Professional Documents
Culture Documents
Period of Training
8th June 2015 To 5th July 2015
Submitted To:Sh.Karmveer
H.O.D.
Mechanical Department
GPC Hanumangarh
ACKNOWLEDGEMENT
Swai Singh
Diploma 2nd Year
Mechanical Engineering
GPC Hanumangarh
LOCATION
Ramgarh gas thermal power plant is situated near
village Ramgarh,60 km away from Jaisalmer . The first unit of 3
MW is not in operation now . The present installed capacity of the
plant is 270.50 MW
STAGE UNIT NO. CAPACITY COST (Rs.Crore) SYNCHORONISING DATE
|.
GT-1
35.5 MW
180
12.01.1996
||.
GT-2
37.5 MW
300
07.08.2002
ST-1
37.5 MW
25.04.2003
|||. GT-3
110 MW
640
20.03.2013
ST-2
50 MW
05.04.2014
2006-2007
2007-2008
2008-2009
2009-2010
2010-2011
2011-2012
2012-2013
2013-2014
GROSS
PLANT LOAD
AUX.POWER
GAS
GENERATION(LU) FACTOR(%)
CONSUMPTION(LU) CONS.(1000SCM)
4041.440
4141.153
3486.782
3539.44
3028.85
5367.94
4979.06
6733.195
41.75%
42.78%
36.00%
36.57%
31.29%
55.30%
51.44%
52.92%
268.179
551.61
333.116
279.029
161.452
95.796
90.245
607.423
240483
248876
209782
213635
183482
297151
272967
398509
FIRST STAGE :
This unit is capable inn electric generation using
both gas and diesel as fuel . In power plant 12 underground tanks
are constructed for storage of diesel having total capacity of 2520
KLt . Necessary equipments for this power plant were supplied by
BHEL(Bharat Heavy Electrical Ltd. ),and building construction was
carried out by Rajasthan State Bridge Construction Corporation.
in this stage only gas turbine (GT-1) is used which
includes a single unit of 35.5 MW .
SECOND STAGE :
First unit of this power plant is being operated by open
cycle system , resulting in higher cost on electricity generation .
Reduction in cost is only possible when first unit is operated on
Combined Cycle System . So under expansion programming of this
project , work of installation of a gas turbine and a steam turbine is
taken in hand . In this system , electricity will be generated by a
steam turbine utilizing heat obtained from exhaust of gas turbines
through a Heat Recovery Boiler . Thus ,no additional fuel will be
required for operating Stem Turbine . Under stage-||, one Gas
Turbine Unit (37.5 MW) was commissioned and synchronized with
the grid on 07-08-2002 . The Steam Turbine Unit (37.5 MW) was also
commissioned and synchronized with the grid on 25-05-2003 and
thus the plant has been made operational in Combined Cycle mode
with a total capacity of 110.5 MW .
THIRD STAGE :
Under stage -|||, one gas unit of 110 MW commissioned
on 20.03.2013 and the steam unit of 50 MW has been synchronized
on dated 05.04.2014.At present activities for the COD of the 50 MW
STG unit is under way.
FOURTH STAGE :
160 MW stage-\\/ Gas Thermal Power Project is under planning
stage . Under stage- \\/ , one Gas Unit of 110 MW and one Steam
Unit of 50 MW capacities is under way .
GAS
PERCENTAGE
NITROGEN
31.9064 %
METHANE
48.5668 %
CARBON DIOXIDE
18.8793 %
ETHANE
0.5009 %
PROPANE
0.0333 %
ISO- BUTANE
0.0285 %
N- BUTANE
0.0513 %
ISO- PENANE
0.0185 %
N- PENANE
0.0130 %
HEXANE
O.OOOO %
TOTAL
100 %
Availability of Water :
Requirement of water for power plant is supplied through Sagar Mal
Gopa branch of IGNP (Indira Gandhi Nahar Project) . For this a 27
kmlong ,5.4 cusec capacity pipe line is laid from RD- 190 of Sagar
Mal Gopa branch to power plant . For ensuring proper electric
supply requirements ,a sub station of capacity 2*250 KVA ,33/0.4 KV
,and a pumping station has been established at RD-190 in addition
to construction of water storage tank of capacity 77000m3 at power
plant .
Energy Generated(MU)
1999-00
228
2000-01
229
2001-02
120
2002-03
221
2003-04
238
2004-05
361.13
2005-06
435.62
2006-07
404.14
2007-08
414.11
2008-09
348.67
2009-10
2010-11
2011-12
2012-13
2013-14
2014-15
Open Cycle :
When Gas Turbine (GT) exhaust is diverted into the
atmosphere due to no provision of HRSG (Heat Recovery Steam
Generator) or non availability of HRSG then it is called is running in
open cycle . In open cycle as a gas turbine high exhaust gas is not
utilized for heat transfer in boiler so its efficiency will come down .
Combined cycle :
When Gas Turbine exhaust is diverted to HRSG in which high
temperature Gas Turbine exhaust gas passes through HP Super
Heater , HP Economizer , LP Evaporator ,LP Economizer , and
Condenser Pre-Heater (CPH) thus heat of gas turbine exhaust get
absorbed by above series of tanks located inside the HRSG and
temperature of Gas Turbine exhaust which is about 570 deg C will
come down to 135 deg C .
By utilizing the heat of Gas Turbine exhaust HRSG (Boiler) generates
Steam which is used to run Steam Turbine Generator (STG) .
Thus we can generates an additional power (about 50 % of gas
turbine) generation in Steam Turbine Generator without any extra
fuel cost . Thus we can get 30 % extra efficiency by running the gas
turbine in combined cycle . As gas turbine is operated on Brayton
Cycle principle and steam turbine is rotated on Rankine Cycle
principle that is why it is called Combined Cycle .
1.2 Combustors :
The fuel (gas) is provided to ten equal flow lines ,each terminating at
a fuel nozzle centered in the end plate of a ten separate combustion
chamber and prior to being distributed to the nozzles ,that fuel is
actually controlled at a rate consistent with the speed and load
requirements of gas turbine . The nozzle introduces the fuel into the
combustion chambers where it mixes with the combustion air and is
ignited by the spark plugs . At instant when fuel is ignited in one
combustion chamber , flame is propagated through connecting
crossfire tubes to all other combustion chamber .
1.4 Turbine :
There are three stage of the turbine and each consists of row of fixed
nozzles followed by a row of rotating turbine buckets . In each
following row of the jet is increased with an associated pressure
drop and in each following row of a moving buckets , a portion of
the kinetic energy of the jet is absorbed as useful work on the
turbine rotor .
1.5 Exhaust :
After passing through the third stage buckets , the gases are directed
into the exhaust hood diffuser which contains a series of turning
vanes to turn the gases from an axial direction , thereby minimizing
exhaust hood losses . The gases then pass into the exhaust plenum
and are introduced to atmosphere through the exhaust stack or to
the HRSG .
2.2.5 Scrubber :
The function of the scrubber is to remove condensate from gas by
centrifugal action by the use of no. parting plates within the
scrubber itself . There is provision of solenoid operated drain valve
for removal of condensate which is sensed by a level switch .
2.2.6 Filter :
The function of filter is to remove any foreign particles from the gas
and to supply totally clean gas . This filters are of cartridge type and
replaceable if D.P. across the filter increases .
Filter Cleaning :
Reverse pulse self cleaning system is provided for cleaning of these
fibers . Processor air is used for these pulsations . Each row is given
reverse pulse at fixed time interval and in predefined rotation .
Water pump
Detergent pump
Super heater ,
CPH ,
Stack (height) .
4.3.1 Condenser :
It is a two pass condenser having 9084 no. of tubes having cooling
surface area of 3070 m2 . It has steam condensing capacity of 137 t/hr
,cooling water flow of 7050 m3/hr .
4.3.2 Ejectors :
Two no. of two pass ejectors are provided each having a capacity of
handling 15 kg/hr dry air 49 kg/hr air- water vapor mixture . One
starting ejector is also there of 220 kg/hr of dry air handling capacity
at a suction pressure of 0.33 atmosphere .
Diesel engine ,
5.4 Laboratory :
Any power plant requires soft water and dematerialized water in
large quantity. There are soft water plant (capacity7.2 t/hr*2) which
is used in the boiler water circuit. Apart from that, a continuous
watch is kept of water chemistry of HRSG water to keep its
parameters (such as ph and conductivity) within a specified range.
HVWS pump ,
Jockey pump.
General :
The axial-flow compressor consist of the compressor rotor and the
enclosing casing. The inlet guide vanes, the seventeen stage of the
rotor and stator balding and the two exit guide vanes are included
with in the compressor casing.
In compressor, air is confined to the space between the rotor and
stator balding where it is compressed in stage by a series of
alternate rotating (rotor) and stationary (stator) aerofoil-shaped
blades. The rotor blades supply the force needed to compress the air
in each stage and the stator blades guide the air so that it enters the
following rotor stage at the proper angle. The compressed air exits
through the compressor discharge casing to the combustion
chambers. Air is exerted from the compressor for turbine cooling
bearing sealing and , during start-up, for pulsation control.
Rotor :
The compressor rotor is an assembly of fifteen wheels two-stub
shaft, through bolts, and the compressor rotor bulkhead. The first
stage rotor blades are mounted on the wheel portion of the forward
stub shaft.
Stator :
a)
b)
c)
d)
e)
2. COMBUSTION SECTION :
General :
The combustion system is the reverse flow type and comprises ten
combustion chambers with liners, flow sleeves, transition pieces and
crossfire tubes. Flame detectors, crossfire tubes, fuel nozzle and
spark plug igniters are also part of the complete system. Hot gases,
generated fro the burning of fuel in the combustion chambers, are
used to drive the turbine.
Combustion Chambers :
Discharge air from the axial-flow compressor enters the combustion
chamber from cavity at the center of the unit. The air flows
upstream along the outside of the combustion liner towards the 1
inner cap. This air enters the combustion chamber reaction zone
through the fuel nozzle swirl tip (when fitted) and through metering
holes in the both the cap and liner. When the nozzles supplied are
not of the type fitted with a swirl tip, the combustion chambers are
fitted with a tabulator system.
The hot combustion gases from the reaction zone pass through a
thermal soaking zone and then into a dilution zone where additional
air is mixed with a combustion gases. Metering holes inn the dilution
zone allows the correct amount of air to enter and cool the gases to
the required temperature. Opening located along the length of the
combustion liner cap provide a film of air for cooling the walls on the
liner and cap. Transition pieces direct the hot gases from the liners
to the turbine nozzles.
3. Spark plugs :
Combustion is a initiated by means of high-voltage, retractableelectrode spark plugs installed in two of the combustion chambers.
This spring-injected and pressure-retracted plugs receive their
energy from ignition transformers. At the time of firing, a spark at
one or both of these plugs ignites the combustion gases in a
chamber. The gases in the remaining chambers are ignited by
crossfire through the tubes that interconnect the reaction zones of
the remaining chambers. As rotor speed increases, chamber
pressure causes the spark plugs to retract and the electrodes are
removed from the combustion zone.
22 kg/cm2
80 kg/cm2
0.5 kg/cm2
16 kg/cm2
2 kg/cm2
120 deg C
50-60 deg C
GENERATOR rpm
3000 rpm
5000 rpm
11 KV
TURBINE MW
35.5 MW
GAS TURBINE-2
( GT-2 )
GAS PRESSURE ( kg/cm2 )
22 kg/cm2
80 kg/cm2
0.5 kg/cm2
16 kg/cm2
2 kg/cm2
120 deg C
50-60 deg C
GENERATOR rpm
3000 rpm
5000 rpm
11 KV
TURBINE MW
37.5 MW
GAS TURBINE-3
( GT-3 )
GAS PRESSURE ( kg/cm2 )
22 kg/cm2
80 kg/cm2
0.5 kg/cm2
16 kg/cm2
2 kg/cm2
120 deg C
50-60 deg C
GENERATOR rpm
3000 rpm
5000Rpm
11 KV
TURBINE MW
110 MW
1. Turbine :
The function of the turbine is to drive the generator at a
speed of 3000 rpm. The heat energy of steam (enthalpy) is
converted in mechanical energy as steam expands in turbine. Before
entering the main stream in turbine it passes through emergency
stop valve and control valve located at turbine floor, there are 53
stage in turbine, one stage consists of a set of fixed blade mounted
on inner casing and rotary blade mounted on turbine shaft. LP
injection is connected after 43 stage of turbine. The turbine shaft is
supported by the front bearing (Journal and thrust bearing) and the
rear bearing (Journal bearing). The axial thrust produced in the
moving blades is balanced by balancing drum located in the front
side of turbine. The residual thrust forces of turbine that have not
been compensated by balancing piston are taken up by the front
thrust bearing. The rear bearing of turbine houses the oil hydraulic
turning device used for running the turbine on bearing gear. Turbine
gland sealing is done to avoid air entry initially at both gland ends at
in running to seal the LP end gland. When turbine is running sealing
is done through turbine leak steam itself and balance steam flows to
condenser.
1.1
1.
2.
3.
4.
5.
6.
7.
HRSG Tripping :
a.
b.
c.
d.
e.
3. Generator :
MW 40.8
Stator volt 11 KV
Pf 0.80
Stator Current 2677 A
MVA 51
Rotor volt 246 V
Rotor amp 717 A
Cooling air (which is further cooled by ACW water in air cooler
located at 0 m.)
(a) Deaerator :
It is two parts; one is Deaerating column where
Deaeration takes place in spray valve cum tray chamber and
another is Feed water storage tank, which is used, as water
reservoir tank with capacity of 27.5 m3. whole assembly is known
as Deaerator. Stream pegging is also done in Deaerator to increase
Deaeration, feed water temperature and BFP suction pressure.
Condensate discharge through CPH (condensate preheater) comes
here in a chamber with 12 spray valve and 9 tray S and Deaeration
takes place. Air comes out of the vent and water flows down in
reservoir feed water storage tank.
(b) HP BFP :
High Pressure Boiler Feed Pumps are in no. and two are
continuously running for full load operation. Its full load parameter
is as follows :Discharge pressure 133.5 kg/cm2
HP BFP trips at 120 kg/cm2 discharge pressure.
(c) LP BFP :
LP BFPs are similar in constructions and operation as HP BFP
mentioned above but with very low capacity as compared to the
HP BFP. Its full load parameter are as follows :
Discharge Pressure 15.28 kg/cm2
LP BFP trips at 14kg/cm2 discharge pressure.
(d) Condenser :
Turbine exhaust is connected to condenser. Condenser here used is
surface condenser. Circulating water pump discharge water flows
through condenser tubes & cools steam in surrounding areas
coming out of turbine. Hot wells is bottom part of condensate
resulting from condensation of steam is collected and we can add
make up water here to compensate line losses of closed water
cycle. The pressure at outlet of condensate is negative.
Condensate pressure (-) 0.9 kg/cm2
Condensate cooling water temperature 33 deg C
(f) Ejector :
Ejectors are used to create vacuum in condenser. Starting ejector is
charged initially to create fast vacuum. Starting Ejector basically
consist of a nozzle through which pressure energy of incoming
auxiliary steam is converted in kinetic energy and passing through
high velocity it entails air from condenser and the exhausted air
and steam flows to the atmosphere.
HRSG Section :
High Pressure Boiler Feed Pump (HP-BFP) :
SUCTION PRESSURE (kg/cm2)
3 kg/cm2
120 kg/cm2
800MMWC
3 kg/cm2
3.5 kg/cm2
3.2 kg/cm2
32 deg C
32 deg C
50 deg C
50-70 deg C
Rpm
2972 rpm
KW
600 KW
2.5 kg/cm2
20 kg/cm2
100 deg C
95 deg C
4000 MMWC
KW
20 KW
RPM
2930 rpm
8.8 kg/cm2
50 deg C
11.2 kg/cm2
180 deg C
-0.92 kg/cm2
0.3 kg/cm2
120 deg C
15 kg
95 amp
HPCV POSITION
0-100 %
LPCV POSITION
0-100 %
8 kg/cm2
9kg/cm2
0.35 kg/cm2
55 deg C
3000 rpm
GENERATOR rpm
3000 rpm
11 KV
TURBINE MW
37.5 MW
8.8 kg/cm2
50 deg C
11.2 kg/cm2
180 deg C
-0.92 kg/cm2
0.3 kg/cm2
120 deg C
15 kg
95 amp
HPCV POSITION
0-100 %
LPCV POSITION
0-100 %
8 kg/cm2
9kg/cm2
0.35 kg/cm2
55 deg C
3000 rpm
GENERATOR rpm
3000 rpm
11 KV
TURBINE MW
50 MW
6. Auxiliaries :
6.1 Circulating Water Pump (CW Pump) :
These are three in nos. and located in pump house. These pumps
are used for circulating water through condenser tubes so as to
condense the turbine exhaust steam
Discharge pressure 2.5 kg/cm2
Flow 4500 m3/hr
Full load Current 43 A
Motor rating 400 KW, 6.6 KV
Deaerator
To HP Boiler
Pressure = 132.05 kg/cm2
Temperature = 130.07 deg C
LP-BFP Motors
To LP Boiler
Pressure = 19.81 kg/cm2
Temperature = 121.02 deg C
35 deg C
C.W. Pump
25 deg C
Make up
Line
C.E.P Pump
To CPH
Section
CPH Section
CPH Section
Gas Turbine
Last Exhaust
CPH 1
CPH 2
From CEP
Discharge
100-150 deg C
13.41 kg/cm2
Deaerator
Temperature =90.95deg C
Pressure
= 13.59 kg/cm2
2 kg/ cm2
LP INJECTION
STEAM
185 deg C
CW Inlet
CW Inlet
CW Output
CW Output
Boiler
Flue Gases
From GT
Exhaust
Boiler
Flue Gases
From GT
Exhaust