Professional Documents
Culture Documents
Virtually all design problems must have been resolved before the end of the final
design stage. Sufficient detail must be provided by the drawings and the report to
allow reasonably accurate estimates of construction and operating costs, as well as
the construction scheduling.
All revisions to construction materials, machinery, and equipment specifications
are made. The updated schedule, cost estimates and specifications are contained in
the final design report.
Once again, it is necessary to verify at the end of the final design stage that the
project remains economically viable. If, by some chance it is not, then a decision
must be made to revise design solutions or the original concepts, or perhaps
terminate the project.
Although it is an apparent and obvious assumption, it must be pointed out that any
changes at this stage are most costly. Final design is the most expensive of the
planning processes. It is therefore important that complete and detailed attention is
given throughout final design.
If final design drawings have to be substantially changed or repeated, the costs are
disproportionately high compared with the costs of the originals.
Stage 5 Construction
The construction phase is the period during which the Contractor or Principal
Contractor (for notifiable project only) takes possession of the construction site to
carry out the path construction and related feature works. When the works are
complete, the site is handed back to the client.
The construction phase does not tend to involve the Client as much on a day to day
basis, and the majority of actions and responsibilities, lie with other parties,
namely, the Project Manager (Clients representative), Designer, Clerk of Works,
CDM Co-ordinator, Principal Contractor or Contractor, and if required Subcontractors.
Once the Contractor has been appointed, they will commence the mobilisation
stage of construction phase, if required appointing Sub-contractors to complete
elements of work, and commencing site set up (welfare facilities, etc).
At this point the Project Manager will arrange the pre-start meeting, and check that
the Contractors insurances are in place. The CDM Co-ordinator will ensure that the
Principal Contractors construction phase health and safety plan and welfare
facilities are in place before site works commence.
During the Construction phase, the Contractor has the major responsibility in
planning and execution the path construction and any related feature works,
including managing, controlling and monitoring health and safety matters on site,
based on their construction phase health and safety plan.