Professional Documents
Culture Documents
Success Story
Collection
00A01A53-01E
Vigilan
tPlant Su
ccess Stories
Power
Contents
01
Eraring Energy
29
03
31
05
33
07
35
Kraftszer Kft
11
Macquarie Generation
37
13
39
15
41
PNOC-EDC
17
43
19
45
21
47
23
SC Electrocentrale Bucuresti SA
49
25
51
Lakeside EFW
27
Seeing clearly gives you the knowledge necessary to anticipate the changes required in your process.
Knowing in advance brings you the speed and flexibility to optimize your plant in real time.
And by acting with agility,
you are able to adapt to the ups and downs of your business environment.
VigilantPlant excels at bringing out the best in your plant and your people - keeping them fully aware,
well informed, and ready to face the next challenge.
Australia
Power
Plant
name: Eraring Power Station
Location:
Location:
Project type: New South Wales, Australia
Project
type: Plant revamping
Plant type:
Plant
type: Coal-fired power plant
Output:
Output:
Order date: 4 x 660MW
Order
date: 2003
Completion:
Completion: August 2004-2005
Eraring Energy
Yokogawa met these requirements for integrated device management across the HART protocol with a combination of its CENTUM CS 3000
DCS and its Plant Resource Manager (PRM) software. The new system integrates all field information into a single database on a PRM server
and allows real-time, remote maintenance of many hundreds of devices, including around 500 EJA transmitters, via the DCS networks and
HART I/O modules. The open architecture of PRM will also allow the diagnostics of smart Fisher valve positioners via the Yokogawa DCS just
by loading diagnostic plug-in software onto the PRM server. This integrated maintenance solution helped Erarings maintenance crew streamline
plant maintenance work.
Another challenge was the tight commissioning schedule. The first outage was planned 15 months after the initial order. To minimize the time
taken for the control system replacement, Yokogawa proposed a unique solution making full use of the capabilities of the Yokogawa DCS and
simulator.
The CENTUM has a unique engineering test function that enables an application functional test on a general-purpose PC without any real
controller hardware. Yokogawa affiliate TechComm Simulation developed the high-fidelity simulation system based on the detailed plant
documentation supplied by the customer. Combining these capabilities, Yokogawa engineers were able to very extensively test the new control
system on the simulator prior to DCS commissioning, thereby minimizing the final tuning work once the unit returned to service.
Eraring plant operators were well trained in the new control system utilizing the simulator. This avoided mistakes that could have occurred if they
had not been familiar with the new system, ensuring a smooth plant commissioning process.
Background
Eraring Power Station, located just north of Sydney, is one of the largest power stations in Australia, comprising four 660MW coal-fired units.
The power station has operated reliably since 1981. To ensure continued reliability for the next few decades, Eraring Energy, the owner
of the power plant, decided to replace the original hard-wired control equipment with a modern integrated control and monitoring system
(ICMS). Significant project drivers were the requirements to maintain plant reliability and to gain operational improvements in order to ensure
the competitiveness in the deregulated Australian power market. The re-instrumentation work started in early 2003 under the leadership of
Yokogawa Australia, which teamed up with TechComm Simulation, a wholly owned Yokogawa subsidiary.
The customer required an integrated system to control the operation of the boilers, turbines, generators and other balance of plant equipment.
Yokogawa proposed an integrated solution comprised of a distributed control system (DCS), plant information management system, field device
management system, full-replica training simulator and field instruments together with strong local support.
System maintainability
Another important issue to be considered was system maintainability. From the late 1990s (before the control system replacement), the
customer had progressively upgraded its analog field instruments selecting Yokogawa DPharp EJA transmitters as well as other vendors
devices. A further requirement was to upgrade the original paper-based field device management system to a Windows-based, user-friendly tool
which integrates various data from multivender HART and analogue devices into a single database. The customer wanted system compatibility
with the DCS and used the opportunity of the plant revamping to achieve tight integration of the field device management system into the DCS.
The Eraring plant has four large units with a total system input/output (I/O) count of more than 40,000 as well as 25,000 interfaces to other plant
auxiliary systems. Yokogawas CENTUM CS 3000 R3 DCS supported this large application in a single architecture while ensuring reliable plant
operation with itspair&spare non-stop controller technology.
To satisfy the need for further operational improvement, a Yokogawa Exaquantum plant information management system was used for longterm data storage, data and alarm logging, and performance calculation. The users can monitor the graphical data for both current and historical
plant information in an Exaquantum window at their own PCs using the Eraring wide area network. This makes it easier for operators and plant
managers to keep informed and to make decisions for future plant operation.
The customer also desired to improve plant operation in the aspects of human resources and operating environment. Yokogawas high fidelity,
full-replica simulator enabled custom-made operator training that fully replicated the characteristics of the Eraring Power Station. This allowed
the operators to be familiar with all aspects of plant operation using the new control system before running the real plant.
The original analog-based control room was replaced with a new control room which is based on the latest ergonomic design, securing
operators higher performance.
The Results
Faster commissioning
The four units at Eraring are being retrofitted progressively, with
the first changeover in August 2004 and the second unit being
completed at the beginning of 2005. The customer was very
pleased that Yokogawa has completed return to service of the first
unit ahead of schedule, with the second unit approximately two
weeks early and similar results expected for the third and fourth
units.
Efficient operation ensuring high reliability
The renovated units give very stable, and at the same time more
flexible operation than before. After the revamping, the customer
now makes everyday load changes at a rate faster than with the
previous control system. This can provide financial benefits in the
competitive Australian electricity market.
Efficient maintenance
Integrated device management enables predictive maintenance, reducing routine maintenance work. Jeff Hogan, Power Station Technicians
Supervisor of Eraring Energy said, The upgrading of field instrument is still in progress but PRM has provided access from our workshop to all
smart instruments on site. When a plant problem occurs we are able to verify the validity of reading and configuration settings of the associated
instrument within a couple of minutes. A great diagnostic tool which enhances the Yokogawa CS3000 System.
System Details
CENTUM CS3000 R3
Exaquantum
Plant Resource Manager (PRM)
TechComm full-replica training simulator
EJA series electronic pressure transmitters, GD series gas density meters
Full functional requirements design, control system software development, factory
acceptance, installation, commissioning & tuning
USA
Power
We decided to handle all the new-system installation in-house, said Stodden. That way our personnel would be very familiar with everything
involved. We were delighted with how smoothly the entire procedure went, and we completed installation in only six weeks. We had virtually no
problems with the CS 3000 hardware or software. Our biggest obstacle was moving the electrical interlocks required to combine the two control
rooms into one. If the Yokogawa system had not worked so well, we would never have made our startup dates.
Originally, he continued, Units 1 and 2 were housed in one control room, while Units 3, 4 and 5 were housed in a separate control room. As
part of this project, we combined these into one. The new system has worked so well, that we now utilize one control operator to run both Units
1 and 2, where before each unit had a dedicated control operator assigned to each unit.
Units 3, 4 and 5 use a hybrid configuration. These units are equipped with an older control system platform, utilizing Hand-Auto Stations for
operator interface. This control system, while dated, is still supported. Therefore, as a step toward uniformity among the units, we utilize the
Yokogawa Operator Console Platform to communicate with the older control system hardware already in place. The operators see the same
style of operator screens as Units 1 and 2, without realizing that it is utilizing a completely different control system. Annunciators and selected
other functions work directly from the CS 3000 control; control loops are displayed on the CS 3000 screens but are processing existing control
loops through an interface.
When asked about acceptance by operators of the new electronic system, Stodden illustrated by quoting one of the men who initially said he
thought the new system was the worst decision we had ever made. But within two months after startup, the same operator asked When are
we going to do the other three units? Suffice it to say that by now our operators are very comfortable and pleased.
Background
In 1957, the City Utilities of Springfield, MO, commissioned a pneumatic distributed control system for its James River Power Plant. At that time,
the plant was considered very advanced because it utilized a centralized control room for operations, instead of a series of separate control
stations located throughout the facility.
Through the years since, explained Maintenance Manager Steve Stodden, we had attempted to keep the existing systemfunctional, but
maintaining a 50-year-old system has proven difficult. Several years ago we started discussions with all plantpersonnel involved about upgrading
the old control system to improve the safety of the plant and to take advantage of modern digital technology. The result is that we now operate
our five generating units with varying stages of a new CS 3000 control system from Yokogawa.
The CS 3000 system has provided the ability for automatic control sequences not previously practical. For example, shutting down a coal feeder
used to require many control manipulations to maintain safe operation of the boiler. The entire sequence is now automatic. We just hit a key
and sit back to watch everything progress through the control sequence, said Stodden with a satisfied smile.
The plant, which celebrated its 50th anniversary in 2007, consists of five coalfired boilers equipped with steam turbines and two natural-gas-fired
turbines. The plant initially was designed to utilize natural gas as its primary fuel, with coal as a winter backup fuel. This switched during the late
1970s driven by the Power Plant and Industrial Fuel Use Act of 1978. The station now utilizes less than 1% natural gas for fuel for the steam
boilers.
Ultra low-NOX burners and overfire air(OFA) were introduced
later to greatly reduce nitrogen oxide emissions in
preparation for EPA standards that went into effect in 2009.
All units of the James River Power Station remain capable
of burning either 100% coal or 100% natural gas in order to
produce electricity.
With the vendor selected, system details were then examined. The initial bid was based on 4-20
mA protocol but replaced by FOUNDATION fieldbus (FF) as advantages of FF emerged. The
plant has five generating units with a total capacity of 253 MW (two 22 MW, one 44 MW, one 60
MW, and one 105 MW).
CENTUM CS 3000
System Configuration
System Details
System:
CENTUM CS 3000
Total I/O:
Approximately 1,400
System configuration: 9 x HIS, 1 x EWS, 1 x SIOS, 1 x GSGW
Other:
PRM (Plant Resource Manager), FF, Bailey INFI90 interface
Scope:
System, project management, design, configuration engineering, commissioning services
Vietnam
Power
Executive Summary
With a power generating capacity of 600 MW, Pha Lai 2 is the largest coal-fired plant in Vietnam. As part of a master plan by the Vietnam
Ministry of Industry to meet rapidly rising demand for power by doubling the countrys generating capacity, the power station was constructed
at a cost of $540 million by Electric of Vietnam (EVN). Located approximately 65 km northeast of Hanoi, Pha Lai 2 and the adjacent Pha Lai
1 power station (a Russian-built facility with eight 220 t/h coal-fired boilers and four 110 MW turbines) are owned and operated by a wholly
owned EVN subsidiary, Pha Lai Thermo Power Joint Stock Company. (PPC). It is estimated that the two power stations supply approximately
80% of Hanois power. In accordance with the Ministry of Industrys master plan, no more than 20% of their power is allotted to private power
companies, and the remainder goes to EVN.
In 2002, Yokogawa successfully designed, installed,
and commissioned a CENTUM CS 3000 distributed
control system (DCS) for the Pha Lai 2 power station,
and it has operated to date without any significant
problems. Along with the Yokogawa DCS, a full
replica plant simulator was installed to provide plant
operator training. The DCS and all related systems are
maintained by Yokogawa Vietnam under the terms of
an annual maintenance contract.
Customer Satisfaction
Nguyen Khac Son, PPCs Chief Executive Officer, said, We are very happy to be using the Yokogawa CENTUM CS 3000 process control
system. We are now operating nonstop without any major problems, using Yokogawas system and field transmitters. We are operating near
capacity almost every day and are sending this power to the national grid. Continuous operation is a very important point. He continued, The
CENTUM CS 3000 is the brain of this power station and the field transmitters are important sensors for monitoring all power plant equipment
and processes. We have a good relationship with Yokogawa Vietnam and look to working with them in the future.
Plant Details
Systems Delivered
Mongolia
Power
Executive Summary
In Mongolia, temperatures fall as low as -40 in mid-winter. The heat and electricity generated by Thermal Power Plant No. 4 (TES4) in the
capital city of Ulaanbaatar is an important lifeline for the people living there. This is the largest coal fired power plant in Mongolia and it generates
70% of the electricity for Mongolias central energy system and 65% of the heat energy used by the Ulaanbaatar district heating system.
TES4 was built many years ago and has been severely affected by the scarcity of spare parts for its legacy systems. Plant shutdowns were a
frequent occurrence due to equipment malfunctions and accidents, disrupting the supply of heat and power. In addition, the plant caused severe
air pollution due to inefficient control of coal combustion. Efforts to correct these problems were also hampered by the loss of many of the plants
original blueprints and other design related documents.
To solve these problems, the Mongolian government decided to execute a plant revamping project in two phases using an official development
assistance (ODA) loan. Phase one for boilers one to four started in 1998 and was completed in 2001. Phase two for boilers five to eight started
in 2001 and was completed in 2007. For this project, Yokogawa delivered control systems and field instrumentation for all eight boilers.
TES4 in winter
The Challenges
The original combustion system used indirect firing, with pulverized coal being transferred from a storage silo whenever the boiler was started
up. With the exception of feed water control, all the boilers and mill burners were manually controlled by operators. There were many equipment
problems and a high risk of explosions, and combustion was extremely low.
In addition, there were just a few of the original blueprints dating back to when the plant was built in the 1980s, and none showed the boiler
First of all, information had to be gathered that would provide a starting point for
the automation design. This was followed by conversion to a direct firing boiler
combustion system in which pulverized coal is directly loaded into the boilers and the
replacement of the old mill burner control systems with a Yokogawa DCS.
Automation of boilers, burners, and balance of plant facilities and changeover
to a new boiler combustion system
To meet the customers requirements for changing the old indirect combustion
system to a direct combustion system, a Yokogawa project team of Russian, English,
Mongolian, and Japanese speakers conducted a detailed investigation of the original
boiler combustion control system and coordinated its activities with a new burner
vendor. They had to crawl around every nook and cranny of this plant to create a
piping & instrument diagram (P&ID) and a cabling drawing that accurately described
the plant configuration. This was dirty and challenging work and it took many days to
complete. Finally they succeeded in bringing together the documentation needed to
design the automation for the plants boilers, burners, and balance of plant facilities
and change to a direct firing boiler combustion system.
Mongolia
Power
10
276
87% reduction
From 1997 to 2007
250
222
16
13.9
12
205
10.3
200
8
102
4.8 4.8
82
3.9
2.8
2005
2004
2001
2000
Year
1999
1997
2006
37
2005
2003
2002
2001
2000
1999
1998
1997
50
2004
47
4.0
64
2007
63
4.8
1.9
1.7
2007
69
2003
100
7.3
2006
127
2002
150
88% reduction
From 1997 to 2007
1998
300
Kilo ton
Year
Customer Satisfaction
More than a year after phase one was fully completed, one of the four boilers
caused a trip. Yokogawa dispatched engineers immediately and made every
effort to solve the problem. The investigation found that the boiler trip was caused
by a malfunction in one of the conventional components left over the old plant
control system. Even though a Yokogawa product was not at fault, the companys
engineers provided the TES4 engineers the support they needed to get the plant
safely operating again.
Mr. Tseveen, Executive Director of TES4, says, Seeing is believing. Whatever
beautiful things sales people say, I will not believe until I see them at work. When
we experienced the plant trip, I learned what makes Yokogawa different from
others. I admire their sincerity and devotion toward customers.
Mr. Tseveen
Executive Director of TES4
11
Australia
Power
Macquarie Generation
Plant Information
Plant
Information
Plant name:
Plant
name: Liddell Power Station
Location:
Location:
Project type: New South Wales, Australia
Project
type: Plant revamping
Plant type:
Plant
type: Coal-fired power plant
Output:
Output:
Order date: 4 x 500MW
Order
date: 2000
Completion:
Completion: 2004
Executive Summary
Macquarie Generations Liddell Power Station is located near Muswellbrook, NSW, approximately 200km north of Sydney in the Hunter Valley. It
comprises four coal-fired boiler steam turbine generator sets, each unit of 500MW capacity.
The project consisted of the replacement of all existing process controls and monitoring and protection systems on each unit as well as the
common station plant equipment. In addition, a substantial part of the field devices were replaced or new loops installed. Complete design and
installation services were also included in the scope, and were provided by Yokogawa Australia in conjunction with alliance partner DownerRML. An Exaquantum Process Information Management System was installed to handle the normal data history, comprising 20,000 tags per
unit plus an additional 20,000 tags for the system common components, making a total of 100,000 tags for the complete system.
The first unit controls were implemented in the new control system in 2002, followed by the common station plant controls. Thereafter, each
subsequent unit will be installed progressively, culminating in final completion in 2004.
The entire project is being conducted under an alliance contract, with the alliance partners comprising Macquarie Generation, Yokogawa
Australia, and Downer-RML as the installation contractor. The alliance arrangement includes the concept of a target price which is the estimated
cost price for completing the work, and which is agreed to by all partners after the completion of the up-front engineering specification.
Payment is made by Macquarie to the alliance partners on the basis of how close the final cost is to the target price, and whether a set of Key
Performance Indicators are met or exceeded.
The CENTUM CS 3000 distributed control system controls all aspects of the project, including all associated plant units. Yokogawas Sydney
and Melbourne offices joined forces on the pursuit of the project with the engineering being performed by the Sydney office.
12
System Details
System:
CENTUM CS 3000
Total I/O:
approximately 30,000
System Configuration: 12x HIS, 20x Screens, 2x EWS
Other:
Exaquantum Information Management system
Scope:
System, project management, design, configuration engineering, installation, commissioning services
13
Japan
Power
14
Plant Information
Plant name: Tachibanawan Thermal Power Station
Location:
Tokushima, Japan
Project type: New
Plant type: Flue gas desulfurization
Output:
2 x 1,050 MW
Order date: 1997
Completion: 2000
Executive Summary
One of Japans largest coal-fired power plants, with advanced environmental protection measures
- Supplies electricity to a wide area in western Japan (Kansai, Chugoku, Shikoku, and Kyushu)
- Has the largest coal-fired generation units in Japan, each with an output of 1,050 MW
- Protects environment by removing NOx/SOx emissions and ash dust, and recycling fly ash
- Integrated control and monitoring of the environmental facilities, supported by Yokogawas highly-reliable CENTUM system and state-of-art
large displays
Background
The Tachibanawan Thermal Power Station is owned by Electric Power Development Co., Ltd. and is located in Anan City, Tokushima Prefecture.
With two 1,050 MW generating units, it is one of the largest coal-fired power plants in Japan.
The station entered commercial operation in 2000 and supplies electricity to a wide area in western Japan through four power utilities that serve
the Kansai, Chugoku, Shikoku, and Kyushu regions.
The plant is well known not only for its stable electricity supply but also its environmental protection measures. The plant layout was optimized
to keep the site size to a minimum, and colors were selected that matched the scenic surroundings of the Seto Inland Sea area. Part of the
fly ash from the combustion process is recycled to make cement. To prevent air pollution, state-of-art environmental control facilities such as
Flue Gas Desulfurization (FGD) systems were installed, removing NOx, SOx and ash dust. In 2004 this plant received ISO14001 certification,
demonstrating that its environmental protection measures meet international standards.
System Details
Output: 2 x 1,050 MW
Control system for environmental control facilities: CENTUM CS
15
Japan
Power
Executive Summary
Flexible operation of circulating fluidized bed (CFB) facility by independent power producer (IPP)
- 149 MW coal-fired power plant operated by IPP
- First use of circulating fluidized bed (CFB) boiler by IPP in Japan
- Fly ash recycled at adjacent cement plant
- Daily operation in swing mode and shutdown/startup responding to shifts in electricity demand
- Controlled by Yokogawas CENTUM system
16
Control room
Background
The Itoigawa Power Plant was constructed adjacent to a cement plant in Itoigawa City, Niigata Prefecture, and is operated by an IPP that
supplies electricity to Tohoku Electric Power, one of Japans major power companies. The use of a 149 MW coal-fired CFB boiler in this power
plant is a first for an IPP in Japan, and this effectively reduces NOx emissions. This power plant also recycles at an adjacent cement plant the fly
ash that is the byproduct of coal combustion.
System Details
System:
Total I/O:
System configuration:
Scope:
CENTUM CS
Aprox. 1,500
4 x HIS, 1 x EWS, 4 x FCD
System, project management, design, configuration engineering, commissioning services
17
Singapore
Power
18
A full-scope, high-fidelity training simulator supplied by Yokogawa enabled a simulator training in all aspects of operating complex plant systems
and has made a significant contribution in raising the skill levels of the highly motivated Tuas Power Station workforce.
Executive Summary
Yokogawa also designed the Tuas Power Stations central control room (CCR), which has won praise from users for its good operating
environment. Our CCR design methodology emphasizes the importance of sound ergonomic design in reducing operator errors and facilitating
the smooth running and control of processes.
The Tuas Power Station and its associated facilities are located on reclaimed land along the western shore of Singapore. The station occupies
an area of approximately 75 hectares and is being built in two stages.
Stage I of Tuas Power Station is comprised of two 600 MW oil-fired steam-generating sets. The power station entered commercial operation in
March 1999 when the first of these units was fully commissioned.
As part of its work in stage I of this project, Yokogawa supplied the CENTUM CS integrated production control system (DCS) for the plants
very large power generation units. Yokogawa Electric Asia Pte. Ltd., Singapore produced the control system in Singapore and carried out all
engineering work.
In addition to supplying Instrumentation & Control (I&C) equipment, Yokogawa handled system design/engineering, configuration, project
management, commissioning services and maintenance.
The Tuas Power Station successfully entered commercial operation on schedule and the plant owner has attributed this in part to Yokogawas
good performance in delivering both products and services.
The development of Stage II comprised of four-block combined cycle power plants was completed in September 2005, which brought the Station
to its licensed capacity of 2,670 MW.
System Details
System:
CENTUM CS
Total I/O:
43,410 (DIO: 37,300, AIO: 5,840)
System configuration: 51 x FCS, 3 x EWS, 29 x operation monitors, 4 x alarm monitors, 2 x CCTV, 3 x sequence-of-events manager/visual
annunciator systems, 2 x on-line performance monitoring systems, 3 x historian systems
19
Korea
Power
To ensure that the commissioning process for its new plant went smoothly, KOSEP turned to Yokogawa and its TechComm
Simulation subsidiary for a full-replica training simulator solution.
The purpose of this full-replica training simulator was twofold:
- To conduct a thorough, off-line test and validation of the DCS configuration prior to the control systems actual loading and commissioning at
the plant.
- To aid in the initial/refresher training of plant operators, which was conducted in parallel with the plant commissioning.
To achieve these objectives, the simulator was required to fully stimulate DCS functions and emulate turbine, generator, and electrical control
functions. Yokogawas full-replica simulator met the customers requirements with high accuracy (> 99% steady state; >95% dynamic state),
calculation of models at less than 250msec per cycle, and the ability to perform performance tests and a wide variety of simulations including
startups, shutdowns, and load changes under normal, abnormal, and emergency operating conditions.
Executive Summary
Background
In Korea, steadily growing demand for electricity together with limited indigenous energy resources and a heightened environmental awareness
have required additional power generation facilities with improved efficiency and environmental performance. Korea South East Power Co., Ltd.
(KOSEP), a wholly owned subsidiary of the government-owned Korean Electric Power Company, constructed two new 800 MW supercritical
coal-fired units in Yonghung, Korea to generate highly efficient, environmentally friendly electricity.
The simulator was delivered on-schedule to the site in September 2002, twelve months before the boiler was to be fired up for the first time. In
collaboration with the DCS manufacturer and Yokogawa, the customer proceeded to test and validate the DCS configuration on the simulator,
conducting an I/O checkout, drive checks, sequence checks, control module checks/tuning, alarm/trip setting, and DCS response checks as well
as tests in which malfunctions and other abnormal situations were simulated. This enabled thorough validation of the control configuration prior
to DCS installation at the site, thereby minimizing the final tuning work. A significant number of potential plant trips and incidents where there was
potential for damage to the plant were identified and resolved before the initial plant startup, ensuring a safe and smooth plant commissioning
process.
Plant Details
Owner:
Output:
Plant efficiency:
Operation mode:
Fuel:
Boiler type:
Turbine:
Generator:
Simulator system:
20
21
Spain
Power
22
In Spain, the demand for electricity and imported natural gas has been rapidly increasing, a trend that is anticipated to continue for years to
come. To augment the countrys energy supply, several new LNG regasfication plants as well as combined cycle gas turbine plants have been
constructed in Spain.
Customer Satisfaction
The SIEMSA engineer commented, We appreciate CENTUM CS 3000s operationality and system reliability. With the UOI solution, the DCS
controls use the same HMI system as the turbine and electrical control system, and there is no need for a dedicated communication gateway
and separate screens. This significantly reduces the engineering time and costs.
To achieve a stable supply of gas and electricity for the country, the Spanish government decided to build the Bahia de Bizkaia Plant. Located in
Bilbao, this plant consists of Bahia de Bizkaia Electricidad (BBE), an 800 MW gas fired combined cycle power station, and Bahia de Bizkaia Gas
(BBG), a regasification facility with regasificators having a total capacity of 2.7 billion cubic meters.
The Bahia de Bizkaia Plant was one of the most significant power projects to be carried out in this region. The project was led and financed by
Ente Vasco de la Energia, Repsol-YPF, British Petroleum, and Iberdrole S.A., with the total investment of approximately 600 million euros.
System Details
23
24
Romania
Power
SC Electrocentrale Bucuresti SA
The Solutions
Unified
UnifiedOperator
OperatorInterface
Interface
Interfa
f ce(UOI)
(UOI)
Data/Message from
Turbine Project
UOI
UOI
Data/Message from
HRSG/BOP Project
UOI
UOI
UOI viewers
(CIMPLICITY)
UOI
Ethernet
tion
Configuration
PC
UOI Server(s)
(CIMPLICITY
Server)
CIMPLICITY
T
Servers
Unit Data
ata Highway for
f r Mark
fo
k VI
Mark VI
ne)
(for Gas Turbin
Turbine)
CENTUM CS
3000 Builder PC
Siemens S7
(fo
f r Steam Turbine
e)
(for
Turbine)
ProSafe RS
SCS(s)
(for safety)
CENTUM CS
3000 FCS(s)
(for HRSG)
CENTUM CS
3000 FCS(s)
(for BOP)
HRSG/BOP
H
RRSSGG//BBOOPPa
and
nnddS
Safe
Safety
aaffeetty
Control
oonnttrrooll
H
a
S
tyyC
C
HRSG/BOP
and
Safety
Control
by
b
Yokogawa
ookkooggaaw
byyY
Y
waa
by
Yokogawa
TT
Turbine
uurrbbiinneeControl
CControl
bby
Turbine
Coonnttrroollby
byy
General
G
eenneerraallE
Electric
lleeccttrriiccC
Company
G
E
Coom
mppaannyy
General
Electric
Company
(Condensate system)
The turbine graphics and other system graphics are shown right. With these
graphics at the CENTUM CS 3000/UOI stations, operators can monitor and
control all the plants different systems with the same look and feel.
The Bucurresti Vest Combined Cycle Heat and Power Plant (CCHP) is located in the Romanian capital of Bucharest and supplies both electricity
and heat to this city. Sited next to two existing 125 MW plants, it was built to meet Romanias rising demand for electric power.
The owner of the plant is SC Electrocentrale Bucureti SA (ELCEN), a major energy supplier in Romania that accounts for approximately 20% of
the nations power generation capacity. ELCENs thermal power plants generate over 2 gigawatts (GW) of electricity, of which 1 GW is supplied
directly to the city of Bucharest.
The Bucuresti Vest CCHP consists of a GE 9E gas turbine that generates up to 135 MW, a heat recovery steam generator (HRSG)
manufactured by Austrian Energy and Environment, and a SKODA steam turbine that generates up to 60 MW.
The main contractor for this plant construction project was the Combined Cycle Division of VA Tech Hydro AG (integrated into the Andritz Group
in 2006). VA Tech Hydros scope of supply included the complete electrical systems and instrumentation and control, all auxiliary plant units such
as gas supply, and all structural engineering. Yokogawa provided the CENTUM CS 3000/UOI distributed control system (DCS), ProSafe-RS
Safety Instrumented System, and the Exaquantum Plant Information Management System, as well as engineering, installation, commissioning,
and operator training services.
The project was executed in a professional manner. The construction period was kept short less than 30 months net to facilitate a rapid
return on investment.
Yokogawas state-of-theart plant control system contributes significantly to high degree of plant automation and plant reliability.
Customer Satisfaction
VA Tech Hydro chose Yokogawas automation system for this project because of the demonstrated capabilities of the CENTUM CS 3000
control system in power plant applications and its compliance with the relevant VGB guidelines. An additional factor leading to this decision was
this systems use of redundant Profibus cards in keeping with the Profibus decentralized periphery (DP) concept and its support of IEC60870
communication profiles.
The design and structure of the CENTUM CS 3000 DCS for this new power plant met this customers high expectations in terms of availability
and operational reliability.
At the operator desk in front of the HMI operator station, the merits of Yokogawas UOI solution become obvious:
- It's easy to navigate through the power plant control and turbine control processes as both are represented in a similar manner and run on the
same visualization platform. The process graphics that were prepared for this project are excellent overall, with well structured and detailed
process overview and operator displays.
- The Consolidated Alarm List software helps operators quickly identify cause and effect relationships in power plant and turbine control.
System Details
Control systems:
Number of I/O points:
System configuration:
25
Thailand
Power
Plant Information
Plant name: Cogeneration plant
Location: Rayong, Thailand
Project type: New
Plant type: Combined cycle cogeneration
Output:
140 MW (2x 40 MW electrical and
1 x 60 MW electrical)
Order date: 2000
Completion: 2002
Executive Summary
The Electricity Generating Public Company Limited (EGCO) was the first independent power producer (IPP) to be established in Thailand as
the result of an initiative by that countrys government to allow broader private sector investment in the power sector. EGCO was incorporated
on May 12, 1992 by the Electricity Generating Authority of Thailand (EGAT), and over the next three years it became a public company and
was listed on the Stock Exchange of Thailand (SET). Operating as a holding company, it invests in power generation and supply and provides
comprehensive operation, maintenance, engineering, and construction services to the power industry and other industries in Thailand as well as
other countries. Furthermore, the company searches for good growth opportunities that are related to its core energy business.
EGCO Cogeneration Co., Ltd, an EGCO Group company,
operates a combined cycle power generation plant at
the Rayong Industrial Park. The plant uses natural gas
from PTT to power gas turbines that generate electricity.
Heat recovery steam generators (HRSG) use waste heat
from the turbines to produce steam for a steam turbine
that generates additional electricity. Sixty percent of the
generated electricity goes to the national grid (EGAT)
and the remaining 40% is utilized by companies at the
Rayong Industrial Park.
To control these processes at the EGCO Cogen power
plant, Yokogawa Thailand installed a CENTUM CS 3000
process control system in 2002. This facility has operated
without any major system failures since then.
26
Each operator workstation has function keys that allow quick access to a target process from the plant overview graphic display. With certain
sequences, clear and easy-to-understand operation procedures are displayed. Operators thus have all the information needed to take quick and
timely action whenever needed, making this a very safe plant.
Plant Details
Customer Satisfaction
According to the Plant Manager, The system allows operators to clearly see the
plants status and know what is going on. With this information, our operators
can take quick action whenever there is a problem with a gas or steam turbine
or with an HRSG. When there is a problem with the transmission lines or some
other part of the national grid, the plant is immediately put into island mode and
provides electricity only to its local customers. We are very pleased with the
performance of Yokogawas CENTUM CS 3000 at our power plant.
System Details
27
Thailand
Power
Executive Summary
A 126 MW gas fired cogeneration power plant built by Thailands Samutprakarn Cogeneration Co., Ltd. began generating electricity on August
23, 1999. Ninety MW of its output is supplied to the Thai National Grid, with the remainder going to local companies. The plant operates 24
hours a day, seven days a week, and is shut down for 35 days once a year for maintenance. A major overhaul is done every six years. For
improved efficiency, this power plant was designed to have more than one thermodynamic cycle, and uses both gas and steam turbines. Two
GE gas turbines burn fuel to produce heat energy and generate electricity, and the waste heat is used to produce steam that passes through an
Alstom steam turbine to generate additional electricity.
The gas fuel for this plant comes from a PTT gas separation plant,
which receives gas via an undersea pipeline from wells in the Gulf of
Thailand. The plants boilers utilize heat recovery steam generators
(HRSG) with a capacity of 80 t/h (max.120 t/h) and a maximum
allowable steam pressure of 65 bar. The steam temperature is 500
degrees Celsius.
28
Customer Satisfaction
Kitpoat Srasomsub, Maintenance Manager, had the following to say about the plants new
control system: We have been very happy with Yokogawas CENTUM CS 3000 since
introducing it in 2007. The system is very reliable and there have been no major problems with
it. We have the important mission of providing a steady supply of electricity to both the EGAT
national grid and local companies 24 hours a day, seven days a week, throughout the year. We
are always striving to improve efficiency and reduce emissions through the visualization of all
plant data.
Mr. Srasomsub
29
Australia
Power
Executive Summary
The Australian Gas Light Company (AGL) was established by private interests in New South Wales in 1837 to light the streets of Sydney with
coal gas. Today, AGL is Australias leading energy provider. AGLs wholesale and retail marketing businesses sell natural gas, electricity, and
associated products and services.
Electricity consumption is growing rapidly in southern Australia. In response to growing summer demand in South Australia, AGL built a power
station in 2001 in Hallett, South Australia, and completed construction of another power station the following year in Somerton, Victoria. Both are
peak power plants that help reduce the likelihood of power blackouts and keep electricity prices stable during periods of peak demand.
The Solution
In these projects for AGL, Yokogawa Australia cooperated closely with the Groups Singapore factory to develop and deliver a fully engineered
control system on specification and on schedule.
For its Hallett and Somerton plants, AGL selected Yokogawas CENTUM CS 3000 together with its Unified Operator Interface (UOI). The system
platform in the UOI is the GE Fanuc CIMPLICITY Human Machine Interface (HMI) system, which fully integrates the controllers for the turbine
and balance of plant (BOP) auxiliaries and uses the same screens/formats in both the turbine and BOP HMI displays. The CIMPLICITY HMI
used in the UOI is a SCADA based design that fully supports AGLs requirement for remote operation capability.
For the Hallett plant, AGL also introduced an automatic turbine optimizer. This embedded system automatically schedules and selects turbines
to flexibly meet peaking market demands.
30
System Details
System:
CENTUM CS 3000/UOI
Scope: (Hallett)
31
Canada
Power
32
The airport is owned by the GTAA1, which hired outside firms to help design, build, and operate the plant. The airport, by meeting the twin
requirements of a coincident demand for electricity and thermal power along with access to fuel (natural gas), was an ideal candidate for a
Cogeneration system. In early 2001, GTAA had constructed a Central Utility Plant for the airport; it replaced a legacy plant torn down as various
airport facilities were being added. The plant supplied steam for heating and chilled water for cooling the airport terminals.This new plant can
supply steam needs but also allows the optional operation of the plants steam boilers in standby mode while using steam from the Cogen
system. The plant was constructed in 2003. A year later the Yokogawa control system was commissioned.
An interesting facet of the design is the use of two once-through steam generators (OTSGs) supplied by Innovative SteamTechnologies (IST)
of Cambridge, Ontario. These units offer several advantages over conventional designs. They are efficient,flexible and capable of full operation
from cold starts within less than 30 minutes. They start, run and finish dry. Conventional-pass stacks, diverter valve systems and stack silencers
are not needed.An OTSG is basically a heat exchanger composed of a series of tubes whose boiler water is simultaneously heated, evaporated
and superheated. Heat recovered in the OTSG supplies the steam turbine at its required temperature and pressure.
Encompassed by the Yokogawa monitoring and control system is the entire Cogen plant including the two OTSGs. Startup, operation and
shutdown of the OTSGs is fully automatic. The complex logic involved was developed by close cooperation of Yokogawa, IST and SNC-Lavalin2
engineers.
Background
Canadas Toronto Pearson International Airport, along with millions of people in Eastern Canada and eight US states, suffered a severe electrical
power outage in 2003. This catastrophic failure made it painfully apparent that the airport neededa reliable, independent source of electricity.
Round-the-clock reliability was simply an absolute must, but the economics of such a system had also to be carefully considered.
These two factors reliability and costs have now been met by a cogeneration power plant design using twin GELM6000PD aero-derivative
gas turbines, each capable of producing 42 MW. Exhaust from the turbines passes through steam generators which run a third steam-driven
generator capable of 33 MW output. Remaining plant heat can be used to heat/cool the airport buildings. Economics were addressed in this
generous design to allow sale of excess power generated to the Ontario power grid. A Yokogawa CENTUM CS 3000 control system, selected
after careful evaluation of system reliability for various vendors, completes the plant.
Not shown but also in the control room is an engineering station. It allows access to technical drawings and related information such as
applicable codes and standards and other engineering information. It includes a system simulator used in operator training and to examine and
test changes in the CS-3000 logic. This logic can be modified through this station. A HART plug-in allows diagnostics for HART I/O. Naturally,
access to the station is fully protected and limited to only the plants certified engineers.
A monthly printout both tabular and graphical by a companion J.D. Edwards software package, using selected inputs from the Yokogawa
files, provides maintenance guidance. Since installation of the Yokogawa system, no major maintenance has been required.
Steve Sadecki in the Cogen Plant control room with multiple flat-screen
displays. Control is provided for plant balance and unit operations.
Monitors provide rapid and complete displays of all system assets. Says
Sadecki, The display formats are very well thought out and extremely
operator friendly. It took me, and fellow operators, less than a week of
training to be completely familiar and comfortable with the system even
though none of us had previous experience withYokogawa equipment.
Steam fed to the OTSGs must be of ultra-high quality. Steam monitoring
and water purification control is included in the CENTUM system.
Those involved with the Cogen plant have been very pleased with reliability of the Yokogawa control system, states Henry Oberhauser, Senior
Manager, Utilities for Greater Toronto Airports Authority (GTAA). The only substantial system outage occurred due to sub-standard process
water supplied by a sub-contractor. We feel Yokogawas claim of seven 9s reliability which translates to less than one minute of downtime in
40 years is well on its way to reality.
The Honourable Donna Camsfield, Minister of Energy, at the Cogen Plant opening on Dec.2, 2005, said in part, Todays plant opening
is another step in Ontarios cogenerational potential and another example of the Greater Toronto Airport Authoritys significant record of
environmental leadership. She cited benefits of cogeneration to include:
Adds more capacity added to the power grid
Produces high combined fuel efficiency
Helps control industry costs
mitigates electricity cost increases
Improves transmission and system reliability
Helps replace coal thus creating a cleaner environment
Increases the number of facilities that recover quickly or even continue to operate in the event of power interruption.
Comments by those associated with the plant and echoed by other industry and government groups visiting the Toronto facility about two such
tours per month since installation attest to the central focus of system reliability. The GTAA facility and its Yokogawa control system qualify on
all counts.
System Details
DCS:
Total I/O:
System configuration:
Scope:
CENTUM CS 3000
Approximately 2000
Dual LCD operator stations, engineering work stations with virtual test function, field controllers, I/O with HART,
sequence of events I/O
Distributed control system including control system software, factory acceptance, commissioning assistance
GTAA operates Pearson Airport, an international gateway with 65 airlines via 82 gates in three terminal buildings. A fourth terminal is currently beingdesigned. The airport generates $14-billion
in annual revenues, $2.8-billion tax revenues and provides 135.000 jobs. It has 16,000 parking spaces.
SNC-Lavalin, one of the leading groups of engineering and construction companies in the world, has office across Canada and in thirty other countries. It is at work in over 100 countries.
33
Thailand
Power
34
Plant Information
Plant name: District cooling system and power
plant at Bangkok's Surarnabhumi airport
Location: Samutprakarn, Thailand
Project type: New
Plant type: Combined cycle cogeneration
Output:
94 MW (2 x 41 MW electrical,
1 x 12 MW thermal)
Order date: 2002
Completion: 2004
Executive Summary
Process overview
Continuous emissions monitoring system
Plant Details
Plant overview
Systems Delivered
Chiller overview
Customer Satisfaction
Seree La-Ongutai, acting general manager, said, We are producing electricity and steam for the whole airport terminal, adjacent hotel and
Thai Airways facilities. It is very hot in Thailand all through the year, so the airport always needs a stable utility. We very much appreciate the
reliability of Yokogawas CENTUM CS 3000, which is the cooling of all our airport facilities here. So far the plant has operated with great stability,
availability and safety, and I believe this is due in good part to the integration of the systems sequence logic functions and the dynamic graphic
displays on the human machine interface (HMI). We are striving to save energy in the whole facility, so we would like to work together with
Yokogawa for continuous improvement.
35
Hungary
Power
Kraftszer Kft
The Challenges and the Solutions
1. Easy set point definition for all plant power generation operations
The district heating set points are defined in Excel and sent to the district heating company.
As shown below, the Excel data can be imported into FAST/TOOLS with just one mouse click.
Plant operators can see the actual daily plant set points on screen.
The Fredi Power Plant project is a showcase for the use of SCADA and STARDOM in a power sector application, and it posed certain unique
operation and control requirements. A FAST/TOOLS SCADA system was seamlessly integrated with a STARDOM automation system, providing
the information needed by power plant managers, operators, and maintenance personnel to efficiently monitor the plants operation and analyze
its performance. A history database integrated into FAST/TOOLS collects and stores the measured and calculated parameters.
The system covers approximately 16,000 items, collects data, creates shift/daily/weekly reports, and makes monthly calculations. The collected
and calculated data is kept for the lifetime of the plant. Through this project, Zugl-Therm Energy Supply Ltd. has achieved the following:
Easy set point definition for all plant power generation operations
The heat produced by the entire plant and the electrical set points for the engines can be defined in an Excel file every 24 hours, with 15
minute resolution, and this data can be easily exported into the FAST/TOOLS system.
Stable electric power generation
The superior control system can respond flexibly to changing heat demand, focusing on the operational conditions of the gas engines.
Power plant optimization
The control system supports on-line calculation of both plant and gas engine efficiency, enabling adjustments for optimal operation.
Control of electric power generation based on net performance
The control application in STARDOM can automatically calculate the in-house power consumption of the power plant. With this function, the
plant can more accurately control the required amount of power to be supplied to the national grid operator.
The plant is located at Fredi t in Budapest. The main contractor is Kraftszer Kft., a Hungarian engineering company that has built a number of
CHP plants, and the plant will be operated by Zugl-Therm Energiaszolgltat Kft.
The Fredi power plant consists of three (3) Wrstil 18V34SG gas engines rated for an electrical output of 18 MWe, three (3) heat exchangers
for each engine that supply the hot water for the district heating system, and auxiliary systems for such functions as fuel and air supply. Natural
gas is the main fuel for the power plant.
The hot water is distributed by Ftv Rt., the main district heating utility in Budapest.
Although the emphasis is on the supply of hot water for district heating, the generated electricity is also supplied to approximately 20,000
households on the public power grid. In Hungary this kind of CHP plant is required to have a minimum total efficiency of 65% per month and
75% per year.
This system is used for the electrical set points as well. In this case the plant manager has to
define the set points for each of the three gas engines. Please refer to the Excel sheet below.
Executive Summary
36
The automation system realized in STARDOM can also recalculate the set points for each gas
engine in the event of a malfunction such as a trip of a gas engine. If one of the gas engines
shuts down, the other two gas engines will increase power output to compensate.
3. Power plant optimization
STARDOM calculates the efficiency factors for each gas engine and for the entire power
plant, and provides data that operators can use to make the plant operate economically and
efficiently.
System Details
Control system:
Number of I/O points:
Field instruments:
Installation:
Start-up:
Commissioning:
Training:
37
China
Power
38
Executive Summary
At a cost of 30 billion yuan ($4.4 billion), PetroChina, China's largest oil producer,
constructed a large refinery and petrochemical complex on a 455 hectare parcel of land
in Dushanzi, a city in Chinas Xinjiang Uyghur Autonomous Region. Using mainly high
sulfur crude oil from the Kazakhstan-China pipeline, the complex processes 10 million
tons of crude oil and produces 1 million tons of ethylene per year. As such it plays an
important role in the China-Kazakhstan energy cooperation strategy.
The utility plant that provides steam, electricity, and water to this complex include five
440 t/h circulating fluidized bed (CFB) boilers, three 100 MW turbines/ generators, and
chemical and water treatment systems.
SIS
The complexs CFB boilers use brown coal as a fuel and are designed to keep CO2
emissions to a minimum. Normally, four of the complexs five boilers are in use and the
remaining boiler is kept on standby and undergoes maintenance.
For the utility plant at this important industrial complex, Yokogawa China successfully
installed a CENTUM CS 3000 integrated production control system and the Plant
Resource Manager (PRM) package.
Boiler
(CENTUM CS 3000)
Water treatment
(GE-PLC)
Total system configuration
Ash treatment
(GE-PLC)
SIS boiler operation display
Customer Satisfaction
Liu Jian Ming, Director of the Utility Control and Instrumentation Department said, Every day we are trying to improve operations at our plant
and to reduce both coal consumption and CO2 emissions, because one of our targets is to achieve sustainable manufacturing. We very much
appreciate that Yokogawa supplies very reliable products and systems, and has been working together with us to provide support. Of the many
vendors that are supplying products and services for this PetroChina utility plant, Yokogawa is one of the best.
Refinery
Petrochemical plant
39
Australia
Power
40
Plant Information
Plant name: Morwell Power Station
Location:
Victoria, Australia
Project type: Control system revamping
Plant type: Coal-fired
Output:
180 MW
Order date: 2005
Completion: 2008
CENTUM CS 3000
control system cabinet
Executive Summary
Energy Brix Australia Corporation (EBAC) commissioned Yokogawa Australia Pty. Ltd. to modernize the Morwell Power Station and Brown Coal
Briquetting Plant by replacing their control and monitoring systems with a modern Yokogawa CENTUM CS 3000 distributed control system (DCS)
and a range of field instruments.
EBAC is a long established electric utility in Morwell, which is in the coal rich Latrobe Valley region approximately 150 kilometers east of
Melbourne, Victoria.The Morwell Power Station has an installed generating capacity of 180 MW and was built in the 1950s by the State
Electricity Commission of Victoria to generate power for the national power grid. The Morwell Station also provides process steam to the
adjacent brown coal briquette factory.
This extensive modernization of the Morwell Stations control systems by EBAC and Yokogawa Australia was completed in 2008.
EBACs goals for undertaking this extensive DCS upgrade were to:
Reduce station operating and maintenance costs
Generate additional power for export
Improve plant operating flexibility
Provide modern conditions for plant operators
Reduce plant emissions
Following the successful completion of this complex and challenging project, Yokogawa Australia and EBAC were jointly awarded the prestigious
2009 PACE Zenith Australia Industry Award for their leadership in the application of technological excellence and innovation.
The PACE Zenith Awards were established in 2004 and are presented to Australian industry annually for outstanding achievements in
technological excellence and innovation. Yokogawa Australias projects have previously won awards in 2005, 2007, and 2008.
CENTUM CS 3000
station operator consoles
The application of modern DCS technology at the Morwell Power Station was highly successful in achieving EBACs objectives. This project
accomplished the following:
Optimized the use of labor by enabling a preventive maintenance approach
Optimized the plants operating configuration by allocating turbine loads, allowing the station to operate at continuous maximum
capability
Coordinated station control (range and pressure and process steam pressure), which in turn allows maximum plant flexibility by optimizing
boiler and turbine loading to take account of fuel quality variation, plant condition, and briquette factory process steam demand
Optimized the consumption of brown coal fuel and minimized flue gas discharge by fully automating combustion control on all boilers
Minimized the consumption of fuel oil, improved furnace stability, and reduced plant stress and operating costs as a result of the
automation of brown coal combustion
Reduced thermal stress on the plant as a result of automating the boiler final steam temperature control
Significantly improved plant safety by automating drum level control and furnace temperature control
Increased operational flexibility and improved station response to load demand variations by fitting modern digital governors to all
five turbine generators
Increased consistency of plant operations and reduced rate of load variation
Reduced maintenance costs through tighter control and more consistent/less stressful operation by reducing the number of significant
excursions outside plant design parameters
Significantly increased continuous MW load output from the available capacity while minimizing steam wastage and improving
operating efficiency by automating steam consumption across all turbines and condensers
Introduced a new screen-based operator interface that allows operators to monitor plant operations while relying on automation systems
to maintain the plant in a stable and controlled condition throughout all steady state, load change, and plant upset conditions
Customer Satisfaction
EBAC believes that the engineering complexity and innovation involved in installing 21st century control systems technology in an old plant
was quite remarkable. Not only did the project increase the reliability of electricity supply, it reduced plant stress and decreased its maintenance
costs. This was accomplished by optimizing the use of raw fuels. The successful outcome of this control system modernization project will allow
the Morwell power generation and briquetting facility to operate well into the future while meeting anticipated economic and emissions standards.
Peter Morrow, General Manager of EBAC (left) and Philip Nicholson, Principal Engineer
of Yokogawa Australia (center) accepted the PACE Zenith Award from Jeremy Needham
of Mitsubishi Electric, the sponsor of the Transport, Power and Infrastructure category.
41
Philippines
Power
42
PNOC-EDC
The Challenges and the Solutions
State-of-the-art FF technology
PNOC-EDC had adopted FF and was aware that there were many vendors of this technology. They needed to select the best partner for the
long haul, and they did this through interviews and plant visits. After speaking with other end users of Yokogawa fieldbus products in the region,
PNOC-EDC saw that Yokogawa was best positioned for a long-term relationship.
PNOC-EDC recognized the importance of optimizing its operational costs and realized that asset management would be a critical success factor
for attaining this objective. Yokogawas versatile PRM platform and fieldbus devices met the operational and technical requirements. With PRM,
PNOC-EDC anticipates lower operational costs, effective maintenance programs, and high system availability.
Critical to the overall operation of the plant was the availability of plant information to PNOC control centers in Negros and in Manila. As part of
the project, the FCRS control system was connected to a WAN by another vendor.
System Layout
Executive Summary
PRM windows
Customer Satisfaction
System Details
PNOC-EDC was very satisfied with Yokogawas performance in the NNGP. The Company
earned the customers trust with its project management expertise and local engineering capabilities.
This project is part of the governments efforts to reduce dependency on oil through the use of renewal
energy sources. The NNGP was inaugurated by no less than the President of The Philippines,
Ms. Gloria Arroyo, who was accompanied by key officials in the power sector.
Control system:
CENTUM CS 3000 & PRM
Number of I/O points: 112 points (14 segments)
Products:
EJX430A (52 units), EJX110A (52 units) and CA71 (1 unit)
System configuration:
FF for advanced field instrumentation
Standard-configuration transmitters for the geothermal application:
EJX430A-FAS3G-917DN/A/X2/D4/M11
EJX110A-FAS3G-917DN/A/X2/D4/M11
PRM for optimal plant asset management
WAN for remote data monitoring
43
Australia
Power
44
The latest dish, SG4, was completed in June 2009, and since then a great deal of effort and research by Mr. Burgess and others has gone into
fine-tuning the solar tracking, sourcing computer, and communication components, testing optical performance, and installing and testing the
first steam generating receiver. Yokogawa has worked closely with these researchers to optimize the performance of this system by providing
a PLC SCADA system that computes the precise position of the sun to ensure millimeter perfect tracking of the sun. The system also includes
safety features that, for example, will put the dish into a parked position at night and before storms to prevent damage from high winds.
As new units are constructed at this ANU facility, the plan is to employ Yokogawas new HXS10 controller as a cost-effective means to
automatically track the sun and ensure maximum efficiency of the solar reflecting dish.
Executive Summary
Led by Associate Professor Dr. Keith Lovegrove, the Australian National Universitys (ANU) Solar Thermal Group has constructed the worlds
largest solar collecting dish on the ANU campus in Canberra. This reflecting parabolic dish is 25 m wide and has 500 m2 of highly efficient
purpose-built mirrors that reflect the suns rays onto a collector coil. This converts water to steam, which drives a steam turbine that generates
electricity. Yokogawas FAST/TOOLS software fine-tunes the dishs ability to automatically track the sun and maximize the energy collected.
This project had its genesis in the early 1970s, when a team lead by Stephen Kaneff and Peter Carden paved the way for the construction of the
White Cliffs solar power station, with 14 comparatively small 20 m2 dishes. Convinced the idea had merit, the team at ANU proceeded to scaleup the solar generator, with the first Big Dish built in 1994 using commercially available space-frame technology. According to lead researcher
Greg Burgess, the aim of the solar project has been to demonstrate that solar generated electricity is viable on a commercial scale. Their
thinking is that building fewer large dishes, which can be easily replicated in the field, is more economic than building lots of smaller ones.
Planning is underway for the construction of a pilot solar generating plant that will prove out the concept already demonstrated by the existing
solar generator dish. Mr. Burgess also sees other potential applications for super-heated steam produced by reflected solar energy. Such is the
intensity of energy generated by the dishs efficient design that when concentrated it can melt through solid aluminum, stainless steel plate, and
even the hardest ceramic known.
Yokogawa Australia is involved in this exciting solar energy project, which may provide the key to future solar energy projects in Australia.
Steam
generation
Customer Satisfaction
Steam
turbine
Dr. Lovegrove explained, As a clean energy source, solar energy is a natural complement to wind and
based on our climate is more available and provides most of the energy when you need it.
As an example, in a large system with an array of dishes all feeding steam to a single efficient large steam
turbine, each dish of this size would contribute the production of more than 100 kW when operating at full
efficiency in full sunlight. Roughly speaking, up to 100 advanced energy-efficient homes could be powered by
every dish. A solar field with the size of the Australian capital Territory (ACT) could power the entire country.
The medium-term goal for the concentrating solar technologies is to make electricity for about the same
cost as wind, which is currently around 10-12 cents a kilowatt/hour. While thats around double the cost of
conventional coal-fired power stations, it may prove to be cheaper than adding carbon capture and storage
to existing coal-fired power stations.
Of course, the ultimate energy economics will be influenced by ruling government policy, with any moves
to tax carbon impacting on fossil fuel power stations and tipping the economics more in favor of alternate
energy sources in the future.
We are very happy with the high reliability of Yokogawas system. This is very important to keep our solar
plant running 24/365. Also, our engineers can easily configure the system at any-time. FAST/TOOLS
benefits us in many ways and allows us to clearly see the entire process, giving us the information we need
to take immediate action.
45
Australia
Power
46
Executive Summary
Yokogawa Australia has supplied its breakthrough HXS10 solar tracking controller to NEP Solar one of the pioneers of solar energy in Australia
for use in a solar cooling project.
NEP Solar of Warriewood on Sydney NSW grew out of companies that were involved in wind farm development, but later became a pioneer
of novel solar applications such as the first solar cooling project in Australia in 2004. NEP Solars local projects to date include a solar cooling
demonstration project under the Renewable Energy Development Initiative
(REDI) at the Commonwealth Scientific and Industrial Research Organization
(CSIRO) Energy Centre in Newcastle, and a solar cooling demonstration project
funded under New South Wales Government's Sustainable Energy. Research
Development Fund (SERDF) in Padstow, partly funded under the New South
Wales governments SERDF.
One of NEP Solars latest projects is a commercial installation of a solar field to
drive a chiller for part of the GPT Charleston Square shopping complex in the
regional city of Newcastle north of Sydney. The 345 m2 PolyTrough 1200 solar
field is mounted on a rooftop above a cinema complex. The chiller uses the heat
from the solar field and a concentrated salt solution in which water gets absorbed
and re-absorbed, exchanging heat in the process. The chilled water from the
absorption chiller feeds into the shopping centers return cooling loop to reduce
the amount of energy expended to further cool the water for the centers air
conditioning system.
Customer Satisfaction
NEP Solars Chief Executive Officer, Johan Dreyer, an engineer with experience as a project manager for one of
Australians largest commercial and industrial construction companies, said, It is very important to control costs and
ensure reliability for solar energy to achieve its potential in Australia. The critical part of the solar system is the ability
to accurately track the sun. We need to focus exactly on one point (the solar tube), and the tracking needs to be very
accurate. Yokogawas HXS10 solar tracking controller makes this possible. Mr. Dreyer went on to say, The efficiency
of the mirrors is such that the system can capture enough solar energy to cool even on a partly cloudy day. In full sun,
direct normal insolation using this type of system can be as high as 1000 watts per square meter.
Flowmeters and temperature sensors such as those produced by Yokogawa can determine how much energy is being
converted into thermal energy to monitor the efficiency of the entire system.
Joint exhibit with NEP Solar at All-Energy Australia
exhibition in October 2011
NEP Solar will next use the Yokogawa HXS10 and the related FAST/TOOLS on a desalination project in Spain and at
a dairy processing plant in Switzerland.
Mr. Dreyer
47
Thailand
Power
48
Executive Summary
In 2005, A.T. Biopower Co., Ltd. built a biomass power plant in Pichit, Thailand. Using ground rice husks as its fuel, this plant generates 22.5
MW of electricity, of which 20 MW is sold to the Electricity Generating Authority of Thailand (EGAT). The plant was built with the support of the
Thai governments Ministry of Energy, which is promoting the construction of power plants by small power producers (SPP) that utilize hydro,
biomass, or thermal cogeneration technology. In addition to promoting the use of renewable energy sources, this policy aims to reduce the
countrys dependence on imported fuel. At present,
about 90% of the electricity generated in Thailand
comes from power plants that rely on non-renewable
fossil fuels, namely, oil, coal, and natural gas. If no
effort is made to find and develop new energy sources,
it is estimated that the countrys coal and natural gas
reserves will be completely exhausted in the next 30
years. The use of modern technology to generate
power from rice husks and other kinds of agricultural
waste will not only contribute to the countrys energy
independence, but will also help reduce environmental
pollution and provide employment opportunities for the
local community.
For A.T. Biopowers biomass cogeneration power plant,
Yokogawa Thailand successfully installed the CENTUM
CS 3000 production control system, field instruments,
and a continuous emission monitoring system (CEMS).
Plant details
Plant type:
Generating capacity:
Fuel:
Daily fuel requirement:
Boiler:
Steam turbine:
Daily water requirement:
Precipitator system:
Thermal power
22.5 MW (internal 2.5 MW)
Rice husks
500 - 600 tons at maximum capacity
91 t/h, 65 bar, Macburney
Shin Nippon
Approximately 2,200 m3
Electrostatic precipitator capable of detecting 99.5% of particulates
Customer Satisfaction
Chanapai Sahudsa, A.T. Biopowers Engineering Manager, had the following to say about Yokogawas solutions: This
is the first plant to be approved by the Thai government under the Clean Development Mechanism (CDM) defined
in the Kyoto Protocol. We are very happy to be using Yokogawas system and products at this rice-husk-fuelled
boiler plant, the worlds largest of its type. We are always looking for ways to improve its operation and make the
combustion process more efficient. We always appreciate the solutions provided by Yokogawa Thailand.
Mr. Sahudsa
49
Japan
Power
50
Executive Summary
Amidst growing concerns about the depletion of fossil fuels and the effects of climate changes caused by rising CO2 emissions and other
factors, there is a growing push to generate power from wind, solar, biomass, and other renewable energy sources and thereby create a more
sustainable society.
Japan Wind Development Co., Ltd. (JWD) is a specialist in wind power generation technology with vast knowledge and expertise in this field.
JWD is building and providing all necessary support services for a nationwide wind power generation network.
In May 2008, JWD completed construction of a wind farm near Rokkasho village in Aomori Prefecture, in northern Honshu. This smart grid wind
farm is the first facility of its type to use sodium sulfur (NaS) batteries to store electricity for supply to the national power grid. These batteries
are charged at night, when the demand for power is lower, and the stored electricity can be supplied to the grid together with the electricity
generated by the wind turbine during the daylight hours. This ensures a steady supply of power to the grid even during those periods when
power production falls as the result of low wind speed.
Charging
Power
Battery
Charging
Smoothed
power to
national grid
To control the transmission of power from the Rokkasho wind farm to the national power grid, Tokyo Densan, a Yokogawa representative and
systems integrator, successfully installed STARDOM network-based controllers and FA-M3 range-free controllers.
Time
12
18
23
Plant details
Customer Satisfaction
Windmills: 34 x 1,500 kW
Battery: NaS type, 2 MW x 17 sets with 17 sets of AC/DC converters
Transmission capacity: 51 MW
Transformer: Primary - 154 kV/60 MVA, secondary - 22 kV/60 MVA
The integrated control system allows JWD to manage the operation of each of its windmills and provide a steady supply of power to the national
power grid. JWD plans to begin constructing wind farms outside Japan, and to this end is working together with Yokogawa and Tokyo Densan
to develop the necessary high-speed systems and equipment. Through this development of renewable energy facilities, JWD hopes to make a
lasting and significant contribution to the building of a more sustainable society.
51
UK
Power
52
Lakeside EFW
The Challenges and the Solutions
Lakeside EFW is continually looking for ways to operate this incineration facility more efficiently. Waste is trucked to the facility, with the vehicles
being weighed on entry into the site and again on exit to calculate the amount of delivered waste. Grab cranes mix the waste in a 7,500 ton
capacity bunker to obtain a more controllable calorific value, then load the waste into a hopper from where it is pushed into the incinerator by
hydraulic rams. The initial firing of the boiler is achieved using an approved low sulfur diesel. Once the waste is burning inside the incinerator,
the diesel burners are switched off and the waste becomes the fuel.
Superheated, dry steam created from the boiler process is used to drive a steam turbine, which in turn drives a generator set. The generator
produces enough electricity to power the Lakeside facility and export 34 MW onto the National Grid. Spent steam from the turbine is condensed
and pumped back to the boiler, making a closed-loop steam/water circuit. The facility has also been designed so that off-site district heating
(combined heat & power - CHP) can be provided to local consumers in the future.
The bottom ash from the waste incineration process is transported by moving belts to dedicated bunkers. Ferrous metals are removed from
the bottom ash for recycling. The ash is removed from the site and processed into an approved aggregate material for road building and
construction.
The hot gases from the incineration process that were used to heat the water contain various compounds and chemicals that need to be treated.
These gases and chemicals are cleaned in a flue gas treatment process. This uses slaked lime to absorb sulfur gases and HCl, activated
carbon to absorb dioxins and heavy metals, and ammonia to reduce NOx gases. The air is subsequently passed through a bag filter before it
is released from the stacks. The emissions are monitored in real time using state-of-the-art, independently calibrated measuring instruments to
ensure compliance with permitted emissions limits.
Executive Summary
As existing fossil fuel reserves have become unviable or unreliable, the challenge of providing a secure energy supply for power generation
within the UK has increased significantly in terms of both financial and environmental cost. At the same time, landfills lack the capacity to handle
the increasing amount of household and municipal waste. While efforts to reduce, re-use, or recycle waste have made some headway, other
options have had to be explored. One such effort underway that is making a valuable contribution toward providing a balanced and secure
energy portfolio for the UK involves the extraction of energy from residual (non-recyclable) waste.
With the integration of the Yokogawa CENTUM CS 3000 and ProSafe-RS systems, operators in the central control room enjoy ready access
to operations throughout the plant. Ergonomically designed CS 3000 human interface stations (HIS) provide a window into all of this facilitys
processes, giving operators real-time access to all the information they need to make quick and timely decisions.
Lakeside EFW Ltd. operates an energy-from-waste (EFW) facility near London that is staffed by experts in energy recovery technologies who
are working hard to ensure the plant remains efficient, technologically up to date, and above all, safe. The plant has the capacity to consume
410,000 tons of household and municipal waste per year and exports at least 34MW per hour to the countrys National Grid. This process
diverts the majority (over 97%) of waste from landfill.
Lakeside EFW uses a mass-burn process to generate high temperatures that are then used to produce high pressure steam. The steam in turn
drives a turbine to produce electricity. Residues and flue gases are carefully treated to minimize the release of environmental pollutants. The
facility operates under strict environmental controls, within the guidelines of the waste incineration directive (WID) and an environmental permit
administered by the environment agency.
For Lakeside EFW, Yokogawa UK installed a CENTUM CS 3000 distributed control system and a ProSafe-RS safety instrumented system to
automate control of the facilitys boilers, burners, and balance of plant facilities. The facility has operated safely with no major system failures
since coming online in 2008.
Central control room
Incoming waste
Customer Satisfaction
Incineration
Generation of electricity
In his comments to Yokogawa, Danny Coulston, General Manager of the Lakeside EFW facility, touched
on the following points:
Everyone at Lakeside EFW is pleased with the high reliability of the Yokogawa systems and their
ease of operation and engineering.
The new plant was designed to meet the requirements of the European Waste Incineration
Directive, which mandates tight controls on the atmospheric release of dioxins, heavy metals, acid
gases, nitrogen oxides, particulates, and other products of the combustion process. This reduces
environmental impact and protects human health, and the facilitys emissions of dioxins and other
health related pollutants are low compared to common air pollution sources such as outdoor
burning and vehicle exhaust.
Lakeside EFW well recognizes the importance of water conservation and has designed the facility
so that all process water and water from maintenance activities is collected in a tank to be reused
as "gray" water for non-critical purposes.
The company has built an education center that extends out over a nearby lake. This is used to
educate the public on the efforts that Lakeside EFW is making toward a sustainable future.
Trademarks
All brand or product names of Yokogawa Electric Corporation in this bulletin are trademarks or registered trademarks of Yokogawa
ElectricCorporation. All other company brand or product names in this bulletin are trademarks or registered trademarks of their
respective holders.
2010
04
302