You are on page 1of 22

Collaboration and Innovation in a

Post-Tensioned Waffle Slab.


Neeta City Shopping Centre
Shaun Sullivan

Structural Systems (Northern) Pty Ltd

Introduction
Collaborative Effort between
Contractor, Consultant & Specialist
Contractor

A Solution to your Weighty Problem


A Post Tensioned Waffle Slab
Structural Systems (Northern) Pty Ltd

Project Overview
Extension and refurbishment of the Neeta City Shopping Center,
Fairfield
Existing 1st Floor car-park converted to a new Big W Store.
Approx 5800m2
New Floor 300 to 400mm above the existing car-park floor.
Floor Live Load increased from 3kPa to 5KPa / 10kPa

Structural Systems (Northern) Pty Ltd

Project Constraints
Operating Woolworths supermarket in floor below +
carpark over
No space beneath could be used for construction
No significant construction noise during business hours.
Weight of new floor less than slab capacity.
Relatively long spans & falls in carpark

Structural Systems (Northern) Pty Ltd

External Upstand
Remained

Kerbs & Planter


Upstand Removed

Structural Systems (Northern) Pty Ltd

Existing Risers

Stormwater pipes
through slab

Structural Systems (Northern) Pty Ltd

Conforming RC Scheme
New waffle slab composite with existing PT floor
Dowels @ 250cts
& scabbling
existing concrete

Reinf. Mat typ +


extra bars at
columns

Locate existing tendons


Styrene void formers
Ribs @ 1600max cts

Existing Tendons

PLAN
Structural Systems (Northern) Pty Ltd

Construction Noise
Approx 30,000 Dowels & 8000m of 200wide scabbling
Scabbling and drilling outside business hours. Costly and timely!
Night

Local
Residents

Day

Woolworths Trading
Hours

Limited time to perform noisy work!

Structural Systems (Northern) Pty Ltd

Night

Local
Residents

Alternative PT Scheme
Post-tensioned waffle slab
Isolated from the existing floor surface.
Connection to Existing Columns by Dowels
Temporary IJ to existing columns to allow movement.

Structural Systems (Northern) Pty Ltd

Typical Scheme Details

200 wide ribs @ 1500 cts


Joint locations reflect existing slab
90mm thick RC slab between ribs
Pour strips for stressing access
Bond breaker to existing slab

Structural Systems (Northern) Pty Ltd

Structural Systems (Northern) Pty Ltd

Structural Systems (Northern) Pty Ltd

Structural Systems (Northern) Pty Ltd

Core Connections
Bars epoxied into core
Sleeved for movement
10mm isolation to
existing slab

Structural Systems (Northern) Pty Ltd

Why Isolate?
Typical Slab Columns deflect to accommodate PT force

As slab is poured directly on existing, columns cannot deflect - posttensioned force lost

Structural Systems (Northern) Pty Ltd

Column Connections
Column Reinf. Located
Oversized holes cores
Tapered isolation gap
(preformed metal mesh)
Grouted at 56 days

Structural Systems (Northern) Pty Ltd

Column Connections

Structural Systems (Northern) Pty Ltd

Back of House Hanging Load


Wider ribs (extra DL) required
in 10KPa area
Unable to prop from below
Load hung from carpark slab
over
Reidbar threaded
reinforcement & plates

Carpark

New Slab
Existing Slab
Woolworths

Structural Systems (Northern) Pty Ltd

Back of House Hanging Load

Structural Systems (Northern) Pty Ltd

Hanging Support
Very long span in 10Kpa area
Unable to span with available
depth
Room underneath slab not
available
Blade column introduced

Structural Systems (Northern) Pty Ltd

Curved Beam
Irregular column grid
Extra concrete and DL
required to span
Composite section used
similar to RC scheme

Structural Systems (Northern) Pty Ltd

Summary
PT solution eliminated significant amount of
construction noise.
Minimal disturbances to existing tenancies
Savings in construction time.
Challenges solved through collaboration of
interested parties
Thankyou

Structural Systems (Northern) Pty Ltd

You might also like