Professional Documents
Culture Documents
Abstract
The Shah Deniz high-pressure gas platform development in
the Azerbaijan sector of the landlocked Caspian Sea required a
unique execution plan, the key components being:
Selection of a production jack-up for a continuous
operational life of up to 30 years
Fabrication of major components outside of the
Caspian
Transport of major components as self floating strips
towed through a canal network into the Caspian Sea
Assembly in Azerbaijan
Reactivation of a largely abandoned construction yard
The use of the worlds largest skirted spud cans with
their
associated
challenges
of
fabrication,
transportation and connection using a unique assisted
pendulum methodology
Installation of foundation utilizing a novel controlled
punch-through technique
This paper describes the overall execution plan and the key
technical challenges that the project team successfully
overcame.
Introduction
At the start of the development planning for the Shah Deniz
gas production platform, all available installation facilities
(crane vessels and transport barges) in the Caspian, along with
construction yards in Azerbaijan, were fully committed to a
series of offshore oil production platforms. Consequently, the
design brief for the Shah Deniz platform included the
requirement that it should not have any impact on those
facilities. The result was the selection of a self-installing jackup production facility with an execution plan based on
maximizing the out-of-country construction coupled with
transportation of large self-floating strips into the landlocked
Caspian via a canal network for final assembly in-country. It
OTC 19110
Strip transport
on semi-sub
vessel
OTC 19110
Strip 0 north
Strip 0 south
Strip 1
Strip 2
Strip 3
Strip 4
Project outline
Produced gas from Shah Deniz is delivered to an onshore
processing plant, the Sangachal terminal near Baku in
Azerbaijan, through a new 93 km 660 mm gas pipeline with
separated condensate flowing to the plant via a parallel 300
mm pipeline. From there, the treated gas is exported via the
new 686 km long South Caucasus Pipeline to the Turkish
border with off-takes in Azerbaijan and Georgia. The
associated condensate, after stabilisation, is exported via the
Baku-Tbilisi-Ceyhan (BTC) oil pipeline to the Mediterranean
Sea.
The Shah Deniz platform in its towing configuration
weighed approximately 32,500 t including the three-skirted
foundations. It fulfils the functions of drilling, production of
gas (900 MMscfd), production of condensate (up to 65,000
bpd) and providing living quarter for 120 people. The platform
is designed for 15 very high-pressure (758 barg) well
completions.
The platforms hull is trapezoidal in shape and measures
88 x 75 x 8 m. The legs, of triangular section of 17 m, are 136
m long and uses forged node technology (a proprietary item)
as well as high strength steel (700 MPa) for the toothed racks.
The components of the legs were manufactured in France and
assembled in Azerbaijan. Their strength and fatigue
characteristics ensure the platform complies with fixed jacket
design codes (as opposed to jack-up design codes).
The water depth is 101 meters and the area is highly
seismic, which had major consequences on the foundations
sizing. Each foundation (spud can) is 30 m in diameter by
12.3 m high and weighs 1,350 t. The elevated weight was
23,700 t and was lifted using 72 jacking units which are
proprietary items manufactured in France. Once at the desired
air gap, the hull was locked to the legs using 9 proprietary
design locking units. The total weight of the platform in
operation is 39,200 t.
An integrated team, BP and Technip, was in charge of the
management and the realization of the contract. Management
and supervision represented approximately 600 people
mobilized on the project.
OTC 19110
OTC 19110
OTC 19110
References
1. T Bayatli, BP Developments, Azerbaijan International,
Summer 2006 (14.2) from the web site:
www.azer.com/aiweb/categories/magazine/ai142_folder/1
42_articles/142_bp_developments.html
2. P.A. Thomas, J.M. Cholley, N. Tcherniguin, C. Hough,
Technip: Large Production Jack-up Foundation:
Experience and new solution Jack-Up Asia conference,
held in Singapore, December 2006.
3. V. Alessandrini, G. Lebois, Technip: A case of using
very large skirt can for self-installing platform, paper
OTC 18688, presented at the Offshore Technology
Conference, held in Houston Texas, 30th April 3rd May
2007.