Professional Documents
Culture Documents
The Finnish Forest Research Institute (Metla), Western Finland Regional Unit, Kaironiementie 15, FI-39700 Parkano, Finland
Tampere University of Technology, PO Box 527, FI-33101 Tampere, Finland
SUMMARY
This paper deals with the energy production and economics of a large-scale biomass-based combined heat and power (CHP)
plant. An activity-based costing model was developed for estimating the production costs of the heat and power of the
bio-CHP. A 100 MW plant (58 MW heat, 29 MW electricity) was used as reference. The production process was divided into
four stages: fuel handling, uidized bed boiler, turbine plant, and ue gas cleaning. The boiler accounted for close to 50% of the
production costs. The interest rates and the utilization rate of the CHP had a signicant effect on the protability. We found that
below 40004500 h per year utilization, the electricity production turned unprotable. However, the heat production remained
protable with high interest rate (10%) and a low utilization rate (4000 h). The protability also depended on the type of
biomass used. We found that, e.g. with moderate interest rates and high utilization rate of the plant, the bio-CHP plant
could afford wood and Reed canary grass as fuel sources. Copyright 2013 John Wiley & Sons, Ltd.
KEY WORDS
activity-based costing; combined heat and power; economics; biofuels; bioenergy
Correspondence
*Heikki Korpunen, The Finnish Forest Research Institute (Metla), Western Finland Regional Unit, Kaironiementie 15, FI-39700 Parkano,
Finland.
E-mail: heikki.korpunen@metla.
{
This article was published online on [29 April 2013]. Errors were subsequently identied in Table V. This notice is included in the online
and print versions to indicate that both have been corrected [14 June 2013].
Received 23 February 2012; Revised 22 February 2013; Accepted 3 March 2013
1. INTRODUCTION
Forest-based fuels are considered to be carbon neutral and to
have other environmental benets in comparison to fossil
fuels [1]. In Finland, the annual consumption of solid forest
fuels during the year 2010 was 5.4 million m3, and by the year
2020, the consumption of forest fuels is planned to be 1213
million m3 [2]. Therefore, forest fuels have become an increasingly important source of revenue to forest owners. The
consumption of these types of fuels has steadily increased,
and energy wood has now clearly gained the status of a timber
assortment instead of a mere by-product in timber procurement.
Because the consumption of energy wood in Finland has
increased 550% (in volume) over the past 10 years [2], the
economic signicance of energy wood has grown rapidly.
However, the Finnish government has strongly subsidized
the bioenergy sector, which complicates evaluating the cost effectiveness of the bioenergy business. The Government has
promised to support renewable energies substantially until
the year 2020. Some estimates of government assistance
state that by 2020 annual subsidies of 300 million euros for
Copyright 2013 John Wiley & Sons, Ltd.
Figure 1. The production processes in a CHP plant. Wide arrows represent material or energy ows such as screw or belt conveyors
and pipelines.
ACcapital
where:
ACcapital
PPv
SLy
I
r v
rv
#
I 1 ISLy
PPv
1 ISLy 1
(1)
(2)
admin
AClab
gd
AC
build
(3)
admin gen
gd
ACbuild
ACadmin gen
AC
admin r
EPr
ACadmin
EPtot
(4)
where:
341
ACadmin
EPr
EPtot
loader
WH HC
loader
(5)
1
X
AC
capital vr
v1
AClab
rp
ACinsur
where:
DOr
refr
Flowr
ref r
Flowr
(7)
n
X
ACtot DOr
r1
ref r
(8)
The net prot (PRnet) of each product in the entire process was calculated with the following equation:
PRnet Market price of end product-UCOtot
Market price of raw material
(9)
DOr
ACadmin r (6)
p1
ACloader
where:
l
m
ACinsur
m
X
Table I. General cost factors in a CHP plant. Labor and energy prices are annual Finnish averages from the year 2010. Energy prices
have been calculated from the Finnish Energy Market Authority (EMV) statistics [17].
Cost factor
Admin. working hours in a day
Admin. working days annually
General director labor cost
Process manager labor cost
Secretaries in administration
Secretary labor cost
Process worker labor cost
Indirect wage costs
Value
Unit
Cost factor
Value
Unit
8
220
35
25
2
17
20
70
h
days
/h
/h
person
/h
/h
%
25
300,000
20,000
3000
38
66.79
54.52
2.5
years
/year
/year
/h
/MWh
/MWh
MW
Table II. The cost factors of production processes in a CHP plant. The factors were used in the example calculations of this study.
Cost factor
Fuel handling
Investment to machinery
Investment to buildings
Annual insurance costs
Ground construction costs
Working hours in a day
Working days in a year
Process managers (in one shift)
Process workers (in one shift)
Secretary for fuel reception
Wheel loaders (in one shift)
Fluidized bed boiler
Investment to machinery
Investment to buildings
Annual insurance costs
Ground construction costs
Working hours in a day
Working days in a year
Process managers (in one shift)
Process workers (in one shift)
Value
Unit
3,351,300
876,000
43,890
773,000
24
365
1
1
1
2
/year
h
d
person
person
person
loaders
26,389,000
6,582,000
329,710
5,810,000
24
365
1
6
/year
h
d
person
person
Cost factor
Value
Unit
Turbine plant
Investment to machinery
Investment to buildings
Annual insurance costs
Ground construction costs
Working hours in a day
Working days in a year
Process managers (in one shift)
Process workers (in one shift)
13,970,000
3,480,000
174,500
3,075,000
24
365
1
3
/year
h
d
person
person
3,840,000
958,000
47,980
845,000
24
365
1
1
/year
h
d
person
person
Table III. Fuel properties and prices used in the example calculations of this study. The raw material market prices are Finnish annual
prices from the year 2010.
Fuel
Scots pine
Norway spruce
Reed canary grass
Energy share
in the fuel mix
90%
90%
10%
Basic density
Energy content,
MC 40%
Raw material
market price
(kg/m3)
(ton/MWh)
(/MWh)
4000 h
4500 h
5000 h
385
400
0.200
0.205
0.318
18.38
18.38
20
72,000
73,800
12,720
81,000
83,025
14,310
90,000
92,250
15,900
10%
Int. J. Energy Res. 2014; 38:339349 2013 John Wiley & Sons, Ltd.
DOI: 10.1002/er
343
Table IV. Annual energy ows for cost driver denitions (units in GWh).
Utilization rate
4000 h
4500 h
5000 h
Fuel handling
(GWh)
Fluidized bed
boiler (GWh)
Turbine
plant (GWh)
360
40
400
232
116
348
360
40
400
232
116
348
360
40
400
405
45
450
261
130.5
391.5
405
45
450
261
130.5
391.5
405
45
450
450
50
500
290
145
435
450
50
500
290
145
435
Flue gas
cleaning (GWh)
360
40
400
232
116
348
116
116
405
45
450
261
130.5
391.5
130.5
130.5
450
50
500
450
50
500
290
145
435
145
145
Table V. Total production costs, wood and Reed canary grass material costs, prots from heat and electricity, and the net prot of the
production in euros according to the plant utilization rate and the interest rate of capital costs (units in million ).
Utilization rate
4000 h
4500 h
5000 h
Interest rate
3%
10.35
1.96*
10.35
10.35
4.06*
5.04*
4%
10.81
5%
11.30
1.5*
1.0*
10.81
11.30
3.04*
10.81
4.58*
2.55*
11.30
4.09*
6%
11.81
7%
12.35
6.62*
0.8*
12.65
7.08*
0.5*
0.035*
11.81
12.35
7.44*
0.9*
14.23
7.97*
2.04*
1.5*
11.81
12.35
8.27*
1.0*
15.81
8.85*
3.58*
3.04*
8%
12.90
9%
13.47
10%
14.06
0.59*
1.16*
1.75*
12.90
13.47
14.06
0.95*
12.90
2.50*
0.38*
13.47
1.92*
0.21*
14.06
1.33*
Int. J. Energy Res. 2014; 38:339349 2013 John Wiley & Sons, Ltd.
DOI: 10.1002/er
10.3
17.2
Fuel handling
100%
Insurance
costs
90%
80%
Wheel loader
costs
70%
60%
50%
Cost of Reed
canary grass
40%
Capital costs
30%
Labor costs
20%
10%
Cost of wood
0%
3
10
345
Table VI. The net prots of wood and Reed canary grass materials in euros per solid cubic meter or ton according to the plant
utilization rate and the interest rate of capital costs.
Interest rate, %
Utilization rate
10
4000 h
Pine, /m (solid)
Spruce, /m3 (solid)
Reed canary grass, /ton
9.73
9.88
10.83
7.51
7.62
7.19
5.16
5.24
3.35
2.71
2.75
0.67
0.14
0.15
4.86
2.51
2.55
9.20
5.26
5.34
13.69
8.08
8.21
18.31
4500 h
15.25
15.49
19.86
13.28
13.48
16.63
11.19
11.37
13.22
9.01
9.15
9.65
6.73
6.84
5.92
4.37
4.44
2.06
1.93
1.96
1.93
0.58
0.59
6.04
5000 h
19.67
19.98
27.09
17.89
18.17
24.18
16.02
16.27
21.11
14.05
14.27
17.90
12.00
12.19
14.55
9.88
10.03
11.07
7.68
7.80
7.48
5.42
5.51
3.78
30
25
20
Pine, /m^3 (5,000 h)
15
10
5
0
-5
-10
Reed canary grass,
/MWh (4,000 h)
Spruce, /m^3 (4,000 h)
-15
-20
-25
3
10
Figure 4. The net prot (/MWh or /m3) of fuel raw materials according to plant utilization rate and interest rate.
3. DISCUSSION
As our study shows, the ABC method is very informative
tool for the energy production industry. Nevertheless, the
validity and reliability of the results depend on the input
data and the selected costing method. In this study, the data
was gathered from real participants in actual markets, and
346
20
Heat (5,000 h)
15
10
Heat (4,500 h)
Heat (4,000 h)
0
-5
Electricity (5,000 h)
-10
-15
Electricity (4,500 h)
-20
-25
Electricity (4,000 h)
3
6
7
8
Interest rate (%)
10
Figure 5. The net prot (/MWh) of heat and electricity according to power plant utilization rate and varying general interest rate (%).
4. CONCLUSIONS
The ABC method suits well the needs of the energy
production industry today. The ABC method provides
valuable information for decision making at many levels.
The idea of different fuel raw materials and two different
output energies would be difcult to manage in detail
without process denition and driver-based cost allocation.
The process-based thinking of the ABC can be useful
when tracing the weak spots in the production, since cost
control and the management of each process become easier
347
NOMENCLATURE
ACcapital r
PPv
SLy
I
AClab
r p
WH
WC
IWC
ACadmin
AClab adm
AClab
gd
ACbuild
ACadmin gen
ACadmin r
EPr
EPtot
ACloader
HCloader
l
m
ACinsur r
DOr
refr
Flowr
UCOtot
PRnet
n
REFERENCES
1. Kaltschmitt M, Reinhardt GA, Stelzer T. Life cycle
analysis of biofuels under different environmental
aspects. Biomass and Bioenergy 1997; 12(2):121134.
2. Finnish Statistical Yearbook of Forestry 2010. In Finnish
with English summary. Finnish Forest Research Institute:
Vantaa, 2011.
3. El-Sayed YM. The Thermoeconomics of Energy
Conversions. Elsevier: Oxford, 2003.
Int. J. Energy Res. 2014; 38:339349 2013 John Wiley & Sons, Ltd.
DOI: 10.1002/er
4. Dornburg V, Faaij APC. Efciency and economy of woodred energy systems in relation to scale regarding heat and
power generation using combustion and gasication technologies. Biomass and Bioenergy 2001; 21:91108.
5. Lappi P, Ollikka K, Ollikainen M. 2009. Optimal fuelmix in CHP plants under a stochastic permit price:
Risk-neutrality versus risk-aversion. Energy Policy
2010; 38:10791086.
6. Wang J-J, Jing Y-Y, Zhang C-F. Weighting methodologies in multi-criteria evaluations. International Journal
of Energy Research 2009; 33:10231039.
7. Wei L, Filip To SD, Pordesimo L, Batchelor W. Evaluation of micro-scale electricity generation cost using
biomass-derived synthetic gas through modeling. International Journal of Energy Research 2011; 35:9891003.
8. Sathre R, Gustavsson L. Process-based analysis of
added value in forest product industries. Forest Policy
and Economics 2009; 11:6575.
9. Turney PBB. Common Cents. How to Succeed with
Activity-Based Costing and Activity-Based Management.
McGraw-Hill: New York, 2005.
10. Kaplan RS, Anderson SR. Time-Driven Activity-Based
Costing. Harvard Business Review. November 2004:19.
11. Hsu H-P, Hsu H-M. Systematic modeling and implementation of a resource planning system for virtual
enterprise by Predicate/Transition net. Expert Systems
with Applications 2008; 35:18411857.
Int. J. Energy Res. 2014; 38:339349 2013 John Wiley & Sons, Ltd.
DOI: 10.1002/er
349