You are on page 1of 166

Hagler Bailly Pakistan

Technical, Management, and Economic Counsel

Associated with PA Consulting Group

Technical Audit Study of


Jamshoro, Guddu and
Muzaffargarh Thermal Power
Stations in Pakistan
Final Report
HBP REF.: R1V02TAG

April 27, 2011

Advanced Engineering Associates International


Islamabad

Technical Audit Study of GENCO Power Plants

Executive Summary
An energy audit of the thermal power stations (TPSs) of the following three state owned
power plants, collectively referred to as GENCOs was carried out:

TPS Jamshoro, or the Jamshoro Power Company Ltd., commonly referred to as


GENCO I,

TPS Guddu, which is a part of Central Power Generation Company Ltd.


commonly referred to as GENCO II), and,

TPS Muzaffargarh, which is a part of Northern Power Generation Company


commonly referred to as GENCO III.D

The main objective of the study was to carry out a baseline evaluation or a benchmarking
for determining efficiency gains and operational improvements to be achieved through
the implementation of the USAID Fixed Amount Reimbursement Agreements (FARA)
Repair and Maintenance Plan currently under implementation at these GENCOs. The
key terms of reference of the study were:

Assess performance parameters such as effective output capability, heat rate and
efficiency and power plant availability of each unit

Identify reasons for drop of plant performance from the design parameters

Carry out a spot fuel oil analysis to determine the heat contents and quality of the
fuel oil being supplied to the power stations

Carry out a brief technical review to assess the potential for using high-viscosity
fuel oil to reduce the plants generation costs

The standard methodologies used by the industry to determine the baseline performance
evaluation of steam and combined cycle power plants are ANSI/ASME PTC-6 and
ANSI/ASME PTC-46 respectively. However, these methodologies could not be followed
for a number of limitations for GENCOs. These limitations include:

Lack of availability of accurate and calibrated instrumentation in the power


station for online or off-line evaluation of efficiency

Lack of trained staff and manpower to carry out detailed measurement procedures
under controlled testing conditions

Software tools to carry out the component-wise heat balance analysis of the plant

Extensive data that includes ambient conditions, design data, correction curves
and operating conditions for the main heat path components such as boilers,
turbines, condensers, and cooling towers.

A specific testing protocol was devised for each unit on the basis of its fuel supply
systems, instrumentation status, and other operating conditions. A number of units were
not available for testing due to different operational reasons. Exhibit I provides a

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Executive Summary

ii

Technical Audit Study of GENCO Power Plants

summary of units that were tested and those not tested along with the reasons for their
unavailability.
Exhibit I: Unit-wise Testing Status of GENCOs
Power Station
TPS Jamshoro

Units Tested

Units Not Tested

Reasons for Not Testing


the Units

Units 1-4

TPS Guddu
Steam Block

Units 1-2

Energy input could not be


measured due to absence of gas
flow meters

Unit 3

Energy input could not be


measured accurately due to due
to errors in gas and RFO flow
meters

Unit 4

On prolonged shutdown from


December 2010 to March 2011
due to break down of air preheater

TPS Guddu CCP


Block

Block 2-A
Block 2-B
(GT 7, GT8, ST 5)
(GT 9, GT10,
ST6)
Block 1
(GT 11, GT12, ST 13)

Energy input could not be


measured accurately due to
lackof functional and calibrated
gas flow meters

TPS Muzaffargarh

Units 2-6

On prolonged shutdown from


November 2010 to mid- April
2011 due to delay in replacement
of super heater tubes

Unit 1

The heat rates and efficiency parameters for the power stations have been calculated only
for the purpose of baseline evaluation or a benchmark for determining efficiency gains
and operational improvements to be achieved after the implementation of the USAID
FARA Repair and Maintenance Plan currently under implementation at these GENCOs.
It should be noted that heat rates in this study were determined under steady loading and
specific ambient and operating conditions of the units during the winter season. Average
annual heat rates for the power stations are likely to be higher due to variations in
ambient conditions and loading levels, inclusive of startups and shutdowns.
Findings and Results

All the steam units of TPS Jamshoro and TPS Muzaffargarh are dual fuel plants having
gas and residual fuel oil (RFO) firing facilities except for Unit 1 of Jamshoro that has
only fuel oil firing capability. However, these plants were only operating on RFO firing
due to shortage of natural gas. TPS Guddu uses medium calorific raw gas from Mari and
Kandhkot. Steam Unit 3 and 4 at Guddu can also operate on mixed firing with RFO as
secondary fuel. Due to poor maintenance of the power stations, GENCOs have lost
nearly one third of their capacity and nearly 17% of their thermal efficiency due to plant
degradation. The Exhibit II shows the unit-wise results of performance evaluation tests
for the power stations.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Executive Summary

iii

Technical Audit Study of GENCO Power Plants

Exhibit II: Results of Output Capability, Heat Rate and Availability of GENCOs
Installed
Capacity
MW

Present
Gross
Capability
MW

Present
Net
Capability
MW

Capacity
Degradation

Design
Heat
Rate

Design
Net
Efficiency

Gross
Heat Rate

Gross
Efficiency

Net Heat
Rate

Net
Efficiency

Average
Availability
in FY2010

Average
Availability
in FY2011

TPS Jamshoro
Unit 1

250

191

176

23%

9,315

36.6%

9,829

34.7%

10,720

31.8%

73%

80%

Unit 2

200

119

112

41%

10,068

33.9%

11,727

29.1%

12,492

27.3%

88%

69%

Unit 3

200

125

113

38%

10,068

33.9%

11,879

28.7%

13,262

25.7%

85%

58%

Unit 4

200

146

133

27%

10,068

33.9%

10,909

31.3%

11,935

28.6%

91%

79%

Total Jamshoro

850

581

535

32%

84%

72%

GT 7

100

93

92

7%

10,763

31.7%

12,840

26.6%

12,896

26.5%

78%

96%

GT 8

100

85

85

15%

10,763

31.7%

13,412

25.4%

13,467

25.3%

98%

92%

ST 5

100

71

69

29%

98%

97%

Total Block 2-A

300

248

246

17%

9,572

35.6%

9,658

35.3%

98%

95%

GT 11

136

80

80

41%

10,629

32.1%

12,196

28.0%

12,261

27.8%

99%

100%

GT 12

136

80

80

41%

10,629

32.1%

12,236

27.9%

12,272

27.8%

99%

100%

ST 13

143

84

81

41%

97%

86%

Total Block 1

415

244

240

41%

98%

95%

Total Guddu CCP

715

493

487

31%

95%

95%

TPS Guddu CCP Block


Block 2-A

Block 1

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

8,081

42.2%

8,218

41.5%

Executive Summary

iv

Technical Audit Study of GENCO Power Plants

Installed
Capacity
MW

Present
Gross
Capability
MW

Present
Net
Capability
MW

Capacity
Degradation

Design
Heat
Rate

Design
Net
Efficiency

Gross
Heat Rate

Gross
Efficiency

Net Heat
Rate

Net
Efficiency

Average
Availability
in FY2010

Average
Availability
in FY2011

TPS Muzaffargarh
Unit 2

210

168

156

20%

9,279

36.8%

10,060

33.9%

10,784

31.6%

88%

83%

Unit 3

210

140

127

33%

9,279

36.8%

9,943

34.3%

10,773

31.7%

81%

96%

Unit 4

320

202

181

37%

9,297

36.7%

10,129

33.7%

11,312

30.2%

97%

60%

Unit 5

200

97

86

51%

10,780

31.7%

11,384

30.0%

13,026

26.2%

47%

72%

Unit 6

200

73

64

63%

10,780

31.7%

12,380

27.6%

14,392

23.7%

77%

78%

1,140

680

614

40%

80%

62%

Total Muzaffargarh

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Executive Summary

Technical Audit Study of GENCO Power Plants

The key results of the performance evaluation tests are described below.
TPS Jamshoro
The average capacity degradation was found to be 32% compared to the installed
capacity with a maximum degradation of 40% for Unit 2 and a minimum degradation of
23% for Unit 1. The average drop in the net efficiency is about 20% from the design
efficiency of the power station. Unit 1 is most efficient with 32% net efficiency against
the design efficiency of 36.6%. The net efficiencies of Units 2-4 ranged between 25.7%
to 28.6% against the design efficiency of 34%. The average availability of the power
station was 84% in FY2010 and 72% in FY2011 (till November 2010). However, if this
availability is corrected for lost output of the plant due to degradation, the availability
factor would drop by about 35%, indicating poor performance of the plant.
TPS Guddu
CCP Block 1 has shown 40% degradation in its capacity from the installed capacity
whereas CCP Block 2-A appears to be in better condition with only 17% capacity
degradation. The gas turbines (GTs 7 and 8) in Block 2-A showed net efficiencies of
27.8% each against the design efficiency of 31.7%. The GT 11 and GT 12 in Block 1
showed the net efficiencies of 26.5% and 25.3% respectively against the design
efficiency of 32.1%. The net efficiency of the Block 2-A and Block 1 were calculated to
be 35.3% and 41.5% respectively. The average availability of the units tested under the
study at power station was in excess of 95% but if this availability is corrected for lost
output of the plant owing to degradation, the availability factor would drop by about
30%, quite low from industry standards.
TPS Muzaffargarh
The power station is operating with an overall capacity degradation of around 40%.
Capacity degradation for the units varied between 20% for Unit 2 to 63% for Unit 6. The
power station is facing an overall degradation of around 18% in its net efficiency. Units
2 and 3 are in better condition with 31% net efficiency compared with their design
efficiency of 36.8%. Unit 4 has a net efficiency of 30% against 36.7% design efficiency.
Units 5 and 6 have efficiencies of 26% and 24% respectively against the design
efficiency of 31.7% for both units. The average availability of the power station was in
80% and 62% in FY2010 and FY2011. The availability of TPS Muzaffargarh would also
drop by 40% if corrected for lost output of the plant.
The auxiliary consumption and energy sent out on many units could not be measured
with accuracy due to indiscrete or absent metering. Therefore gross output capability and
heat rates should be used for the benchmarking purpose in this study.
Conclusions

Based on the observations of the audit team, interviews with the power stations
management and operational staff and review of historic records of the plants, and
capacity and heat rate tests conducted at the operational units, a number of reasons were
identified behind the overall decline in the performance of the power stations studied.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Executive Summary

vi

Technical Audit Study of GENCO Power Plants

Quality of RFO

None of the samples complied with Pakistan Standard and Quality Control Authority
(PSQCA) specifications for RFO. High specific gravity values were obtained due to
higher water contents. Only one sample met the standard calorific value of 18,200
Btu/lb. Moreover, the low calorific value up to 8.5% below the minimum permissible
limit was observed due to high specific gravity, water and ash contents.
Measurement Accuracy of Energy Input and Output

The discrete measurement of fuel supplied and energy generated and sent out for each
unit of the plant was found to be inadequate.

No credible measurement system exists for RFO received from the supplier as
well as fed to the installed units from the storage facilities of the plant. The same
applies to natural gas supplied and consumed at Guddu power station. At Guddu,
the gas supplied to residential colony is not measured. Measurement instruments
are either not calibrated, non-functional, or absent.

No uniform standards are followed for measurement of energy output. Auxiliary


supply is not discrete or fully measured for each unit resulting in inappropriate
accounting of auxiliary consumption.

Testing quality and procedures adopted by plants internal laboratories are also
highly questionable as they lack transparency and quality control. None of the
RFO samples complied with Pakistan Standard and Quality Control Authority
(PSQCA) specifications in one or more tests. Water and ash contents were found
to be higher than the maximum limits prescribed by the PSQCA

Lack of Preventive Maintenance

A number of maintenance activities are long overdue and have already resulted in loss of
output capability, increasing heat rates and lower availability.

GENCO managements are forced to delay the overhauling of the plants and are
not able to carry out regular preventive maintenance to avoid break-down of the
plants for the following reasons:

Refusal of shut-down time by the system operator (NTDC) due to shortages in


power supply in the country,

Delay in payments to GENCOs against power sales, and

Delay in procurements of parts and services for plants major overhauling.

Poor Housekeeping

GENCO managements are paying little attention to simple housekeeping activities which
do not require large expenditures. Examples include:

Frequent steam leakages in boiler and other steam usages increase heat loss at the
plant as well as raise water purification cost due to excessive use of chemicals.

A number of critical plant components are not operating at their optimal


conditions, causing frequent tripping and breakdowns of the units.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Executive Summary

vii

Technical Audit Study of GENCO Power Plants

Plant management is generally oblivious to environmental conservation and


protection. Massive oil spills and un-optimal combustion results in higher rate of
toxic emissions and effluent discharges causing environmental threats to adjacent
population, flora and fauna.

Lack of Performance Evaluation, Monitoring, and Reporting

No attention is given to the performance evaluation of the plants and as such no standards
are observed to assess the performance of the plants.

The present monitoring and reporting system covers a few technical parameters
and is not capable to provide a detailed assessment of the plants.

Plants are running in manual mode in the absence of modern monitoring and
control systems.

The absence of performance evaluation standards and an on-line integrated


management information system (MIS) severely limits the ability of the
management to take prompt decisions and initiate actions and remedial measures
for efficient operation of the plants.

Limited Financial and Administrative Autonomy

Managements of GENCO plants have limited financial autonomy to take independent


decisions.

Payments to GENCOs are not made on time which results in deferment of


maintenance routines which is a major reason behind plant output and efficiency
degradation.

Approval process for procurement of spare parts and services through


international tendering is cumbersome and time consuming.

Management is not empowered to initiate a performance-based human resource


management system to promote efficiency and competition.

The plants are suffering from overstaffing with majority of staff working
without specialized industrial training to perform their duties

Occupational health, safety, and environmental management system and


relevant trainings are not observed at the plants increasing the potential of a
safety hazard at the plant

Recommendations

In order to improve the performance of the GENCOs, the following recommendations are
made:

A standard measurement and testing protocol needs to be devised for GENCOs


for all measurement to avoid errors in financial transactions. GENCOs should
carry out a detailed exercise to devise a robust measurement mechanism for RFO
receipts at the plants to reduce oil pilferages and acceptance of substandard oil.

A third party RFO testing mechanism should be established on regular basis to


ensure the quality of fuel received from supplier. The contracts with the fuel

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Executive Summary

viii

Technical Audit Study of GENCO Power Plants

supplier should include penalties or correction in price for supply of substandard


oil.

A detailed management study is required to prescribe key performance indicators


pertaining to financial, human and environmental performance of the plant and
the procedures to evaluate them on sustainable basis.

The Inspection, Testing and Records (ITR) and Maintenance Management System
(MMS) sections may be merged to form a Performance Monitoring Section
(PMS) at each power station to provide a wider range of performance evaluation
and monitoring services.

On-line analyzers and instruments with communication channels to a central


performance modeling system should be installed to assess the performance and
efficiency of the plant on a continuous basis. The PMS should operate this
system and advise the operations and maintenance staff on corrective and
preventive actions to be taken to meet the performance targets.

Special training and workshops should be arranged to educate and train the
management and staff about best industrial practices to operate and maintain the
power stations.

The capacity of in-house repair and maintenance workshops should be enhanced


with modern machines, tools and training of staff to provide maintenance services
of critical parts locally to reduce down-time

There is a need to establish an R&D or a Technical Services section to carryout


research on technical and management problems of the power stations and devise
solutions

Switching to heavier grade RFO will require capital investment in the


infrastructure for storage, handling, transportation, and utilization of RFO. A
detailed feasibility study including the infrastructure analysis of PSO and required
modifications at the steam turbine and diesel engine based power plants and
assessment of the resulting cost savings is recommended to ascertain the
economics of burning heavier grade fuel oils.

The government is currently implementing a Generation and Transmission Improvement


Plan (GTIP) for the GENCOs. The resolution of management and operational issues
identified in this study require a complete change in the management approach and
operational environment of the GENCOs. The government could consider bringing in
independent management under a performance based O&M contract based on a structure
of incentives and penalties against the performance of the power stations. The terms and
conditions of the O&M contract could be designed in a manner to make the contractor
responsible for injecting investment for rehabilitation of the units and bringing in highly
trained and experienced senior managers. The O&M contractor may be given extended
authority to reward and motivate employees and to take disciplinary action and adjust the
size of the work force. This approach will help in establishing and expanding the O&M
industry and in improving the efficiency of the power sector in the country.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Executive Summary

ix

Technical Audit Study of GENCO Power Plants

Contents
1.

Introduction...................................................................................... 1-1
1.1
1.2
1.3
1.4

2.

Methodology .................................................................................... 2-1


2.1
2.2
2.3
2.4

3.

Fuel Supply Arrangements ...................................................................... 3-1


TPS Jamshoro .......................................................................................... 3-5
TPS Guddu ................................................................................................ 3-6
TPS Muzaffargarh ..................................................................................... 3-7

Maximum Present Capability ......................................................... 4-1


4.1
4.2
4.3
4.4

5.

Limitations of Standard Methodologies and Approach


Adopted for the Study .............................................................................. 2-1
Measurements and Collection of Data on Plant Performance............... 2-2
Testing of Fuel Quality ............................................................................. 2-2
Testing Arangements and Schedule ....................................................... 2-3

Description of GENCO Plants ........................................................ 3-1


3.1
3.2
3.3
3.4

4.

Objectives and Scope of Work ................................................................ 1-1


Study Team ............................................................................................... 1-3
Acknowledgement .................................................................................... 1-3
Organization of the Report ...................................................................... 1-3

General Approach and Overall Limitations ............................................ 4-1


TPS Jamshoro .......................................................................................... 4-1
TPS Guddu ................................................................................................ 4-2
TPS Muzaffargarh ..................................................................................... 4-2

Heat Rate Analysis .......................................................................... 5-1


5.1
5.2

Definitions ................................................................................................. 5-1


Limitations in Assessment of Heat Rates ............................................... 5-1
5.2.1 Testing Schedule.............................................................................. 5-1
5.2.2 Measurement of Fuel Flow ............................................................... 5-1
5.2.3 Metering of Electrical Output ............................................................ 5-2
5.2.4 Application of Heat Rate Assessment............................................... 5-3

5.3

TPS Jamshoro .......................................................................................... 5-3


5.3.1 Testing Procedures and Data Analysis ............................................. 5-3
5.3.2 Results ............................................................................................. 5-3

5.4

TPS Guddu ................................................................................................ 5-5


5.4.1 Testing Procedures and Data Analysis ............................................. 5-6
5.4.2 Results ............................................................................................. 5-6

5.5

TPS Muzaffargarh ..................................................................................... 5-8


5.5.1 Results ............................................................................................. 5-8

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Contents

Technical Audit Study of GENCO Power Plants

6.

7.

8.

Power Plant Availability .................................................................. 6-1


6.1
6.2

Definitions and Limitations ...................................................................... 6-1


Data and Results ...................................................................................... 6-2
6.2.1 TPS Jamshoro ................................................................................. 6-2
6.2.2 TPS Guddu ...................................................................................... 6-2

6.3

TPS Muzaffargarh ..................................................................................... 6-3

Major Reasons for Degradation of Performance.......................... 7-1


7.1

Technical Issues ....................................................................................... 7-1


7.1.1 Measurement Accuracy of Fuel Received ........................................ 7-1
7.1.2 Fuel Oil Quality ................................................................................. 7-2
7.1.3 Lack of Preventive Maintenance....................................................... 7-3
7.1.4 Poor Housekeeping .......................................................................... 7-5

7.2

Management Issues and Recommenadations........................................ 7-7


7.2.1 Lack of Performance Evaluation ....................................................... 7-7
7.2.2 Limited Financial and Administrative Autonomy ............................... 7-7
7.2.3 Absence of Plant Automation and
Management Information System ..................................................... 7-8
7.2.4 Other Management Issues ............................................................... 7-9

7.3

Detailed Technical Assessment of GENCOs ........................................ 7-10


7.3.1 TPS Jamshoro ............................................................................... 7-10
7.3.2 TPS Guddu .................................................................................... 7-16
7.3.3 TPS Muzaffargarh .......................................................................... 7-26

Usage of High Viscosity Fuel Oil in GENCO Power Plants ......... 8-1
8.1
8.2
8.3
8.4
8.5

Fuel Oil Standards .................................................................................... 8-1


Potential for use in Power Generation in Paksitan ................................ 8-1
Modifications Required in Fuel Oil Handling at the Power Plants ........ 8-2
Modification and Adjustments Required in the Boilers ......................... 8-2
Fuel Oil Procurement and Supply ........................................................... 8-3

APPENDICES
Appendix A: Fuel Oil Analysis Results
Appendix B: Data and Results of the GENCOs Capacity Test
Appendix C: Testing Procedures for Measurment of GENCOs Gross and
Net Heat Rates
Appendix D: Calculation of GENCOs Gross and Net Heat Rates
Appendix E: Power Plant Availability

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Contents

xi

Technical Audit Study of GENCO Power Plants

Exhibits
Exhibit 1.1:

Locations of Power Stations Studied .................................................... 1-2

Exhibit 1.2:

Formation of the Consulting Team ........................................................ 1-3

Exhibit 3.1:

Natural Gas Supply Arrangements at the Power Stations ..................... 3-2

Exhibit 3.2:

GENCOwise Installed and Derated Capacities, Plant and


Fuel Types, and Efficiencies from PEPCO Statistics ............................. 3-3

Exhibit 3.3:

200 MW Steam Unit No. 2 at TPS Jamshoro ........................................ 3-5

Exhibit 3.4:

Oil Storage Tanks at TPS Jamshoro ..................................................... 3-6

Exhibit 3.5:

200 MW Steam Unit No. 3 at TPS Guddu ............................................. 3-6

Exhibit 3.6:

RFO Storage Capacity at the Power Stations-TPS Guddu.................... 3-7

Exhibit 3.7:

200 MW Steam Unit No. 6 at TPS Muzaffargarh ................................... 3-8

Exhibit 3.8:

Oil Decanting from Railway Wagons and Tank Lorries atTPS


Muzaffargarh ........................................................................................ 3-9

Exhibit 3.9:

RFO Storage Capacity at the Power Stations-TPS Muzaffargarh ......... 3-9

Exhibit 3.10: Oil Storage Tanks at TPS Muzaffargarh ............................................. 3-10


Exhibit 4.1:

Unit-wise Installed Capacity and Present


CapabilityTPS Jamshoro .................................................................... 4-1

Exhibit 4.2:

Unit-wise Installed Capacity and Present Capability of Units


Tested Under the StudyTPS Guddu.................................................... 4-2

Exhibit 4.3:

Unit-wise Installed Capacity and Present Capability of Units


Tested Under the Study TPS Muzaffargarh ....................................... 4-3

Exhibit 5.1:

Unit-wise Gross and Net Heat Rate and


EfficiencyTPS Jamshoro ..................................................................... 5-4

Exhibit 5.2:

Unit-wise Gross and Net Heat Rate and


EfficiencyTPS Guddu .......................................................................... 5-7

Exhibit 5.3:

Unit-wise Gross and Net Heat Rate and


EfficiencyTPS Muzaffargarh ............................................................... 5-9

Exhibit 6.1:

Unit-wise AvailabilityTPS Jamshoro .................................................... 6-4

Exhibit 6.2:

Unit-wise Availability TPS Guddu ....................................................... 6-5

Exhibit 6.3:

Unit-wise AvailabilityTPS Muzaffargarh .............................................. 6-7

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Exhibits

xii

Technical Audit Study of GENCO Power Plants

Exhibit 7.1:

Average Degradation in Performance of GENCOs ............................... 7-1

Exhibit 7.2:

Summary of Results of Fuel Oil Testing ................................................ 7-2

Exhibit 7.3:

Poor Maintenance of Insulation at TPS Jamshoro ................................ 7-4

Exhibit 7.4:

Steam Leakages at TPS Muzaffargarh ................................................. 7-5

Exhibit 7.5:

View of a Nonfunctional Soot Blower at TPS Jamshoro ........................ 7-6

Exhibit 7.6:

Oil Spillage at Storage Facility at Muzaffargarh .................................... 7-6

Exhibit 7.7:

View of the Joint Control Room of Units 3 and 4 at TPS Jamshoro ....... 7-8

Exhibit 7.8:

Smoke Showing Poor Combustion at Unit No. 6 at


TPS Muzaffargarh................................................................................. 7-9

Exhibit 7.9:

River Water Quality Supplied at TPS Jamshoro in January 2011........ 7-11

Exhibit 7.10: Reasons for Drop in Performance of the PlantTPS Jamshoro........... 7-12
Exhibit 7.11: Damaged Air Pre-heater due to Fire of Unit No. 4 at TPS Guddu ....... 7-16
Exhibit 7.12: Poor Cooling of Turbine Section of Unit No. 3 at TPS Guddu ............. 7-18
Exhibit 7.13: Reasons for Drop in Performance of the Steam
UnitsTPS Guddu ............................................................................... 7-19
Exhibit 7.14: View of Under Repair Induced Draft Fan of Unit No. 1 at
TPS Muzaffargarh............................................................................... 7-26
Exhibit 7.15: Unit-wise Reasons for Drop in Performance of the
Steam UnitsTPS Muzaffargarh ......................................................... 7-28
Exhibit 8.1:

RFO Specifications ISO 8217:2010 ...................................................... 8-4

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Exhibits

xiii

Technical Audit Study of GENCO Power Plants

1. Introduction
Advanced Engineering Associates International (AEAI) engaged Hagler Bailly Pakistan
to carry out an energy audit of the thermal power stations (TPSs) of the following three
state owned power plants:
1. TPS Jamshoro, or the Jamshoro Power Company Ltd., commonly referred to as
GENCO I,
2. TPS Guddu, which is a part of Central Power Generation Company Ltd.
commonly referred to as GENCO II), and,
3. TPS Muzaffargarh which is a part of Northern Power Generation Company
commonly referred to as GENCO III.
These thermal power stations are collectively referred to as GENCOs in this report. The
locations of these thermal power stations in the country are shown in Exhibit 1.1.
1.1

Objectives and Scope of Work

The main objective of the study was to carry out a baseline evaluation or a benchmarking
for determining efficiency gains and operational improvements to be achieved through
the implementation of the USAID Fixed Amount Reimbursement Agreements (FARA)
Repair and Maintenance Plan currently under implementation at these GENCOs. The
main features of the scope of work of the study were:

Visual inspection of all units of three GENCO power stations, review of the
station logbooks and other available records to establish main reasons for the poor
performance of the plants and the present generation capacity. Interviews and
discussions with the plant managers/operators and determine the reasons for poor
performance.

Drawing of performance profile of each unit including operating parameters, such


as effective output capability, power plant availability, heat rate and efficiency of
each unit.

Determination of specific fuel consumption and monitor on line calorific value of


fuel being injected into each machine.

Carrying out a spot fuel oil analysis to determine the heat contents and quality of
the fuel oil being supplied to the power stations.

Determination of heat rate and efficiency of each unit.

Carrying out a brief technical review to assess the potential for using highviscosity fuel oil to reduce the plants generation costs.

Preparation and submission of Energy Audit Report for each of the GENCOs.

Three teams of power generation experts were formed to carry out the site visits and
conduct tests to assess the capacity and heat rates of the operational units of the plants.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Introduction

1-1

Technical Audit Study of GENCO Power Plants

Exhibit 1.1: Locations of Power Stations Studied

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Introduction

1-2

Technical Audit Study of GENCO Power Plants

1.2

Study Team

The study team consisted of experienced engineers who have been extensively involved
in the construction and operation of the power stations studied, and have retired from
senior positions at the GENCOs. The names and specific assignment of the consultants
involved in the study are listed in Exhibit 1.2.
Exhibit 1.2: Formation of the Consulting Team
Name of Consultant

Responsibility

Manzar Naeem Qureshi

Team Leader

Muhammad Qasim Shaikh

TPS Jamshoro

Abdul Waris Khan

TPS Guddu Combined Cycle Power Station Block

Abdul Aziz Chandio

TPS Guddu Steam Power Station Block

Abdul Karim Leghari

TPS Muzaffargarh

Additional staff was engaged at each power station to assist the Consultants in taking
concurrent meter readings of input and output energy measurements at the power
stations.
1.3

Acknowledgement

The management of the GENCOs extended their generous cooperation in facilitating the
audit teams, and allowed unhindered and unlimited access to power station equipment,
instruments, data records and personnel for interviews. HBP management would like to
extend their profound gratitude to the management of the GENCOs for their support in
completing the assignment.
1.4

Organization of the Report

Section 2 of the report describes the methodology used to carry out the capability and
efficiency tests for the GENCOs. Section 3 provides an overview of the power stations
in terms of configuration and fuel supply arrangements. Section 4 presents the results of
the unit-wise maximum capability tests for each power station. Section 5 provides
detailed procedures employed for carrying out the heat rate tests and presents the results
of heat rate and efficiency for each unit of the power stations. Section 6 shows the unitwise annual availability in terms of load factor, utilization factor and availability.
Section 7 provides a detailed account of the main technical and management reasons
causing the drop in performance of these power stations. Section 8 sums up the
conclusions and recommendations of the study.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Introduction

1-3

Technical Audit Study of GENCO Power Plants

2. Methodology
2.1

Limitations of Standard Methodologies and Approach Adopted for


the Study

The standard methodologies used by the industry to determine the baseline performance
evaluation of steam and combined cycle power plants are ANSI/ASME PTC-6 and
ANSI/ASME PTC-46 respectively. Application of these methodologies helps in accurate
determination of performance of the power stations and generation of analysis and
information for optimization of their performance. These standard methodologies have
the following requirements:

Availability of accurate and calibrated instrumentation in the power station for


online or off-line evaluation of efficiency

Trained staff and manpower to carry out detailed measurement procedures under
controlled testing conditions

Software tools to carry out the component-wise heat balance analysis of the plant

Extensive design data and correction curves for the main heat path components
such as boilers, turbines, condensers, and cooling towers.

Ambient conditions including temperature and humidity, and

Data on operating conditions at the inlet and outlet of the main heat path
components, such as temperatures, flow rates, and stream composition.

None of the GENCOs studied fulfill the requirements listed above. Preparing the
GENCOs to fulfill these requirements would require extensive capacity building and
installation of necessary instrumentation, which was beyond the scope and schedule of
this study. It was therefore not possible to conduct a comprehensive audit of the
performance of the GENCOs using the standard industry methodologies given the
prevailing conditions and the operating environment in the GENCOs and the time
constraints for the study. In view of these limitations, the standard industry
methodologies were modified and applied in a simplified manner to measure the capacity
and input and output energy of the plants to calculate the heat rate and efficiency, and to
work out the plant availability on monthly and annual basis.
Industry experience indicates that heat rate test conducted by using formal ASTM-6
procedure has an accuracy of about 3%. Given the poor condition of instrumentation that
were not properly calibrated, unusual operating conditions for testing, and improvised
test protocols, the accuracy of the heat rate tests under this study could range between
5-10% as per expert judgment. This aspect should be kept in view while comparing the
results of benchmarking conducted under this study with the follow-up tests to be
conducted after completion of FARA program.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Methodology

2-1

Technical Audit Study of GENCO Power Plants

2.2

Measurements and Collection of Data on Plant Performance

Special teams, comprising of instrumentation experts, were formed to carry out tests at
each unit. A specific testing protocol was devised for each unit on the basis of its fuel
supply systems, instrumentation status, and other operating conditions. The measurement
points were marked beforehand and measurement procedures were established keeping in
view the operating constraints of the unit. Special proformas were designed to prescribe
the measurement specifications and to maintain testing records. Standard conversions
and definitions were used to calculate the output and heat rates of the units. The
measurement procedures were documented and are presented in Section 5 of this report.
Residual fuel oil (RFO) consumption was calculated by using dip-tape, calibration charts
of the feeding tanks, and specific gravity of RFO at observed temperatures. Natural gas
consumption at TPS Guddu was measured through the meters installed at the units in the
power station. Electrical outputs at gross and sent-out meters, and auxiliary consumption
were recorded at the metering locations of the units studied. All the readings were taken
concurrently and coordination was managed through mobile phones and hand held radio
phones.
The Consultants did not engage any serving person from the GENCOs for the purpose of
assisting the teams in reading of instruments or recording the observations. No unit logsheet entries and event registers were used or consulted for extracting the information and
data for the purpose of calculation of heat rates. The Consultants ensured uninterrupted
operation of the plants throughout the testing period. The testing schedule was designed
to avoid interference with operations and management of the power station. The
Consultants relied to the extent possible on the installed measurement instruments, and
used their own equipment such as dip-tapes to carry out the assignment where required.
2.3

Testing of Fuel Quality

RFO

RFO samples were drawn from the main storage tanks of these power stations in
accordance with the ASTM methodology; Standard Practice for Manual Sampling of
Petroleum and Petroleum Products: D 4057 95 (Reapproved 2000). The parameters
studied to assess the quality of RFO included specific gravity, flash point, pour point,
water contents, sulfur, ash content and calorific value.
A composite sample was drawn from each of the storage tanks consisting of a blend
created from the upper, middle, and lower samples from a single tank. The sample was
obtained with the help of a specially designed sampling tube also called special thief.
The bottom sample was taken from the height of 1.5 to 2.0 meters from bottom of the
tank as the outflow of the tank was drawn from the height of 1.0 meters. The samples
were packed in aluminum bottles and dispatched to an independent laboratory for testing.
In all, eighteen samples were drawn; 4 from TPS Jamshoro; 5 from TPS Guddu; and 9
from TPS Muzaffargarh. Samples were collected during the period of December 29,
2010 to January 5, 2011 and analysis was carried out by Quality Control Laboratory of
Attock Refinery Limited, Morgah Rawalpindi.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Methodology

2-2

Technical Audit Study of GENCO Power Plants

2.4

Testing Arangements and Schedule

The detailed procedures developed for performance testing of each unit are described in
Section 5 of this report.
TPS Jamshoro

Prior to conducting the performance tests, inspections of all the units at the power plant
were carried out in the presence of the representatives of the power station management.
The operational conditions of the units were observed and necessary information and
details were gathered.
Although all the units were in operating condition, the plant management could run only
one unit at a time due to shortage of demineralized water. Further, the units could not
operate at optimum load on continuous basis for longer periods on RFO firing due to
choking of rotary air pre-heaters. Therefore, the Consultants team faced considerable
difficulty in finding an appropriate window of time to carry out heat rate and capacity
tests for continuous three days without interruption at optimum operating conditions.
Heat rate and capacity tests at the plants were performed in the following sequence:

Unit 1: January 19-21, 2011 for heat rate tests and January 21-23, 2011 for
capacity tests

Unit 2: January 21-23, 2011 for both heat rate and capacity tests

Unit 3 & 4: February 17-19, 2011 for both heat rate and capacity tests

TPS Guddu

Meetings were held with the concerned management of each unit before the beginning of
testing. Block 2 B comprising of Units 6, 9 and 10 did not have functional gas flow
meters and therefore could not be tested. Similarly, Unit 4 was on long shut down due to
break down of air pre-heater. Units 1 & 2 also do not have gas flow meters and therefore
were not tested. The testing of these units was deferred until gas flow meters are made
operational on all of these units and repair/replacement of air pre-heater of Unit 4.
Capacity and Heat Rate Tests at the plants were performed in the following sequence:

Unit 3: December 30, 2010 to January 1, 2011

Block 2 A (Unit 5, 7& 8): December 30, 2010 to January 2, 2011

Block 1 (Unit 13, 11& 12): January 3-6, 2011

TPS Muzaffargarh

Before undertaking the performance tests, inspection of all the units installed in different
phases (1 & 2) was carried out in the presence of representatives of the power station
management. The operational conditions of the units were observed and necessary
information and details were gathered.
Unit 1 was placed under a long shutdown since November 11, 2010 for
repair/replacement of super heater tubes. However, the repair/replacement of ends of
super-heater tubes was delayed due to arrival of Russian experts of the Original

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Methodology

2-3

Technical Audit Study of GENCO Power Plants

Equipment Manufacturer (OEM). The unit could not be restarted until the middle of
April 2011 and therefore the performance testing of this unit could not be conducted.
Heat Rate Tests & Capacity Tests at the plants were performed in the following
sequence:

Unit 2 & 3: January 9-11, 2011

Unit 4: January 5-7, 2011

Unit 5 & 6: January 2-4, 2011

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Methodology

2-4

Technical Audit Study of GENCO Power Plants

3. Description of GENCO Plants


Total installed capacity of the three power plants studied is 3,8551 MW out of which
2,840 MW consists of dual fuel steam turbines, and 1,015 MW of gas fired gas turbine
combined cycle (CCGT) power plants installed at Guddu. The dual fuel plants operate
on pipeline quality natural gas and residual fuel oil (RFO), whereas CCGT units installed
at Guddu use medium calorific value (MCV) gas (780-800 Btu/scft).
Nearly 90% of the installed capacity of GENCOs is over 15 years old, and is generally in
poor condition. Due to the weak financial conditions prevailing amongst power sector
entities, the Water and Power Development Authority (WAPDA) which owned the units
until 1998 and the Pakistan Electric Power Company Ltd. (PEPCO) which owns them
now, have not been able to allocate adequate funds to meet the operational and
maintenance expenditures of these plants. These factors have contributed to a gradual
loss of effective capacity, efficiency, and dispatch availability of these plants.
Consequently, the GENCOs are currently operating their plants at a derated capacity that
is 25% below their respective nameplate capacities. The combined cycle units at Guddu,
however, are an exception and can operate on full capacity if natural gas injection
pressures are restored to the design levels.
The average forced outage rate for the GENCOs has been about 12%, compared with 6%
for thermal IPPs in the country. Nearly all of the GENCO power plants studied are
operating at a much lower efficiency levels than the industry-wide standards for plants of
similar age and configuration. Exhibit 3.2 provides a snapshot of the current status, age,
and origin of these plants.
3.1

Fuel Supply Arrangements

Most of the steam units at the power stations have the provision of dual fuel combustion
on natural gas and RFO. Unit 1 at TPS Jamshoro can only operate on RFO. The Steam
Units 1-2, and combined cycle units at TPS Guddu operate on MCV gas supplied from
Mari, Kandhkot, and Zamzama gas fields. The power station-wise details of the fuel
supplies are given below.
Natural Gas

All the power stations have connections with the utilities for supply of natural gas.
However, gas utilities used these plants as swing customers and curtailed the gas supplies
during winter to meet the heating demand of the residential and commercial consumers.
TPS Jamshoro and TPS Muzaffargarh do not have firm supply contracts with their
respective gas supply utilities and therefore receive natural gas only when there is surplus
in the national gas network. The county is presently facing a shortfall in the natural gas
supplies due to rising gas demand and the gas utilities have been unable to maintain
supply of pipeline quality gas to these power stations even during the summer period.

Power System Statistics, 34th Edition, 2009

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Description of GENCO Plants

3-1

Technical Audit Study of GENCO Power Plants

Exhibit 3.1 contains the sources and fuel supply arrangements for natural gas for the
GENCO plants.
Exhibit 3.1: Natural Gas Supply Arrangements at the Power Stations
Power Station

Gas Supply Source

Contract Status

TPS Jamshoro

Sui Southern Gas Company

No firm contract as and


when available

TPS Guddu

Mari Gas Mari Gas Company*

60 MMscfd

Kandhkot gas Pakistan Petroleum Limited

(110 + 90) MMscfd

Zamzama Gas through SNGPL and SSGC No firm contract Not


networks
supplied since 2005
TPS Muzaffargarh
*

Sui Northern Gas Pipelines

No firm contract as and


when available

Gas supplies to Guddu from Mari have been reduced to 60 MMscfd from 110 MMscfd after diversion of
50 MMscfd to Fatima Fertilizer from November 27, 2009.

Residual Fuel Oil (RFO)

RFO is supplied to all GENCOs by Pakistan State Oil (PSO). However, only TPS
Muzaffargarh has a fuel supply agreement with PSO, whereas the government has
advised TPS Jamshoro and TPS Guddu to purchase RFO from PSO exclusively. PSO
mainly supplies the RFO from Karachi through railway tank wagons and tank lorries.
GENCO plants are designed to operate on fuel oil having kinematic viscosity of 180
centistokes (cst) during summer and 120 cst during winter.
RFO Measurement

The GENCOs follow a uniform procedure for measurement of the quantity of RFO
received from PSO. The initial volumetric measurement is taken by using dip-sticks for
both railway tank wagons and tank lorries and fuel oil volumes are converted to weight
for the calculation of payments by using specific calibration charts for the lorries/wagons
after applying corrections for temperature and specific gravity of RFO. For tank lorries,
the weighbridges are also present at all the power stations. The weight of RFO calculated
using dip-sticks is verified at the weighbridges by taking measurements of the tank lorries
before and after the oil decanting. Several checks are applied to ensure complete
decanting of RFO from tank lorries and railway wagons. The weighbridge measurement
is not used for making payments to fuel supplier.
All tank lorries and railway wagons are tested for temperature and specific gravity of the
fuel oil and about 20-25% are randomly selected for detailed analysis of RFO
specifications in the local laboratory of the concerned power station. A small proportion
of the samples are also tested through independent laboratories to verify the result of the
internal laboratory. RFO that does not meet specifications is rejected for procurement.
The results of the third party analysis of the RFO samples collected from GENCO power
stations are presented in Appendix-A.
Oil Storage

All the power stations have their own RFO storage facilities at their premises for storage
of 20-30 day requirement of RFO.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Description of GENCO Plants

3-2

Technical Audit Study of GENCO Power Plants

Exhibit 3.2: GENCOwise Installed and Derated Capacities, Plant and Fuel Types, and Efficiencies from PEPCO Statistics
Plant

Installed Capacity
(MW)

Year of Commissioning

Fuel

Country of Origin

Thermal Efficiency
(Design)

TPS Jamshoro
Unit 1

250

January 1990

RFO

Japan

36.6%

Unit 2

200

December 1990

Natural Gas/RFO

China

33.9%

Unit 3

200

June 1990

Natural Gas/RFO

China

33.9%

Unit 4

200

January 1991

Natural Gas/RFO

China

33.9%

TPS Guddu
Steam
Unit 1

110

1974

Natural Gas

Czech Slovakia

28.0%

Unit 2

110

1974

Natural Gas

Czech Slovakia

28.0%

Unit 3

210

1980

Natural Gas/RFO

USSR

30.0%

Unit 4

210

1980

Natural Gas/RFO

China

30.0%

GT-7

100

December 1985

Natural Gas

USA

31.7%

GT-8

100

March 1986

Natural Gas

ST-5

100

December 1987

N/A

GT-9

100

April 1986

Natural Gas

GT-10

100

April 1986

Natural Gas

ST-6

100

March 1988

N/A

CCGT Block 2-A

31.7%

CCGT Block 2-B

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

USA

31.7%
31.7%

Description of GENCO Plants

3-3

Technical Audit Study of GENCO Power Plants

Plant

Installed Capacity
(MW)

Year of Commissioning

Fuel

Country of Origin

Thermal Efficiency
(Design)

CCGT Block 1
GT-11

136

September 1992

Natural Gas

Germany

32.1%

GT-12

136

December 1992

Natural Gas

ST-13

143

May 1994

N/A

Unit 1

210

September 1993

Natural Gas/ RFO

Russia

36.8%

Unit 2

210

March 1994

Natural Gas/ RFO

Russia

36.8%

Unit 3

210

February 1995

Natural Gas/ RFO

Russia

36.8%

Unit 4

320

December 1997

Natural Gas/ RFO

China

36.7%

Unit 5

200

February 1995

Natural Gas/ RFO

China

31.7%

Unit 6

200

August 1995

Natural Gas/ RFO

China

31.7%

32.1%

TPS Muzaffargarh

th

Source: Power System, Statistics, 34 Edition, 2009.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Description of GENCO Plants

3-4

Technical Audit Study of GENCO Power Plants

3.2

TPS Jamshoro

TPS Jamshoro is one of the major generation installation connected to the National Grid
System in the south of Pakistan. The present installed capacity of TPS Jamshoro is
850 MW consisting of four steam power units. Exhibit 3.3 shows 200 MW Steam
Turbine Unit No. 2 at TPS Jamshoro.
Exhibit 3.3: 200 MW Steam Unit No. 2 at TPS Jamshoro

The staff strength at the power station is 1,550. About 50% of the staff is residing in the
residential colony with their families built adjacent to the power house. The residential
colonies provide all the basic and civil amenities like school, hospital, recreational
centers, playgrounds, mosques, and shopping centers to cater for the needs of the
employees.
Water supply for cooling and drinking is taken from the Indus River through a pipeline
and pumping station network. For drinking purpose, the river water is only clarified
whereas for supply to the power plant it is treated further to produce demineralized water
for boilers.
RFO decanting: TPS Jamshoro has decantation arrangements for both railway tank
wagons and road tankers. However, the power station receives RFO only through tank
lorries from Karachi as delivery through railway was discontinued in 2003. The station
has two arrangements for decanting of RFO from tank lorries and railway wagons; an
open channel and an oil receiving header. The channel is normally used during dry
weather whereas the oil header was initially constructed to decant oil during rainy periods
but it is used round the year due to increasing number of incoming tank lorries. Oil is
lifted by transfer pumps from the channel and header into storage tanks. In recent times,

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Description of GENCO Plants

3-5

Technical Audit Study of GENCO Power Plants

RFO Storage: TPS Jamshoro has common RFO storage facilities for all units. It has
4 main storage tanks of 26,500 tonnes each having a total storage of 106,000 tonnes at the
plant. These tanks are interconnected and used as common storage for all units. Exhibit
3.4 shows the oil storage facilities at TPS Jamshoro.
Exhibit 3.4: Oil Storage Tanks at TPS Jamshoro

3.3

TPS Guddu

TPS Guddu has both steam and combined cycle units that operate on medium calorific
value (MCV) gas from Mari, Kandhkot and Chachar. Exhibit 3.5 shows a view of the
turbine hall of 200 MW Steam Unit No. 3 at TPS Guddu.
Exhibit 3.5: 200 MW Steam Unit No. 3 at TPS Guddu

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Description of GENCO Plants

3-6

Technical Audit Study of GENCO Power Plants

The plant has a staff of about 1,950 persons living with their families at the residential
colony built adjacent to the powerhouse. Civil amenities like schools, hospitals,
recreational centers, playgrounds, mosques, and shopping centers have been provided at
the cost of the company to cater for the needs of the employees.
Water supply for cooling and for boiler feed water is taken from the Indus River through
a pipeline and pumping station network at the nearby Begari Feeder, Sindh. For drinking
purposes, the water taken from the canal is clarified and supplied through overhead tanks.
Water is treated to produce demineralized water for boiler feed and other usage at the
plant.
TPS Guddu is the major generation installation connected to the national grid system in
Pakistan in the middle of the country. The other important feature of this plant is that it
generates electricity on MCV gas to provide electricity at a comparatively lower cost to
national grid.
Oil Decanting: The power station has decantation arrangement for road tankers. Oil is
decanted into a channel and lifted by transfer pumps into storage tanks.
Oil Storage: TPS Guddu has common storage facilities for the steam units 3 & 4. The
plant has 9 storage tanks with total capacity of 56,400 tonnes of RFO. Exhibit 3.6 shows
the RFO storage facilities at the power stations.
Exhibit 3.6: RFO Storage Capacity at the Power Stations-TPS Guddu
Power Station

Unit No.

TPS Guddu

Total

3.4

No. of FO
Tanks

Capacity of each Tank


(Tonnes)

Total Storage Capacity


(Tonnes)

12,000

24,000

5,000-5,500

21,000

3,800

11,400

56,400

TPS Muzaffargarh

TPS Muzaffargarh is connected to the National Grid System in the mid-country near
major load centers. The present installed capacity of TPS Muzaffargarh is 1,350 MW
consisting of six steam power units. The Exhibit 3.7 shows the 200 MW Steam Turbine
of Unit No. 6 at TPS Muzaffargarh.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Description of GENCO Plants

3-7

Technical Audit Study of GENCO Power Plants

Exhibit 3.7: 200 MW Steam Unit No. 6 at TPS Muzaffargarh

The plant has staff strength of around 1,500 personnel most of which live with their
families in the residential colony built adjacent to the powerhouse. Like other GENCO
plants, the staff residential colony provides the civil amenities like school, hospital,
recreational centers, playgrounds, mosques, and shopping centers.
Water for cooling and drinking purpose is supplied through 35 Tube-wells, which are
installed along the banks of Taliri canal flowing 8Km away in the east.
Muzaffargarh Thermal Power Plant is the major generation installation connected to the
National Grid System in Pakistan in the middle of the country.
Oil Decanting: The power station has decantation arrangements for both railway tank
wagons as well as tank lorries. Similar to TPS Jamshoro, the oil is decanted into a deep
channel and lifted by transfer pumps into storage tanks. The decantation of RFO at
Unit 4 as well as Unit 5 & 6 is carried out through oil receiving headers. Presently, only
the header for Unit 4 is operational. Exhibit 3.8 shows the RFO decanting station with
both railway wagons and tank lorries off-loading oil.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Description of GENCO Plants

3-8

Technical Audit Study of GENCO Power Plants

Exhibit 3.8: Oil Decanting from Railway Wagons and Tank Lorries
at TPS Muzaffargarh

Oil Storage: Each phase of TPS Muzaffargarh has its own dedicated storage facilities
that have now been interconnected and can supply fuel to all the operating units. The
power station has 11 storage tanks with a maximum capacity of around 241,000 tonnes.
Exhibit 3.9 shows the phase-wise installed RFO storage capacity at the power stations.
Exhibit 3.10 shows the Oil Storage Facilities at TPS Muzaffargarh.
Exhibit 3.9: RFO Storage Capacity at the Power Stations-TPS Muzaffargarh
Power Station
TPS
Muzaffargarh

Unit No.

Capacity of each Tank Total Storage Capacity


(Tonnes)
(Tonnes)

1, 2 & 3

20,000 18,500

120,000 to 111,000

20,000 ~ 18,500

40,000 37,000

5&6

27,000 ~ 25,000

81,000 75,000

Total

11

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

No. of FO Tanks

241,000-223,000

Description of GENCO Plants

3-9

Technical Audit Study of GENCO Power Plants

Exhibit 3.10: Oil Storage Tanks at TPS Muzaffargarh

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Description of GENCO Plants

3-10

Technical Audit Study of GENCO Power Plants

4. Maximum Present Capability


4.1

General Approach and Overall Limitations

The capacity tests were carried out under certain limitations and restrictions specific to
each unit of the power plants. Most of the units could not be operated, even for a shorter
duration of time, under full opening of the turbine steam control valve, as recommended
under ASME PTC-6, to assess their maximum output capability. Based on their
experience, the management had apprehended risk of damage to heater tubes in the
boilers and other risks if the boilers were operated above certain loads. Owing to these
reasons and the prevailing shortage of power generation capacity in the country, it was
agreed with the power station managements that the units will be operated in safe mode
for testing purposes to avoid any disruption in operations. The capacity tests were carried
out for continuous operation of each unit for 3-4 hours at a time with gross and net output
capacity observed and recorded at an interval of one hour. The test was carried out for
three days at a unit. The gross and net capability of the unit was calculated on the basis
of average readings over the testing period. Detailed data on capacity measurements for
each unit of the Jamshoro, Guddu and Muzaffargarh power stations is provided in
Appendix B as Exhibit B.1, B.2 and B.3 respectively.
4.2

TPS Jamshoro

Limitations of Test: The speed governors of Units 2-4 were not functioning on auto
control. The load was therefore adjusted manually to maintain output at a certain level.
In case of Unit 1, the output of the unit was temporarily reduced to 187 MW from 200
MW because of overheating of turbine bearing.
Results: The results of the capacity tests for TPS Jamshoro are presented in Exhibit 4.1.
The capacity tests indicated a maximum degradation of around 40% for Unit 2 from its
design capacity and a minimum degradation of around 23% for Unit 1. The overall
power station capability has dropped by 32% in the present operating conditions.
Exhibit 4.1: Unit-wise Installed Capacity and Present CapabilityTPS Jamshoro
Unit No.

Installed
Capacity
MW

Present Gross
Capability
MW

Auxiliary Load
MW

Present Net
Capability
MW

Capacity
Degradation

Unit 1

250

191

15

176

23%

Unit 2

200

119

112

41%

Unit 3

200

125

12

113

38%

Unit 4

200

146

13

133

27%

Total

850

581

46

535

32%

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Maximum Present Capability

4-1

Technical Audit Study of GENCO Power Plants

4.3

TPS Guddu

Limitations of Test: The gas flow meters of steam Unit 1 and Unit 2 and CCP Block 2B
were not functional and therefore tests could not be carried out for these units. Steam
Unit 4 was on extended shut down from December 11, 2010 to March 15, 2011 due to
damaged air preheater and therefore could not be tested in the timeframe of this study.
Gas flow meters for CCP Block 1 and Block 2-A were functional and capacity tests were
therefore carried out at these two units only.
Results: CCP Block 1 has shown 40% degradation in its capacity from the installed
capacity whereas CCP Block 2-A appears to be in better condition with only 17%
capacity degradation, most of which was contributed by the steam turbine Unit 5 which
has lost about 29% of its capacity. Exhibit 4.2 provides the unit-wise installed capacity
and present capability of the units assessed under the testing procedures.
Exhibit 4.2: Unit-wise Installed Capacity and Present Capability of Units Tested
Under the StudyTPS Guddu
Installed
Capacity
MW

Present Gross Auxiliary Load


Capability
MW
MW

Present Net
Capability
MW

Capacity
Degradation

CCP Block 1
GT 11

100

93

92

7%

GT 12

100

85

85

15%

ST 13

100

71

69

29%

Total Block 1

300

248

246

17%

GT 7

136

80

80

41%

GT 8

136

80

80

41%

ST 5

143

84

81

41%

Total Block 2-A

415

244

240

41%

Total

715

493

487

31%

CCP Block 2-A

4.4

TPS Muzaffargarh

Limitations of Test: Unit 1 was on extended shut down from November 2010 to end of
March 2011 due to delay in arrival of experts from the Russian manufacturer of
equipment to supervise the replacement work. Units 2-6 were tested.
Results: Results of capacity tests for Units 2-6 are presented in Exhibit 4.3. Significant
degradation was observed on all units when compared with their respective design
capacities. Unit 2 was in the best operating condition with 20% degradation in capacity
whereas Unit 6 was the worst with 63% degradation in capacity.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Maximum Present Capability

4-2

Technical Audit Study of GENCO Power Plants

Exhibit 4.3: Unit-wise Installed Capacity and Present Capability of Units Tested
Under the Study TPS Muzaffargarh
Unit No.

Installed
Capacity
MW

Present Gross
Capabilit
MW

Auxiliary Load
MW

Present Net
Capability
MW

Capacity
Degradation

Unit 2

210

168

11

156

20%

Unit 3

210

140

13

127

33%

Unit 4

320

202

21

181

37%

Unit 5

200

97

11

86

51%

Unit 6

200

73

10

64

63%

Total

1,140

680

66

614

40%

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Maximum Present Capability

4-3

Technical Audit Study of GENCO Power Plants

5. Heat Rate Analysis


5.1

Definitions

The following definitions were followed in the analysis of heat rates:


Heat Rate: Heat rate of a plant is the amount of thermal energy required to generate one
unit of electrical energy and is generally expressed as K calories/kWh or Btu/kWh. In
this report, Btu/kWh has been adopted as the standard units for heat rate.
Thermal Efficiency: Thermal efficiency of the power plant also simply referred to as the
efficiency of the plant is the ratio of the output energy to the input energy of the plant. It
is usually calculated as 3,412/ (heat rate of the plant) expressed in Btu units.
Gross and Net Efficiency: Both the heat rate and efficiency could be gross or net
depending on the point of measurement of the output of the plant. The gross efficiency is
the ratio of the total energy generated from the plant to the total energy input whereas the
net efficiency is calculated as the ratio of total energy sent-out from the plant to the total
energy input of the plant. The energy sent-out is calculated by subtracting auxiliary
consumption of the plant and losses of plants cable and step-up transformer from the
gross generation of the plant. In certain cases, a discrete sent-out meter is installed at the
plant that can provide a direct measure of the energy sent out from the plant.
5.2

Limitations in Assessment of Heat Rates

A number of limitations were encountered in carrying out the heat rate tests and
efficiency in nearly all the cases. These are summarized in the following sections.
5.2.1

Testing Schedule

The GENCO power stations do not have functional flow meters to measure the fuel oil
supplied to each unit in continuous manner over a specified period. Oil measurements
were taken by using dip-tapes from the service tank or main storage tank depending on
the specific arrangement for each unit. Service tanks are smaller in size and provide
storage of 3-4 hours of units consumption and need to be refilled every 4 hours. The
refilling process takes about 1-2 hours. The testing team was working in single shift and
therefore could only record observations during daytime working hours. Owing to these
reasons, heat rate tests were carried out for continuous operation of each unit for 2-3
hours at a time with input and output energy observed and recorded. The test was carried
out once in the morning and once in the afternoon and continued for three days to capture
variations in the heat rates under different operating conditions of the unit. The present
gross and net heat rates and resulting efficiency of the plant were calculated on the basis
of average of the observed readings over the testing period.
5.2.2

Measurement of Fuel Flow

The steam units at the power stations studied have the provision of dual fuel combustion
on natural gas and RFO with the exception of Unit 1 at TPS Jamshoro that can only
operate on RFO and the Units 1-2 and combined cycle units at TPS Guddu that operate

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Heat Rate Analysis

5-1

Technical Audit Study of GENCO Power Plants

on medium calorific value (MCV) gas. However, as gas was not being supplied to the
plants during the study period, the heat rates of all the dual fuel steam units were tested
on RFO.
It was observed that the GENCOs have not followed a standard fuel supply arrangement.
No credible measurement system was in place for the RFO received from supplier at the
power plants. Similarly, no credible measurements were being taken for the RFO fed to
each unit from plants main storage. Most of the measurement instruments were either
not calibrated, non-functional, or simply missing. At TPS Muzaffargarh and TPS Guddu,
many units have common fuel supply pipelines without adequate measurement
instruments at each unit. Similarly, a number of units do not have RFO service tanks to
monitor their fuel flow. The same is the case at Guddu where gas flow meters are mostly
missing and gas is supplied through common pipelines to the steam and CCGT units. It
was therefore quite a challenge to discretely measure the fuel input at most of the units.
RFO consumption was calculated by using dip-tape, calibration charts of the feeding
tanks (the specific day storage or service tank or the main storage tank, where a day tank
is not present), and specific gravity of RFO at observed temperatures. The input valves
of the respective feeding tanks of the concerned units were closed before the beginning of
the tests and sealed with locks to stop inflow of RFO and recirculation of RFO and
condensate. Electrical outputs at gross and sent-out meters, and auxiliary consumption
were recorded at the respective meter locations. All the readings at a specific time were
taken concurrently and coordination was managed through use of devices such as mobile
phones and RF radio equipment. Special teams, comprising of instrumentation experts,
were formed to concurrently read the measurement instruments to carry out tests at each
unit.
At TPS Guddu, the residential colony is also supplied gas from the header meant for
steam Units 1 and 2 with no gas measurement for the residential colony. The residential
gas consumers have individual gas meters at their premises but due to severe leakages in
the gas distribution network, the consumers are charged a flat rate with respect to size of
their houses.
5.2.3

Metering of Electrical Output

The same applied to the output side of the plants as no uniform standards are followed for
measurement of energy output. Auxiliary supply is not discrete for certain units resulting
in inappropriate accounting of auxiliary consumption. In many instances, auxiliary
consumption is not even fully measured. The units at TPS Muzaffargarh do not have
discrete sent-out meters at each unit to record net output. In case of TPS Jamshoro, the
measurement scale of the sent-out meter was in GWh at the NTDC grid station, giving
little resolution to measure the difference in kWh. The cable and step-up losses could not
be calculated at any instance due to absence of appropriate metering protocol and
therefore were not included in the calculation of net heat rate and efficiency. It was
therefore recommended to use the gross heat rates and efficiency as the baseline or
benchmark for the purpose of this study instead of net heat rate and efficiency.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Heat Rate Analysis

5-2

Technical Audit Study of GENCO Power Plants

5.2.4

Application of Heat Rate Assessment

The heat rates and efficiency parameters for the power stations have been calculated only
for the purpose of baseline evaluation or a benchmark for determining efficiency gains
and operational improvements to be achieved after the implementation of the USAID
FARA Repair and Maintenance Plan currently under implementation at these GENCOs.
It should be noted that heat rates in this study were determined under steady loading and
specific ambient and operating conditions of the units during the winter season. Average
heat rates for the power stations are likely to be higher due to variations in ambient
conditions and loading levels, inclusive of startups and shutdowns.
5.3
5.3.1

TPS Jamshoro
Testing Procedures and Data Analysis

TPS Jamshoro has four dual fuel steam units that were operating on RFO only during the
testing period. Heat rate tests were carried out for all the units of the power station. The
specific procedure for calculation of heat rates for TPS Jamshoro is illustrated in
Appendix C. The unit-wise detailed data compiled on heat rate measurements for TPS
Jamshoro is presented in Appendix D as Exhibit D.1.
5.3.2

Results

The gross and net heat rate and efficiency for the generation units at TPS Jamshoro are
presented in Exhibit 5.1. Unit 1 is most efficient with 32% net efficiency against the
design efficiency of 36.6%. The net efficiencies of Units 2-4 ranged between 25.7% to
28.6% against the design efficiency of 34%, corresponding to an overall drop in the
efficiency of the power station of about 20% compared to the design.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Heat Rate Analysis

5-3

Technical Audit Study of GENCO Power Plants

Exhibit 5.1: Unit-wise Gross and Net Heat Rate and EfficiencyTPS Jamshoro

Unit No.

Gross Energy
Generation
(kWh)

Unit 1

2,786,946

27,392

9,829

34.7%

231,862

Unit 2

1,361,912

15,971

11,727

29.1%

Unit 3

1,242,596

14,761

11,879

Unit 4

1,422,838

15,521

10,909

Fuel
Consumption
(Mmbtu)

Gross Heat
Rate
(Btu/kWh)

Gross
Efficiency*

Auxiliary
Consumption
(kWh)

Net Sent-out
Energy
(kWh)

Net Heat Rate


(Btu/kWh)

Net Efficiency
(%)

2,555,084

10,720

31.8%

83,370

1,278,542

12,492

27.3%

28.7%

129,597

1,112,999

13,262

25.7%

31.3%

122,336

1,300,502

11,935

28.6%

Gross heat rates and efficiency is recommended to be used for benchmarking purpose.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Heat Rate Analysis

5-4

Technical Audit Study of GENCO Power Plants

5.4

TPS Guddu

TPS Guddu has two main set of power generation units, a steam block and a Combined
Cycle Power Station (CCP) block. In the steam block complex, the plant has four (4)
steam units out of which Units 1 and 2 can operate only on natural gas. Units 3 and 4 are
dual fuel on natural gas and RFO. In the CCP block, the plant has three combined cycle
sub-blocks of (2 GT+1 ST) gas fired CCGT. The plant receives MCV gas from Mari,
Kandhkot and Chachar.
Measurement of Fuel Supply

TPS Guddu has major shortcomings with respect to fuel measurement both on supply
side as well as for the consumption in the power plant. No gas sales meters are installed
by the gas suppliers at the premises of the plant and gas is billed from the meters installed
at the supplier end of the pipelines. Gas from various supply sources is mixed at a gas
mixing station on the plants premises. The mixing station has separate headers for steam
and CCP blocks from where it is branched through separate pipelines to each unit. The
gas is supplied at a pressure for of 11 bar to steam units and at 23 bar to CCP. No
measurements are taken for the outflow of gas from mixing headers. Units 3 and 4 have
functional gas flow meters whereas Units 1 and 2 are operating without the gas flow
meters. Units 1 and 2, therefore, have no gas inflow measurements to establish the input
energy for the purpose of calculation of heat rate and efficiency. The heat rate and
capacity testing of Units 1 and 2 was postponed until installation of appropriate gas
metering system on supply of gas to each unit.
Fuel oil is also supplied to Units 3 and 4 through a common line with no service tanks but
the two units have separate RFO flow meters to measure their respective RFO
consumption. The testing of Unit 4 could not be carried out due long shut down caused
by damage of air pre-heater. Testing was limited to Unit 3 for these reasons.
The pipelines supplying gas to CCP block also do not have a gas meter at the gas mixing
header. Out of three CCP sub-blocks, the Block 2-B does not have functional gas flow
meters to measure gas consumed in the gas turbines (Unit 9 and 10). Gas consumption of
Block 2 B could therefore not be ascertained for calculation of the heat rate and
efficiency of this block.
Attempts were made to establish fuel input of the steam Units 1 and 2 and that of CCGT
Block 2-B by using secondary data from the plant operations. Due to absence of credible
data, gas consumption of these units could not be segregated. It was therefore decided to
postpone the heat rate and capacity testing of these units until installation of appropriate
gas metering system.
Measurement of Energy Output

On the output side, all units at TPS Guddu have their individual gross energy generation
meters. However, the steam units do not have adequate metering on their auxiliary
supply as well as that of sent-out energy. Unit wise auxiliary load for steam units was
calculated on the basis of connected auxiliary load at a fixed rate of 8% of gross
generation. The sent-out energy was calculated by subtracting the estimated auxiliary
consumption from gross generation. All the CCP blocks have appropriate meters for

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Heat Rate Analysis

5-5

Technical Audit Study of GENCO Power Plants

gross generation, auxiliary consumption and energy sent-out. Therefore, it is again


recommended to use gross heat rates and efficiency for the benchmarking of steam units.
5.4.1

Testing Procedures and Data Analysis

Specific procedures were developed to carry out energy measurements for steam and
CCP blocks of the power station which have been illustrated in Appendix C. The unitwise detailed data compiled on heat rate measurements for TPS Guddu is presented in
Appendix D as Exhibit D.2.
5.4.2

Results

The summary of results of heat rate tests for TPS Guddu is presented in Exhibit 5.2. The
heat rate test of the Guddu Steam Unit 3 showed inaccurate results in terms of its
efficiency higher than the design efficiency of the unit. It appears the measurement of the
existing gas flow meter is not reliable and it was showing lower consumption of gas than
the actual. The heat rate test of Unit 3 therefore was rejected.
The gas turbines (GTs 7 and 8) in Block 2-A showed the net efficiencies of 27.8% each
against the design efficiency of 31.7%. The GT 11 and GT 12 in Block 1 showed the net
efficiencies of 26.5% and 25.3% respectively against the design efficiency of 32.1%.
The net efficiency of the Block a-A and Block 1 were calculated to be 35.3% and 41.5%.
The design efficiencies of these clocks under combined cycle operations were not
provided by the management.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Heat Rate Analysis

5-6

Technical Audit Study of GENCO Power Plants

Exhibit 5.2: Unit-wise Gross and Net Heat Rate and EfficiencyTPS Guddu
Gross Energy
Generation
(kWh)

Fuel
Consumption
(MMBtu)

Gross Heat
Rate*
(Btu/kWh)

Gross
Efficiency*
(%)

Auxiliary
Consumption
(kWh)

Net Sent-out
Energy
(kWh)

Net Heat Rate


(Btu/kWh)

Net Efficiency
(%)

CCP Block 1
GT 11

7,192,000

92,347

12,840

26.6%

31,360

7,160,640

12,896

26.5%

GT 12

6,633,000

88,962

13,412

25.4%

26,880

6,606,120

13,467

25.3%

ST 13

5,116,000

110,000

5,006,000

0.0%

18,941,000

181,309

9,572

35.6%

168,240

18,772,760

9,658

35.3%

GT 7

6,346,000

77,396

12,196

28.0%

33,685

6,312,315

12,261

27.8%

GT 8

6,320,000

77,331

12,236

27.9%

18,701

6,301,299

12,272

27.8%

ST 5

6,482,000

267,000

6,215,000

0.0%

19,148,000

154,727

8,081

42.2%

319,386

18,828,614

8,218

41.5%

Total Block 1
CCP Block 2-A

Total Block 2-A


*

Gross heat rates and efficiency is recommended to be used for benchmarking purpose.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Heat Rate Analysis

5-7

Technical Audit Study of GENCO Power Plants

5.5

TPS Muzaffargarh

TPS Muzaffargarh has six steam units installed in two phases. Phase 1 consists of
Units 1-3, and Phase 2 units 5-6. Unit 4 at TPS Muzaffargarh is managed separately by a
Resident Engineer. Unit 1 of phase 1 was on extended shut down during the testing
period so heat rate tests could not be carried out. TPS Muzaffargarh does not have
individual net output meters at each unit as each unit directly feeds to common busbars at
the switchyards. Unit wise net output, therefore, was calculated by subtracting auxiliary
consumption from gross generation. The detailed procedure for calculation of heat rate
for each unit is given here under.
The specific procedures for calculation of heat rates for TPS Muzaffargarh at each phase
of the power station are illustrated in Appendix C. The unit-wise detailed data compiled
on heat rate measurements for TPS Muzaffargarh is presented in Appendix D as
Exhibit D.3.
5.5.1

Results

The unit wise gross and net heat rate and efficiency of TPS Muzaffargarh are presented in
Exhibit 5.3. Units 2 and 3 are in better condition with 31% net efficiency compared with
their design efficiency of 36.8%. Unit 4 has a net efficiency of 30% against 36.7%
design efficiency. Units 5 and 6 have efficiencies of 26% and 24% respectively against
the design efficiency of 31.7% for both units. The power station is facing an overall
degradation of around 18% in its net efficiency.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Heat Rate Analysis

5-8

Technical Audit Study of GENCO Power Plants

Exhibit 5.3: Unit-wise Gross and Net Heat Rate and Efficiency TPS Muzaffargarh
Gross Energy
Generation
(kWh)

Fuel
Consumption
(MMBtu)

Gross Heat
Rate*
(Btu/kWh)

Gross Efficiency*
(%)

Auxiliary
Consumption
(kWh)

Net Sent-out
Energy
(kWh)

Net Heat Rate


(Btu/kWh)

Net Efficiency
(%)

Unit 1

Unit 2

3,665,000

36,870

10,060

33.9%

246,074

3,418,926

10,784

31.6%

Unit 3

3,083,000

30,655

9,943

34.3%

237,521

2,845,479

10,773

31.7%

Unit 4

4,982,400

50,468

10,129

33.7%

521,000

4,461,400

11,312

30.2%

Unit 5

1,757,700

20,010

11,384

30.0%

221,585

1,536,115

13,026

26.2%

Unit 6

1,409,940

17,455

12,380

27.6%

197,128

1,212,812

14,392

23.7%

Unit No.

Gross heat rates and efficiency is recommended to be used for benchmarking purpose.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Heat Rate Analysis

5-9

Technical Audit Study of GENCO Power Plants

6. Power Plant Availability


6.1

Definitions and Limitations

The availability of the plant is best represented by the Plant Availability Factor which is
calculated as:
Plant Availability = (Running Hours / Total Hours over the period x 100)

Equation 6.1

This expression is further expanded to include the capacity lost due to constrained low
load operations over certain duration and is modified as:
Plant Availability = ( Running Hours x load served during low load operations+
Running Hours x Rated Capacity of the plant) x 100/ (Total Hours over the period x
Rated Capacity of the plant)
Equation 6.2
As power plants are subject to planned and unforeseen shutdowns, it is normal practice to
calculate plant availability over a longer duration such as on monthly or annual basis. In
view of the short visits to the plants during this study, no tests were carried out to
calculate the plant availability. Instead, plant availability was assessed on the basis of the
data compiled and reported by the power station management under the monthly
E-forms2 for the period of July 2009-November 2010.
GENCOs also do not follow any standards for plant availability. In Pakistan, the
Independent Power Producers (IPPs) set up under the 1994 Power Policy were allowed a
minimum of 85.7% plant availability that include allowances of 8.3% and 6% for planned
and forced outages respectively. The partial outages are also counted for the IPPs in their
availability calculations. Further IPPs outages during high demand months are given
higher weightage than those during low demand months. In later power policies,
government has further tightened the standards for IPPs by raising the plant availability
top 89%.
Plant availability factor for GENCOs should be worked out using Equation 6.2 by
including the impact of both the outages and the low load operations (partial outages).
However, GENCOs report availability factor in E-forms on the basis of full outages only,
by using the simplified Equation 6.1. However, the impact of low load operations
(partial outages) can be captured by taking the other performance indicators in to
consideration such as Plant Utilization Factor3 and Plant Load Factor4 for the same

E-forms is a standard reporting template used by GENCOs to assess and report the performance of
individual units and power station on monthly basis. At the completion of a fiscal year, an annual
E-form is generated at the pattern of monthly E-form. Major parameters indicated in the E-form are
units generated, units sent out, auxiliary consumption, fuel consumption, heat rates, maximum load,
minimum load, load factor, utilization factor, capacity factor, forced and planned shut-down hours, and
plant availability.
Plant Utilization Factor is the ratio of Units generated in KWh and the product of the de-rated Load in
KW and hours of the period over which the calculations are made.
Plant Load Factor is the ratio of Units generated in KWh and the product of the maximum Load in KW
and hours of the period over which the calculations are made

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Power Plant Availability

6-1

Technical Audit Study of GENCO Power Plants

period. These indicators give a good indication of the generation capability of the plant
over that period.
It must be noted that GENCOs report Plant Utilization Factor on the basis of derated
capability of the units that shows higher plant utilization. In order to provide the true
perspective of the plant availability, it is recommended that all power plant performance
indicators, such as load factor, utilization factor, capacity factor and availability factor,
should be worked out on the basis of the installed capacity so as to reflect the true picture
of the plant.
6.2

Data and Results

The consultants requested the management of GENCOs to provide hourly loading profile
and outage record in electronic form for all units for the period of July 2009 to November
2010 to assess the plant availability parameters. The management claimed that they do
not prepare the hourly loading and outage profile in electronic form due to shortages of
trained staff. Instead they provided unit-wise tripping data and monthly E-form for the
specified period that contained summary of the availability parameters. Despite the
definitions and quality issues, the availability data was taken from the E-forms of the
power stations after carrying out spot checks on the accuracy of data.
6.2.1

TPS Jamshoro

Unit wise data compiled on power plant availability on monthly basis for TPS Jamshoro
is presented in Appendix E as Exhibit E.1. Unit wise performance parameters
representing power plant availability on annual basis for TPS Jamshoro are summarized
in Exhibit 6.1. Units 2-3 have shown good availability ranging between 84% to 90%
during FY2010 as the units were operated in safe (derated) mode by the management.
However, if the Plant Availability Factor was corrected for derated output of the units,
the availability of the units would have dropped further by 20-25%, well below the
standards maintained by the IPPs. Lower availability of the Units 2-4 ranging between
58% tom 78% during FY2011 is mainly due to shortage of demineralized water for boiler
operations. The large difference in the load factor and utilization factor based on
installed capacity is a good indicator that plant was not able to operate on its rated output
for most of the time.
6.2.2

TPS Guddu

Unit wise data compiled on power plant availability on monthly basis for TPS Guddu is
presented in Appendix E as Exhibit E.2. Unit wise performance parameters
representing power plant availability on annual basis for TPS Guddu are shown in
Exhibit 6.2. The availability of CCP Block 2-A and Block 1 was mostly above 90% due
to operation on natural gas. CCP Block 2-B was low during FY2010 due to extended
shut downs from November 2009 to May 2010 needing major overhaul that has been
delayed due to procurement of spare parts and availability experts from the supplier. The
availability of this block improved in FY2011 due to improvement in gas turbine
operations. Steam Unit 6 was not available till November 2010 due to a major overhaul.
The availability of steam Unit 1 has been low at 60% during FY2011. The availability of
steam block otherwise has generally been shown good ranging between 82% to 93% but

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Power Plant Availability

6-2

Technical Audit Study of GENCO Power Plants

like TPS Jamshoro, it should be interpreted with caution due to operation on derated
output.
6.3

TPS Muzaffargarh

The unit wise data compiled on power station availability on monthly basis for TPS
Muzaffargarh is presented in Appendix E as Exhibit E.3. Unit wise performance
parameters representing power plant availability on annual basis for TPS Muzaffargarh
are shown in Exhibit 6.3. The output capability of all units of Muzaffargarh has declined
over the past two years with average degradation recorded over 40%. It appears that
management is gradually reducing the output capability of these units to improve the
availability of the units. Unit 5 was operated at a maximum of 120 MW in FY2010
compared with 200 MW of installed capacity and performed poorly with 47% availability
but it improved 74% at lower load. The availability of Unit 4 dropped from 97% in
FY2010 to 60% in the FY2011 along with a reduction in the maximum output of the unit
of about 20% from the previous year. Units 1 and 2 have shown consistent availability of
over 80% but have shown a decline of 31% and 45% in their respective output
capabilities from the previous year. The availability of Unit 6 has been steady at around
75% but this unit too was operating at only 135 MW during FY2010 and further
decreasing to 95 MW during FY2011 compared with 200 Mw of installed capacity.
These performance indicators clearly indicate low reliability levels in GENCOs that are
mainly due to lack of preventive maintenance and curtailing the operational and
maintenance expenditures.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Power Plant Availability

6-3

Technical Audit Study of GENCO Power Plants

Exhibit 6.1: Unit-wise AvailabilityTPS Jamshoro

Unit No.

Period

Unit 1

FY2010
FY2011 YTD

Unit 2

FY2010
FY2011 YTD

Unit 3

FY2010
FY2011 YTD

Unit 4

FY2010
FY2011 YTD

Installed
Capacity
(IC)
MW

Derated
Capacity
(DC)
MW

250

187

200

200

200

160

160

160

Maximum
Load
MW

Minimum
Load
MW

Load
Factor
(%)

Utilization
Factor
(%)

Scheduled
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availability
Factor
Availability (Time-base)
(Hrs.)
(%)

200

63

64%

50%

1,592

737

6,431

73%

180

63

68%

53%

481

245

2,946

80%

180

90

75%

75%

140

889

7,731

88%

170

100

60%

49%

806

318

2,549

69%

180

100

75%

69%

770

572

7,417

85%

170

100

49%

49%

864

673

2,134

58%

175

100

81%

79%

141

688

7,931

91%

170

100

55%

52%

88

298

2,886

79%

Note: Data available till November 2010 for FY2011

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Power Plant Availability

6-4

Technical Audit Study of GENCO Power Plants

Exhibit 6.2: Unit-wise Availability TPS Guddu

Unit No.
Unit 1

Period
FY2010

Installed
Capacity
(IC)
MW

Derated
Capacity
(DC)
MW

110

60

FY2011 YTD
Unit 2

FY2010

110

60

FY2011 YTD
Unit 3

FY2010

200

170

FY2011 YTD
Unit 4

FY2010

200

150

FY2011 YTD

Maximum
Load
MW

Minimum
Load
MW

Load
Factor
(%)

Utilization
Factor
(%)

Scheduled
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availability
Factor
Availability (Time-base)
(Hrs.)
(%)

60

10

81%

45%

361

777

7,622

87%

55

20

53%

33%

1,154

289

2,229

61%

70

10

83%

52%

850

7,910

90%

65

15

68%

45%

251

3,421

93%

170

20

77%

70%

558

1,057

7,145

82%

130

10

52%

51%

393

128

3,151

86%

150

10

73%

59%

1,786

6,974

80%

150

10

21%

18%

394

3,278

89%

92

10

93%

85%

81

8,530

78%

103

50

87%

87%

133

3,539

96%

90

40

93%

79%

142

8,618

98%

85

42

87%

74%

3,382

92%

82

81%

62%

144

8,616

98%

70

77%

46%

102

3,570

97%

259

60

89%

76%

50

122

8,588

98%

240

124

84%

69%

94

81

3,497

95%

CCP Block 2-A


Unit 7

FY2010

100

90

FY2011 YTD
Unit 8

FY2010

100

90

FY2011 YTD
Unit 5

FY2010

100

82

FY2011 YTD
Block 2-A FY2010
FY2011 YTD

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

300

262

149

282

Power Plant Availability

6-5

Technical Audit Study of GENCO Power Plants

CCP Block 2-B


Unit 9

FY2010

100

90

FY2011 YTD
Unit 10

FY2010

100

90

FY2011 YTD
Unit 6

FY2010

100

82

FY2011 YTD
Block 2-B FY2010

300

262

FY2011 YTD

70

16

27%

24%

6,367

70

2,323

27%

100

20

26%

63%

913

1,237

1,521

41%

108

10

30%

32%

5,591

294

2,875

33%

105

10

62%

78%

250

399

3,023

82%

67

20%

18%

6,311

281

2,167

25%

0%

0%

3,672

0%

212

28%

24%

6,090

215

2,455

28%

200

20

52%

47%

1,612

545

1,515

41%

100

16

96%

60%

126

8,634

99%

80

20

99%

60%

3,671

100%

80

13

101%

60%

96

8,664

99%

80

20

90%

58%

3,665

100%

98

11

91%

55%

269

8,491

97%

84

20

80%

36%

507

3,165

86%

278

111

95%

58%

165

8,595

98%

244

78

90%

51%

177

3,495

95%

CCP Block 1
Unit 11

FY2010

136

90

FY2011 YTD
Unit 12

FY2010

136

80

FY2011 YTD
Unit 13

FY2010

143

98

FY2011 YTD
Block 1

FY2010

415

FY2011 YTD

268

Note: Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Power Plant Availability

6-6

Technical Audit Study of GENCO Power Plants

Exhibit 6.3: Unit-wise AvailabilityTPS Muzaffargarh

Unit No.

Period

Unit 1

FY2010

Installed
Capacity
(IC)
MW

Derated
Capacity
(DC)
MW

210

160

FY2011 YTD
Unit 2

FY2010

210

200

FY2011 YTD
Unit 3

FY2010

210

160

FY2011 YTD
Unit 4

FY2010

320

250

FY2011 YTD
Unit 5

FY2010

200

120

FY2011 YTD
Unit 6

FY2010

200

FY2011 YTD

135

Maximum
Load
MW

Minimum
Load
MW

Load
Factor
(%)

Utilization
Factor
(%)

Scheduled
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availability
Factor
Availability (Time-base)
(Hrs.)
(%)

160

110

81%

61%

852

7,908

90%

110

65

59%

31%

515

3,157

86%

200

110

85%

76%

703

378

7,671

88%

110

65

73%

64%

471

155

3,046

83%

160

50

71%

47%

899

7,117

81%

160

100

66%

53%

163

3,509

96%

250

130

89%

88%

240

8,520

97%

205

110

49%

41%

1,222

327

2,205

60%

120

20

38%

25%

3,426

1,712

4,121

47%

95

20

58%

31%

436

593

2,643

72%

135

20

65%

46%

624

1,568

6,729

77%

95

20

63%

35%

807

2,865

78%

Note: Data available till November 2010 for FY2011

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Power Plant Availability

6-7

Technical Audit Study of GENCO Power Plants

7. Major Reasons for Degradation of Performance


The analysis presented in Section 4 to Section 6 of this report indicates significant
degradation in the performance of the GENCOs from their design parameters. The
degradation in the output, efficiency, and availability for the power stations studies is
summarized in Exhibit 7.1.
Based on the observations of the audit team, interviews with the plants management and
operational staff and review of historic records of the plants, a number of reasons were
identified behind the overall decline in the performance of the power stations studied.
These reasons were categorized as technical and management to facilitate the
identification of remedial measures.
Exhibit 7.1: Average Degradation in Performance of GENCOs
Installed
Capacity
MW

Present
Present
Capacity
Average
Average
Average
Gross
Net
Degradation Design Net
Net
Availability
Capability Capability
Efficiency Efficiency in FY2011
MW
MW

Jamshoro

850

581

535

32%

34.7%

28.6%

72%

Guddu

715

493

487

31%

N/A*

38.9%

80%

1,140

680

614

40%

35.2%

28.9%

78%

Muzaffargarh
*

The design heat rate of CCP Guddu was not available.

7.1

Technical Issues

The power stations are suffering from a number of chronic technical problems that are
severely affecting the operational and financial performance of the plants.
7.1.1

Measurement Accuracy of Fuel Received

GENCOs purchase 1.5-2.0 million tonnes of RFO annually amounting to


Pak Rs 75-100 billion at the present price of Rs 50,000/tonne. RFO measurement system
through dip-stick or dip-tapes is generally considered to be reasonably accurate if carried
out by a trained person and in stable tank conditions, and volumes converted to weight by
using accurate calibration charts and temperature corrections. This method is applied in
most of the RFO transactions in the country. Application of this measurement procedure,
however, requires strict adherence to specified procedures, documentation of
measurements, and skilled and experienced operators and monitoring supervisors. The
procedures being practiced by the GENCOs for measurement of fuel oil are lacking in
most of these elements. There is excessive human intervention at every stage of
transactions and the system is highly prone to errors and malpractices. Following
observations were made during the inspection of GENCOs.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-1

Technical Audit Study of GENCO Power Plants

No fuel flow measurements are taken for natural gas and for the RFO supplied
from storage tanks in the units where flow meters are not present.

On units where flow meters are available for RFO or natural gas, the meters are
either non-functional or not calibrated on regular basis.

Fuel consumption at the units is not measured in real time on regular basis and
instead the power station management relies on estimated consumption rates
worked out through accounting exercise derived from invoices of the fuel
purchased, inventory levels, and energy generated over an operating period. Such
calculations have serious limitations in determining accurate heat rates and
efficiency as they ignore critical parameters such as quality of fuel received in
each batch, and allocation of fuel to individual units for a multi-unit power station
from common storage facilities.

The validity of such accounting exercises is highly questionable for setting up the heat
rate and efficiency benchmark for the plants or individual units.
7.1.2

Fuel Oil Quality

Procedures for sampling and analysis of RFO are described in Section 2 of this report.
None of the samples complied with Pakistan Standard and Quality Control Authority
(PSQCA) specifications for RFO in one or more tests. High specific gravity values were
obtained due to higher water contents. Moreover, the low calorific value was observed
due to high specific gravity, water and ash contents. Results of fuel oil testing are
summarized in Exhibit 7.2. The detailed testing results of the analysis are provided in
Appendix A.
Exhibit 7.2: Summary of Results of Fuel Oil Testing
Test

PSQCA
TPS Jamshoro
Specifications Min
Max

TPS Guddu

TPS Muzaffargarh

Min

Max

Min

Max

Specific Gravity @ 15.6 C

0.970 Max

0.969

0.985

0.950

0.972

0.966

0.971

Water Contents Vol. %

0.5% Max

1.2%

1.8%

8.0%

4.2%

1.4%

2.8%

Sulfur, Total, % mass

3.5% Max

2.8%

3.2%

2.5%

2.9%

2.7%

3.0%

Ash Content, % Wt.

0.1% Max

0.3%

1.4%

0.0%

0.5%

0.0%

4.2%

17,844 18,202

16,660

17,438

17,076

18,089

Clorific Value, Gross,


BTU/Ib

18,200 Min

All the power stations have their own laboratories to analyze fuel oil on a daily basis.
However, it was observed that the laboratory staff assigned for collection of samples was
not adequately trained, and the testing procedures prescribed under the standards are not
likely being fully complied with. This is evident from the results of the analysis of RFO
tested from an independent reputed laboratory as part of this assignment and summarized
in Exhibit 7.2. All of the 18 samples taken from three plants did not meet the Pakistan
Standards for Quality Control Authority (PSQCA) specifications on specific gravity,
water contents, ash content, and calorific value. Substandard RFO coupled with

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-2

Technical Audit Study of GENCO Power Plants

inaccurate measurements impacts plant performance and results in financial losses to


GENCOs due to high fuel costs. A third party RFO testing mechanism should be
established on regular basis to ensure the quality of fuel received from supplier. The
contracts with fuel supplier should include penalties or correction in price for supply of
substandard oil. Moreover, GENCOs should carry out a detailed exercise to devise a
robust measurement mechanism for RFO receipts at the plants to reduce oil pilferages
and acceptance of substandard oil.
7.1.3

Lack of Preventive Maintenance

A number of maintenance activities are long overdue and have already resulted in loss of
output capability, increasing heat rates and lower availability.

GENCO managements are forced to delay the overhauling of the plants and are
not able to carry out regular preventive maintenance to avoid break-down of the
plants for the following reasons:

Refusal of shut-down time by the system operator (NTDC) due to shortages in


power supply in the country,

Delay in payments to GENCOs against power sales, and

Delay in procurements of parts and services for plants major overhauling,

GENCO plants were designed to run on dual fuel with natural gas as primary fuel.
RFO is only used as backup fuel supply during infrequent gas outages. However,
TPS Muzaffargarh and Jamshoro have not received gas from the gas utilities on a
regular basis since 2005 and have run on RFO on continuous basis. The RFO
supplied to GENCOs contain up to 3.5% sulfur and other undesired impurities
such as vanadium. Continuous operation of steam units on RFO has increased the
breakdown frequency and lost time due to excessive corrosion caused by
formation of sulfuric acid in the flue gas circulation path and depositions of
vanadium oxide and ash on heat exchanging metal surfaces of boiler, reducing
their performance. Poor quality of RFO supplied to GENCOs has only
exacerbated this problem.

Most of the GENCO units urgently need detailed inspections for the hot gas/steam
path components to plug leakages and heat losses. Key plant components such as
soot blowers, a significant proportion of boiler tubes, high pressure (HP) feed
water heaters, and auxiliary equipment are not functioning. These have a direct
impact in the form of reduction in output and efficiency of the units Exhibit 7.3
show examples of poor maintenance at TPS Jamshoro resulting in damaged
insulation and flue gas ducts.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-3

Technical Audit Study of GENCO Power Plants

Exhibit 7.3: Poor Maintenance of Insulation at TPS Jamshoro

Poor Maintenance of Flue Gas Duct at TPS Jamshoro


The capacity of in-house workshops should be enhanced with modern machines, tools,
and training of staff to provide maintenance services for critical parts locally to reduce
down-time.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-4

Technical Audit Study of GENCO Power Plants

7.1.4

Poor Housekeeping

GENCO managements are paying little attention to simple housekeeping activities which
do not require large expenditures. Examples include:

Frequent steam leakages in boiler and other steam usages increase heat loss at the
plant as well as raise water purification cost due to excessive use of chemicals.
Exhibit 7.4 shows steam leakages at RFO heating system at Muzaffargarh. Such
leakages on continuous basis cause significant drop in efficiency.

A large number of soot blowers have become non-operational due to their


metallurgy or poor design. This increases the rate of clogging of heater elements.
A non-functional soot blower at Unit 3 of TPS Jamshoro is shown in Exhibit 7.5.

Plant management is generally oblivious to environmental conservation and


protection. Massive oil spills and un-optimal combustion results in higher rate of
toxic emissions and effluent discharges causing environmental threats to adjacent
population, flora and fauna. Exhibit 7.6 shows significant oil spillage at
Muzaffargarh RFO decanting and storage facility.

There is a need to establish a Research and Development (R&D) or a Technical Services


section to carryout research on such problems and devise solutions.
Exhibit 7.4: Steam Leakages at TPS Muzaffargarh

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-5

Technical Audit Study of GENCO Power Plants

Exhibit 7.5: View of a Nonfunctional Soot Blower at TPS Jamshoro

Exhibit 7.6: Oil Spillage at Storage Facility at Muzaffargarh

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-6

Technical Audit Study of GENCO Power Plants

7.2

Management Issues and Recommenadations

Management of the power station is responsible to carry out safe, economic, and reliable
operation of the plants. Deficiencies highlighted below were common to all the plants.
7.2.1

Lack of Performance Evaluation

No attention is given to the performance evaluation of the plants and as such no standards
are observed to assess the performance of the plants.

Each power station has an Inspection, Testing and Record (ITR) section but their
role is limited to monitoring of a few technical parameters. The power stations
also have a Maintenance Management System (MMS) which evaluates and
compiles the performance parameters of the power station and generates E-forms
on monthly and annual basis.

A detailed management study is required to prescribe key performance indicators


pertaining to financial, human and environmental performance of the plant and
the procedures to evaluate them on sustainable basis.

The ITR and MMS sections may be merged to form a Performance Monitoring
Section (PMS) at each power station to provide a wider range of performance
evaluation and monitoring services. In addition to the activities carried out by
ITR and MMS, the PMS should develop a 24-hour capability for continuous
analysis of trends in performance and losses. With this capability the PMS will
be in a position to provide definitive advice on discrepancies on fuel receipts,
inventories, and heat rates. By adding analyses and instruments over time, the
trend analysis can help identify emerging problems and form the basis for
management decisions for improvement of plant performance.

7.2.2

Limited Financial and Administrative Autonomy

Managements of GENCO plants have limited financial autonomy to take


independent decisions.

Payments to GENCOs are not made on time which results in deferment of


maintenance routines which is a major reason behind plant output and efficiency
degradation.

Approval process for procurement of spare parts and services through


international tendering is cumbersome and time consuming. It takes on the
average 18 months from initiating the tendering process to procure spare parts and
services from international sources due to time consumed in preparation of tender
documents, advertisement notices and evaluation of tenders, tender awards and
inspections, and manufacturing and transportation of goods. In addition, it takes
significantly long time before the tendering process can be initiated to get internal
approvals for procurement.

Best industry practices are not observed for financial management of the power
plants and important financial instruments such as a maintenance reserve fund to
cater for the financial needs of plants maintenance cycles are not available.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-7

Technical Audit Study of GENCO Power Plants

7.2.3

Absence of Plant Automation and Management Information System

Exhibit 7.7 shows the control room of Units 3 & 4 at the Jamshoro power plant mainly
consisting of manual and analogue instrumentation. General observations are
summarized below.

Plants are running in manual mode in the absence of modern monitoring and
control systems.

Most of the instrumentation is analogue in nature and readings are recorded


manually in the log sheets. Limited data is organized in electronic form and
therefore it is difficult to carry out meaning full analyses on plant performance
and identify problem areas.

Vital on-line analyzers necessary for optimization and control of plant operation
are missing.

The absence of performance evaluation standards and an on-line integrated


management information system (MIS) severely limits the ability of the
management to take prompt decisions and initiate actions and remedial measures
for efficient operation of the plants.

Exhibit 7.7: View of the Joint Control Room of Units 3 and 4 at TPS Jamshoro

The impact of absence of such on-line facilities and controls could be observed
frequently at the plants where air-fuel mixing ratio is not monitored due to absence of
on-line analyzers that allows escape of un-burnt fuel through plants exhaust which is
visible as black smoke (Exhibit 7.8). This not only contributes heavily towards
degradation of air quality in the surroundings of the plant but also increases the fuel
consumption of the plant raising the heat rate and cost of fuel.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-8

Technical Audit Study of GENCO Power Plants

Exhibit 7.8: Smoke Showing Poor Combustion at Unit No. 6 at TPS Muzaffargarh

All the units of GENCOs should be upgraded with installation of on-line analyzers and
instruments with communication channels to a central thermal model should be provided
to assess the performance of the plant on continuous basis.
7.2.4

Other Management Issues

The plants are suffering from overstaffing with majority of staff working without
specialized industrial training to perform their duties.

No occupational health, safety, and environmental management system and


relevant trainings were observed at the plants increasing the potential of a safety
hazard at the plant.

Inventory control system is primitive and in certain instances not operational that
result in un-optimal inventory levels at the plant, causing a direct financial burden
in the form of working capital.

GENCOs, like other power sector entities, lack any performance based human
resource management systems to promote efficiency and competition.

Simple housekeeping and safety measures such as firefighting facilities are


inadequate and completely missing in certain cases.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-9

Technical Audit Study of GENCO Power Plants

The government is currently implementing a Generation and Transmission Improvement


Plan (GTIP) for the GENCOs. Under this Action Plan, the Board of Directors of
GENCOs will be reconstituted by induction of directors from private sector to bring in
improvements in the GENCOs performance. In the absence of financial stakes, the
effectiveness of the new management at a higher level may be doubtful. Furthermore, the
resolution of a number of management and operational issues identified in the study need
a complete change in the management approach and operational environment of the
GENCOs which could prove to be a major challenge for the new management. Under
these circumstances, government could consider bringing in independent management
under a performance based O&M contract based on a structure of incentives and
penalties against the performance of the power stations. The terms and conditions of the
O&M contract could be designed in a manner to make the contractor responsible for
injecting investment for rehabilitation of the units and bringing in highly trained and
experienced senior managers capable of using state-of-the-art management tools and
industry standard O&M procedures. The O&M contractor may be given extended
authority to reward and motivate employees and to take disciplinary action and adjust the
size of the work force. This approach will help in establishing and expanding the O&M
industry and in improving the efficiency of the power sector in the country.
7.3

Detailed Technical Assessment of GENCOs

7.3.1

TPS Jamshoro

Reasons for the degradation of performance of each unit at TPS Jamshoro are listed in
Exhibit 7.10. Significant among these are summarized below:

All the units have too many leaking points and need nearly 8-10% make up water
per day for generation of steam in the boiler. Such high leakages not only
increase the operating cost of the plant but also result in heat losses in the form of
leaking steam and injection of cold make up water.

The water treatment facilities and other chemical plants are in poor condition and
require complete rehabilitation. The situation becomes critical if the treatment
facilities come under stress. An example of this is the significant increase in the
level of total dissolved solids (TDS) in the fresh water supply of the plant from
the Indus River following the floods in July 2010. The comparison of the
recommended quality and the actual water received during the month of
January 2011 are shown below in Exhibit 7.9 below. This severely affected the
availability of plant during the period of October 2010 to January 2011 period.
High levels of TDS in water significantly reduced the purification capacity of
demineralization plant and substantially increased the consumption of chemicals
adding to the O&M cost of the plant. The demineralization plant could not
produce enough water to operate even two out of four installed power generation
units simultaneously.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-10

Technical Audit Study of GENCO Power Plants

Exhibit 7.9: River Water Quality Supplied at TPS Jamshoro in January 2011
pH

T.H
(ppm)

Chloride
(ppm)

Conductivity
(S/cm)

Total Desolved Solvents


(TDS)
(ppm)

7.5-8.5

96-120

40-80

350-500

320

900

514

3,260

2,445

A common reverse osmosis (RO) plant needs to be installed to meet the


requirements of demineralized water.

The Units 2-4 show a general pattern of decline in output and efficiency while
running on RFO due to deposit of soot on heat exchange metal surfaces of heaters
and gradual chocking of air pre-heater. Most of the soot blowers are not
operational and cleaning of soot cannot be carried out. This results in eventual
shut down of unit for cleaning when output reaches the minimum loading limits
of the units. The use of chemical additives (magnesium) should be allowed at all
units to covert vanadium to magnesium vanadium pentoxide to avoid vanadium
deposits on tube and element surfaces. So far, the budget for chemicals additives
of only one unit has been included in FARA. The funds for other three units
should be provided for reliable and continuous operation of these units on RFO

The High Pressure (HP) heaters have become non-functional since long and need
replacement after thorough review of design and metallurgy of the tubes.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-11

Technical Audit Study of GENCO Power Plants

Exhibit 7.10: Reasons for Drop in Performance of the PlantTPS Jamshoro


Unit 1

Unit 2

Unit 3

Unit 4

Boiler
Detailed Inspection of boiler needs Detailed Inspection of boiler needs Detailed Inspection of boiler needs Detailed Inspection of boiler needs
to be carried out. Last carried out to be carried out. Last carried out to be carried out. Last carried out to be carried out. Last carried out
in 2000
in 2002-2003
in 2002-2003
in 2002-2003
Total of 38 soot blowers are
installed, but mostly inoperative
and need replacement

Total of 36 soot blowers are


installed, but mostly inoperative
and need replacement

Total of 36 soot blowers are


installed, but mostly inoperative
and need replacement

Total of 36 soot blowers are


installed, but mostly inoperative
and need replacement

Final super heater coils are


damaged and need immediate
replacement

Final super heater coils are


damaged and need immediate
replacement
(Included in FARA)

Inal super heater coils are


damaged and need immediate
replacement
(Included in FARA)

Final super heater coils are


damaged and need immediate
replacement
(Included in FARA)

3-way burner valves are damaged 3-way burner valves are damaged 3-way burner valves are damaged
and need replacement
and need replacement
and need replacement
(Included in FARA)

Furnace Safety Supervisory


System (FSSS) along with furnace
flame monitoring are damaged
and need replacement
(Included in FARA)

Actuators of boiler feed pumps are Actuators of boiler feed pumps are Actuators of boiler feed pumps are
damaged and need replacement
damaged and need replacement
damaged and need replacement
(Included in FARA)
(Included in FARA)
(Included in FARA)

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

FSSS along with furnace flame


monitoring are damaged and need
replacement
(Included in FARA)

FSSS along with furnace flame


monitoring are damaged and need
replacement
(Included in FARA)

Spares are required for


overhauling of steam turbine

Major Reasons for Degradation of Performance

7-12

Technical Audit Study of GENCO Power Plants

Unit 1

Unit 2

Unit 3

Unit 4

Turbines
Spares reqquired for overhauling
of turbine
(Included in FARA)

High pressure feed water (HP) are HP are bypassed due to severe
bypassed due to severe leakages leakages in heater tubes. Needs
in heater tubes. Needs tube
tube replacements
replacements

HP are bypassed due to severe


leakages in heater tubes. Needs
tube replacements

HP are bypassed due to severe


leakages in heater tubes. Needs
tube replacements

Unit does not have electronic


hydraulic governor (EHG) are
missing aand turbine is presently
manually operated. EHG along
with data acquisition system need
to installed to automated unit
output controls
(Included in FARA)

Unit does not have EHG and is


presently manually operated.
EHG along with data acquisition
system need to installed to
automated unit output controls
(Included in FARA)

Unit does not have EHG and is


presently manually operated.
EHG along with data acquisition
system need to installed to
automated unit output controls
(Included in FARA)

Unit does not have EHG and is


presently manually operated.
EHG along with data acquisition
system need to installed to
automated unit output controls
(Included in FARA)

Digital recorder/event recorder


system needs to be installed

Digital recorder/event recorder


system needs to be installed

Digital recorder/event recorder


system needs to be installed

Digital recorder/event recorder


system needs to be installed

Auto control on turbine needs to


be installed

Auto control on turbine needs to


be installed

Auto control on turbine needs to


be installed

Temperature scanners on turbine


need to be installed

Temperature scanners on turbine


need to be installed

Temperature scanners on turbine


need to be installed

Data loggers and data plotter on


turbine need to be installed

Data loggers and data plotter on


turbine need to be installed

Data loggers and data plotter on


turbine need to be installed

Data loggers and data plotter on


turbine need to be installed

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-13

Technical Audit Study of GENCO Power Plants

Unit 1

Unit 2

Unit 3

Unit 4

Air pre-heater elements and seals


are damaged and need
replacement

Air pre-heater elements and seals


are damaged and need
replacement

Air pre-heater elements and seals


are damaged and need
replacement

Induced draft (ID) fans dampers


are damaged

Induced draft (ID) fans dampers


are damaged

Induced draft (ID) fans dampers


are damaged

ID fan Impellers are damaged

ID fan Impellers are damaged


(Included in FARA)

ID fan Impellers are damaged


(Included in FARA)

Cooling tower fans need


All 12 cooling tower fans need
redundance and require additionla overhauling
bank
(Included in FARA)

All 12 cooling tower fans need


overhauling
(Included in FARA)

All 12 cooling tower fans need


overhauling
(Included in FARA)

Air Handling System


Flue gas duct & air-preheater
bottom hoppers needs repair &
maintenance
(Included in FARA)
Air pre-heater elements and seals
are damaged and need
replacement
(Included in FARA)

Cooling System

Drive shafts of cooling tower fans


need replacement
(Included in FARA)

Drive shafts of cooling tower fans


need replacement
(Included in FARA)

Drive shafts of cooling tower fans


need replacement
(Included in FARA)

Gear stystem for cooling tower


fans needs to be added

Gear stystem for cooling tower


fans needs to be added

Gear stystem for cooling tower


fans needs to be added

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-14

Technical Audit Study of GENCO Power Plants

Unit 1

Unit 2

Unit 3

Unit 4

Miscellaneuos
Last major overhauling was
carried out in Y1999 and is long
overdue since 2007. Supervisory
experts needed for overhaul ($2-3
million)

Drain valve (high pressure & high


temperature), safety, by-pass
spray control valves need
replacement.

Off-line efficiency monitoring


system and training need to be
provided
(Included in FARA)

Off-line efficiency monitoring


system and training need to be
provided
(Included in FARA)

Off-line efficiency monitoring


system and training need to be
provided
(Included in FARA)

Drain valve (high pressure & high


temperature), safety, by-pass
spray control valves need
replacement.

Drain valve (high pressure & high


temperature), safety, by-pass
spray control valves need
replacement.

Drain valve (high pressure & high


temperature), safety, by-pass
spray control valves need
replacement.

Steam convertor needs repair and maintenance

A common steam convertor unit with condensate recirculation needs


to be installed for Units 2-4

Clorination plant for treatment of


water for boiler use is not
functional and needs complete
rehabilitation.

Clorination plant for treatment of


water for boiler use is not
functional and needs complete
rehabilitation

Clorination plant for treatment of


water for boiler use is not
functional and needs complete
rehabilitation

Demineralization/ deionization
plan needs complete
rehabilitation.

Demineralization/ deionization
plan needs complete
rehabilitation.

Demineralization/ deionization
plan needs complete
rehabilitation.

Demineralization/ deionization
plan needs complete
rehabilitation.

Instrumentation and auto


operating system of
Demineralization plant is not
functional and needs rehabilitation

Instrumentation and auto


operating system of Demi
neralization plant is not functional
and needs rehabilitation

Instrumentation and auto


operating system of
Demineralization plant is not
functional and needs rehabilitation

Instrumentation and auto


operating system of
Demineralization plant is not
functional and needs rehabilitation

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-15

Technical Audit Study of GENCO Power Plants

7.3.2

TPS Guddu

Reasons for the degradation of performance at TPS Guddu are given in Exhibit 7.13.
Like other GENCOs, poor maintenance of the plant has resulted in damage to key plant
components. Significant problems are summarized below:

The CCP Block 1 is facing significant load reduction as it requires major over
hauling. The units are run in safe mode as inspection of hot gas path components
has not been carried out since 2002. The management apprehends break down of
hot gas path components if run on full load.

On CCP Block 2, the auxiliary supply is not secured in case of total plant shut
down (black out). This can cause damage to plant and excessive outage in case of
black out. Black start capability for auxiliaries needs to be ensured through
installation of a diesel generator and connection with grid.

Silting of intake water structure at Begari Sindh Feeder Canal reduces the supply
of condenser cooling water for all units that results in drop in plant output and
efficiency. Problem can be solved with dredger or remodeling of intake water
channel.

The Kandhkot and Mari gas pipeline need to be re coated as its coating has
deteriorated at places and the pipeline is exposed to corrosion. Gas leakage from
rupture in the pipeline can result in extended outage at the plant.

Exhibit 7.11 shows pictures of the damaged airpreheater of Unit 4 due to fire resulting
in an outage of nearly three months for the unit. Exhibit 7.12 shows inadequate cooling
of the turbine section of Unit 3
Exhibit 7.11: Damaged Air Pre-heater due to Fire of Unit No. 4 at TPS Guddu

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-16

Technical Audit Study of GENCO Power Plants

Damaged Air Pre-heater Elements due to Fire of Unit No. 4 at TPS Guddu

Melted Air Pre-heater due to Fire of Unit No. 4 at TPS Guddu

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-17

Technical Audit Study of GENCO Power Plants

Exhibit 7.12: Poor Cooling of Turbine Section of Unit No. 3 at TPS Guddu

Poor Cooling of Unit No. 3 at TPS Guddu

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-18

Technical Audit Study of GENCO Power Plants

Exhibit 7.13: Reasons for Drop in Performance of the Steam UnitsTPS Guddu
Unit 1-2

Unit 3

Unit 4

CCP Block 2-A and 2-B

CCP Block 1

Boiler
All of the boiler tubes are
week and cannot sustain
full temperatures and
pressures. All boiler tubes
should be replaced.

The performance of
Boiler insulation is very
operation feed water pump poor and damaged
has dropped significantly
due to impellor damage and
need repair/replacement

HRSG by-pass and


Isolation damper have
leakages, need to be
replaced
(Only Block 2A Included in
FARA)

Boiler feed pumps


performance reliability has
significantly dropped and
therefore need replacement
for the safe and continuous
operation of the boiler.

The performance of
operation condensate pump
has dropped significantly
due to damaged impellor
and inter-stage seals and
need repair/replacement.
Their respective regulating
valves are also not
functioning properly and
need repair/replacement.

Super heater and reheater


temperature control
injection regulators are not
working resulting in
temperature variations at
the inlet of turbine.

Feed water controllers not


functioning and need to be
replaced
(Only Block 2A Included in
FARA)

High pressure (HP) heaters


are out of service since
long and require
replacement after modified
metallurgy of tubes. If
replaced, it can significantly
reduce the fuel
consumption

Inlet/outlet motorized valves


of feed water and
condensate lines are not
functioning properly and
need repair/replacement.

Safety valves of boiler


drum, super heaters and reheater have leakage and
need repair/replacement.

HRSG drum insulation has


deteriorated and need to
replaced
(Only Block 2A Included in
FARA)

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-19

Technical Audit Study of GENCO Power Plants

Unit 1-2

Unit 3

Unit 4

CCP Block 2-A and 2-B

Refractory of boiler is badly No analyzers for exhaust


damaged causing heat loss gases are present resulting
and need rebuilding.
in ineffective control on
combustion.

Drums level transmitter


malfunction and causing
tripping, and need to be
replaced.
(Only Block 2A Included in
FARA)

Hydraulic seal of boiler is


damaged since long
resulting in heat loss and
needs to be reinstalled.

HP heaters are out of


service since long and
require replacement after
modified metallurgy of
tubes. If replaced, it can
significantly reduce the fuel
cost.

Flue gas leakages due to


damage in Heeat recovery
staem generator (HRSG)
bypass dampers and
isolation damper
controllers, damage control
system, need to be
replaced.
(Only Block 2A Included in
FARA)

HP heaters are out of


service since long and
require replacement after
modified metallurgy of
tubes. If replaced, it can
significantly reduce the fuel
cost.

No analyzers for exhaust


gases are present resulting
in ineffective control on
combustion.

CCP Block 1

Soot blowing system is not


effective both in furnace
and air pre-heaters need
rehabilitation.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-20

Technical Audit Study of GENCO Power Plants

Unit 1-2

Unit 3

Unit 4

CCP Block 2-A and 2-B

CCP Block 1

Super heater tubes are


week and cannot sustain
full temperatures and
pressures. The tubes need
to be replaced.
Boiler safety valves are
leaking and needs repair.
Periodic blow-down valves
of the boiler are leaking and
needs replacement.
Boilers burners are
chocked and need
replacement.
No analyzers for exhaust
gases are present resulting
in ineffective control on
combustion.

No analyzers for exhaust


gases are present resulting
in ineffective control on
combustion.

Turbine
Control cable deterioration
because of overheating
from flue gases
(Only Block 2A Included in
FARA)

The present instruments


and controls system is
obsolete and spare parts
are no more available.
The complete system
need to be replaced.

SSS clutch vibration on gas


turbines, need rebalancing

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-21

Technical Audit Study of GENCO Power Plants

Unit 1-2

Unit 3

Unit 4

CCP Block 2-A and 2-B

CCP Block 1

GT lift oil pumps dont build


required pressure. Need to
be replaced
Air Handling System
GRC fans are out of order
and need replacement to
reduce fuel consumption.

Flue gas ducts on both


sides is leaking and needs
repair.

Both regulators of flue gas


recirculation fan (GRC) fans
are not working thereby
affecting the performance
of boiler and need
replacement
Steam inlet air-heater
(calorifier) are not working
resulting in entry of cold air
in the boiler and need
replacement.

Cooling System
Circulating cooling water
pumps are not delivering
water at the full output
resulting into low vacuum
and hence lower turbine
output

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

20% condenser tubes have


been plugged due to
leakages and need
replacement to improve the
condenser vacuum to
increase output and
efficiency of turbine

The filer screens at the inlet


of CW pumps are damaged
due to which the debris
flows into the condenser
and causes tube chocking
resulting in load reduction
and stoppage of unit. The
screens need replacement.

Evaporator cooler not


functioning, filling material
needs to be replaced
(Only Block 2A Included in
FARA)

Silting of intake water


structure at Begari Sindh
Feeder results in
reduction in the quantity
of condenser cooling
water. Problem can be
solved with dredger or
remodelling of intake
water channel

Major Reasons for Degradation of Performance

7-22

Technical Audit Study of GENCO Power Plants

Unit 1-2
Reverse flow valves of
condenser cooling are not
functioning therefore
backwashing of the
condenser ids not carried
out. These valves require
replacement.

Unit 3
Cooling Water (CW)pumps
are not providing sufficient
water for the condenser
cooling. Also the fine
screens installed ion the
inlet of CW pumps are
damaged.

Unit 4

CCP Block 2-A and 2-B

CCP Block 1

One bay of cooling towers


need to be added for Unit 5
& 6 to improve condenser
vacuum

The RCC structure of


cooling towers has
developed cracks, Need
to be reinforced

Impellers of cooling water


(CW) pumps have been
eroded and need
replacement.
The reliability of 6 kV
Motors of CW pumps,
condensate pumps, ID/FD
fans, feed pumps, cooling
tower pumps has
significantly dropped due to
local rewinding and need
replacement of an
appropriate rewinding
solution.
At Unit 1, a number of
condenser tubes need
replacement due to
leakage.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-23

Technical Audit Study of GENCO Power Plants

Unit 1-2

Unit 3

Unit 4

CCP Block 2-A and 2-B

CCP Block 1

Leakage of acidic water


from demi-water plant
seeped into cable trenches
and damaged control
cables resulting in
excessive nuisance tripping

The air filters get


clogged in fog resulting
in reduction of load or
shut down of the gas
turbines. A solution
such as use of protective
cover at KAPCO power
plant may be able to
solve the problem.

Cooling tower structure is


completely damaged and
result in closure of the plant
during canal closure and
floods.
Generator
Generators are not able to
take maximum load due
drop in hydrogen supply
from Hydrogen generation
plant. Hydrogen generation
plant needs transformer
replacement to get to its full
capacity.
Miscillenous
AUX Standby auxiliary
transformer (6/0.4 kV) T7
requires replacement to
ensure standby
arrangements.

Reduction in amp-hour of
station battery bank due to
aging, needs replacement

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-24

Technical Audit Study of GENCO Power Plants

Unit 1-2

Unit 3

Unit 4

CCP Block 2-A and 2-B

CCP Block 1

Overhead crane bus bar


deforms in hot weather.
Needs to be replaced
The governing system of
Diesel generator for black is
not functioning therefore
DG set is no more in
service. Need
repair/replacement
Work is under progress at
Unit No. 9 and stat of the
art controlling and
monitoring system is being
installed by G.E. The unit
is not being completed due
to trouble in its exciter.
Performance to be
evaluated after the
completion of work.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-25

Technical Audit Study of GENCO Power Plants

7.3.3

TPS Muzaffargarh

Major reasons for the degradation of performance at TPS Muzaffargarh are listed in
Exhibit 7.15. Significant problems are summarized below:

Soot blowers of Unit 5 and 6 are not functional and cause significant degradation
in plants output and efficiency with continuous operation. The use of chemical
additives (magnesium) should be allowed to avoid vanadium deposits on tube and
element surfaces. The budget for chemicals additives has been included in FARA.

Nearly 50% of the cooling tower fans of Units 2, 3 and 6 are not functioning
thereby significantly affecting the condenser operations of these units due to
lower vacuum. The immediate replacement/repair of the damaged fans of all the
units is needed as lower efficacy of cooling tower results in drop of output and
efficiency of the turbine to back pressure at the condenser end.

Cooling water treatment needs to be improved with modifications in the treatment


systems to avoid damage to cooling water system components from scaling. The
up-gradation has been included in FARA for all units of TPS Muzaffargarh.

The calorifiers of Units 2, 3, 5 and 6 are not fully operational due to damage to
headers resulting in loss in efficiency for these units.

Unit 1 requires major overhaul and has been out of service since November
2011due to non-availability of experts from the manufacturer of the equipment
(OEM). The unit is expected to be back in service around end March 2011.
Exhibit 7.14 show the under repair induced draft (ID) fan of Unit 1.
Exhibit 7.14: View of Under Repair Induced Draft Fan of
Unit No. 1 at TPS Muzaffargarh

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-26

Technical Audit Study of GENCO Power Plants

Under Repair Induced Draft Fan of Unit No. 1 at TPS Muzaffargarh

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-27

Technical Audit Study of GENCO Power Plants

Exhibit 7.15: Unit-wise Reasons for Drop in Performance of the Steam UnitsTPS Muzaffargarh
Unit 1-3

Unit 4

Unit 5 & 6

Frequent leakages in boiler super-heater


tubes, causing load restriction and also forced
shut downs. The ends of super-heater tubes
need to be replaced
(Included in FARA)

Formation of scale deposits on heating


surfaces is a frequent phenomenon. Fuel
additive system for the fuel oil is required to be
launched

Soot-blowing system is defective.


Rehabilitation of soot-blowers installed at
superheaters, reheaters and regenerative
airheaters is required urgently

Performance of boiler feed water pumps is not Steam coil air heaters are deteriorated. The
upto the mark. Major overhauling of feed
air heaters are required to be
water pumps is required to be carried out
repaired/replaced

Formation of scale on heat transfer surfaces


including superheaters and reheaters is a
common phenomenon. Fuel additive system
is required to be launched
(Included in FARA)

FSSS system is not functioning effectively and FSSS system is not functioning effectively and
needs to be up-graded.
needs to be up-graded.
(Included in FARA)
(Included in FARA)

Boiler

Soot blowing system is non-functional.


Rehabilitation of furnace soot blowers and
regenerative air preheater is essentially
required

Frequent economizer tubes leakages occur


causing load restriction beyond 100 MW. The
rehabilitation of economizer tubes is required
(Included in FARA)
Formation of scale on heating surfaces is too
frequent. Fuel additive system is required to
be introduced

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-28

Technical Audit Study of GENCO Power Plants

Unit 1-3

Unit 4

Unit 5 & 6
Feed water pumps hydraulic coupling problem
is experienced. The hydraulic coupling
problem is required to be set right
(Included in FARA)
HP Heaters tubes are damaged. Damaged
tubes are required to be replaced/repaired

Turbine

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Low Pressure turbine rotor blades of last stage


were removed after damages. The blades
need to be reinstalled with new ones and
balancing of turbine is essentially required
(Included in FARA)

Intermidiate Pressure (IP) and Low Pressure


(LP) turbine rotors are badly deteriorated. The
replacement of rotors is needed urgently
(Included in FARA)

Turbine Supervisory Instrumenttaion (TSI)


needs upgradation
(Included in FARA)

Gland seals of HP/IP turbines are


deteriorated. Replacement is required

DEH system needs to be replaced.


(Included in FARA)

The performance of turbines DEH-III and data


acquisition systems DAS-100 is not funtioning
in a satisfatory manner. Installation of a
complete distribution control system (DCS),
including sensors, transmitters, and actuators
ffor Turbiner governing system DEH-III and
boiler tuurbine auto regulation system needs
to be installed.
(Included in FARA)

Major Reasons for Degradation of Performance

7-29

Technical Audit Study of GENCO Power Plants

Unit 1-3

Unit 4

Unit 5 & 6

Air Handling System


Flue gas ducts are worn-out & damaged at
several points. The affected areas of flue gas
ducts should be repaired/replaced

Air preheater elements are deteroated.


Elements of pre-heater need to be replaced
with new ones
(Included in FARA)

GRC motor is defective. The Motor needs


replacement.
(Included in FARA)
Regeneraytive airheater (RAH) elements are
badly deteriorated. Cold & hot elements are
required to be replaced
(Included in FARA)
ID fans (both sides A & B) are badly damaged.
The major components of ID fans need to be
replaced

ID fans impellers, its casing and inlet dampers


are badly deteriorated. The deteriorated
components of ID fans require replacement.
(Included in FARA)
GRC fans impellers are defective. The
defective components GRS fans require
replacement.
(1 set Included in FARA)

Flue gas duct is worn out and damaged. The


flue duct is in bad shape hence its
rehabilitation is essentially required

Air flue duct is damaged and leaking at


several points. Rehabilitation of flue gas duct,
air plennum and expansion joints is required
(Included in FARA)
Air pre-heater hot and cold elements are
damaged. The calorifiers have also
deteriorated. Replacement of air preheater
with the new one is required, Calorifiers aso
need to be repaired/replaced
(Included in FARA)

Cooling System
Condenser Vacuum system is faulty. The
condenser Vacuum system and allied cooling
water system need to be rectified

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Working of gooling tower is not satisfactory.


Gear boxes of cooling water fans & blades are
Special cooling water treatment system should worn out. Replacement of damaged parts is
be introduced
required
(Included in FARA)

Major Reasons for Degradation of Performance

7-30

Technical Audit Study of GENCO Power Plants

Unit 1-3

Unit 4

Cooling tower fans are defective. Existing


fans of cooling towers need to be replaced
with new ones and chemical treatment system
is to be managed on regular basis
(Cost of Electric motor is included in FARA)

Unit 5 & 6
Water showering louvers and their fittings are
deteriorated. Rehabilitation of these
components is needed

Generator
Performance of excitation system is not
satisfactory. Modification of excitation system
need to be carried out.
(Included in FARA)

Generator Hydrogen coolers of unit no. 6 are


defective. Replacement of hydrogen coolers
is required to be done urgently
The Bearings of TURBO genmerator are
damaged and need replavcement.
(Included in FARA)`
The generator excitation system needs
modifications. Protection relays of genertor
also need to be replaced.
(Included in FARA)

Miscillenous

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

AVR system is not functioning properly. Its


modification is required
(Included in FARA)

Boiler ingnition system needs to be converted


from natural gas to HSD/furnace oil ddue to
absence of gas
(Included in FARA)

Uninterupted power supply (UPS) for control


systems system is not working properly.
Existing UPS system need to be replaced
(Included in FARA)

6.6 kV motors of cooling water pumps, CP, ID


fans, FD Fans and Boiler Feed pumps are
damagaed and ned replacement
(Included in FARA)

Major Reasons for Degradation of Performance

7-31

Technical Audit Study of GENCO Power Plants

Unit 1-3

Unit 4

Unit 5 & 6

Technical problems on turbine and generators 0.4 kV motors of cooling towers are damaged
are being faced. Major overhauling and
and need to be replaced.
balancing of turbines is essentially required
(Included in FARA)

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Major Reasons for Degradation of Performance

7-32

Technical Audit Study of GENCO Power Plants

8. Usage of High Viscosity Fuel Oil in GENCO


Power Plants
RFO is used in dual fuel power stations when natural gas is not available. RFO is
available in several grades with kinematic viscosity ranging from 30 centistoke (cst) to
700 cst. In Pakistan, power plants use RFO with kinematic viscosity of 180 cst during
summer and 120 cst during winter. Generally the price of RFO decreases as its viscosity
increases. A suggestion was made to assess the potential of using RFO having the
viscosity of 380 cst and above in GENCO power stations as a cost saving measure.
Higher viscosity fuel oils tend to have a higher ash and metals content compared to those
with lower viscosity. Oils with higher viscosity also require additional heating to make
them pump-able and transportable through the piping systems in cold weather.
The ToRs for the study required an investigation of the technical feasibility of using fuel
oils with kinematic viscosity of 380 cst (referred to as heavier RFO in this section) in the
GENCO power stations to reduce the cost of fuel for power generation in the country.
This section discusses the major factors that need to be considered for switching to fuel
oils with higher viscosity.
8.1

Fuel Oil Standards

In Pakistan power stations and industrial plants are designed to operate on 180 cst during
summer and 120 cst during winter. The country as such does not have any experience of
using more viscous fuel oil to date. Pakistan Standards for Quality Control Authority
(PSQCA) therefore does not have any reference to the more viscous fuel oil grades.
Internationally, residual fuel oil is also referred to as marine fuel and its specifications are
guided by ISO 8217: 2010Classification of marine fuels. Exhibit 8.1 shows the
specifications of various grades of Marine Residual Fuel Oil. The specifications indicate
an increasing trend of vanadium, metals, and ash contents with increasing viscosities.
Increasing concentrations of these parameters lead to a decline in performance of steam
plants and increase in operations and maintenance (O&M) cost.
8.2

Potential for use in Power Generation in Paksitan

Heavier fuel oils of 380 cst and above are used in power generation in many countries
including India and Brazil. The following is a summary of factors that could limit their
usage in the power plants in Pakistan.
Steam Plants

Heavier residual fuel oils can be used with greater flexibility in steam power plants than
in diesel sets due to the external combustion mode of firing and minimal retrofits of oil
burners to burn fuels of varying viscosities. Steam power plants can therefore be
designed to use heavier grades of fuel oil. However, in existing steam power stations, use
of heavier fuel oils can affect the output and operational efficiency due to the limitations
of the installed oil handling system.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Usage of High Viscosity Fuel Oil in GENCO Power Plants

8-1

Technical Audit Study of GENCO Power Plants

Diesel Engines

In addition to modification of the oil storage and handling system, the fuel injection
systems of the power plants using diesel engine technology would require replacement.
In addition, presence of higher concentration of vanadium will cause hot corrosion at the
exhaust valves thereby increasing the operational and maintenance cost of the plant.
The use of heavier RFO in existing diesel engine plants therefore should be considered
only after careful assessment of the economics of operations on such RFO grades.
Gas Turbines

The experience of use of RFO being marketed in Pakistan in gas turbines in Pakistan at
the KAPCO and Rousch CCGT power stations show a significant 10-15% degradation of
power output and loss of thermal efficiency of the plant and about 8-10% additional shut
down time required for periodic washing of turbine blade due to deposition of vanadium.
Due to these problems, Rousch power plant switched to gas firing for reliable operation
of the plant. The use of even heavier grades of RFO in gas turbines with substantially
higher vanadium content (higher by a factor of three) and 50% higher ash content will not
be feasible.
The above discussion indicates that the steam power stations are the only units where use
of RFO of higher viscosity of the order of 380 cst could be considered.
8.3

Modifications Required in Fuel Oil Handling at the Power Plants

Significant modifications can be required at the oil handling system of steam power
stations right from decanting from railway or road tankers to final consumption at the
boiler.
Decanting time: Due to higher viscosity, decanting will take much longer time
especially during winter as the oil will have to be heated to its pour point to permit
pumping.
Up-gradation of decanting facilities: The capacity of the decanting facility may have to
be enhanced to accommodate larger number of tankers at a time to decant desired amount
of oil in a day.
Modification in oil heating system: The heating system would need modification to
provide higher amount of heat to raise the temperature of the oil. Besides additional heat
input, heat losses in the oil storage and handling system would also increase, which will
have a negative impact on the overall thermal efficiency of the plant.
Pumping requirements: In order to flow more viscous oil, the capacity of fuel oil filling
pumps from decanting stations to storage tanks and oil feed pumps from storage tanks to
boilers will need replacement or revamping.
8.4

Modification and Adjustments Required in the Boilers

Heavier oils have different physical properties that may require modifications in the
boiler components to attain optimal efficiencies for the plants.
Burner design: Burner design may need modifications to allow for adequate fuel
atomization and combustion in the furnace.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Usage of High Viscosity Fuel Oil in GENCO Power Plants

8-2

Technical Audit Study of GENCO Power Plants

Soot blowing frequency: With nearly 50% higher ash contents in the oil, the frequency
of the soot blower operations is likely to increase. The GENCO power plants have
manually operated soot blowers and majority of them are not even operational. In such
conditions, the plants may need more frequent shut downs for washing of heater elements
and tubes in the boiler.
Oil additives/chemical usage: The higher concentration of vanadium in heavier fuel oil
will increase the rate of depositions on heat exchanging surfaces of boiler needing
frequent washing causing frequent shutdowns. These depositions can be reduced through
use of fuel additives that will add to the existing O&M costs.
Emissions: Due to higher concentration of micro carbon residue in the oil, the overall
emissions from the plant may increase.
All of the above factors would require capital investment at the plant to modify the oil
handling system and plant O&M procedures to accommodate the usage of high viscous
oil and will cost additional O&M expenses on recurring basis.
8.5

Fuel Oil Procurement and Supply

RFO of 120 cst and 180 cst kinematic viscosity is produced by local refineries which
meets nearly 50% of the country demand. GENCOs power stations contribute nearly
25-30% in the total demand of RFO in the country. Pakistan State Oil Company (PSO)
manages the fuel oil supply in the country through oil imports from the Middle East on a
regular basis to meet the domestic deficit. Since the specifications of local and imported
oil are similar, PSO maintains a uniform infrastructure for storage, handling, and
transport of RFO for the market in the country.
Fuel oil availability: PSO will need to develop special tendering mechanism for import
of heavier grade of RFO. In the absence of firm quantity contracts with GENCOs, it will
always be a challenge for PSO to estimate the order size and frequency of supply to
minimize its market risks.
Modification of port handling facilities: Modification of decanting facilities from ships
to port storage and onward handling of oil to depots will be required on the lines similar
to that of fuel oil handling systems at the power plants.
Dedicated storage: PSO will have to maintain dedicated storage for heavier RFO and
will have to modify oil handling systems at their depots.
PSO may not be willing to serve the market of heavy heavier grade RFO within the
prevailing pricing mechanisms and may look for premiums to cover the risks. Such
premiums will add to the delivered price of the heavier grade RFO, which may eliminate
the advantage offered by the lower international market price.
Use of Heavier Grade Fuel Oil in GENCOs

Switching to heavier grade RFO will require capital investment in the infrastructure for
storage, handling, transportation, and utilization of RFO. A detailed feasibility study
including the infrastructure analysis of PSO and required modifications at the steam
turbine and diesel engine based power plants and the assessment of resulting cost savings
is recommended to ascertain the economics of burning heavier grade fuel oils.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Usage of High Viscosity Fuel Oil in GENCO Power Plants

8-3

Technical Audit Study of GENCO Power Plants

Exhibit 8.1: RFO Specifications ISO 8217: 2010


Paramenter

Unit
2

Viscosity at 50 C

mm /s
3

Limit

RMA

RMB

RMD

RME

RMG

RMK

10

30

80

180

180

380

500

700

380

500

700

Max

10

30

80

180

180

380

500

700

380

500

700

Max

920

960

975

991

991

1010

10

14

15

18

20

Density at 15 C

kg/m

Micro Carbon
Residue

% mm

Max

2.5

Aluminium + silicon

mg/kg

Max

25

40

50

60

Sodium

mg/kg

Max

50

100

50

100

Ash

% mm

Max

0.04

0.070

0.10

0.15

Vanadium

mg/kg

Max

50

150

350

450

CCAI

Max

850

860

0.30

Water

870

% V/V

Max

Max

30

Max

30

Min

60

% m/m

Max

Statutory requirements

Total Sediment, aged % m/m

Max

0.10

Acid Number*

Max

2.5

Pour point (Upper)


Summer

Pour Point (Upper)


Winter
Flash Point
Sulphur

mgKOH/g

Used Lubricating Oils mg/kg


1
(ULO)
1
Calcium and Zinc
or Calcium and
Phosphorus

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Max

0.50

The fuel shall be free from ULO, and shall be considered to contain ULO when either one of the following
conditions is met:
Calcium >30 and Zinc >15 or
Calcium >30 and phosphorus >15

Usage of High Viscosity Fuel Oil in GENCO Power Plants

8-4

Technical Audit Study of GENCO Power Plants

Appendix A: Fuel Oil Analysis Results


See following pages.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix A

A-1

Technical Audit Study of GENCO Power Plants

ATTOCK REFINERY LIMITED


QUALITY CONTROL LABORATORY
FURNACE FUEL OIL TEST REPORT

Sample Report #: C-HBP-2

Sample Source:

Hagler Bailly Pakistan

Date Received: 07-01-11

Time Received:

1600 Hrs

Date Reported: 19-01-11

Time Reported:

1200 Hrs

No.

5
6
7
8

Test

Method

PSQCA5
Specifications

Results
JT-16
(1-E02962)

JT-2
(2-E02963)

JT-3
(3-E02964)

JT-4
(4-E02965)

GT-17
(6-E02966)

GT-3
(7-E02967)

0.9703

0.9710

0.9691

0.9851

0.9739

0.9722

1.

Specific Gravity @ 15.6 C

ASTM D12988 0.970 Max

2.

Flash Point, PMCC, C

ASTM D93

66 Min

83

80

85

82

95

85

3.

Pour Point, C

ASTM D97

24 Max

4.

Water Contents Vol. %

ASTM D95

0.5 Max

0.2

1.8

1.2

1.2

8.0

4.2

5.

Sulfur, Total, % mass

ASTM D4294

3.5 Max

3.1196

3.1467

2.8299

3.0688

2.8608

2.9092

6.

Ash Content, % Wt.

ASTM D482

0.1 Max

0.303

0.759

1354

0.272

0.014

0.505

7.

Clorific Value, Gross, BTU/Ib

ASTM D240

18,200 Min

18,208

17,844

17,981

17,929

16,813

17,438

PSQCA=Pakistan Standards for Quality Control Authority


JT=Jamshoro Storage Tanks
GT= Guddu Storage Tanks
ASTM=American Society for Testing And Materials

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix A

A-2

Technical Audit Study of GENCO Power Plants

Sample Report #: C-HBP-2

Sample Source:

Hagler Bailly Pakistan

Date Received: 07-01-11

Time Received:

1600 Hrs

Date Reported: 19-01-11

Time Reported:

1200 Hrs

Method

PSQCA
Specifications

No.

Test

Results
GT-5
(7-E02968)

GT-8
(8-E02969)

GT-9
(9-E02970)

0.9699

0.9626

0.9503

MT9-2
(10-E02971)

MT-3
(6-E02972)

MT-A (Unit-4)
(7-E02973)

0.9749

0.9655

0.9700

1.

Specific Gravity @ 15.6 C

ASTM D1298 0.970 Max

2.

Flash Point, PMCC, C

ASTM D93

66 Min

81

71

88

89

52

52

3.

Pour Point, C

ASTM D97

24 Max

4.

Water Contents Vol. %

ASTM D95

0.5 Max

5.6

5.8

2.8

2.4

2.4

5.

Sulfur, Total, % mass

ASTM D4294 3.5 Max

2.5506

2.7017

2.5465

2.8807

2.7814

2.7327

6.

Ash Content, % Wt.

ASTM D482

0.1 Max

0.032

0.004

0.018

2.942

1.365

4.202

7.

Clorific Value, Gross, BTU/Ib

ASTM D240

18,200 Min

16,860

17,364

17,428

17,678

17,229

17,123

MT= Muzaffargarh Storage Tanks

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix A

A-3

Technical Audit Study of GENCO Power Plants

Sample Report #: C-HBP-2

Sample Source:

Hagler Bailly Pakistan

Date Received: 07-01-11

Time Received:

1600 Hrs

Date Reported: 19-01-11

Time Reported:

1200 Hrs

No.

Test

Method

PSQCA
Specification
s

Results
MT-B
(Unit-4)
(13-E02974)

MT-1
(14-E02975)

MT-2
(15-E02976)

MT-4
(16-E02977)

MT-5
(17-E02978)

MT-6
(18-E02979)

0.9713

0.9699

0.9690

0.9710

0.9663

0.9683

1.

Specific Gravity @ 15.6 C

ASTM D1298 0.970 Max

2.

Flash Point, PMCC, C

ASTM D93

66 Min

58

54

66

68

67

68

3.

Pour Point, C

ASTM D97

24 Max

4.

Water Contents Vol. %

ASTM D95

0.5 Max

2.6

1.6

1.4

2.8

5.

Sulfur, Total, % mass

ASTM D4294 3.5 Max

3.0092

3.0396

3.0688

2.7182

2.8471

2.8318

6.

Ash Content, % Wt.

ASTM D482

0.1 Max

3.989

3.153

0.025

0.025

0.022

0.034

7.

Clorific Value, Gross,


BTU/Ib

ASTM D240

18,200 Min
17,076

17,350

18,014

18,089

17,803

17,826

Remarks: All eighteen samples does not comply Pakistan Standard and Quality Control Authority (PSQCA) specifications for Furnace Fuel Oil (FFO) in one or more tests.
High specific gravity values are obtained due to higher water contents. Moreover, the low calorific value is obtained due to high specific gravity, water and ash
contents. This report shall not be produced/made part of any investigation/inquiry/ or used for any litigation purpose. Samples were collected by M/s Hagler Bailly
Pakistan (HBP) and received at room temperature.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix A

A-4

Technical Audit Study of GENCO Power Plants

Appendix B: Data and Results of the GENCOs


Capacity Test
Exhibit B.1: Results of the Capacity Test of TPS Jamshoro
Unit 1
Date

Time

Gross Output
(MW)

21/01/2011

11:00

200

16

184

12:00

200

16

184

13:00

187

15

172

14:00

187

15

172

11:00

187

15

172

12:00

187

15

172

13:00

187

15

172

14:00

187

15

172

11:00

200

16

184

12:00

200

15

185

13:00

187

15

172

14:00

187

15

172

191

15

176

22/01/2011

23/01/2011

Average

Auxiliary Load
(MW)

Net Output
(MW)

Unit 2
Date

Time

Gross Output
(MW)

21/01/2011

11:00

125

118

12:00

125

119

13:00

125

119

14:00

125

118

11:00

125

119

12:00

122

116

13:00

122

115

14:00

110

103

11:00

102

96

12:00

112

106

13:00

117

110

14:00

113

107

119

112

22/01/2011

23/01/2011

Average

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Auxiliary Load
(MW)

Net Output
(MW)

Appendix B

B-1

Technical Audit Study of GENCO Power Plants

Unit 3
Date

Time

Gross Output
(MW)

17/02/2011

11:00

132

12

120

12:00

130

11

119

13:00

125

12

113

14:00

124

11

113

10:00

124

12

112

11:00

125

11

114

12:00

124

12

112

13:00

124

12

112

10:00

124

12

112

11:00

118

12

106

12:00

125

12

113

13:00

125

12

113

125

12

113

18/02/2011

19/02/2011

Average

Auxiliary Load
(MW)

Net Output
(MW)

Unit 4
Date

Time

Gross Output
(MW)

17/02/2011

11:00

152

13

139

12:00

150

13

137

13:00

150

13

137

14:00

152

13

139

10:00

146

13

133

11:00

150

13

137

12:00

148

13

135

13:00

149

13

136

10:00

145

13

132

11:00

130

13

117

12:00

138

13

125

13:00

141

12

129

146

13

133

18/02/2011

19/02/2011

Average

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Auxiliary Load
(MW)

Net Output
(MW)

Appendix B

B-2

Technical Audit Study of GENCO Power Plants

Exhibit B.2: Results of the Capacity Test of TPS Guddu


CCP Block 2-A (GT7, GT8, ST5)
GT 7

GT 8

ST5

Date

Time

Gross
Output
(MW)

Auxiliary
Load
(MW)

Net Output
(MW)

Gross
Output
(MW)

Auxiliary
Load
(MW)

Net Output
(MW)

Gross
Output
(MW)

30/12/2010

1000

95

0.37

95

85

0.35

85

68

1100

95

0.37

95

85

0.38

85

1300

95

0.38

95

85

0.34

1500

80

0.40

80

85

1700

80

0.40

80

0900

95

0.36

1100

95

1300

31/12/2010

01/01/2011

02/01/2011

Net Output
(MW)

Gross
Output
(MW)

67

248

246

69

68

249

247

85

71

70

251

249

0.36

85

72

71

237

235

85

0.35

85

72

71

237

235

95

85

0.34

85

72

71

252

250

0.39

95

85

0.34

85

72

71

252

250

1600

90

0.39

90

85

0.34

85

73

72

248

246

1700

90

0.39

90

85

0.34

85

73

72

248

246

0900

95

0.37

95

85

0.35

85

67

66

247

245

1100

95

0.37

95

85

0.37

85

67

66

247

245

1300

95

0.36

95

85

0.37

85

68

67

248

246

1600

95

0.36

95

85

0.35

85

71

70

251

249

0900

95

0.38

95

85

0.36

85

72

71

252

250

1100

95

0.37

95

85

0.35

85

72

71

252

250

1300

95

0.38

95

85

0.36

85

69

68

249

247

1600

95

0.40

95

85

0.36

85

72

71

252

250

93

0.38

92

85

0.35

85

71

69

248

246

Average

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Auxiliary
Load
(MW)

CCP Block 2-A


Auxiliary
Load
(MW)

Net Output
(MW)

Appendix B

B-3

Technical Audit Study of GENCO Power Plants

CCP Block 1 (GT11, GT12, ST13)


GT 11

03/01/2011

0900

1100

80

80

80

80

83

80

243

239

1300

80

80

80

80

83

80

243

239

1600

81

81

80

80

84

81

245

241

0900

80

80

80

80

84

81

244

240

1100

80

80

80

80

84

81

244

240

1300

80

80

80

80

84

81

244

240

1600

80

80

80

80

85

82

245

241

0900

80

80

80

80

83

80

243

239

1100

80

80

80

80

84

81

244

240

1300

80

80

80

80

83

80

243

239

1600

80

80

80

80

83

80

243

239

0900

80

80

80

80

86

83

246

242

1100

80

80

80

80

86

83

246

242

1300

80

80

80

80

87

84

247

243

1600

80

80

80

80

87

84

247

243

80

80

80

80

84

81

244

240

06/01/2011

Average

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Net Output
(MW)

Gross
Output
(MW)

Auxiliary
Load
(MW)

Net Output
(MW)

Gross
Output
(MW)

Auxiliary
Load
(MW)

CCP Block 1

Time

05/01/2011

Auxiliary
Load
(MW)

ST 13

Date

04/01/2011

Gross
Output
(MW)

GT 12

Net Output
(MW)

Gross
Output
(MW)

Auxiliary
Load
(MW)

Net Output
(MW)

Appendix B

B-4

Technical Audit Study of GENCO Power Plants

Exhibit B.3: Results of the Capacity Test of TPS Muzaffargarh


Unit 2
Date

Time

Gross Output
(MW)

09/01/2011

10:00

160

11

149

11:00

170

11

159

12:00

170

11

159

13:00

170

10

160

10:00

170

11

159

11:00

170

11

159

12:00

170

11

159

13:00

170

11

159

10:45

170

12

158

11:45

170

12

158

14:45

160

12

148

15:00

160

12

148

168

11

156

10/01/2011

11/01/2011

Average

Auxiliary Load
(MW)

Net Output
(MW)

Unit 3
Date

Time

Gross Output
(MW)

09/01/2011

11:00

140

13

127

12:00

140

13

127

13:00

140

13

127

14:00

140

13

127

10:00

140

13

127

11:00

140

13

127

12:00

140

13

127

13:00

140

13

127

10:45

140

14

126

11:45

140

14

126

14:45

140

14

126

15:00

140

14

126

140

13

127

10/01/2011

11/1/2011

Average

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Auxiliary Load
(MW)

Net Output
(MW)

Appendix B

B-5

Technical Audit Study of GENCO Power Plants

Unit 4
Date

Time

Gross Output
(MW)

05/01/2011

14:55

202

21

181

15:55

202

21

181

16:55

202

21

181

17:55

203

22

181

10:15

201

21

180

11:15

202

21

181

12:!5

204

22

182

13:15

202

21

181

9:30

202

21

181

10:30

201

21

180

11:30

202

20

182

12:30

202

21

181

202

21

181

06/01/2011

07/01/2011

Average

Auxiliary Load
(MW)

Net Output
(MW)

Unit 5
Date

Time

Gross Output
(MW)

02/01/2011

12:00

100

11

89

13:00

100

11

89

14:00

100

12

87

15:00

95

86

10:40

98

11

87

11:40

98

11

86

12:40

97

12

85

13:40

98

12

86

9:45

96

11

85

10:45

96

11

85

11:45

96

11

85

12:45

95

11

84

97

11

86

03/01/2011

04/01/2011

Average

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Auxiliary Load
(MW)

Net Output
(MW)

Appendix B

B-6

Technical Audit Study of GENCO Power Plants

Unit 6
Date

Time

02/01/2011

10:30

71

61

11:30

71

62

12:30

70

61

13:30

71

10

61

10:30

74

65

11:30

77

68

12:30

76

10

67

13:30

75

10

65

21:30

74

10

64

10:30

74

10

64

11:30

73

10

63

12:30

73

64

73

10

64

03/01/2011

04/01/2011

Average

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Gross Output
(MW)

Auxiliary Load
(MW)

Net Output
(MW)

Appendix B

B-7

Technical Audit Study of GENCO Power Plants

Appendix C: Testing Procedures for Measurment


of GENCOs Gross and Net Heat
Rates
C.1 TPS Jamshoro
All of the four units at TPS Jamshoro have similar instrumentation arrangement for
measurement of fuel input and electrical output. Exhibit C.1 shows the energy
measurement system at TPS Jamshoro. The diagram indicates the ideal location of the
measuring instruments for appropriate measurement input and output energy of the plant
along with the actual instrumentation on ground at each unit. As can be seen from the
diagram, RFO received from the tank lorry is measured with dipstick because of the
absence of RFO flow meters at the oil receiving terminal. The separate RFO pipelines
feed each unit through a dedicated service tank (day tank) through a flow meter. The
calibration status of the flow meter however was not available and therefore the readings
of flow meters were not considered for the testing purpose.
The power station has arrangements to measure gross generation and auxiliary
consumption at each unit but have no meter at the sent-out of each unit within the power
station premises. The sent-out electrical energy meters for each unit are located at the
adjoining NTDC 500 kV grid station.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-1

Technical Audit Study of GENCO Power Plants

Exhibit C.1: Schematic Diagram Show Status of Measurement of Fuel Input and Electrical Output TPS Jamshoro Unit 1-4

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-2

Technical Audit Study of GENCO Power Plants

C.1.1

Power Testing Procedure and Data Collected

TPS Jamshoro has net sent-out meters at each unit located at the incoming busbar of the
NTDC switchyard. These meters are at the premises of the nearby NTDC grid station
and record energy sent-out at the scale of GWh. It is therefore, recommended that gross
heat rates and efficiency should be used for the benchmarking purpose in future. The
detailed procedure for calculation of heat rate for each unit is given below. The input and
output measurement arrangement is same for all the four units of this power station.
1. Heat rate tests were conducted in two (2) sessions (in morning and in evening) for
a duration of 3 hours.
2. These units have their individual service tanks where the RFO consumption was
measured using dip-tape during the test period. Flow meters were present on all
the units but calibration records of the flow meters were not available. The
readings from flow meters were noted for record purposes but not used in the heat
rate analysis.
3. The fuel feeding tank was isolated by closing respective valves of supply and
recirculation.
4. Each unit has gross energy generation meter and a unit auxiliary meter. Some of
the auxiliaries were fed from other sources such as starting transformer through a
separate meter. All units have independent net sent-out energy meters for energy
delivered at the busbar of the NTDC switchyard. However, the measurement
scale of the sent-out meter at the busbar of the NTDC switchyard was in GWh
and therefore it was not possible to accurately capture the variations in KWh.
Therefore, net generation was calculated at the unit output point by subtracting
total auxiliary consumption from gross generation. The step-up transformer and
cable losses for the units from generator terminal up to NTDC switchyard could
not be calculated.
5. The readings of all the input and output measurement points were taken
concurrently in the presence of station staff:
a. Unit fuel input: The RFO consumption volume (in kilo or 000 liters) was
measured at the service tank of the unit by using dip-tape and calibration
charts for the service tanks. Temperature at the service tank was also recorded
simultaneously. RFO consumption in metric tonnes was calculated after
applying corrections for temperature and specific gravity of RFO.
b. Unit energy output: Readings from gross energy meters, station auxiliary
meters and other meters of auxiliary consumption through starting
transformers were taken to measure the gross and net output of the plant after
applying appropriate multiplying factors for respective meters.
The detailed procedures for calculation of heat rates for TPS Jamshoro Units 1-4 are
presented in Appendix D.2.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-3

Technical Audit Study of GENCO Power Plants

C.2 TPS Guddu


All the units at TPS Guddu have similar instrumentation arrangement for measurement of
fuel input and electrical output for its steam and CCP blocks. Only Steam Unit 3 of the
steam block could be tested. Steam unit 3 and 4 are dual fired units capable of both
natural gas and RFO firing.
RFO received from the tank lorry is measured with dipstick because of the absence of
RFO flow meters at the oil-receiving terminal. The RFO is fed to Unit 3 and 4 through a
common pipeline directly from main storage tanks. Both units have separate flow
meters, however, the calibration status of the flow meter was not available and therefore
the readings of flow meters were not considered for the testing purpose.
Guddu receives medium calorific value raw gas from Kandhkot, Mari and Chachar. Gas
meters are not present to measure the gas received at the power station. Since the
pipelines are owned by Guddu power station, gas suppliers bill the power station from the
meters installed at gas fields nearly 70-80 kilometers away from the power station. No
gas flow meters are present at Steam Units 1 and 2. The gas flow meters at Steam unit 3
and Block 2B were either not functional or not calibrated.
The power station has arrangements to measure gross generation and auxiliary
consumption at each unit but have no meter at the sent-out of each unit within the power
station premises. The sent-out electrical energy meters for each unit are located at the
adjoining NTDC 500 kV grid station.
Exhibit C.2 shows the energy measurement system at the steam block Units 3 and 4
whereas Exhibit C.3 shows the energy measurement system at the CCP block of TPS
Guddu.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-4

Technical Audit Study of GENCO Power Plants

Exhibit C.2: Schematic Diagram Show Status of Measurement of Fuel Input and Electrical Output
Steam Block Unit 3-4

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-5

Technical Audit Study of GENCO Power Plants

Steam Unit 1-2 and Steam Unit 4

Steam Units 1 and 2 were not tested due to absence of gas flow meters. Unit 4 could not
be tested due to long shutdown due to breakdown of air pre-heater.
Steam Unit 3

The detailed procedure for calculation of heat rate for Unit 3 is given here under:
1. The unit was running on mixed firing. The unit has operational gas and RFO flow
meters. The consumption of gas was noted from gas flow meters at the specified
time intervals.
2. These units do not have their individual service tanks and RFO is directly fed
from main storage tanks through a common line for Units 3 & 4. RFO Flowmeters were present on both the units but calibration status of the flow meters was
not available. Since Unit 4 was on prolonged shutdown, RFO was measured
directly at the feeding (main storage) tank using the dip-tape.
3. Since feeding tank did not require frequent refills, heat rate tests were conducted
in one session in the morning for duration of 6 hours.
4. The feeding tank was isolated by closing respective valves of supply and
recirculation.
5. The Unit has gross energy generation and sent-out meters with no discrete
measurement of auxiliary consumption.
6. The readings of all the input and output measurement points were taken
concurrently in the presence of station staff:
a. Unit fuel input: The readings of flow-meters installed in respective units were
noted down concurrently with the dip measurement at the feeding tank.
Temperatures at storage tanks were also recorded simultaneously.
b. Unit energy output: The measurements were taken from gross energy and sent
out meters. The auxiliary consumption and losses in step-up transformer and
cables/lines up to sent-out busbar of the power station were calculated by
subtracting the sent-out energy from the gross energy generation.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-6

Technical Audit Study of GENCO Power Plants

Exhibit C.3: Schematic Diagram Show Status of Measurement of Fuel Input and Electrical Output
TPS CCP Block 2-A and CCP Block 1

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-7

Technical Audit Study of GENCO Power Plants

CCP Blocks

The detailed procedure for calculation of heat rate for Block 1 and Block 2-A is given
here under:
1. Due to availability of functional flow meters for gas measurement, heat rate tests
were conducted in single session over the day for the duration of 8 hours.
2. The gas consumption was measured at the gas flow meters installed at the inlet of
each gas turbine.
3. The unit has meters for gross energy generation, auxiliary consumption and
energy sent-out at all units.
4. The readings of all the input and output measurement points were taken
concurrently in the presence of station staff:
a. Unit fuel input: The reading of flow-meters installed in respective control
rooms were noted down.
b. Unit energy output: The measurements were taken from gross energy,
auxiliary supply, and sent out meters.
The detailed procedures for calculation of heat rates for TPS Guddu CCP Block are
presented in Appendix D.2.
C.3 TPS Muzaffargarh
TPS Muzaffargarh was constructed in three phases and each phase has its own
arrangements for input and output of energy. Phase 1 consists of Units 1-3, Phase
2consists of Units 5 and 6 whereas Unit 4 is managed as separate entity in the power
station.
Exhibit C.4, C.5 and C.6 present energy measurement system at Phase 1, Phase 2 and
Phase 3 of TPS Muzaffargarh. The diagram indicates the ideal location of the measuring
instruments for appropriate measurement input and output energy of the plant along with
the actual instrumentation on ground at each unit. Similar to arrangements at other
GENCO power stations, RFO received from the tank lorry is measured with dipstick
because of the absence of RFO flow meters at the oil receiving terminal. Although power
station has dedicated storage facilities for each phase, these facilities were interconnected
and are now used as common storage facilities for units. Units 1-4 do not have service
tanks are instead fed directly from main storage tanks. Units 5-6 have dedicated service
tanks. RFO flow meters are present on all units but these were either not functional or
their calibration status was not known and therefore the readings of flow meters were not
considered for the testing purpose.
The power station has arrangements to measure gross generation and auxiliary
consumption at each unit but have no meter at the sent-out of each unit within the power
station premises. A number of units did not have discrete sources for their auxiliary
consumption and were sharing the sources with other units. The sent out electrical
energy meters for the power station are located at the adjoining NTDC grid stations.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-8

Technical Audit Study of GENCO Power Plants

Exhibit C.4: Schematic Diagram Show Status of Measurement of Fuel Input and Electrical Output
TPS Muzaffargarh Unit 2-3

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-9

Technical Audit Study of GENCO Power Plants

C.3.1

Testing Procedures and Data Analysis

Unit 1

This unit was not available for testing due to an extended shut down.
Units 2 and 3

1. Heat rate tests were conducted in two (2) sessions (in morning and in evening) for
duration of 3 hours.
2. These units do not have their individual service tanks and RFO is directly fed
from main storage tanks through a common line for Units 1-3. Flow-meters were
present on both the units but calibration records for the meters were not available.
Prior to running main heat rate tests on the units, the flow meters were manually
adjusted to bring their readings in close proximity to the oil consumption
measured through the dip method from the main storage tank feeding oil to these
units.
3. The feeding tank was isolated by closing respective valves of supply and
recirculation
4. This unit has gross energy generation meter and station auxiliary meters. Some of
the auxiliary requirement was fed from other sources such as starting transformers
through a separate meter. This unit does not have an independent net output
energy meter so net output was calculated by subtracting total auxiliary
consumption from the gross generation. The losses in step-up transformer and
cables/lines up to sent-out busbar of the power station could not be calculated due
to absence of sent-out meter at the unit.
5. The readings of all the input and output measurement points were taken
concurrently in the presence of station staff:
a. Unit fuel input: The reading of flow-meters installed in respective control
rooms were noted down concurrently with the dip measurement at the feeding
tank. Temperatures at storage tanks and flow meters were also recorded
simultaneously.
b. Unit energy output: Readings from gross energy meters, station auxiliary
meters and other meters of auxiliary consumption through starting
transformers were taken to measure the gross and net output of the plant after
applying appropriate multiplying factors for respective meters.
The detailed procedures for calculation of heat rates for Units 2-3 TPS Muzaffargarh are
presented in Appendix D.3.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-10

Technical Audit Study of GENCO Power Plants

Exhibit C.5: Schematic Diagram Show Status of Measurement of Fuel Input and Electrical Output
TPS Muzaffargarh Unit 4

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-11

Technical Audit Study of GENCO Power Plants

Unit 4

1. Heat rate tests were conducted in two (2) sessions (in morning and in evening) for
duration of 3 hours.
2. Unit 4 does not have its individual service tanks and RFO is directly fed from a
dedicated main storage tanks. Flow-meter was present but calibration status of
the meter was not available. The actual RFO consumption was directly measured
through dip method from the main storage tank feeding to the unit.
3. The feeding tank was isolated by closing respective valves of supply, recirculation
and condensate etc.
4. The Unit has gross energy generation meter and station auxiliary meters. The
Unit does not have an independent net output energy meter so net output was
calculated by subtracting total auxiliary consumption from the gross generation.
The losses in step-up transformer and cables/lines up to sent-out busbar of the
power station could not be calculated due to absence of sent out meter at the Unit.
5. The readings of all the input and output measurement points were taking
concurrently in the presence of station staff:
a. Unit fuel input: The RFO consumption was measured at the feeding tank with
the dip-tape. Temperature at storage tank was also recorded simultaneously.
b. Unit energy output: Readings from gross energy meters and station auxiliary
meters were taken to measure the gross and net output of the plant after
applying appropriate multiplying factors for respective meters.
The detailed procedures for calculation of heat rates for Unit 4 TPS Muzaffargarh are
presented in Appendix D.3.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-12

Technical Audit Study of GENCO Power Plants

Exhibit C.6: Schematic Diagram Show Status of Measurement of Fuel Input and Electrical Output
TPS Muzaffargarh Unit 5-6

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-13

Technical Audit Study of GENCO Power Plants

Units 5 and 6

1. Heat rate tests were conducted in two (2) sessions (in morning and in evening) for
duration of 3 hours.
2. The Units have their individual service tanks. Flow-meters were present but were
not functional at these units so the actual RFO consumption was directly
measured through dip method from the service tank feeding to the unit.
3. The feeding tank was isolated by closing respective valves of supply, recirculation
and condensate etc.
4. The Unit has gross energy generation meter and station auxiliary meters. The
Unit does not have an independent net output energy meter so net output was
calculated by subtracting total auxiliary consumption from the gross generation.
The losses in step-up transformer and cables/lines up to sent-out busbar of the
power station could not be calculated due to absence of sent out meter at the Unit.
5. The readings of all the input and output measurement points were taking
concurrently in the presence of station staff:
a. Unit fuel input: The RFO consumption was measured at the feeding tank with
the dip-tape. Temperature at storage tank was also recorded simultaneously.
b. Unit energy output: Readings from gross energy meters and station auxiliary
meters were taken to measure the gross and net output of the plant after
applying appropriate multiplying factors for respective meters.
The detailed procedures for calculation of heat rates for Units 2-3 TPS Muzaffargarh are
presented in Appendix D.3.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix C

C-14

Technical Audit Study of GENCO Power Plants

Appendix D: Calculation of GENCOs Gross and


Net Heat Rates
See following pages.

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

Appendix D

D-1

Technical Audit Study of GENCO Power Plants

Exhibit D.1: Calculation of Gross and Net Heat Rate and Efficiency TPS Jamshoro

Gross
Generation

Auxiliary
Consumption
Meter Readings

Aux. Consumption

000' kWh

000' kWh

0.922

150.5

32,399

0.922

0.922

54.8

39,881

3,816

32,788

59.00

0.931

0.931

188.3

35,776

1.690

61.00

0.930

0.930

65.3

39,881

4,902

36,267

1515

4.540

61.00

0.930

0.930

176.0

36,795

1715

2.060

58.00

0.931

0.932

79.8

39,881

3,837

37,196

1000

4.715

58.00

0.931

0.932

183.1

40,535

1200

2.195

59.50

0.931

0.932

85.1

39,881

3,910

40,932

1430

4.370

59.50

0.931

0.932

169.6

41,402

1630

2.000

62.00

0.922

0.922

76.6

39,881

3,709

41,771

1015

4.333

64.00

0.928

0.928

167.6

45,159

1215

1.996

65.00

0.927

0.928

77.0

39,881

3,614

45,529

1515

4.115

48.00

0.937

0.938

160.8

46,088

1715

1.820

61.00

0.930

0.930

70.4

39,881

3,604

46,458

1430

3.918

62.00

0.922

1630

1.430

62.00

1000

4.850

1230

Total

Hagler Bailly Pakistan


R1V02TAG: 04/27/11

95.7

122.9

96.2

98.0

93.0

90.6

90.4
687

27,392

389

491

401

397

369

370

370
2,787

184,644

184,675
184,936

185,017

185,313

185,383

185,684

185,759
185,789

22,713

40

33

22,743

33

22,756

22,759

33

22,741

22,758
30

22,729

22,754
30

22,726

22,742
30

185,714

22,739
31

185,413

000' kWh

22,728
32

185,345

000'
kWh

22,724
39

185,048

000' kWh
22,712

32

184,974

Total Aux.
Consump-tion

Gross
Generation
Meter Readings

000' kWh

Aux. Feed
through Startup Tr.

Total Heat Input

000' kWh

Aux. through
start-up
transformer
meter Readings

RFO Average
3
Heating Value

MMBtu

Meter
s

RFO Specific
Gravity @
1
0.55% Water
Contents

MBtu/
Tonne

RFO Specific
Gravity

Tonnes

Tank Temperature

Tonne
s

Time

Dip-Tape
Readings

RFO
Consumption

22-1-2011

21-1-2011

20-1-2011

19-1-2011

Date

RFO Weight in
2
Tank

Calculations of Gross and Net Heat Rates and Efficiency Unit 1 TPS Jamshoro

31

31

31
232

Appendix D

D-2

Technical Audit Study of GENCO Power Plants

Total Fuel Input

2
3

Gross Generation
Gross Heat Rate

27,392
2,787
9,829

MMBtu

Gross Efficiency

34.7%

Auxiliary Consumption

232

000 kWh

6
7

Sent Out Energy


Net Heat Rate

2,555
10,720

000 kWh
Btu/kWh

Net Efficiency

31.8%

000 kWh
Btu/kWh

1. Standard RFO specific gravity was adjusted for water contents in RFO. The RFO
present at the TPS Jamshoro had average water contents of 1.1% at the main storage
tanks. It was assessed to reduce by 50% at temperature range of 55-65 Co at the
service tank. A water content of 0.55% was therefore assessed for be present at
service tank stage. In future, however, a sample for RFO analysis should be taken
from service tank instead of storage tank to calculate the exact concentration of water
contents.
2. RFO volume converted to weight by using calibration charts of the service tanks.
3. The RFO present at the TPS Jamshoro had average heating value of 40,103
MMBtu/Tonne at water contents of 1.1% at the main storage tanks. The heating
value was also corrected for the water contents of 0.55% at service tank stage which
worked out to be 38,881 MMBtu/Tonne.

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix D

D-3

Technical Audit Study of GENCO Power Plants

000'
kWh

000'
kWh

000'
kWh

457,286

82,265

226

82,278

82,294

226

82,307

82,421

225

82,434

82,450

230

82,463

82,574

230

82,588

82,601

226

82,614

21-1-2011 1030

4.010 62.00

0.922

0.922

175.8

1230

2.195 62.00

0.922

0.922

105.1

70.7 39,881

1500

4.060 63.00

0.929

0.929

179.1

1700

2.335 65.00

0.927

0.928

111.4

67.7 39,881

22-1-2011 1030

4.025 68.00

0.926

0.926

177.1

1230

2.333 68.00

0.926

0.926

111.1

66.0 39,881

1500

3.667 61.00

0.930

0.930

163.9

1700

1.997 61.00

0.930

0.930

98.4

23-1-2011 1000

3.535 57.00

0.932

0.932

159.1

1200

1.884 57.00

0.932

0.932

94.2

1400

3.915 56.00

0.933

0.933

174.1

1600

2.245 56.00

0.933

0.933

108.5

65.7 39,881

Total

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

65.5 39,881

64.9 39,881

400.5

2,820 457,512

457,795

2,698 458,021

460,016

2,633 460,241

460,517

2,612 460,747

462,700

2,589 462,930

463,157

2,618 463,383
15,971

1,362

Total Aux.
Consump-tion

000'
kWh

Aux. through
start-up
transformer meter
Readings
Aux. Feed through
Start-up Tr.

MMBtu

Gross Generation
Meter Readings

MBtu/
Tonne

Total Heat Input

Aux. Consumption

Tonnes Tonnes

RFO Average
3
Heating Value

RFO Consumption

RFO Weight in
2
Tank

RFO Specific
1
Gravity @ 0.55%
Water Contents

Auxiliary
Consumption
Meter Readings

Gross Generation

Meters

RFO Specific
Gravity

Time

Tank Temperature

Date

Dip-Tape
Readings

Calculations of Gross and Net Heat Rates and Efficiency Unit 2 TPS Jamshoro

000'
kWh

000'
kWh

000'
kWh

7,227
13

7,228
7,229

13

13

13

7,249

14

14

7,247
7,248

7,239
7,246

14

7,238
7,239

13

7,229
7,237

13

14

14

14
83

Appendix D

D-4

Technical Audit Study of GENCO Power Plants

Total Fuel Input

15,971

MMBtu

2
3

Gross Generation
Gross Heat Rate

1,362
11,727

000 kWh
Btu/kWh

Gross Efficiency

29.1%

Auxiliary Consumption

83

000 kWh

6
7

Sent Out Energy


Net Heat Rate

1,279
12,492

000 kWh
Btu/kWh

Net Efficiency

27.3%

1. Standard RFO specific gravity was adjusted for water contents in RFO. The RFO
present at the TPS Jamshoro had average water contents of 1.1% at the main storage
tanks. It was assessed to reduce by 50% at temperature range of 55-65 C at the
service tank. A water content of 0.55% was therefore assessed for be present at
service tank stage. In future, however, a sample for RFO analysis should be taken
from service tank instead of storage tank to calculate the exact concentration of water
contents.
2. RFO volume converted to weight by using calibration charts of the service tanks.
3. The RFO present at the TPS Jamshoro had average heating value of 40,103
MMBtu/Tonne at water contents of 1.1% at the main storage tanks. The heating
value was also corrected for the water contents of 0.55% at service tank stage which
worked out to be 38,881 MMBtu/Tonne.

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix D

D-5

Technical Audit Study of GENCO Power Plants

17-2-2011 1130 3.870 64.00

0.928

0.928

185.3

1330 1.995 64.00

0.928

0.928

111.5

73.9

39,881

MMBtu

000'
kWh

000'
kWh

Aux. through startup transformer


meter Readings

Aux. Consump-tion

Auxiliary
Consumption Meter
Readings

000'
kWh

000'
kWh

908,168

164,906

2,946

908,418

250 164,929

000'
kWh

Total Aux.
Consump-tion

MBtu/
Tonne

Gross Generation

Gross Generation
Meter Readings

Total Heat Input

RFO Average
3
Heating Value

RFO Consumption

RFO Weight in
2
Tank

RFO Specific
1
Gravity @ 0.55%
Water Contents

Tonne Tonne
s
s

Aux. Feed through


Start-up Tr.

Meter
s

RFO Specific
Gravity

Tank Tempe-rature

Dip-Tape Readings

Time

Date

Calculations of Gross and Net Heat Rates and Efficiency Unit 3 TPS Jamshoro

000'
kWh

000'
kWh

35,505
23

35,507

25

1500

1700

39,881

18-2-2011 1000 4.160 67.00

0.926

0.927

196.4

1200 2.260 67.00

0.926

0.927

121.7

74.7

39,881

1330 3.970 63.00

0.929

0.929

189.4

1530 2.065 63.00

0.929

0.929

114.3

19-2-2011 1000 4.105 57.00

0.932

0.932

1200 2.260 56.00

0.933

1330 4.050 58.00


1530 2.190 58.00
Total

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

910,948

165,170

2,980

911,193

245 165,193

23

35,535

26

911,380

165,210

35,536

75.1

39,881

2,995

911,636

256 165,235

25

35,539

27

195.4

913,950

165,170

35,562

0.933

122.5

72.9

39,881

2,908

914,194

244 165,193

23

35,564

26

0.931

0.932

193.1

914,378

165,499

35,566

0.931

0.932

119.6

73.5

39,881

2,933

914,626

248 165,522

24

35,568

26

370.1

14,761

1,243

35,532

130

Appendix D

D-6

Technical Audit Study of GENCO Power Plants

Total Fuel Input

14,761

MMBtu

2
3

Gross Generation
Gross Heat Rate

1,243
11,879

000 kWh
Btu/kWh

Gross Efficiency

28.7%

Auxiliary Consumption

Sent Out Energy

7
8

130

000 kWh

Net Heat Rate

1,113
13,262

000 kWh
Btu/kWh

Net Efficiency

25.7%

1. Standard RFO specific gravity was adjusted for water contents in RFO. The RFO
present at the TPS Jamshoro had average water contents of 1.1% at the main storage
tanks. It was assessed to reduce by 50% at temperature range of 55-65 C at the
service tank. A water content of 0.55% was therefore assessed for be present at
service tank stage. In future, however, a sample for RFO analysis should be taken
from service tank instead of storage tank to calculate the exact concentration of water
contents.
2. RFO volume converted to weight by using calibration charts of the service tanks.
3. The RFO present at the TPS Jamshoro had average heating value of 40,103
MMBtu/Tonne at water contents of 1.1% at the main storage tanks. The heating
value was also corrected for the water contents of 0.55% at service tank stage which
worked out to be 38,881 MMBtu/Tonne.

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix D

D-7

Technical Audit Study of GENCO Power Plants

Total Heat Input

Gross Generation
Meter Readings

Gross Generation

Auxiliary
Consumption Meter
Readings

Aux. Consump-tion

Aux. through startup transformer


meter Readings

Aux. Feed through


Start-up Tr.

Total Aux.
Consump-tion

MMBtu

000'
kWh

000'
kWh

000' kWh

000'
kWh

000'
kWh

000'
kWh

000'
kWh

980,414

162,654

162,947

295

162,973

26

984,264

162,992

3,299 984,557

293

163,018

26

25

19

63.00

0.929

0.929

203.9

1400

2.200

66.00

0.927

0.927

119.4

84.5

1500

1700

39,881

18-2-2011 1030

4.330

67.00

0.926

0.927

203.1

983,751

1230

2.200

67.00

0.926

0.927

119.3

83.8

39,881

3,340 984,045

1400

4.370

61.00

0.930

0.930

205.4

1600

2.280

64.00

0.928

0.928

122.7

82.7

19-2-2011 1030

4.370

57.00

0.932

0.932

205.9

1230

2.370

60.00

0.930

0.931

126.5

79.4

1430

4.140

59.00

0.931

0.931

196.6

1600

2.650

59.00

0.931

0.931

137.7

58.9

Total

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

RFO Consumption

4.338

RFO Weight in
2
Tank

17-2-2011 1200

RFO Specific
1
Gravity @ 0.55%
Water Contents

RFO Specific
Gravity

Meters

Date

Time

Tank Tempe-rature

MBtu/
Tonne

Dip-Tape Readings

RFO Average
3
Heating Value

Calculations of Gross and Net Heat Rates and Efficiency Unit 4 TPS Jamshoro

Tonnes Tonnes

389.2

39,881

39,881

39,881

39,881

3,370 980,766

987,219

3,165 987,495

987,775

2,348 987,981
15,521

352

277

206
1,423

162,680

163,260

26

26

26

163,285
163,310
163,329

25

19

26

122

Appendix D

D-8

Technical Audit Study of GENCO Power Plants

Total Fuel Input

15,521

2
3

Gross Generation
Gross Heat Rate

Gross Efficiency

1,423
10,909
31.3%

Auxiliary Consumption

6
7

Sent Out Energy


Net Heat Rate

1,301
11,935

Net Efficiency

28.6%

122

MMBtu
000 kWh
Btu/kWh

000 kWh
000 kWh
Btu/kWh

1. Standard RFO specific gravity was adjusted for water contents in RFO. The RFO
present at the TPS Jamshoro had average water contents of 1.1% at the main storage
tanks. It was assessed to reduce by 50% at temperature range of 55-65 C at the
service tank. A water content of 0.55% was therefore assessed for be present at
service tank stage. In future, however, a sample for RFO analysis should be taken
from service tank instead of storage tank to calculate the exact concentration of water
contents.
2. RFO volume converted to weight by using calibration charts of the service tanks.
3. The RFO present at the TPS Jamshoro had average heating value of 40,103
MMBtu/Tonne at water contents of 1.1% at the main storage tanks. The heating
value was also corrected for the water contents of 0.55% at service tank stage which
worked out to be 38,881 MMBtu/Tonne.

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix D

D-9

Technical Audit Study of GENCO Power Plants

Exhibit D.2: Calculation of Gross and Net Heat Rate and EfficiencyTPS Guddu
CCP Block 2-A: GT 7
Date

1000

MCF
801,690

MWh
83,904

Auxiliary
Consumption
Reading
5,503

2.

1100

803,240

84,000

5,504

3.

1300

806,290

84,189

5,505

4.

1500

809,210

84,370

5,507

1700

811,840

84,530

5,508

900

834,350

85,935

5,518

7.

1100

837,360

86,122

5,519

8.

1300

9.

1600

844,750

86,583

5,522

10.

1700

846,110

86,670

5,523

1.

Time

30-12-2010

5.
6.

11.

31-12-2010

01-01-2011

Gas Flow

Gross Generation

900

869,830

88,162

5,533

12.

1100

872,800

88,350

5,534

13.

1300

875,850

88,542

5,535

14.
15.
16.

02-01-2011

17.
18.

88,822

5,537

900

905,150

90,435

5,547

1100

909,170

90,623

5,548

1300

20.

912,220

1600

916,820

Initial Gas Meters Reading

801,690

MCF

2.

Final Gas Reading

916,820

MCF

3.

Difference

115,130

MCF

4.

Gas Calorific Value

802.11

Btu/Scf

5.

Total Fuel Input

92,347

MMBtu

6.

Intial Gross Generation Reading

83,904

MWh

7.

Final Gross Generation Reading

91,096

MWh

8.

Difference

7,192

MWh

9.

Gross Generation

7,192,000

kWh

10.

Gross Heat Rate

12,840

11.

Gross Efficiency

27%

12.

Intial Auxiliary Consumprion Reading

5,503

13.

Final Auxiliary Consumprion Reading

5,552

14.

Difference

15.

Mutliplying Factor

16.

Auxiliary Consumption

17.

Sent Out Energy

18.

Net Heat Rate

12,896

19.

Net Efficiency

26%

R1V02TAG: 04/23/11

90,811

1.

Hagler Bailly Pakistan

880,430

19.

1600

5,550

91,096

5,552

Btu/kWh

49
640
31,360

kWh

7,160,640

kWh
Btu/kWh

Appendix D

D-10

Technical Audit Study of GENCO Power Plants

CCP Block 2-A: GT 8


Date

Time

Gas Flow

Gross Generation

Auxiliary
Consumption
Reading
6,559

1000

MCF
891,530

MWh
41,323

2.

1100

892,980

41,408

6,560

3.

1300

895,890

41,581

6,561

4.

1500

898,780

41,751

6,562

5.

1700

901,580

41,922

6,563

900

924,220

43,286

6,572

7.

1100

927,120

43,460

6,573

8.

1300

9.

1600

934,270

43,887

6,575

10.

1700

935,630

43,973

6,576

900

958,290

45,334

6,585

12.

1100

961,070

45,502

6,586

13.

1300

963,960

45,672

6,587

14.

15.

1600

968,300

45,928

6,589

900

992,330

47,358

6,598

17.

1100

995,220

47,529

6,609

18.

1300

998,090

47,699

6,600

19.

20.

1600

1.

6.

11.

16.

30-12-2010

31-12-2010

01-01-2011

02-01-2011

1.

Initial Gas Meters Reading

2.

Final Gas Reading

891,530

MCF

1,002,440

MCF

3.

Difference

4.

Gas Calorific Value

110,910
802.11

MCF
Btu/Scf

5.

Total Fuel Input

88,962

MMBtu

6.

Intial Gross Generation Reading

41,323

MWh

7.

Final Gross Generation Reading

47,956

MWh

8.

Difference

6,633

MWh

6,633,000

kWh

9.

Gross Generation
Gross Heat Rate

13,412

11.

Gross Efficiency

25%

12.

Intial Auxiliary Consumprion Reading

6,559

13.

Final Auxiliary Consumprion Reading

6,601

14.

Difference

15.

Mutliplying Factor

16.

Auxiliary Consumption

17.

Sent Out Energy

18.

Net Heat Rate

13,467

19.

Net Efficiency

25%

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

1,002,440

10.

47,956

6,601

Btu/kWh

42
640
26,880

kWh

6,606,120

kWh
Btu/kWh

Appendix D

D-11

Technical Audit Study of GENCO Power Plants

CCP Block 2-A: ST5


Date

1.

Time

30-12-2010

Gas Flow
MCF

1000

Gross
Generation
MWh
15,623

Auxiliary
Consumption
Reading
4,157

2.

1100

15,694

4,157

3.

1300

15,828

4,158

4.

1500

15,975

4,158

5.

1700

16,104

4,159

900

17,109

4,160

7.

1100

17,243

4,161

8.

1300

9.

1600

17,578

4,162

10.

1700

17,650

4,162

900

18,690

4,164

12.

1100

18,821

4,164

13.

1300

18,955

4,165

6.

11.

31-12-2010

01-1-2011

14.

1600

19,159

4,165

900

20,276

4,167

17.

1100

29,400

4,167

18.

1300

20,533

4,168

15.
16.

02-1-2011

19.
20.

1600

1.

Initial Gas Meters Reading

MCF

2.

Final Gas Reading

MCF

3.

Difference

MCF

4.

Gas Calorific Value

5.

Total Fuel Input

6.

Intial Gross Generation Reading

15,623

MWh

7.

Final Gross Generation Reading

20,739

MWh

8.

Difference

5,116

MWh

9.

Gross Generation

5,116,000

kWh

10.

Gross Heat Rate

11.

Gross Efficiency

12.

Intial Auxiliary Consumprion Reading

4,157

13.

Final Auxiliary Consumprion Reading

4,168

14.

Difference

15.

Mutliplying Factor

16.

Auxiliary Consumption

17.

Sent Out Energy

18.

Net Heat Rate

19.

Net Efficiency

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

20,739

4,168

Btu/Scf
-

MMBtu

Btu/kWh

11
10,000
110,000

kWh

5,006,000

kWh
Btu/kWh

Appendix D

D-12

Technical Audit Study of GENCO Power Plants

CCP Block 2-A


1.

Total Fuel Input

2.

Gross Generation

3.

Gross Heat Rate

4.

Gross Efficiency

5.

Auxiliary Consumption

6.

Sent Out Energy

7.

Net Heat Rate

8.

Net Efficiency

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

181,309 MMBtu
18,941,000 kWh
9,572 Btu/kWh
36%
168,240 kWh
18,772,760 kWh
9,658 Btu/kWh
35%

Appendix D

D-13

Technical Audit Study of GENCO Power Plants

CCP Block 2-A: GT 11


Date

1100

MCF

256,005

MWh

952,690

Auxiliary
Consumption
Reading

729,322

3.

1300

256,713

952,855

730,200

4.

1.
2.

03-01-2011

Time

5.

Gas Flow

Gross Generation

1600

257,770

953,102

731,538

900
1100

263,804
264,533

954,502
954,672

738,999
739,908

8.

1300

265,225

954,832

740,757

9.

10.

1600

266,288

955,079

742,077

900
1100

272,323
273,034

956,481
956,646

749,434
750,322

956,811

751,225

6.
7.

11.
12.

04-01-2011

05-01-2011

13.

1300

14.

15.

1600

274,805

957,058

752,576

900
1100
1300

280,832
281,542
282,214

958,458
958,623
958,789

760,040
760,877
761,706

16.
17.
18.

06-01-2011

19.

20.

1600

273,743

283,328

1.

Initial Gas Meters Reading

256,005

HCM

2.

Final Gas Reading

283,328

HCM

3.

Difference

27,323

HCM

4.

Unit conversion

5.

Gas Consumption

96,490

MCF

6.

Gas Calorific Value

802.11

Btu/Scf

7.

Total Fuel Input

77,396

MMBtu

8.

Intial Gross Generation Reading

952,690

MWH

9.

Final Gross Generation Reading

959,036

MWH

10.

Difference

6,346

MWH

11.

Gross Generation

12.

Gross Heat Rate

12,196

13.

Gross Efficiency

28%

14.

Intial Auxiliary Consumprion Reading

729,322

15.

Final Auxiliary Consumprion Reading

763,007

16.

Auxiliary Consumption

17.

Sent Out Energy

18.

Net Heat Rate

12,261

19.

Net Efficiency

28%

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

3.53

6,346,000

959,036

763,007

HCM to MCF

kWh
Btu/kWh

33,685

kWh

6,312,315

kWh
Btu/kWh

Appendix D

D-14

Technical Audit Study of GENCO Power Plants

CCP Block 2-A: GT 12


Date

1.

03-01-2011

Time

Gas Flow

Gross Generation

MCF

MWh

Auxiliary
Consumption
Reading

2.

1100

873,114

476,780

326,176

3.

1300

873,818

476,944

326,672

4.

5.

1600

874,899

477,193

327,448

900

880,922

478,579

331,606

7.

1100

881,632

478,743

332,118

8.

1300

882,360

478,910

332,639

9.

10.

1600

883,437

479,158

333,401

900

889,480

480,550

337,454

12.

1100

890,178

480,711

337,939

13.

1300

890,901

480,878

338,454

14.

15.

1600

891,941

481,119

339,193

900

897,970

482,515

343,244

17.

1100

898,684

482,678

343,689

18.

1300

899,413

482,845

344,145

19.

20.

1600

6.

11.

16.

04-01-2011

05-01-2011

06-01-2011

900,414

1.

Initial Gas Meters Reading

2.

Final Gas Reading

3.

Difference

4.

Unit conversion

5.

Gas Consumption

96,409

MCF

6.

Gas Calorific Value

802.11

Btu/Scf

7.

Total Fuel Input

77,331

MMBtu

8.

Intial Gross Generation Reading

476,780

MWH

9.

Final Gross Generation Reading

483,100

MWH

10.

Difference

6,320

MWH

11.

Gross Generation

12.

Gross Heat Rate

12,236

13.

Gross Efficiency

28%

14.

Intial Auxiliary Consumprion Reading

326,176

15.

Final Auxiliary Consumprion Reading

344,877

16.

Auxiliary Consumption

17.

Sent Out Energy

18.

Net Heat Rate

12,272

19.

Net Efficiency

28%

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

873,114

HCM

900,414

HCM

27,300.00

HCM

3.53

6,320,000

483,100

344,877

HCM to MCF

kWh
Btu/kWh

18,701

kWh

6,301,299

kWh
Btu/kWh

Appendix D

D-15

Technical Audit Study of GENCO Power Plants

CCP Block 2-A: ST13


Date

1.
2.

03-01-2011

Time

Gas Flow
MCF

1100

Gross Generation
MWh

675,538

Auxiliary
Consumption
Reading

344,914

3.

1300

675,703

4.

5.

1600

675,956

344,931

900
1100

677,382
677,551

344,990
344,997

8.

1300

677,721

345,004

9.

10.

1600

677,975

345,015

900
1100

679,402
679,571

345,074
345,081

13.

1300

679,739

345,088

14.

15.

1600

679,989

345,099

900
1100

681,409
681,583

345,157
345,164

18.

1300

681,758

345,171

19.

20.

1600

682,020

6.
7.

04-01-2011

11.
12.

16.
17.

05-10-2011

06-01-2011

1.

Initial Gas Meters Reading

MCF

2.

Final Gas Reading

MCF

3.

Difference

MCF

4.

Gas Calorific Value

Btu/Scf

5.

Total Fuel Input

MMBtu

6.

Intial Gross Generation Reading

675,538

MWH

7.

Final Gross Generation Reading

682,020

MWH

8.

Difference

6,482

MWH

9.

Gross Generation

6,482,000

kWh

10. Gross Heat Rate

Btu/kWh

11. Gross Efficiency

0%

12. Intial Auxiliary Consumprion Reading

344,914

MWh

13. Final Auxiliary Consumprion Reading

345,181

MWh

267

MWh

14. Difference
15. Mutliplying Factor
16. Auxiliary Consumption

kWh

6,215,000

kWh

18. Net Heat Rate

Btu/kWh

19. Net Efficiency

0%

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

345,181

1,000
267,000

17. Sent Out Energy

344,920

Appendix D

D-16

Technical Audit Study of GENCO Power Plants

CCP Block 1
1.

Total Fuel Input

2.

Gross Generation

3.

Gross Heat Rate

4.

Gross Efficiency

5.

Auxiliary Consumption

6.

Sent Out Energy

7.

Net Heat Rate

8.

Net Efficiency

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

154,727 MMBtu
19,148,000 kWh
8,081 Btu/kWh
42%
319,386 kWh
18,828,614 kWh
8,218 Btu/kWh
42%

Appendix D

D-17

Technical Audit Study of GENCO Power Plants

Exhibit D.3: Calculation of Gross and Net Heat Rate and Efficiency TPS Muzaffargarh
Calculations of Gross and Net Heat Rates and Efficiency Unit 2 TPS Muzaffargarh

9-01-2011

1015

12.888

81.00

0.918

14,794

1415

12.608

80.00

0.919

14,482

1530

12.514

80.00

0.919

14,374

1730

12.368

80.00

0.919

14,206

11.217

81.00

0.918

12,876

1345

10.947

80.00

0.919

12,574

1500

10.861

80.00

0.919

12,475

1900

10.584

79.00

0.919

12,165

11-01-2011 1045

9.507

82.00

0.918

10,906

1445

9.232

80.00

0.919

10,604

1500

9.214

80.00

0.919

10,583

1900

8.932

80.00

0.919

10,260

10-01-2011 945

Total

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

RFO Average
3
Heating Value

Total Heat Input


for Unit 2

Gross
Generation
Meter Readings

Gross
Generation

Total Auxiliary
Consumption
from Table B

Tonnes

Total RFO
Consump-tion
for Unit 2

Tonnes

Proportion of
RFO attributed
2
to Unit 2

Total RFO
Consump-tion
for Unit 2 and 3

Co

RFO Weight in
1
Tank

Meters

RFO Specific
Gravity

Time

Tank Temperature

Date

Dip-Tape
Readings

Table A

Tonnes

MBtu/ Tonne

MMBtu

000' kWh

kWh

kWh

5,277,770
312.4

55%

171.6

39,278

6,740

5,278,445

675,000

41,976

340,000

21,780

680,000

42,240

672,000

42,134

668,000

47,784

630,000

50,160

3,665,000

246,074

5,278,655
167.7

55%

92.5

39,278

3,634

5,278,995
5,281,765

302.1

55%

166.3

39,278

6,534

5,282,445
5,282,660

310.6

56%

172.6

39,278

6,779

5,283,332
5,286,002

302.3

54%

164.5

39,278

6,460

5,286,670
5,286,710

323.9
1,719.1

53%

171.2
938.7

39,278

6,724
36,870

5,287,340

Appendix D

D-18

Technical Audit Study of GENCO Power Plants

11-01-2011

8,993

1415

8,994

1530

8,994

1730

8,994

945

8,998

1345

8,999

1500

8,999

1900

9,000

1045

9,003

1445

9,004

1500

9,004

1900

9,005

22,704

11,088

6,565

0.68

17,952

22,440

6,566

0.35

9,240

6,570

21,938

6,570

0.70

18,480

21,648

0.71

18,744

21,384

1,320

41,976

0.11

2,904

1,452

21,780

0.10

2,640

1,320

42,240

0.11

2,904

1,452

42,134

0.48

12,672

6,336

47,784

0.58

15,312

7,656

50,160

Difference

Aux. through
start-up
transformer meter
Readings

2,640

6,574

6,575

3,182

3,182

3,182
5,142

0.75

19,800

6,574
0.81

0.10

3,182

6,574
0.82

3,182

3,181

6,570
0.83

kWh

3,182

6,569
0.85

kWh

3,181

6,566
0.42

kWh

kWh

6,565
0.86

Total Aux.
Consump-tion

10-01-2011

1015

Aux. Feed through


Start-up Tr. For
Unit 2

9-01-2011

Aux. Feed through


Start-up Tr.

kWh

Aux. Consumption Side B

Aux. Consumption Side B4

Auxiliary
Consumption
Meter B Readings

Aux. Consumption Side A4

Time

Aux. ConsumptionSide A

Date

Auxiliary
Consumption
Meter A Readings

Table B

5,142
5,142

0.80

21,120

5,143

Total

246,074

Hagler Bailly Pakistan

Appendix D

R1V02TAG: 04/23/11

D-19

Technical Audit Study of GENCO Power Plants

Total Fuel Input

36,870

2
3

Gross Generation
Gross Heat Rate

3,665,000
10,060

Gross Efficiency

33.9%

Auxiliary Consumption

6
7

Sent Out Energy


Net Heat Rate

Net Efficiency

246,074
3,418,926
10,784

MMBtu
kWh
Btu/kWh
kWh
kWh
Btu/kWh

31.6%

1. RFO volume converted to weight by using calibration charts of the storage tanks
using the conversion of 1,250 Tonnes/meter.
2. Unit 1-3 are supplied RFO from a common storage tank. The total supply from the
storage tank was divided on the basis of proportion of the consumption recorded by
RFO flow meters installed at each of these units. Unit 1 was not operational so total
consumption was divided between Unit 2 and 3 accordingly
3. The RFO present at the TPS Muzaffargarh had average heating value of 39,278
MBtu/Tonne at the main storage tank feeding Unit 2 and 3.
4. Auxiliary consumption of Sides A and B and start-up Transformer converted to kWh
by using the multiplying factor of 26,400 for Auxiliary Meters. The start-up
transformer was shared between Unit 2 and 3 so its total supply was divided equally
between Units 2 and 3.

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix D

D-20

Technical Audit Study of GENCO Power Plants

Calculations of Gross and Net Heat Rates and Efficiency Unit 3 TPS Muzaffargarh

10-01-2011

11-01-2011

12.608

80.00

0.919

14,482

1530

12.514

80.00

0.919

14,374

1730

12.368

80.00

0.919

14,206

945

11.217

81.00

0.918

12,876

1345

10.947

80.00

0.919

12,574

1500

10.861

80.00

0.919

12,475

1900

10.584

79.00

0.919

12,165

1045

9.507

82.00

0.918

10,906

1445

9.232

80.00

0.919

10,604

1500

9.214

80.00

0.919

10,583

1900

8.932

80.00

0.919

10,260

Hagler Bailly Pakistan

Total Auxiliary
Consumption
from Table B

1415

Gross
Generation

14,794

Gross
Generation
Meter
Readings

0.918

Total Heat
Input for Unit 2

81.00

RFO Average
4
Heating Value

12.888

Total RFO
Consump-tion
for Unit 2

1015

Proportion of
RFO attributed
3
to Unit 2

Total RFO
Consump-tion
for Unit 2 and 3

Co

RFO Specific
Gravity

Meters

Time

Total

R1V02TAG: 04/23/11

Tonnes

Tank Temperature

9-01-2011

Tonnes

Dip-Tape
Readings

Date

RFO Weight in
2
Tank

Table A

Tonnes

MBtu/ Tonne

MMBtu

000' kWh

kWh

kWh

6,055,416
312.4

45%

140.8

39,278

5,532

6,055,974

558,000

41,712

280,000

21,648

560,000

40,656

570,000

40,841

555,000

46,728

560,000

45,936

3,083,000

237,521

6,056,155
167.7

45%

75.2

39,278

2,953

6,056,435
6,058,735

302.1

45%

135.8

39,278

5,334

6,059,295
6,059,465

310.6

44%

138.0

39,278

5,422

6,060,035
6,062,240

302.3

46%

137.9

39,278

5,415

6,062,795
6,062,830

323.9
1,719.1

47%

152.7
780.5

39,278

5,999
30,655

6,063,390

Appendix D

D-21

Technical Audit Study of GENCO Power Plants

11-01-2011

9,815

1415

9,816

1530

9,816

1730

9,816

945

9,819

1345

9,820

1500

9,820

1900

9,821

1045

9,824

1445

9,825

1500

9,825

1900

9,826

Total

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

19,800

10,164

9,577

0.78

20,592

19,536

9,578

0.38

10,032

9,582

19,325

9,583

0.75

19,800

19,272

0.76

20,064

19,272

1,320

41,712

0.11

2,904

1,452

21,648

0.10

2,640

1,320

40,656

0.11

2,904

1,452

40,841

0.48

12,672

6,336

46,728

0.58

15,312

7,656

45,936

Difference

Aux. through
start-up
transformer
meter Readings

2,640

9,586

9,587

3,182

3,182

3,182
5,142

0.80

21,120

9,587
0.73

0.10

3,182

9,586
0.73

3,182

3,181

9,582
0.73

kWh

3,182

9,581
0.74

kWh

3,181

9,577
0.39

kWh

kWh

9,576
0.75

Total Aux.
Consump-tion

10-01-2011

1015

Aux. Feed
through Start-up
Tr. For Unit 2

9-01-2011

Aux. Feed
through Start-up
Tr.

kWh

Aux. Consumption Side B

Aux. Consumption Side B4

Auxiliary
Consumption
Meter B
Readings

Aux. Consumption Side A5

Time

Aux. Consumption Side A

Date

Auxiliary
Consumption
Meter A
Readings

Table B

5,142
5,142

0.72

19,008

5,143

237,521

Appendix D

D-22

Technical Audit Study of GENCO Power Plants

Total Fuel Input

30,655

2
3

Gross Generation
Gross Heat Rate

3,083,000
9,943

Gross Efficiency

34.3%

Auxiliary Consumption

6
7

Sent Out Energy


Net Heat Rate

Net Efficiency

237,521
2,845,479
10,773

MMBtu
kWh
Btu/kWh
kWh
kWh
Btu/kWh

31.7%

1. RFO volume converted to weight by using calibration charts of the storage tanks
using the conversion of 1,250 Tonnes/meter.
2. Unit 1-3 are supplied RFO from common storage tank. The total supply from storage
tank was divided on the basis of proportion of the consumption recorded by RFO
flow meters installed at each of these units. Unit 1 was not operational so total
consumption was divided between Unit 2 and 3 accordingly
3. The RFO present at the TPS Muzaffargarh had average heating value of 39,278
MBtu/Tonne at the main storage tank feeding Unit 2 and 3.
4. Auxiliary consumption of Sides A and B and start-up Transformer converted to kWh
by using the multiplying factor of 26,400 for Auxiliary Meters. The start-up
transformer was shared between Unit 2 and 3 so its total supply was divided equally
between Units 2 and 3.

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix D

D-23

Technical Audit Study of GENCO Power Plants

Auxiliary
Consumption
Meter Readings

Gross Generation

Gross Generation

Gross Generation
Meter Readings

499,933

51,219

0.936

0.937

13,749

39,278

500,079

51,293

50.00

0.936

0.937

13,739

500,087

51,297

10.455

50.00

0.936

0.937

13,551

369.4

39,278

14,509

500,234

301.0

1,444,800

51,373

154.0

154,000

900

10.025

51.00

0.935

0.936

12,986

500,696

51,610

1230

9.888

52.00

0.935

0.936

12,801

39,278

500,843

51,683

1245

9.877

52.00

0.935

0.936

12,786

500,853

51,688

1645

9.717

52.00

0.935

0.936

12,579

406.6

39,278

15,972

501,022

326.0

1,564,800

51,775

165.0

165,000

910

9.060

53.00

0.934

0.935

11,722

501,707

52,126

1310

8.900

53.00

0.934

0.935

11,515

39,278

501,877

52,209

1520

8.805

54.00

0.934

0.934

11,385

501,968

52,254

1850

8.672

54.00

0.934

0.934

11,213

508.8

39,278

19,986

502,118

411.0

1,972,800

52,328

202.0

202,000

0.936

1830

10.608

50.00

1840

10.600

2210

Total

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

RFO Specific
Gravity

50.00

1,284.9

MBtu/
Tonne

MMBtu

50,468

kWh

Total Aux.
Consump-tion

10.740

Time

Aux.
Consumption

5-01-2011 1500

7-01-2011

Total Heat Input

RFO
Consumption

13,921

Co

6-01-2011

RFO Average
3
Heating Value

RFO Weight in
2
Tank

0.937

Tank Temperature

Tonnes

Dip-Tape
Readings

Tonnes

Meters

Date

RFO Specific
1
Gravity @ 0.55%
Water Contents

Calculations of Gross and Net Heat Rates and Efficiency Unit 4 TPS Muzaffargarh

kWh

4,982,400

521,000

Appendix D

D-24

Technical Audit Study of GENCO Power Plants

Total Fuel Input

2
3

Gross Generation
Gross Heat Rate

Gross Efficiency

Auxiliary Consumption

6
7

Sent Out Energy


Net Heat Rate

Net Efficiency

50,468
4,982,400
10,129

MMBtu
kWh
Btu/kWh

33.7%
521,000
4,461,400
11,312

kWh
kWh
Btu/kWh

30.2%

1. RFO volume converted to weight by using calibration charts of the storage tanks
using the conversion of 1,384.74 Tonnes/meter.
2. The RFO present at the TPS Muzaffargarh had average heating value of 39,278
MBtu/Tonne at the main storage tank feeding Unit 4.
3. Auxiliary consumption converted to kWh by using the multiplying factor of 1,000 for
Auxiliary Meters.

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix D

D-25

Technical Audit Study of GENCO Power Plants

Calculations of Gross and Net Heat Rates and Efficiency Unit 5 TPS Muzaffargarh

4-01-2011

RFO Average
4
Heating Value

Total Heat Input


for Unit 2

Tonnes

MBtu/ Tonne

MMBtu

1230

5.345

38.00

0.943

0.943

197

1530

3.050

41.00

0.941

0.942

112

1630

5.135

38.00

0.943

0.943

189

1930

3.105

39.00

0.942

0.943

114

1030

4.990

36.00

0.944

0.945

184

1400

2.985

36.00

0.944

0.945

110

1530

5.545

36.00

0.944

0.945

204

1900

3.100

36.00

0.944

0.945

114

915

5.415

35.00

0.945

0.945

200

1245

2.925

36.00

0.944

0.945

108

1605

5.540

37.00

0.943

0.944

204

1935

3.130

37.00

0.943

0.944

115

Total

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

kWh

kWh

0.8

287,280

35,151

0.7

275,940

35,151

0.6

245,700

30,615

0.8

317,520

41,010

0.8

317,520

39,593

0.8

313,740

40,065

1,757,700

221,585

Difference

Total RFO
Consump-tion for
Unit 2

Tonnes

Gross Generation
Meter Readings

RFO Weight in
2
Tank

RFO Specific
Gravity @ 1.08%
Water Contents

RFO Specific
Gravity

Co

Total Aux.
Consump-tion
from Table B

3-01-2011

Meters

Gross Generation

2-01-2011

Time

Tank Temperature

Date

Dip-Tape
Readings

Table A

5,827
84.6

39,707

3,361

5,827
5,828

74.8

39,707

2,969

5,828
5,832

73.9

39,707

2,933

5,833
5,833

90.1

39,707

3,577

5,834
5,838

91.8

39,707

3,647

5,838
5,839

88.7
503.9

39,707

3,523
20,010

5,840

Appendix D

D-26

Technical Audit Study of GENCO Power Plants

Aux. Feed
through Start-up
Tr.

Aux. Feed
through Start-up
Tr. For Unit 5

Total Aux.
Consump-tion

kWh

kWh

kWh

0.01

2,263

1,131

35,151

0.01

2,263

1,131

35,151

0.01

2,640

1,320

30,615

0.01

2,640

1,320

41,010

0.01

2,640

1,320

39,593

0.01

2,640

1,320

40,065

Difference

Aux. through
start-up
transformer meter
Readings

Aux.
5
Consumption

Aux.
Consumption

Auxiliary
Consumption
Meter Readings

Table B

kWh

19,929

1,314

19,929

0.72

34,020

19,930

1,314
1,314

19,930

0.72

34,020

19,934

1,314
1,314

19,935

0.62

29,295

19,335

1,314
1,314

19,336

0.84

39,690

19,940

1,314
1,314

19,940

0.81

38,273

19,941

1,314
1,314

19,942

0.82

38,745

1,314

Total

221,585

Total Fuel Input

20,010

MMBtu

2
3

Gross Generation
Gross Heat Rate

1,757,700
11,384

kWh
Btu/kWh

Gross Efficiency

30.0%

Auxiliary Consumption

6
7

Sent Out Energy


Net Heat Rate

Net Efficiency

221,585

kWh

1,536,115
13,026

kWh
Btu/kWh

26.2%

1. RFO volume converted to weight by using calibration charts of the service tanks
using the conversion of 39 Tonnes/meter.
2. The RFO present at the TPS Muzaffargarh had an average heating value of 39,278
MBtu/Tonne at the main storage tank feeding Unit 2 and 3.
3. Auxiliary consumption was converted to kWh by using multiplying factor of 47,250
for Auxiliary Meters. In addition, reading of start-up Transformer was converted to
kWh by using the multiplying factor of 264,000 for transformer Meters. The start-up
transformer was shared between Unit 5 and 6 so its total supply was divided equally
between Units 5 and 6.

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix D

D-27

Technical Audit Study of GENCO Power Plants

Calculations of Gross and Net Heat Rates and Efficiency Unit 6 TPS Muzaffargarh

RFO Average
4
Heating Value

Total Heat Input


for Unit 2

40.00

0.942

0.942

173

1405

2.730

41.00

0.941

0.942

100

1540

4.710

39.00

0.942

0.943

173

1840

2.955

40.00

0.942

0.942

109

1045

4.435

38.00

0.943

0.943

163

1400

2.445

40.00

0.942

0.942

90

1600

4.790

38.00

0.943

0.943

176

1930

2.705

38.00

0.943

0.943

100

900

4.840

37.00

0.943

0.944

178

1230

2.795

39.00

0.942

0.943

103

1500

4.535

37.00

0.943

0.944

167

1830

2.455

39.00

0.942

0.943

90

Total

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

kWh

kWh

0.6

226,800

33,450

0.5

204,120

28,461

0.6

238,140

32,505

0.7

253,260

34,395

0.6

241,920

33,922

0.7

245,700

34,395

1,409,940

197,128

Difference

Total RFO
Consump-tion for
Unit 2

4.710

RFO Specific
Gravity

1035

Gross Generation
Meter Readings

RFO Weight in
2
Tank

MMBtu

Co

Total Aux.
Consump-tion
Table B

4-01-2011

MBtu/ Tonne

Meters

Time

Gross Generation

3-01-2011

Tonnes

Tank Temperature

2-01-2011

Tonnes

Dip-Tape
Readings

Date

RFO Specific
Gravity @ 1.08%
Water Contents

Table A

3,650
72.8

39,707

2,892

3,651
3,651

64.6

39,707

2,565

3,651
3,654

73.3

39,707

2,912

3,655
3,655

76.7

39,707

3,046

3,656
3,659

75.4

39,707

2,995

3,659
3,660

76.7
439.6

39,707

3,045
17,455

3,661

Appendix D

D-28

Aux. Feed
through Start-up
Tr.

Aux. Feed
through Start-up
Tr. For Unit 5

Total Aux.
Consump-tion

kWh

kWh

kWh

0.01

2,640

1,320

33,450

0.01

2,112

1,056

28,461

0.01

2,640

1,320

32,505

0.01

2,640

1,320

34,395

0.01

2,640

1,320

33,922

0.01

2,640

1,320

34,395

Difference

Aux. through
start-up
transformer
meter Readings

Aux.
5
Consumption

Aux.
Consumption

Auxiliary
Consumption
Meter Readings

Technical Audit Study of GENCO Power Plants

kWh

17,297
17,298

1,314
0.68

32,130

17,298
17,299

1,314
0.58

27,405

17,302
17,302

0.66

31,185

0.70

33,075

1,314
1,314

0.69

32,602

17,307
17,308

1,314
1,314

17,306
17,307

1,314
1,314

17,303
17,304

1,314

1,314
1,314

0.70

33,075

1,314

Total

197,128

Total Fuel Input

17,455

MMBtu

2
3

Gross Generation
Gross Heat Rate

1,409,940
12,380

kWh
Btu/kWh

Gross Efficiency

27.6%

Auxiliary Consumption

6
7

Sent Out Energy


Net Heat Rate

Net Efficiency

197,128

kWh

1,212,812
14,392

kWh
Btu/kWh

23.7%

1. RFO volume converted to weight by using calibration charts of the service tanks
using the conversion of 39 Tonnes/meter.
2. The RFO present at the TPS Muzaffargarh had average heating value of 39,278
MBtu/Tonne at the main storage tank feeding Unit 2 and 3.
3. Auxiliary consumption was converted to kWh by using multiplying factor of 47,250
for Auxiliary Meters. In addition reading of start-up Transformer was converted to
kWh by using the multiplying factor of 264,000 for transformer Meters. The start-up
transformer was shared between Unit 5 and 6 so its total supply was divided equally
between Units 5 and 6.

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix D

D-29

Technical Audit Study of GENCO Power Plants

Appendix E: Power Plant Availability


See following pages.

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-1

Technical Audit Study of GENCO Power Plants

Exhibit E.1: Power Plant Availability-TPS Jamshoro


Steam Unit 1
Installed Capacity
Derated Capacity
Month

250 MW
187 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schedld.
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availablity
(Hrs.)

Total Hours
of Month

Availability
Factor
(Time-base)

Jul, 09

135

100

85

52

739

744

99%

Aug, 09

150

125

67

46

152

592

744

80%

Sep, 09

165

125

77

57

91

629

720

87%

Oct, 09

165

63

78

58

38

706

744

95%

Nov, 09

150

125

58

39

216

504

720

70%

Dec, 09

744

744

0%

Jan, 10

200

63

12

11

632

112

744

15%

Feb, 10

200

125

85

77

29

643

672

96%

Mar, 10

180

140

80

65

114

630

744

85%

Apr, 10

187

63

88

75

40

680

720

94%

May, 10

180

125

90

74

744

744

100%

Jun, 10

187

125

51

43

266

454

720

63%

Jul, 10

180

63

84

69

63

681

744

92%

Aug, 10

180

63

87

71

744

744

100%

Sep, 10

160

70

77

56

28

692

720

96%

Oct, 10

180

65

56

46

83

98

564

744

76%

Nov, 10

150

63

34

23

370

84

266

720

37%

Total FY2010

200

63

64

50

1,592

737

6,431

8,760

73%

Total FY2011 YTD*

180

63

68

53

481

245

2,946

3,672

80%

* Data available till November 2010


Hagler Bailly Pakistan
R1V02TAG: 04/23/11

Appendix E

E-2

Technical Audit Study of GENCO Power Plants

Steam Unit 2
Installed Capacity
Derated Capacity
Month

200 MW
160 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor (%)

Schedld.
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availablity
(Hrs.)

Total Hours
of Month

Availability
Factor
(Time-base)

Jul, 09

180

100

79

81

116

628

744

84%

Aug, 09

180

100

62

66

180

564

744

76%

Sep, 09

165

90

84

81

716

720

99%

Oct, 09

170

100

75

75

105

639

744

86%

Nov, 09

175

100

61

63

208

512

720

71%

Dec, 09

170

140

82

82

61

683

744

92%

Jan, 10

170

120

80

80

10

734

744

99%

Feb, 10

120

120

69

69

108

564

672

84%

Mar, 10

170

100

76

76

78

666

744

90%

Apr, 10

165

90

88

85

720

720

100%

May, 10

165

90

64

63

140

599

744

81%

Jun, 10

160

100

85

80

15

705

720

98%

Jul, 10

140

100

94

77

744

744

100%

Aug, 10

140

100

86

71

21

723

744

97%

Sep, 10

130

100

60

46

134

586

720

81%

Oct, 10

110

110

27

17

527

217

744

29%

Nov, 10

170

100

31

31

279

162

279

720

39%

Total FY2010

180

90

75

75

140

889

7,731

8,760

88%

Total FY2011 YTD*

170

100

60

49

806

318

2,549

3,672

69%

* Data available till November 2010


Hagler Bailly Pakistan
R1V02TAG: 04/23/11

Appendix E

E-3

Technical Audit Study of GENCO Power Plants

Steam Unit 3
Installed Capacity
Derated Capacity
Month

200 MW
160 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor (%)

Schedld.
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availablity
(Hrs.)

Total Hours
of Month

Availability
Factor
(Time-base)

Jul, 09

130

100

72

55

142

602

744

81%

Aug, 09

135

120

90

71

744

744

100%

Sep, 09

140

100

90

74

720

720

100%

Oct, 09

130

100

66

50

216

528

744

71%

Nov, 09

175

100

38

39

398

322

720

45%

Dec, 09

180

100

68

72

164

580

744

78%

Jan, 10

170

100

74

74

744

744

100%

Feb, 10

170

100

63

63

157

48

467

672

70%

Mar, 10

170

100

85

85

25

719

744

97%

Apr, 10

160

100

91

86

720

720

100%

May, 10

160

100

65

62

193

551

744

74%

Jun, 10

170

150

94

94

720

720

100%

Jul, 10

170

100

91

91

744

744

100%

Aug, 10

170

100

48

48

320

25

399

744

54%

Sep, 10

170

100

58

58

156

564

720

78%

Oct, 10

170

100

47

47

316

428

744

57%

Nov, 10

544

176

720

0%

Total FY2010

180

100

75

69

770

572

7,417

8,760

85%

Total FY2011 YTD*

170

49

49

864

673

2,134

3,672

58%

* Data available till November 2010


Hagler Bailly Pakistan
R1V02TAG: 04/23/11

Appendix E

E-4

Technical Audit Study of GENCO Power Plants

Steam Unit 4
Installed Capacity
Derated Capacity
Month

200 MW
160 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor (%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

165

130

86

83

24

720

744

97%

Aug, 09

160

140

63

59

226

518

744

70%

Sep, 09

150

100

84

74

73

647

720

90%

Oct, 09

170

100

78

78

86

658

744

88%

Nov, 09

175

100

94

97

720

720

100%

Dec, 09

175

100

94

97

744

744

100%

Jan, 10

170

100

86

86

58

686

744

92%

Feb, 10

170

100

62

62

141

531

672

79%

Mar, 10

170

100

91

91

744

744

100%

Apr, 10

165

100

81

79

62

658

720

91%

May, 10

160

150

90

85

744

744

100%

Jun, 10

150

100

69

60

159

561

720

78%

Jul, 10

155

100

60

55

253

491

744

66%

Aug, 10

170

100

57

57

235

502

744

67%

Sep, 10

170

100

17

17

125

595

720

83%

Oct, 10

170

100

79

79

744

744

100%

Nov, 10

140

100

62

51

166

554

720

77%

Total FY2010

175

100

81

79

141

688

7,931

8,760

91%

Total FY2011 YTD*

170

100

55

52

488

298

2,886

3,672

79%

* Data available till November 2010


Hagler Bailly Pakistan
R1V02TAG: 04/23/11

Appendix E

E-5

Technical Audit Study of GENCO Power Plants

Exhibit E.2: Power Plant Availability-TPS Guddu


Steam Unit 1
Installed Capacity
Derated Capacity
Month

100 MW
60 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schedld.
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availablity
(Hrs.)

Total Hours
of Month

Availability
Factor
(Time-base)

Jul, 09

50

15

83%

44%

101

643

744

86%

Aug, 09

50

10

73%

43%

172

572

744

77%

Sep, 09

50

25

88%

43%

42

678

720

94%

Oct, 09

50

25

97%

44%

740

744

100%

Nov, 09

55

30

80%

46%

91

629

720

87%

Dec, 09

60

10

87%

48%

10

734

744

99%

Jan, 10

60

10

85%

48%

29

715

744

96%

Feb, 10

55

50

97%

49%

672

672

100%

Mar, 10

55

30

92%

48%

34

710

744

95%

Apr, 10

55

35

41%

41%

361

359

720

50%

May, 10

50

20

73%

43%

162

582

744

78%

Jun, 10

50

25

72%

40%

133

587

720

82%

Jul, 10

50

20

47%

34%

268

476

744

64%

Aug, 10

50

20

88%

42%

10

735

744

99%

Sep, 10

50

20

92%

43%

11

709

720

98%

Oct, 10

55

50

39%

47%

434

310

744

42%

Nov, 10

720

720

Total FY2010

60

10

81%

45%

361

777

7,622

8,760

87%

Total FY2011 YTD*

55

20

53%

33%

1,154

289

2,229

3,672

61%

* Data available till November 2010


Hagler Bailly Pakistan
R1V02TAG: 04/23/11

Appendix E

E-6

Technical Audit Study of GENCO Power Plants

Steam Unit 2
Installed Capacity
Derated Capacity
Month

100 MW
60 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Schedld.
Factor @ DC Outage (Hrs.)
(%)

Forced
Outage
(Hrs.)

Availablity
(Hrs.)

Total Hours
of Month

Availability
Factor
(Time-base)

Jul, 09

50

10

70%

44%

204

540

744

73%

Aug, 09

50

10

92%

43%

25

719

744

97%

Sep, 09

50

10

74%

43%

717

720

100%

Oct, 09

50

10

96%

49%

60

684

744

92%

Nov, 09

70

30

75%

56%

106

614

720

85%

Dec, 09

70

50

93%

60%

738

744

99%

Jan, 10

70

50

93%

62%

30

714

744

96%

Feb, 10

70

50

77%

62%

138

534

672

79%

Mar, 10

70

10

81%

59%

96

648

744

87%

Apr, 10

65

20

77%

51%

84

636

720

88%

May, 10

60

10

87%

53%

78

666

744

90%

Jun, 10

60

40

79%

45%

20

700

720

97%

Jul, 10

50

50

93%

42%

741

744

100%

Aug, 10

55

15

64%

43%

744

744

100%

Sep, 10

55

15

43%

38%

149

571

720

79%

Oct, 10

65

25

57%

46%

18

726

744

98%

Nov, 10

65

40

85%

56%

81

639

720

89%

Total FY2010

70

10

83%

52%

850

7,910

8,760

90%

Total FY2011 YTD*

65

15

68%

45%

251

3,421

3,672

93%

* Data available till November 2010


Hagler Bailly Pakistan
R1V02TAG: 04/23/11

Appendix E

E-7

Technical Audit Study of GENCO Power Plants

Steam Unit 3
Installed Capacity
Derated Capacity
Month

210 MW
170 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Schedld.
Factor @ DC Outage (Hrs.)
(%)

Forced
Outage
(Hrs.)

Availablity
(Hrs.)

Total Hours
of Month

Availability
Factor
(Time-base)

Jul, 09

140

60

51%

67%

325

40

380

744

51%

Aug, 09

140

50

58%

65%

233

65

446

744

60%

Sep, 09

140

30

68%

66%

70

650

720

90%

Oct, 09

140

30

81%

69%

165

579

744

78%

Nov, 09

155

50

92%

73%

47

673

720

93%

Dec, 09

170

100

94%

76%

744

744

100%

Jan, 10

170

100

74%

75%

151

593

744

80%

Feb, 10

160

140

98%

75%

672

672

100%

Mar, 10

160

20

83%

73%

100

644

744

87%

Apr, 10

150

40

83%

69%

97

623

720

87%

May, 10

150

50

79%

68%

125

619

744

83%

Jun, 10

140

20

66%

60%

197

523

720

73%

Jul, 10

120

30

79%

45%

740

744

99%

Aug, 10

100

20

19%

45%

393

91

259

744

35%

Sep, 10

130

10

9%

43%

32

688

720

96%

Oct, 10

130

100

98%

61%

744

744

100%

Nov, 10

130

80

56%

61%

720

720

100%

Total FY2010

170

20

77%

70%

558

1,057

7,145

8,760

82%

Total FY2011 YTD*

130

10

52%

51%

393

128

3,151

3,672

86%

* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-8

Technical Audit Study of GENCO Power Plants

Steam Unit 4
Installed Capacity
Derated Capacity
Month

200 MW
150 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Schdld.
Factor @ DC Outage Hours
(%)

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

110

20

81%

43%

738

744

99%

Aug, 09

120

40

62%

45%

169

575

744

77%

Sep, 09

100

20

6%

36%

666

54

720

7%

Oct, 09

100

20

63%

63%

387

357

744

48%

Nov, 09

150

20

88%

66%

36

684

720

95%

Dec, 09

150

130

99%

71%

744

744

100%

Jan, 10

150

130

81%

69%

116

628

744

84%

Feb, 10

150

30

73%

65%

137

535

672

80%

Mar, 10

150

30

92%

68%

26

718

744

96%

Apr, 10

150

10

60%

57%

178

542

720

75%

May, 10

150

110

92%

66%

744

744

100%

Jun, 10

140

20

77%

56%

64

656

720

91%

Jul, 10

120

20

32%

39%

391

353

744

47%

Aug, 10

120

50

17%

51%

744

744

100%

Sep, 10

0%

0%

720

720

100%

Oct, 10

0%

0%

744

744

100%

Nov, 10

150

10

56%

0%

717

720

100%

Total FY2010

150

10

73%

59%

1,786

6,974

8,760

80%

Total FY2011 YTD*

150

10

21%

18%

394

3,278

3,672

89%

* Data available till November 2010


Hagler Bailly Pakistan
R1V02TAG: 04/23/11

Appendix E

E-9

Technical Audit Study of GENCO Power Plants

Block 2-A: GT Unit 7


Installed Capacity
Derated Capacity
Month

100 MW
90 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

85

10

94

81

13

731

744

98%

Aug, 09

85

10

98

83

744

744

100%

Sep, 09

85

80

78

85

719

720

100%

Oct, 09

85

80

102

88

741

744

100%

Nov, 09

90

25

100

90

715

720

99%

Dec, 09

90

70

102

92

744

744

100%

Jan, 10

90

60

99

91

17

727

744

98%

Feb, 10

90

80

100

90

672

672

100%

Mar, 10

90

42

78

88

149

595

744

80%

Apr, 10

90

42

92

85

13

707

720

98%

May, 10

92

55

83

77

738

744

99%

Jun, 10

80

60

88

73

24

696

720

97%

Jul, 10

90

70

79

82

96

648

744

87%

Aug, 10

94

80

90

86

13

731

744

98%

Sep, 10

97

90

93

92

10

710

720

99%

Oct, 10

99

75

91

90

744

744

100%

Nov, 10

103

50

81

86

14

706

720

98%

92

10

93

85

149

81

8,530

8,760

97%

103

50

87

87

133

3,539

3,672

96%

Total FY2010
Total FY2011 YTD*

* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-10

Technical Audit Study of GENCO Power Plants

Block 2-A: GT Unit 8


Installed Capacity
Derated Capacity
Month

100 MW
90 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

80

40

91

74

735

744

99%

Aug, 09

75

40

102

77

744

744

100%

Sep, 09

75

75

80

77

720

720

100%

Oct, 09

75

75

97

81

28

716

744

96%

Nov, 09

85

80

99

85

716

720

99%

Dec, 09

85

40

101

87

12

732

744

98%

Jan, 10

85

40

99

86

16

728

744

98%

Feb, 10

85

80

101

86

672

672

100%

Mar, 10

90

65

91

82

744

744

100%

Apr, 10

90

65

83

76

10

710

720

99%

May, 10

85

55

72

67

60

684

744

92%

Jun, 10

70

60

100

70

718

720

100%

Jul, 10

80

70

88

70

741

744

100%

Aug, 10

75

70

89

71

744

744

100%

Sep, 10

70

70

102

71

720

720

100%

Oct, 10

80

42

59

76

282

462

744

62%

Nov, 10

85

65

96

82

715

720

99%

Total FY2010

90

40

93

79

142

8,618

8,760

98%

Total FY2011 YTD*

85

42

87

74

282

3,382

3,672

92%

* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-11

Technical Audit Study of GENCO Power Plants

Block 2-A: Steam Unit 5


Installed Capacity
Derated Capacity
Month

100 MW
82 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

72

10

76

57

31

713

744

96%

Aug, 09

70

10

82

59

14

730

744

98%

Sep, 09

68

30

70

61

717

720

100%

Oct, 09

68

30

94

68

23

721

744

97%

Nov, 09

80

20

88

72

13

707

720

98%

Dec, 09

78

34

90

70

744

744

100%

Jan, 10

78

10

86

69

22

722

744

97%

Feb, 10

82

65

87

72

672

672

100%

Mar, 10

79

23

82

65

744

744

100%

Apr, 10

79

23

68

56

29

691

720

96%

May, 10

68

12

72

49

743

744

100%

Jun, 10

66

74

49

712

720

99%

Jul, 10

70

10

71

53

56

688

744

93%

Aug, 10

67

36

74

51

32

712

744

96%

Sep, 10

54

45

86

47

716

720

99%

Oct, 10

48

74

36

744

744

100%

Nov, 10

51

22

79

41

10

710

720

99%

Total FY2010

82

81

62

144

8,616

8,760

98%

Total FY2011 YTD*

70

77

46

102

3,570

3,672

97%

* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-12

Technical Audit Study of GENCO Power Plants

CCP Block 2-A (GT7, GT8, ST5)


Installed Capacity
Derated Capacity
Month

300 MW
262 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

237

60

88

71

18

726

744

98%

Aug, 09

230

60

94

73

739

744

99%

Sep, 09

228

185

76

74

719

720

100%

Oct, 09

228

185

98

79

18

726

744

98%

Nov, 09

255

125

96

82

713

720

99%

Dec, 09

253

144

98

83

740

744

99%

Jan, 10

253

110

95

82

18

726

744

98%

Feb, 10

257

225

96

83

672

672

100%

Mar, 10

259

130

84

78

50

694

744

93%

Apr, 10

259

130

82

72

17

703

720

98%

May, 10

245

122

76

64

22

722

744

97%

Jun, 10

216

125

88

64

11

709

720

98%

Jul, 10

240

150

79

69

52

692

744

93%

Aug, 10

236

186

85

70

15

729

744

98%

Sep, 10

221

205

94

70

715

720

99%

Oct, 10

227

124

76

67

94

650

744

87%

Nov, 10

239

137

86

70

10

710

720

99%

Total FY2010

259

60

89

76

50

122

8,588

8,760

98%

Total FY2011 YTD*

240

124

84

69

94

81

3,497

3,672

95%

* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-13

Technical Audit Study of GENCO Power Plants

Block 2-B: GT Unit 9


Installed Capacity
Derated Capacity
Month

100 MW
90 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

70

44

101

71

740

744

99%

Aug, 09

70

44

94

71

53

691

744

93%

Sep, 09

70

16

101

71

720

720

100%

Oct, 09

70

16

24

72

559

13

172

744

23%

Nov, 09

720

720

Dec, 09

744

744

Jan, 10

744

744

Feb, 10

672

672

Mar, 10

744

744

Apr, 10

720

720

May, 10

744

744

Jun, 10

720

720

Jul, 10

744

744

Aug, 10

90

80

76

693

51

744

7%

Sep, 10

100

80

39

84

383

337

720

47%

Oct, 10

100

80

61

78

160

584

744

78%

Nov, 10

100

20

23

76

169

549

720

76%

70

16

27

24

6,367

70

2,323

8,760

27%

100

20

26

63

913

1,237

1,521

3,672

41%

Total FY2010
Total FY2011 YTD*

* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-14

Technical Audit Study of GENCO Power Plants

Block 2-B: GT Unit 10


Installed Capacity
Derated Capacity
Month

100 MW
90 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

75

45

90

72

50

694

744

93%

Aug, 09

75

60

100

75

744

744

100%

Sep, 09

75

10

89

75

720

720

100%

Oct, 09

75

10

33

80

503

241

744

32%

Nov, 09

720

720

Dec, 09

744

744

Jan, 10

744

744

Feb, 10

672

672

Mar, 10

744

744

Apr, 10

720

720

May, 10

744

744

Jun, 10

108

10

47

77

244

476

720

66%

Jul, 10

90

20

80

79

72

672

744

90%

Aug, 10

105

60

67

77

64

680

744

91%

Sep, 10

100

70

78

88

82

638

720

89%

Oct, 10

100

50

64

81

153

591

744

79%

Nov, 10

100

10

18

63

250

28

443

720

61%

Total FY2010

108

10

30

32

5,591

294

2,875

8,760

33%

Total FY2011 YTD*

105

10

62

78

250

399

3,023

3,672

82%

* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-15

Technical Audit Study of GENCO Power Plants

Block 2-B: Steam Unit 6


Installed Capacity
Derated Capacity
Month

100 MW
82 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

65

52

54

278

466

744

63%

Aug, 09

66

82

54

741

744

100%

Sep, 09

67

26

83

56

720

720

100%

Oct, 09

67

26

25

52

503

240

744

32%

Nov, 09

720

720

Dec, 09

744

744

Jan, 10

744

744

Feb, 10

672

672

Mar, 10

744

744

Apr, 10

720

720

May, 10

744

744

Jun, 10

720

720

Jul, 10

744

744

Aug, 10

744

744

Sep, 10

720

720

Oct, 10

744

744

Nov, 10

720

720

67

20

18

6,311

281

2,167

8,760

25%

3,672

3,672

0%

Total FY2010
Total FY2011 YTD*
* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-16

Technical Audit Study of GENCO Power Plants

CCP Block 2-B (GT9, GT10, ST6)


Installed Capacity
Derated Capacity
Month

300 MW
262 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

210

95

82

66

111

633

744

85%

Aug, 09

211

109

92

67

19

725

744

97%

Sep, 09

212

52

91

67

720

720

100%

Oct, 09

212

52

27

68

522

218

744

29%

Nov, 09

720

720

Dec, 09

744

744

Jan, 10

744

744

Feb, 10

672

672

Mar, 10

744

744

Apr, 10

720

720

May, 10

744

744

Jun, 10

108

10

47

26

480

81

159

720

22%

Jul, 10

90

20

80

26

496

24

224

744

30%

Aug, 10

195

140

39

51

248

252

244

744

33%

Sep, 10

200

150

59

57

240

155

325

720

45%

Oct, 10

200

130

63

53

248

104

392

744

53%

Nov, 10

200

30

20

46

380

10

331

720

46%

Total FY2010

212

28

24

6,090

215

2,455

8,760

28%

Total FY2011 YTD*

200

20

52

47

1,612

545

1,515

3,672

41%

* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-17

Technical Audit Study of GENCO Power Plants

Block 1: GT Unit 11
Installed Capacity
Derated Capacity
Month

136 MW
90 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

80

60

101

60

744

744

100%

Aug, 09

80

80

102

60

744

744

100%

Sep, 09

80

16

88

59

718

720

100%

Oct, 09

80

16

103

61

744

744

100%

Nov, 09

80

80

101

60

715

720

99%

Dec, 09

100

60

84

62

742

744

100%

Jan, 10

100

60

80

59

10

734

744

99%

Feb, 10

80

80

101

60

672

672

100%

Mar, 10

80

80

91

60

88

657

744

88%

Apr, 10

80

80

100

60

713

720

99%

May, 10

80

80

101

60

740

744

99%

Jun, 10

80

20

99

59

712

720

99%

Jul, 10

80

60

102

60

743

744

100%

Aug, 10

80

30

91

59

744

744

100%

Sep, 10

80

40

102

60

720

720

100%

Oct, 10

80

20

99

60

744

744

100%

Nov, 10

80

70

100

60

720

720

100%

100

16

96

60

126

8,634

8,760

99%

80

20

99

60

3,671

3,672

100%

Total FY2010
Total FY2011 YTD*

* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-18

Technical Audit Study of GENCO Power Plants

Block 1: GT Unit 12
Installed Capacity
Derated Capacity
Month

136 MW
80 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

80

13

101

60

742

744

100%

Aug, 09

80

80

102

60

744

744

100%

Sep, 09

80

70

100

59

720

720

100%

Oct, 09

80

70

102

60

741

744

100%

Nov, 09

80

80

102

60

720

720

100%

Dec, 09

80

80

92

61

80

664

744

89%

Jan, 10

80

80

102

61

10

734

744

99%

Feb, 10

80

80

102

60

672

672

100%

Mar, 10

80

80

103

61

744

744

100%

Apr, 10

80

80

101

60

720

720

100%

May, 10

80

40

101

59

743

744

100%

Jun, 10

80

60

101

59

720

720

100%

Jul, 10

80

80

102

60

744

744

100%

Aug, 10

80

20

91

58

740

744

99%

Sep, 10

80

20

58

53

720

720

100%

Oct, 10

80

50

101

59

744

744

100%

Nov, 10

80

70

100

60

717

720

100%

Total FY2010

80

13

101

60

96

8,664

8,760

99%

Total FY2011 YTD*

80

20

90

58

3,665

3,672

100%

* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-19

Technical Audit Study of GENCO Power Plants

Block 1: Steam Unit 13


Installed Capacity
Derated Capacity
Month

143 MW
98 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

91

38

82

53

16

728

744

98%

Aug, 09

90

11

97

62

11

733

744

99%

Sep, 09

92

38

90

58

717

720

100%

Oct, 09

92

38

99

64

744

744

100%

Nov, 09

95

41

97

64

720

720

100%

Dec, 09

98

43

90

62

744

744

100%

Jan, 10

98

43

89

63

28

716

744

96%

Feb, 10

65

54

142

65

668

672

99%

Mar, 10

94

42

92

61

744

744

100%

Apr, 10

91

38

54

48

205

515

720

72%

May, 10

43

38

95

29

742

744

100%

Jun, 10

83

38

60

35

720

720

100%

Jul, 10

42

35

90

28

31

713

744

96%

Aug, 10

40

28

95

28

32

712

744

96%

Sep, 10

40

20

79

28

158

562

720

78%

Oct, 10

82

30

47

43

285

459

744

62%

Nov, 10

84

38

89

52

720

720

100%

Total FY2010

98

11

91

55

269

8,491

8,760

97%

Total FY2011 YTD*

84

20

80

36

507

3,165

3,672

86%

* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-20

Technical Audit Study of GENCO Power Plants

CCP Block 1 (GT11, GT12, ST13)


Installed Capacity
Derated Capacity
Month

415 MW
268 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Schdld.
Outage
Hours

Forced
Outage
Hours

Available
Hours

Total Hours
of Month

Availability
Factor
(Time Base)

Jul, 09

251

111

94

57

738

744

99%

Aug, 09

250

171

100

60

740

744

100%

Sep, 09

252

124

93

59

718

720

100%

Oct, 09

252

124

101

62

743

744

100%

Nov, 09

255

201

100

61

718

720

100%

Dec, 09

278

183

88

61

27

717

744

96%

Jan, 10

278

183

89

61

16

728

744

98%

Feb, 10

225

214

113

61

671

672

100%

Mar, 10

254

202

95

61

29

715

744

96%

Apr, 10

251

198

84

56

73

647

720

90%

May, 10

203

158

100

49

742

744

100%

Jun, 10

243

118

86

51

717

720

100%

Jul, 10

202

175

99

49

11

733

744

99%

Aug, 10

200

78

92

48

12

732

744

98%

Sep, 10

200

80

80

47

54

666

720

92%

Oct, 10

242

100

82

54

98

646

744

87%

Nov, 10

244

178

96

57

719

720

100%

Total FY2010

278

111

95

58

165

8,595

8,760

98%

Total FY2011 YTD*

244

78

90

51

177

3,495

3,672

95%

* Data available till November 2010

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-21

Technical Audit Study of GENCO Power Plants

Exhibit E.1: Power Plant Availability-TPS Muzaffargarh


Steam Unit 1
Installed Capacity
Derated Capacity
Month

210 MW
160 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Utilization
Factor @ IC
(%)

Schedld.
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availablity
(Hrs.)

Availability
Factor
(Time-base)

Jul, 09

155

110

86

66

51

744

100%

Aug, 09

155

110

78

61

46

65

679

91%

Sep, 09

145

110

80

58

44

37

683

95%

Oct, 09

160

130

86

69

52

78

666

90%

Nov, 09

160

110

99

79

60

717

100%

Dec, 09

160

110

76

61

46

166

578

78%

Jan, 10

160

130

86

69

53

64

680

91%

Feb, 10

150

110

89

67

51

55

617

92%

Mar, 10

150

110

58

44

33

122

622

84%

Apr, 10

140

130

98

69

52

720

100%

May, 10

140

115

61

43

32

242

502

68%

Jun, 10

130

110

71

46

35

22

698

97%

Jul, 10

110

105

69

38

29

118

626

84%

Aug, 10

110

100

37

21

16

187

557

75%

Sep, 10

100

95

80

40

30

101

619

86%

Oct, 10

100

65

80

40

30

69

675

91%

Nov, 10

100

65

31

16

12

40

680

94%

Total FY2010

160

110

81

61

46

852

7,908

90%

Total FY2011 YTD

110

65

59

31

23

515

3,157

86%

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-22

Technical Audit Study of GENCO Power Plants

Steam Unit 2
Installed Capacity
Derated Capacity
Month

210 MW
200 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Utilization
Factor @ IC
(%)

Schedld.
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availablity
(Hrs.)

Availability
Factor
(Time-base)

Jul, 09

180

110

95

85

81

744

100%

Aug, 09

180

110

99

89

85

744

100%

Sep, 09

180

110

98

88

84

11

709

98%

Oct, 09

180

170

99

89

85

744

100%

Nov, 09

165

120

29

24

23

498

223

31%

Dec, 09

200

175

53

53

51

206

91

447

60%

Jan, 10

180

140

93

84

80

56

680

91%

Feb, 10

150

110

82

74

70

95

577

86%

Mar, 10

150

110

90

81

77

71

673

90%

Apr, 10

140

130

100

90

86

719

100%

May, 10

140

115

96

86

82

744

100%

Jun, 10

130

110

82

74

70

54

666

93%

Jul, 10

110

105

74

66

63

471

273

37%

Aug, 10

110

100

62

48

46

31

713

96%

Sep, 10

100

95

61

54

52

39

681

95%

Oct, 10

100

65

82

74

70

86

658

88%

Nov, 10

100

65

85

77

73

720

100%

Total FY2010

200

110

85

76

73

703

378

7,671

88%

Total FY2011 YTD

110

65

73

64

61

471

155

3,046

83%

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-23

Technical Audit Study of GENCO Power Plants

Steam Unit 3
Installed Capacity
Derated Capacity
Month

210 MW
160 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Utilization
Factor @ IC
(%)

Schedld.
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availablity
(Hrs.)

Availability
Factor
(Time-base)

Jul, 09

150

110

86

64

49

744

100%

Aug, 09

160

110

71

57

43

102

642

86%

Sep, 09

140

105

82

57

44

38

682

95%

Oct, 09

160

110

73

58

44

66

678

91%

Nov, 09

160

80

89

71

54

36

684

95%

Dec, 09

160

70

37

30

23

194

550

74%

Jan, 10

90

50

68

31

23

131

613

82%

Feb, 10

80

65

57

23

18

261

412

61%

Mar, 10

130

70

61

39

30

Apr, 10

130

110

83

54

41

720

100%

May, 10

110

80

94

52

39

738

99%

Jun, 10

130

110

52

34

26

66

654

91%

Jul, 10

160

145

34

28

21

742

100%

Aug, 10

160

110

83

66

51

67

677

91%

Sep, 10

160

110

78

62

47

14

706

98%

Oct, 10

160

100

83

67

51

81

663

89%

Nov, 10

160

100

54

43

33

720

100%

Total FY2010

160

50

71

47

36

899

7,117

81%

Total FY2011 YTD

160

100

66

53

41

163

3,509

96%

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-24

Technical Audit Study of GENCO Power Plants

Steam Unit 4
Installed Capacity
Derated Capacity
Month

320 MW
250 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Utilization
Factor @ IC
(%)

Schedld.
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availablity
(Hrs.)

Availability
Factor
(Time-base)

Jul, 09

230

130

86

80

63

742

100%

Aug, 09

235

145

87

83

65

741

100%

Sep, 09

235

130

96

92

72

720

100%

Oct, 09

245

215

82

82

64

91

653

88%

Nov, 09

250

160

78

79

62

99

621

86%

Dec, 09

250

160

96

98

77

19

725

97%

Jan, 10

250

160

98

100

78

739

99%

Feb, 10

250

220

88

100

78

672

100%

Mar, 10

245

160

90

90

70

14

730

98%

Apr, 10

235

160

89

88

69

720

100%

May, 10

230

160

90

85

66

738

99%

Jun, 10

220

160

87

78

61

720

100%

Jul, 10

200

110

30

28

22

442

301

40%

Aug, 10

185

140

37

28

22

333

102

310

42%

Sep, 10

195

160

76

60

47

120

601

83%

Oct, 10

205

165

75

63

49

145

14

886

119%

Nov, 10

205

160

28

24

18

183

210

109

15%

Total FY2010

250

130

89

88

69

240

8,520

97%

Total FY2011 YTD

205

110

49

41

32

1,222

327

2,205

60%

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-25

Technical Audit Study of GENCO Power Plants

Steam Unit 5
Installed Capacity
Derated Capacity
Month

200 MW
120 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Utilization
Factor @ IC
(%)

Schedld.
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availablity
(Hrs.)

Availability
Factor
(Time-base)

Jul, 09

80

80

57

31

18

161

583

78%

Aug, 09

100

20

45

30

18

252

492

66%

Sep, 09

90

40

34

20

12

425

295

41%

Oct, 09

110

25

16

12

603

141

19%

Nov, 09

120

110

22

17

10

424

111

185

26%

Dec, 09

115

70

24

19

11

380

161

204

27%

Jan, 10

110

50

79

58

35

98

646

87%

Feb, 10

110

35

80

59

35

71

601

89%

Mar, 10

110

25

30

22

13

351

393

53%

Apr, 10

45

45

20

559

161

22%

May, 10

100

20

647

97

13%

Jun, 10

95

95

38

24

14

897

323

45%

Jul, 10

95

30

70

44

27

15

729

98%

Aug, 10

75

50

60

30

18

253

491

66%

Sep, 10

75

20

72

36

22

718

100%

Oct, 10

80

30

71

38

23

166

578

78%

Nov, 10

80

80

16

593

127

18%

120

20

38

25

15

3,426

1,712

4,121

47%

95

20

58

31

19

436

593

2,643

72%

Total FY2010
Total FY2011 YTD

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-26

Technical Audit Study of GENCO Power Plants

Steam Unit 6
Installed Capacity
Derated Capacity
Month

200 MW
135 MW
Max. Load
(MW)

Min. Load
(MW)

Load Factor
(%)

Utilization
Factor @ DC
(%)

Utilization
Factor @ IC
(%)

Schedld.
Outage
(Hrs.)

Forced
Outage
(Hrs.)

Availablity
(Hrs.)

Availability
Factor
(Time-base)

Jul, 09

135

110

84

76

51

744

100%

Aug, 09

120

40

64

51

35

169

575

77%

Sep, 09

120

40

45

36

25

233

487

68%

Oct, 09

100

20

72

48

32

162

743

100%

Nov, 09

100

100

35

23

16

374

70

276

38%

Dec, 09

100

25

53

35

24

250

15

479

64%

Jan, 10

90

20

38

23

15

446

298

40%

Feb, 10

105

20

66

46

31

180

492

73%

Mar, 10

100

40

84

56

38

50

695

93%

Apr, 10

95

95

92

59

40

720

100%

May, 10

95

30

67

43

29

182

562

76%

Jun, 10

95

60

80

51

34

62

658

91%

Jul, 10

95

90

76

48

32

48

696

94%

Aug, 10

90

30

56

34

23

174

570

77%

Sep, 10

85

20

36

15

10

511

209

29%

Oct, 10

85

30

75

44

30

74

670

90%

Nov, 10

80

25

70

37

25

720

100%

135

20

65

46

31

624

1,568

6,729

77%

95

20

63

35

24

807

2,865

78%

Total FY2010
Total FY2011 YTD

Hagler Bailly Pakistan


R1V02TAG: 04/23/11

Appendix E

E-27

You might also like