An application of variable sampling interval control charts. Journal
of Quality Technology 27: 275282.
Burr, I.W. (1942). Cumulative frequency distribution. Annals of Mathematical Statistics 13:
215-232.
Burr, I.W. (1967). The effect of non-normality on constants for X and R charts. Industrial
26
Costa, A.F.B. (1994). X-BAR chart with run rule and variable sample size. Journal of Quality
27
Niaki, S.T.A., Ershadi, M.J., Malaki, M. (2010). Economic and economic-statistical designs
of MEWMA control charts, A hybrid Taguchi loss, Markov chain and genetic algorithm
approach. International Journal of Advanced Manufacturing Technology 48: 283-296.
Neuhardt, J.B. (1987). Effect of correlated sub-samples in statistical process control. IIE
28
Woodall, W.H. (1986). Weakness of the economic design of control charts. Technometrics
28: 408409.
Yang K., Hancock W.M. (1990). Statistical quality control for correlated samples.
29
Appendix
Using the Burr transformation given in (2) and (3), equation (17) becomes
Y M
Y M
k 1'
k1
O 0 = Pr
Pr
S
S
1 n 1
1 n 1
k 1'
k1
Pr Y M S
Pr Y M S
(A.1)
n
n
1
1
1
1
1
1
1
k
c
c k
'
k1
k1
1 Max 0, M S
1 Max 0, M S
n
n
1
1
1
1
k ' n
k1 n
Y M
1
O1 1 Pr
1 n 1
S
1
1
k 1' n
k1 n
1 Pr M S
Y M S
(A.2)
n
n
1
1
1
1
1
1
1
k
c
c k
'
1
1 Max 0, M S k 1 n
1 Max 0, M S
1
1
n
1
1
X 0 k j
P0 j Pr 0 k j 1
n
X 0 k j' 1
+ Pr 0 k j'
n
0 , LCL X UCL
0 , LCL X UCL
n
30
1
1O0
1
1
k
c
c k
k
k
j 1
j
1+Max 0,M S
1+Max 0,M S
1
1
1
1
n
n
1 Max
k 'j
0, M S
1 n 1
for j 1, 2, ..., m -1
c k
'
k j 1
1 Max 0, M S
1
1
(A.3)
P0m Pr 0 k m'
X 0 k m
0 , LCL X UCL
n
n
1
1
1
k
c
c k
1 O0
'
k
k
m
m
1 Max 0, M S
1 Max 0, M S
1 n 1
1 n 1
(A.4)
X 0 k j
P1 j Pr 0 k j 1
0 , LCL X UCL
n
n
Pr 0 k j'
X 0 k j' 1
0 , LCL X UCL
n
n
1 O1
1 Max
1
c
k j 1 n
0,
M
S
1 n 1
31
1 Max
k j n
0,
M
S
1 n 1
1 Max
k 'j n
0, M S
1 n 1
for j 1, 2, ..., m -1
c k
'
k j 1 n
1 Max 0, M S
1 n 1
(A.5)
X 0 k m
P1m Pr 0 k m'
0 , LCL X UCL
n
n
1 O1
1 Max
1
c
k m' n
0, M S
1 n 1
32
(A.6)
1 Max
k m n
0, M S
1 n 1