Professional Documents
Culture Documents
Their usage?
-
Service time is the time the ship stays at the berth whether it works or not.
Task: In Nov 23rd 2005, a container ship arrived at Amsterdam Port to load the cargo. At 9:00
am, the ship arrived at the port. However, all adequate service points had been occupied so the
ship had to wait for an available berth until 5:00 am on the next day and then started loading. It
finished loading work at 6:00 am in Nov 26th and was allowed to leave the berth 1hour later.
Question: Determine Waiting Ratio for the ship, assuming that Amsterdam Port operates 24
hours a day.
Solution:
Waiting time (9:00 am of Nov 23rd - 5:00 am of Nov 24th): WT = 20 hrs
Service time (5:00 am of Nov 24th 7:00 am of Nov 26th): ST = 50 hrs
20
Waiting Ratio 50 =0.4
Task:
There are two incoming ships A and B to Berth no.1 for discharging cargo. Ship A is served at
the berth as soon as it arrives at the port at 1 p.m. with handling time of 10 hrs. Ship B arrives at
the port at 2 p.m. with 4 hrs handling. Two ships leave the berth right after finishing their
discharging.
Question: Determine Service Time Ratio for Berth no.1, assuming that the length of Berth no.1 is
not long enough to serve two ships at one time and the port operates 24hrs a day.
Solution:
ST of Ship A = 10 hrs
ST of Ship B = 4 hrs
Service Time Ratio
10+ 4
=7 (hrs )
2
The total time the ship spends in the port from arrival at the port to final departure
Cumulated WT + ST
Total Number of Ships
Task:
There are two incoming ships A and B to Berth no.1 for discharging cargo. Ship A is served at
the berth as soon as it arrives at the port at 1 p.m. with handling time of 10 hrs. Ship B arrives at
the port at 2 p.m. with 4 hrs handling. Two ships leave the berth right after finishing their
discharging.
Question: Determine Turnaround Time Ratio for Berth no.1, assuming that the berth is not long
enough to serve two ships at one time and the port operates 24 hours a day.
Solution:
Ship A: WTA + STA = 0 + 10 = 10 (hrs)
Ship B: WTB + STB = 9 + 4 = 13 (hrs)
Turnaround Ratio
10+13
=11.5(hrs )
2
10% is acceptable
Lower is better
Task: In 2000, Port X has cumulated Service Time and cumulated Waiting Time as 8,000 and
1,750 hrs respectively.
Question:
a)
b)
Solution:
a)
GW Ratio=
1,750
0.219 21.9
8,000
3
7,500
0.856
8,760
85.6%
Task:
A vessel arrived at the berth at 4 a.m. and started unloading the cargo. Because of the rainfall
from 7 a.m. to 10 a.m., the vessel had to stop temporarily and then continued working. At 2 p.m.,
the unloading crane was broken down and spent 1.5 hrs to repair. The vessel finished unloading
at 5 p.m. on the same day.
Question: Determine Berth Working Time Ratio
Solution:
Total Service Time (4 a.m. 5 p.m.) = 13 (hrs)
Total Time Worked = 13 3 1.5 = 8.5 (hrs)
Berth Working Time Ratio=
8.5
0.65
13
65%
Total tonnagehandled
Total hours port
Total tonnagehandled
Total hours worked
Total tonnagehandled
Total hours on berth
Task:
In the first week of January ship arrived at the port at 5 a.m., waited for a free berth until 7 a.m.
and then started loading the cargo. The crane was broken down from 9:30 a.m. - 1:30 p.m. After
loading totally 1,350 tonnes of the cargo, the ship was let go at 5 p.m. on the same day.
Question:
a) Determine Port Ship Output
b) Determine Berth Ship Output
c) Determine Working Ship Output
Solution:
Total tonnage handled = 1,350 tonnes
Total hours in port (5 a.m. - 5 p.m.) = 12 hrs
Total hours on berth = 12- 2 = 10 hrs
Total hours worked = 10 4 = 6 hrs
Port SO =
Berth SO =
1,350
12
1,350
10
= 112.5 tonnes/hr
= 135 tonnes/hr
Working SO =
1,350
6
= 225 tonnes/hr
Tonnage handled
Average Output/Gang/Hour Total gang x hours worked
Task: The table shows the gangs used to handle the cargo in Port no.1 on the same day with the
following information:
Number of Gangs
Ship
Working hours
Tonnage handled
02
16
1,200
04
10
1,500
03
12
2,000
1,200+1,500+2,000
2 x 16+ 4 x 10+3 x 12
9
3
= 43.5 (tonnes/gang/hr)
= 3 (gangs)
Task: Calculate Utilization Rate of the crane in Port X, assuming that its total available time for
use is 147 hrs/week and the time it actually operates to handle the cargo is 86 hrs/week.
Solution:
Rate of Utilization of Crane =
86
147
= 0.59 = 59%
Task:
Containerized Cargo
TEU
20
35
30
10
20 x 6+35 x 3+30 x 10
20+35+30
= 6.2 days
Service
Opening hours
Non-coordinated hours
Tugs/ pilots
06:00 22:00
Handling
00:00 24:00
Customs clearance
08:00 18:00
Delivery/ receipt
06:00 20:00
Port office
07:00 17:00
Total
Solution:
Service
Opening hours
Non-coordinated hours
Tugs/ pilots
06:00 22:00
08 hrs
Handling
00:00 24:00
0 hr
Customs clearance
08:00 18:00
14 hrs
Delivery/ receipt
06:00 20:00
10 hrs
Port office
07:00 17:00
12 hrs
Total
46 hrs
= 46/24
Total
delayed
Number of ship calls
Task: During the first month of 2013, U.S. Port had 75 ship calls. Total delayed times of these
calls is 10.
Question: Determine Punctuality Ratio
Solution:
10
75
Punctuality Ratio =
= 13.3%
Task:
In 2005, Port X has total scheduled working days of 350 days. Because of 2 strikes lasting for 28
days and 10 days respectively, Port X had to stop working temporarily.
Question: Determine Reliability Ratio of Port X
Solution:
Reliability Ratio =
350 (28+10)
350
= 89%
V. BERTH CAPACITY
Annual Maximum Berth Capacity:
1.
2.
3.
12-15
Bags
20-25
Pre-slung bags
40-50
Pallets
25-40
Containerized cargo:
Gantry crane
200-250
Ship crane
120-150
RO RO
300-500
Dry bulk
1,000
Task:
In Port X, there are 6 berths in the general cargo terminal with the followings:
Tons/gang/worked hour: 20 tonnes;
Number of gangs/Ship: 3 gangs;
Worked time/Service time: 60%;
Maximum berth occupancy ratio: 74%
Question: Calculate the maximum capacity of the terminal for general cargo
Solution:
Tonnes/Ship/worked hour = 20 x 3 = 60 tonnes
Tonnes/Service hour = 60 x 0.6 = 36 tonnes
Annual Maximum Berth Capacity = 36 x 24 x 365 x 0.74 x 6 = 1,400,198.4 tonnes for the 6
berth terminal
VI. STORAGE CAPACITY
Storage Capacity:
Storage Capacity =
= 876,712 tonnes
11