Professional Documents
Culture Documents
PROJECT NAME
DOCUMENT NO.
: [KP-00+++-CY712-B7501]
TITLE
OWNER
PAGES
Purpose
For Information
For Review
For Approval
For Construction
As-Built
03.02.2015
For Construction
M.T
T.S
O.S
O.S
05.01.2015
For Construction
M.T
T.S
O.S
O.S
Rev.
No.
DATE
DESCRIPTION
Owner
Ministry of Electricity (MOE)
of Kurdistan Regional Government
Contractor
POSCO ENGINEERING
& CONSTRUCTION CO., LTD.
Main Subcontractor
GAMA POWER SYSTEMS ENGINEERING &
CONTRACTING,INC.
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
2 of 49
CONTENT
1.0
PURPOSE....................................................................................................................... 3
2.0
3.0
RESPONSIBILITIES ....................................................................................................... 3
4.0
DEFINITIONS / ABBREVIATIONS................................................................................... 8
5.0
MATERIALS .................................................................................................................... 8
6.0
EQUIPMENT ................................................................................................................... 9
7.0
8.0
9.0
10.0
EXECUTION ..................................................................................................................13
11.0
12.0
13.0
14.0
15.0
REFERENCES ...............................................................................................................49
16.0
ATTACHMENTS .............................................................................................................49
1.0
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
3 of 49
PURPOSE
The main objective of this document is to ensure that all activities are carried out:
In accordance with approved procedures, specifications and drawings etc.
Using special working and control processes which have been previously qualified,
Using qualified and when certified personnel for carrying out special processes,
Using materials which are kept under control from the receiving throughout the
entire Working cycle,
By performing all tests, measurements and inspections required by the contract.
2.0
SCOPE OF WORK
This method statement is a clarification of the work of Boiler Steel Structure, and
Pressure Parts including of all required accessories (Hanger rods, Steam Drum, downcomer
pipes, Headers, Buckstays, Furnace and HRA walls, coil tubes, Riser pipes, Link pipes,
casings, etc.) from the phase of preassembly until erection completion at Khabat Power Plant,
Khabat, IRAQ. All is subject to our normal terms and conditions of assembly.
3.0
RESPONSIBILITIES
3.1 PROJECT MANAGER
Project Manager has the following responsibilities ;
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
4 of 49
Be responsible to the Project Manager for performance of the project to meet the
criteria of effective cost control and compliance with project schedule.
Follow up with responsible parties to ensure that schedules are maintained or
improved.
Assure the scheduling and/or cost control report by planning, analyzing, and
forecasting of project performance for management.
Assess the effects of all deviations for project schedule, at the earliest possible time,
for evaluation and remedial action by Project Manager.
Preparation of all trend, status and progress reports.
Assure communications between other engineering and construction disciplines.
3.2 SITE MANAGER
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
Be responsible to the Project Manager for planning, coordinating and directing the
engineering and design work to meet the criteria of anticipated job quality with
economic design.
Supervise and coordinate the work of the various engineering disciplines.
Establish engineering and also define the delivertives and non-delivertives.
Work with the lead engineers to formulate, evaluate and execute practical, economical
and efficient design concepts suitable for the specific requirements of the project.
Resolve the conflicts among the engineering disciplines during the engineering and
design work.
Monitor engineering and design progress and report problems to the Project Manager
for resolution.
Be responsible for coordinating overall execution at site.
Set up and administer general operation of field office including camp facilities.
Review constructability throughly prior to site opening. Coordinate with the construction
members to prevent or solve possible problems.
Supervise and control field staffs in site organization. Delegate and assign to each
group of site organization all necessary functions to be performed during the phase of
construction. Check construction-planning documents to see whether any problem may
arise in future. Plan for preventive measure or set up a contingency plan.
Establish a plan of construction execution considering actual site conditions.
Direct field purchasing activities including material warehousing, and expedite site
delivery.
Preside weekly schedule meeting, weekly safety meeting, and monthly progress review
meeting to assure that all activities are performed in accordance with original planning.
Prepare construction status reports for the main-subcontractor and head office.
Direct all construction activities under execution and evaluate the result of field test.
Approve requests for field extra work order, change order, and memorandum work.
Maintain cooperative contact with client's project manager.
o
o
o
o
o
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
5 of 49
Submit monthly progress report to the client and expedite the approval on it.
Submit monthly invoice for erection portion to the client and expedite the payment of it.
Approve various field-originated reports to be submitted to the head office.
Prepare Final Construction Report.
Establish in accordance with contractual requirements an Inspection & Test Plan (ITP)
indicating the extent of inspection based on item criticality.
3.3 SITE ENGINEER
o
o
o
o
o
o
o
o
The site engineer carries full responsibility for the safe completion of the all works
carried out during the operation as per the Method Statement. It is the responsibility of
site engineer to ensure that the supervisor adequately briefing on the contents of this
method statement. Except that supporting QA/QC Manager works.
Plan, organize, direct, execute and coordinate the Boiler Erection.
Supervise, direct and control all personnel assigned to the Boiler Erection.
Be responsible, through Supervisor/foreman, for construction.
Follow up with responsible parties to ensure that schedules are maintained or
improved.
Assess the effects of all deviations for project schedule, at the earliest possible time,
for evaluation and remedial action by Site management.
Preparation of all trend, status and progress reports.
Preparation and following of the all required work permits, safe rules.
Preparation of all lifting plan for all critical lifting operation (such as over the 20ton lifting
operation, multi-lifting equipment used operation and complicated material lifting
operations)
Assure communications between other engineering and construction disciplines
3.4 SUPERVISOR/FOREMAN
Supervisor-foreman take responsibility for the provision of an efficient and effective work on
site operation. Prior the commencement of works, the supervisor-foreman must ensure that all site
personnel are adequately briefing on contents of this Method Statement and work. Also the control
of the working area is under his responsibility either the engineer is there or not.
o
o
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
6 of 49
3.5 PERSONNEL
All personnel the priority is to finish the job without failure and mistake. For developing
the experimantation the personnel trainings and certification will done. The trainings and
certificates to be given are; HSE Induction, Height Works, Safe Rigging and Slinging,
Barricading, Radiography test, Crane operations, Night Work, Emergency Response,
Working at Wind and Rain, Safety Belt Usage, Permit to Work, Confined Space Work, Rigger
and Signalman, Manbasket Training and Pressurised Tubes Training. The welders will
certificated after welder quality test.
QA/QC Manager is responsible for all quality matters related to the installation of all works
including the administration of non-conformance management in close cooperation with various
related departments.
QC Manager/Engineer shall be responsible;
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
7 of 49
All personnel who will be employed on the construction site shall attend this course as
a matter of priority. Personnel who require additional training to meet specific Contract
requirements shall be subject to the training stipulations of Construction Safety Plan. It
shall be the responsibility of the Project Manager to appoint a Safety Manager.
The HSE Manager shall prepare a safety control instruction to cover the construction
site activities.
It shall be responsibility to ensure that all site personnel and visitors adhere fully to
these instructions by means of continual monitoring and regular auditing.
To ensure all lifting equipment and accessories have valid certification
To ensure all activities are being executed as per GAMA HSE plan and related
procedures.
o
o
o
o
4.0
Doc. No
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
8 of 49
DEFINITIONS / ABBREVIATIONS
5.0
MATERIALS
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
9 of 49
6.0
EQUIPMENT
Other equipments
welding machine
Air compressor
PWHT machines
Power generator
Hydrotest pumps
Ventilation fans
7.0
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
10 of 49
8.0
Large materials will be stored in their closed wooden/steel boxes in lay-down area and
stored. All material will given to site after signature the material request form and those forms
were under control system taken until finishing the work. For availability and conservation;
such as fittings, valves, bolts, nuts, washers,
equipments and rest of small materials will be catagorized and kept in MTEK project
warehouse. In accordance of technical specifications preservations of the all material will be
kept untill project finish date. MTEK will manage the material receiving procedure. In case of
any damage or dismatch between materials and material list then MTEK will sent RFI and
action of GAMA will be requested.
Large bore (2''<D) pipes will be delivered to lay-down area as prefabricated spools(if
need) and small bore (0<D2") pipes without prefabrication (as loose lenghts). For rest of the
pipe erection material such as valves, fittings, flanges, steam traps, filters, flow meters, orifice
plates, spectacles, gaskets, support materials, silencers, bolts, nuts, washers will
be
Doc. No
Table.1
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
11 of 49
9.0
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
12 of 49
ERECTION PLAN
9.1 STEEL STRUCTURE
Steel structure erection order will be followed according erection manual. Main steel
members bolting without any empty holes at boiler tier 1, second tier could be start without
awaiting the completion of verticality and torqueing of boiler tier 1. During the erection of
boiler tier 2 members, Tier 1 verticality and torqueing continue, and tier 1 verticality and
torqueing must finalize before tier 2 erection completion time. Also grouting will be executed
after completion of boiler tier 1 verticality and torqueing. In addition this method is applicable
for the following tiers, like tier 3 erection start before the completion of tier 2 verticality and
torqueing and tier 2 verticality and torqueing must finalize before tier 3 erection completion
time and before erection of heavy girder. After the completion of Tier 3 main structure final
bolt tightening; pressure part erection will begin which sequence is written down as;
Doc. No
10.0
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
13 of 49
EXECUTION
10.1 STEEL STRUCTURE
For any type of work, erection, preassembly etc. all steps will be controlled by QA/QC
department and also construction team. All assemblies and erections will be taken to
checklist forms and archieved until finishing the job.
Anchors will hand overed by civil directly to Mitek A.. when the inspection will be finished
The top of the foundation base shall be cleaned and free of laitance, loose particles, oil or
grease. Laitance shall be removed by chipping. Anchor bolts shall be cleaned and padding shall
be performed by using shim plates. The shim and grout plan shall be discussed with the
Equipment erection supervisor prior to commencement of work. Adequate quantity of shim packs
shall be provided. The shim packs shall be placed so that the load will be evenly distributed. It
should be confirmed with the Equipment erection supervisor that the resultant load imposed at
each location will not damage the foundation. The shim packs shall be leveled with the top of the
shim being at the "Bottom of Base Plate Elevation". The column base plates are to be set on top
of shim packs. After shimming works, all elevation dimensions are checked. non-tapered steel
shims are required if sufficient contact area does not exist. Mild steel shims are acceptable
regardless of the steel grade of the column or bearing material. If required, these shims must be
contained, usually with a tack weld, so that they cannot be worked out of the joint. Full-contact
bearing is always achieved when lighter sections are centered over heavier sections of the same
nominal depth.
After the alignment and bolting of the steel structure, but before grouting, all anchor bolts
and nuts shall be tightened while the shims are checked with regard to their tight fit. After the
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
14 of 49
hardening of the grouting compound, the anchorage shall again be checked and if required the
nuts shall be tightened once again. All base plates shall be grouted and cured with the "nonshrink" grout as per the grout manufacturer's instructions.
Erection chief is be sure that chosen cranes or lifting equipments for erection are correct
and safe.
Crane lifting capacity charts shall be referred to and used during lifting studies.
Crane, boom-truck and lifting equipments command and signalled by educated and
certified riggers.
All pre-assembly and erection areas including the full space for crane operation shall be
clearly marked and barricaded to prevent to others (other than the erection team and
authorized personel) from entering and/or walking through the work area.
Tool-box trainings should be given before erection started and periodically after on.
Erection can not be started if responsible foreman and/or erection engineer not
available on site.
Erection area to be cleaned from scrap, waste and unused materials. Erection can not be
continu without having required permissions and apply safety regulations. Install platforms and
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
15 of 49
scaffolding for erection if necessary, and technical safety give approve for usage. Scaffolds and
platforms shall be erected by competent persons. The methods of lifting and fixing shall be
determined so that the members are not damaged during the handling process. During erection, all
work shall be securely bolted, however no permanent bolting and welding shall be done unless the
correct positioning and alignment of the member has been obtained. All completed work shall be
within the required dimensional tolerances and all materials shall be free of twists or distortions
that are likely to affect the structural integrity. It shall be checked to ensure that the correct bolt
type as indicated by the manufacturers stamp is used and the bolt length is correct.
Columns shall be positioned on the concrete foundations, with the nuts on the fixing bolts
left loose. These nuts shall be tightened using air operated or manual torque wrenches and special
care shall be taken to provide surfaces that are free from loose mill scale, dirt, oil, burrs or any
other defect which would prevent tight sealing. After erection two columns, beams and vertical
bracings between the columns, the connection bolts are installed but not tightened. Then all
necessary dimensions like column verticality, space between connection plates etc. are adjusted
in to correct dimensions. Finally, all bolts are tightened with calibrated torque wrench according
bolt type.
Tolerances for out of plumb and levels shall be as specified in the specifications and
drawings. After the alignment and bolting of the steel structure, but before grouting, all anchor
bolts and nuts shall be tightened while the shims are checked with regard to their tight fit. After
the hardening of the grouting compound, the anchorage shall again be checked and, if required,
the nuts shall be tightened once again. No flame or electrode cutting (carbone electrode method)
shall be allowed for field made holes. Where field made holes are required for high strength bolts,
they shall be drilled or sub-drilled and reamed to the specified size. Column panels will be
mounted by crain in accordance to the project to anchor bolts. Manlift will help to erection team if
necessary. If using manlift is impossible, safety belt will be used by using two extension rope with
shock absorber. After obtaining the project conformity by take necessary measures, to ensure the
safety by tightening anchor bolts.
10.1.5
PRE-ERECTION
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
16 of 49
Pre-assembly size will be determined based on the limitations of the transportation means
and width of the access roads as well as lifting capacity of the available cranes. All the preassembled structure will be securely tightened as per this Method Statement in such a way that no
damage or unacceptable deflection on the structure are to be observed.
10.1.6
ERECTION
Wind velocities values shall be taken daily. When wind velocities ar above 25 knots (if it is
less, limits determined by the manufactured shall be fallowed) all lifting operations to height will
cease unless the rated load and boom lengths can be reduced according to manufacturers
specifications. Measurements for the wind speed shall be done directly from the cranes
aerometer and shall be crosscheckted by the handheld units. All lifts above ground level must
account for wind force, i.e.side loads, down drafts etc. as applied to the load and the boom. Wind
scale table is given in attached. According to attached lifting study and crane lifting capacity table,
column, beam, bracing etc. components can be erected one by one or pre-erected on leveled
ground partly and erect as panel. Adequate safe lifting capacity of the cranes is to be confirmed
from the load charts of the cranes. For cranes not herein attached, load charts will be submitted
for approval, before the start of the respective work.
Before erection starts, the erection area shall be back-filled, leveled and compacted as
necessary to perform easy, sound and safe operation including crane, truck, trailer etc.
movements. Column panels will be erected by using crane(s) in accordance with IFC drawings.
Manlift will help to erection team if necessary. After obtaining the project conformity by take
necessary measures, to ensure the safety by tightening anchor bolts. If beams, vertical bracing
etc can not be installed to ensure the safety by using chain block or using steel wire block. In
necessary situation to ensure the column itself safety by using on two points with steel wire. When
erection is done, all necessary survey controls to be done for control the erection as shown in
drawings and tolerances. All parts connecting bolts to be checked as shown in the drawings and
against the suitable torque value. Loosen bolts need to be tightened again.
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
17 of 49
properly prepared templates or equal approved methods. The correct fusion bevel shall then be
cut. All weld spatter shall be removed and where steelwork is to be blast-cleaned all traces of spatter
shall be removed before commencement of blasting. Welding procedure specifications and their
records will be per AWS D1.1. Welder certification will be per AWS D1.1.
10.1.8
After steelwork has been erected and the final procedures for connection completed, the
exposed surfaces of any nuts, bolts, washers and untreated areas together with the surfaces of
steelwork where the coating is damaged shall be prepared, primed and painted with a system
equivalent to that applied at Works.
10.1.9
TORQUING METHOD
10.1.9.1 NON-PRELOADED BOLTS
The design of bolted connections loaded in shear should bearing type. No preloading and
special provisions for contact surfaces are required. If shear plane passes through the threaded
portion of the bolt, it should be taken into account for the bolt shear resistance calculation. The
design of bolted connections loaded in tension should be connections with non-preloaded bolts.
No preloading is required.
If oversized or slotted holes are used, it should be taken into account for the bolt slip
resistance calculation. The class of friction surface of plates connected by preloaded bolts should be
taken into account in the slip factor for the bolt slip resistance calculation. In oversized holes used
to increase tolerances in erection, or where a joint loaded in shear is subject to impact, significant
vibration or load reversal, slip-resistant bolted connections should be used. In beam-to-column
bolted joints of the main frames, slip-resistant connections shall be used. Values of preloading
force for tightening high strength preloaded bolts should be the following;
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
18 of 49
Table2.
Bolt tightening will be proceed as follows;
First, all loose bolts will be tightened by manual wrench.
Then, the bolts which are already manually tightened are tightened to 50-70% of the torque
value by using manual torque wrench. After torquing, the bolts are marked with I with using
permanent metal marker.
After that, the bolts which are already torqued to 50-70% of the torque value, are tightened to
100%. Then I marking is converted to + with using permanent metal marker.
Finally all torqued bolts are checked whether or not to reach requested torque values.
Suitable tools (e.g. air or hydraulic operated torque wrench for great load ranges and manual
torque wrenches for small load ranges) shall be used for tightening the nuts. Bolts shall be
tightened always by turning nuts. Only where avoidable, the bolt head may be turned with the
approval of GAMA. Bolts shall be tightened progressing systematically from the center to the free
edges of joint. Tightening of bolts shall be controlled all the time. The work shall be done by
competent and experienced bolting crews. Bolted connections shall be drifted to proper position
and the holes inspected to ensure that bolt threads will not be damaged by forcing the bolts in
place. Connections shall be tightly drawn together using not less than 25 percent of the total
number of bolts in the completed joints, but never less than two bolts. Bolts for initial tightening
shall be distributed uniformly about the joint. Visual inspection of bolt tightness shall be performed
by checking whether the notched tail or bolt shears off or not.
Bolt heads and nuts shall rest squarely on their mating surfaces. Where the surface of the bolt
head or nut and the surface of the steel members form an inclination greater than the acceptance
limits, larger, tapered or smooth beveled washers shall be used to make the contact tight and
compensate for the lack of parallelism according to the standards.
Any bolt assemblies which size when being tightened shall be replaced. All bolt heads shall
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
19 of 49
be faced upward if applicable. Unless others specified, two carburized washers per bolt shall be
used at all times. One washer under the bolt head and one under the nut shall be used. Drifts shall
be used to correct hole alignments, if possible. Drifts of a larger diameter than the hole being
drifted shall not be used.
Offset holes may be corrected by reaming according to the standards. Missing holes shall
be drilled but flame-cutting of the holes is not permitted. Erection bolts shall be replaced by the
specified bolts as soon as possible. High strength bolts shall not be used as erection bolts.
Tension control bolts use design features that indirectly indicate tension. The most common
alternative design bolt is the twist-off bolt or tension control (TC) bolt. An assembly tool holds this
bolt from the nut end while an inner spindle on the tool grips a spline section connected to the end
of the bolt. An outer spindle on the tool turns the nut and tightens the fastener. When the
designated torque has been reached, the spline snaps off. This type of torque control system
allows for quick inspection, if the spline is gone then, in theory, the bolt has been properly
tightened. Although each tension control bolt assembly (bolt, nut and washer) lot is tested by the
manufacture to ensure it meets the minimum required clamp load, this system is based on torque
control to snap the spline. Because of this torque based system, bolt assemblies must be used in
their as-received (clean and lubricated by the manufacture), and strict adherence to the
requirements of the appropriate standard, particularly those for storage, cleanliness, and
verification is necessary. The A325 equivalent TC bolts are manufactured to the ASTM F1852
standard (Standard Specification for "Twist Off" Type Tension Control Structural Bolt/Nut/Washer
Assemblies, Steel, Heat Treated, 120/105 Ksi Minimum Tensile Strength). The A490 equivalent
TC bolts are to the ASTM F2280 standard (Standard Specification for "Twist Off" Type Tension
Control Structural Bolt/Nut/Washer Assemblies, Steel, Heat Treated, 150 Ksi Minimum Tensile
Strength). Each bolt is preassembled with an ASTM F436 flat washer and the appropriate heavy
hex nut and sold as an assembly. The F1852 bolts are available plain finished or mechanically
galvanized. The F2280 bolts are only available in plain finish.
Almost the whole of TS bolts which BHI supplied are S10T, some assembled parts of
top structural steel are required to use F10T (exp.for Tier.4: 160EA). S10T is torque shear type
which does not need torque value(fin- tale will be dropped by itself when they reach to required
shaft force)
Alternative Design Bolts (Tension Control Bolts/ Bolt rivet)
DWG.1
Doc. No
10.2
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
20 of 49
Although all the application will do under boiler erection manual KP-90H++-VM600V0110.
10.2.1
HANGER ROD
The hanger rods will be preassembled at the ground level to PPSL framing structure
before erection and will be erected to the correct position with steel structure. If required
tailing will be made for protection of the hanger rods for any type of damage during lifting.
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
21 of 49
DWG.2
10.2.2
STEAM DRUM
The proper erection will made with two HTE H-140 1400kn capacity hydraulic jacks.
Steam Drum will lift until reaches 40m level. After that it will slide to project location (DWG.4).
Hydraulic jacks/Chain blocks to be use for sliding horizontally to south side. Sliding operation
occurs between steel structure and Jack base plate with teflon. (DWG.5) Teflon to be use for
preventing any damage on steel structure. After sliding, drum lifting will continue until exact
level. Basicly lifting sequence given below;
(1) Hydraulic Jacks (strand) will be prepared before operation.
(2) Steam Drum will take inside of boiler from west side. Undo the truck height and
other conditions some steels may taken out from steel structure (such as vertical
brace, beam, etc).
(3) Strand jack hook to be tie to drum lifting lug directly. And than lifting will start.
(4) Steam Drum will lift until reaches 40m level. After that it will slide to project
location.
(5) Drum U-bend support structure erection to be completed.
(6) U-bend and Pin erection to be complete, steam drum put down precisely.
(7) Drum Levelling to be adjust by Liner plate.
(8) Finally, remove all temporary lifting system and attacments (jack, strand, plate,
scaffolding, etc)
Doc. No
DWG.3
DWG.4
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
22 of 49
Doc. No
DWG.5
DWG.6
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
23 of 49
Doc. No
10.2.3
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
24 of 49
HRA Roof wall will be lifted after ground assembly erection completion as one piece
which are including of roof panel, roof inlet header, str.outlet header, furn.rear.outlet header,
psh.outlet header and loose tubes (DWG.8). Headers will be transported from the lay-down
area to site in their original transportation boxes. Headers will be placed right beneath the
plan position onto HRA Roof panel and proper assembly will be made.
Erection will be done with hydraulic jacks (DWG9). After erection the fixing will be
done directly to hanger rods (DWG.7) or temporary hanging with wires will done. Detailed
lifting method will be given at least two days before erection. The hanging method during
lifting will be done as explained at 10.3 PREPERATION AND RIGGING section.
DWG.7
Doc. No
DWG.8
DWG.9
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
25 of 49
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
26 of 49
DWG.10
10.2.4
Upper stringer loose tubes to be installed after Roof Panel lifting. Stringers
installation will be made there with hand lifting equipments as chain block, trifore etc.
10.2.5
DOWNCOMER PIPES
The downcomers spools will be ground assembled or erected one by one according the
erection status. The erected spools will be temporarely fixed and welded on field on scaffold.
The welding surface will be cleaned proper fit-up will be made and QA/QC will be allow the
fit-up and then preheating operation will be done and weld will begin under WPS, PQR.
Doc. No
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
27 of 49
DWG.11
Headers (DRW.12) will be lifted directly upwards and when header reaches to position, one
team will install temporarely fixing will be done with the proper material. Hydraulic Jacks/Crane
will be used for lifting operation. After completion of lifting, crane/jack will release the load onto
fixing support. Slings will be removed from the header and lifting operation will be completed.
During to lifting operation and stand by period
preventing any damage. After installation alignment will be done as per seen at (DRW.13). Before
hydrotest all supports shall be completed according to drawings.
Doc. No
DWG.12
DWG.13
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
28 of 49
Doc. No
10.2.7
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
29 of 49
BUCKSTAY LIFTING
Buckstays will be lifted on panels by ground assembly which are possible. Buckstays
that ground assembly is not possible will be erected directly upward and when buckstay
reaches to position, one team will install temporarely fixing will be done with the proper
material. Hydraulic Jacks/Crane will be used for lifting operation. After completion of lifting,
crane/jack will release the load onto fixing support. Slings will be removed from the header
and lifting operation will be completed. During to lifting operation and stand by period
buckstay will be protected to preventing any damage.
Photo.1
DWG.14
Doc. No
10.2.8
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
30 of 49
The preassembly and lifting operation of the wall panels could not done as one set
depending of the allowance the steel structure boiler zone. Because of the high lenghts
preassembly will not done at wall panels. As seen at following drawings the coloured parts
(DWG.16, DWG.17, DWG.18) will be erected directly and assembled according Quality
requirement. During to assembly dimensional check to be verified as per ITP requirement.
When assembling of furnace panel, in order to avoid mismatching of buckstay hole with
welding shrinkage, allowable tolerance will be considered not only as full length of panel but
also each panel of panel.
Transportation details are explained at 11.0 TRANSPORTATION, PREPERATION AND
RIGGING section.
DWG.15
Doc. No
DWG.16
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
31 of 49
Doc. No
DWG.17
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
32 of 49
Doc. No
DWG.18
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
33 of 49
Doc. No
10.2.9
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
34 of 49
Coils are to be ground assembled as reheater 1st bank to reheater 2nd bank joint
number FW-RH-02, final superheater 1st bank to final superheater 2nd bank joint number
FW-FSH-02, primary superheater 1st bank to primary superheater 2nd bank and to primary
superheater 3rd bank joint numbers are FW-PSH-03 and FW-PSH-04. Stringer will be in
single pieces.
The erection will be done as same as the lifting method explained at section 11.1.
Crane, vincy or hydraulic jacks will be used during lifting. After lifting temporary wires or
hanging mechanism will be prepared for hanging the coils before welding. After the welding
activities all quality requirements will be done.
DWG.19
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
35 of 49
Photo 2.
Such a lifting device (photo.2) will be designed and produced at site for lifting the preassembled coils. During lifting operation and stand by period coils will be protected to
preventing any damage. The coils will be fixed to device with bolt and nuts and tailed from
horizantal position to vertical position as defined at lifting part. The certification of the lifting
device will be made by a third party.
10.2.10
The preassembly and lifting operation of the lower section wall panels could be done as
one set depending of the allowance the steel structure boiler zone (DWG.20). Because of the
high lengths (apr.17m) preassembly will not done too much. During to preassembly
dimensional check to be verified as per ITP requirement. measuring dimensions and crossdimension check, usage of propan before welding, making all NDT tests before erection, use
of
proper
preassembly
desck
etc.
Transportation
details
are
explained
at
11.0
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
36 of 49
DWG.20
10.2.12 BOILER INTERNAL & INTERCONNECTION PIPING LIFTING AND
INSTALLATION
Piping will be discussed under 3 group which are riser pipes, link (transfer) pipes and
feeder pipes. General sequence for piping is as follows:
Fit-Up Checks:
QC welding release
welding
NDT:
Doc. No
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
37 of 49
DWG.23
Doc. No
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
38 of 49
Link pipe will be erected together with riser pipes in taking care of sequence at roof
location. After that first hanging with temporary wires/chain blocks. Then adjust the position
for proper fit-up. Within QA/QC department control and procedures the weld and NDT tests
will be done.
DWG.24
Doc. No
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
39 of 49
When the pipes reaches to side the spools will be begin to ground assembly across
the site conditions and hanging will be begin as same riser pipes and link ducts first
temporary and then the weld will be done with QA/QC department control and procedures
and NDT test will be done. After this hanger will be put on and connection to the pipe will be
made.
DWG.26
Doc. No
10.2.12.4
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
40 of 49
SUPPORT
10.2.13
The casing attachments on pressure part tubes will be welded before the hydrotest.
However, corner part of skin casing should be erected before installation of link plate for
buckstay because of limited area for casing installation (DWG.27,DWG.28).
All weldings will be controlled by QA/QC team and required NDT test will be made
before hydrotest.
DWG.27
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
41 of 49
DWG.28
10.2.14
10.2.15
Doc. No
11.0
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
42 of 49
DWG.29
2- To take the complete weight of the wall, special lifting eye pads will be pre-fabricated at site.
Doc. No
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
43 of 49
DWG.31
3- In order to place eye pads, membrane plates will be cut to be welded after completion of
erection, lifting points as sample shown on the drawing below.
DWG.31
DWG.32
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
44 of 49
Photo 2.
11.2 TRANSPORTATION
material in work site. Vehicles and cranes; such as trucks, trailers, pick-ups and
mobile/crawler cranes, hi-ups will be inspected periodically and used by certified operators.
Doc. No
11.3
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
45 of 49
LIFTING
After arrival of the pressure part material under the boiler, they will be placed under
Furnace Hall. Crane, hydraulic jacks or any other lifting equipment will be used for lifting activities.
If need Lifting beam will be obtained.
Certified lifting equipments/device (crane, trailer, shackles, slings, ropes etc.) will be used
by trained riggers. In the lifting operations the erector will indicate the safety measures to be taken.
The detailed lifting plan for the each lifted material which is over 20ton or material that will be lifted
with more then one lifting equipment will be submit to GAMA for approval 1 week before the lifting
of the material.
Water wall lifting example:
123456-
DWG.33
This rigging type will be used for lifting.
Doc. No
[KP-00+++-CY712-B7501]
Rev. No.
Page
1
46 of 49
DWG.34
11.3 WELDING
Welding procedure specifications which are in attachement and their records will be ASME
Section IX. Welder certification will be per ASME Section I. The boiler will have A Stamp which the
responsibility area is boiler proper-The ASME Boiler and Pressure Vessel Code (ASME BPVC)
and Boiler external piping and joints ASME Section Committe B31.1. All pressure part weldings
will be performed according to the details on drawings and ASME Section IX, ASME 31.1. The
design resistance of fillet welds in calculations of welded connections should be taken considering
the real throat thickness to be used in the welding. Length of fillet welds shall not be less than four
times the nominal size of the weld or 40 mm whichever is more. As a minimum, the size of a weld
to be used on stressed connections is 6 mm fillet.
Doc. No
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
47 of 49
DWG.35
12.0
QUALITY REQUIREMENTS
QA/QC Manager is responsible for all quality matters related to the installation of pipe
works including the administration of non-conformance management in close co-operation
with various related departments.
QA/QC Engineer shall be responsible for the development of PQR/WPS, Qualification
and approval of PQR/WPS, requisition of correct consumables for the Project Monitoring the
performance of the welders, Evaluation and Recording of the repair rate of the welders,
Penalize and no welding the welders whose repair rate is high.
QC Inspector shall be responsible to verify the correct implementation of the project
Doc. No
Rev. No.
Page
[KP-00+++-CY712-B7501]
1
48 of 49
13.0
The proper scaffolding, lift and lifting equipments will be used which all will be
certicated. At proper areas safety net will be used. All workers will have proper PPEs. The
detailed HSE plan is attached. MTEK A.. will obey GAMAs HSE plan with international
standards and local laws.
14.0
RISK ASSESSMENTS
The Risk Assessment is attached.
15.0
REFERENCES
DRAWINGS
TECHNICAL SPECIFICATIONS
Doc. No
Rev. No.
Page
ASME Sec. I
ASME 31.1
ASME IX
ISO-E-GSS-B-16
AWS-ASTM-E-7018
AWS-ASTM-E-9018 DI
16.0
[KP-00+++-CY712-B7501]
ATTACHMENTS
Attachment-1
Attachment-2
Attachment-3
Attachment-4
HSE Plan
Job Safety Analyses and Risk Assessment (for Steel Structure)
Job Safety Analyses and Risk Assessment (for Pressure Part)
WPS List
1
49 of 49