Introduction
Collaborative Effort between
Contractor, Consultant & Specialist
Contractor
Project Overview
Extension and refurbishment of the Neeta City Shopping Center,
Fairfield
Existing 1st Floor car-park converted to a new Big W Store.
Approx 5800m2
New Floor 300 to 400mm above the existing car-park floor.
Floor Live Load increased from 3kPa to 5KPa / 10kPa
Project Constraints
Operating Woolworths supermarket in floor below +
carpark over
No space beneath could be used for construction
No significant construction noise during business hours.
Weight of new floor less than slab capacity.
Relatively long spans & falls in carpark
External Upstand
Remained
Existing Risers
Stormwater pipes
through slab
Conforming RC Scheme
New waffle slab composite with existing PT floor
Dowels @ 250cts
& scabbling
existing concrete
Existing Tendons
PLAN
Structural Systems (Northern) Pty Ltd
Construction Noise
Approx 30,000 Dowels & 8000m of 200wide scabbling
Scabbling and drilling outside business hours. Costly and timely!
Night
Local
Residents
Day
Woolworths Trading
Hours
Night
Local
Residents
Alternative PT Scheme
Post-tensioned waffle slab
Isolated from the existing floor surface.
Connection to Existing Columns by Dowels
Temporary IJ to existing columns to allow movement.
Core Connections
Bars epoxied into core
Sleeved for movement
10mm isolation to
existing slab
Why Isolate?
Typical Slab Columns deflect to accommodate PT force
As slab is poured directly on existing, columns cannot deflect - posttensioned force lost
Column Connections
Column Reinf. Located
Oversized holes cores
Tapered isolation gap
(preformed metal mesh)
Grouted at 56 days
Column Connections
Carpark
New Slab
Existing Slab
Woolworths
Hanging Support
Very long span in 10Kpa area
Unable to span with available
depth
Room underneath slab not
available
Blade column introduced
Curved Beam
Irregular column grid
Extra concrete and DL
required to span
Composite section used
similar to RC scheme
Summary
PT solution eliminated significant amount of
construction noise.
Minimal disturbances to existing tenancies
Savings in construction time.
Challenges solved through collaboration of
interested parties