You are on page 1of 2

METHOD PRE CONSTRUCTION TERMITE CONTROL

TREATMENT
PRE CONSTRUCTION SOIL TREATMENT
Pre Construction Soil Treatment implies laying down a chemical barrier to prevent termites
from getting back and forth between wood and soil. Termites need wood for food and soil for
moisture, so they constantly travel back and forth between wood and soil. Where this situation
does not exist, termites build the shelter tubes (Mud tubes) to span foundation walls and
other parts of the building that separate wood from the soil. Besides building the tubes in and
over foundation walls, termites may also build them inside the walls if constructed of concrete
blocks or other porous material. In the case of slab buildings, termites enter through
expansion joints, cracks, opening for utility and service connections.
EXECUTION & SEQUENCE OF WORK
Stage I Plinth Treatment
Once the backfilling is completed and prior to lay the leveling screed of ground floor slab,
Roding will be done along the edge of beams and on entire slab area at one meter center.
Then the termiticide will be injected by means of pressure injection treatment.
In addition to the above treatment blanket spraying will be carried out on soil surface covered
by the leveling screed of ground slab. Anti termite treatment will not be done under the base
slab of sump, lifts and etc. which are in below the water table.
Stage II Barrier Treatment
Once the leveling is completed in the building area along the exterior walls for paving Roding
will be done along the foundation and termeticide will be injected to soil by creating an one
meter wide effective chemical barrier along the exterior foundation.
CHEMICAL USED
1. The chemical used will be IMIDACLOPRID based termiticide the strength solution will
be 2.5mlt. 1lt water emulsion.
2. The rate of used will be approx. 5Lit of mixture per 1Sq. Meter.
EPA approved chemical will be used for termite control purposes and the treatment process
will not make any contamination on the ground water table and surface water sources in and
around the site. The termiticide used is agricultural friendly chemical and it will not make any
adverse effect on existing and proposed flora and fauna, in the park, such as trees plants and
fish in the ponds.

PROJECT QUALITY CONTROL: RESPONSIBILITIES


Slurry sealing
ASPHALT PAVING, TRANSPORTING, PLACING &

Method Statement for ABC Construction


Compressive Strength Test (Cube Crushed Test)
Bitumen Extraction Test
Flakiness Index Test
Field Density Test
Plastic Limit Test (Pl)
Liquid Limit Test (Ll)
Proctor Compaction Test
Method Statement for Slurry sealing
Method Of StatementTack Coat and Asphalting
ROAD MARKING
Method of Plastering
FORMWORK
METHOD PRE CONSTRUCTION TERMITE CONTROL
METHOD OF BRICK MASONRY WORK
Rock Blasting
Method Statement for Access Constructions
Method Statement for Road Marking
Method Statement for Culvert Construction
EARTH WORKS ( Road Constructions )
Method Statement for Construction of Turfing

You might also like