Da Nhim Hydropower Plant Expansion Project

Bidding documents Package 12.02 (DNE-D2)

SCHEDULE T-9 Organization Chart and Manning Schedul


Name of Bidder:

LILAMA 18/LILAMA 45.4 JOINT VENTURE


1

2
2.1

Organization Chart and Manning Schedule.


(To be attached herewith)
T-9-1 Head office Organization Chart
T-9-2 Site Organization Chart
T-9-3 Manning Schedule
Description of the site organization chart.
Project Manager:
- The Project Manager is assigned by Project Management Board - to be in charge of management of
Project.
- Act as the first line contact for issue related to contracts, budgets, and service performance.
- Manage the project to meet the requirements of project.
- Manage all of joint venture member and provide information to the construction team.

2.2

Technical Mangement Specialisst

- The Technical Management specialist is assigned by Project Management Board - to be in charge of


documents and construction control.
2.2

Design Unit & Chief Design Engineer:

- The Design Unit is assigned by LILAMA 18 JSC. - to be charge of management of the design & doc
- Chief Design Engineer has the responsibility to review the technical documents and design consulta
2.3

Site Manager:

- The Site Manager is the head of the project management team at site. The Site Manager is responsib
management review, ensuring that the quality system is effective and valid for the project, that non-co
and acted and that all personnel performing Work affecting quality are qualified for the task. The revie
however the results of the review are brought back to Site Manager for action.
- He shall coordinate with Owner representatives & concerning Parties at site to check up the time sch
approved by the Owner and quality of on-going works.
2.4

Chief Site Engineer:

- With direct authority from the Site Manager, is responsible for all fabrication and construction activi
utilized within the project and convening weekly progress meeting with the project team to review sta
engineering and drawing production, procurement and delivery schedule, safety and other associated p
2.5

Quality Control Representative:

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

- Responsibilities for the implementation of the quality assurance plan and for the activities affecting
scope of works. Prepares the internal Audits schedule and works with others to identify and control no
up the project QA/QC team and takes necessary action to ensure the proper co-ordination of project qu
- The QCR monitors the point of receipt for engineering information received from Owners Enginee
received is scheduled and issued to the appropriate section of Owners Engineer.
2.6

HSE Manager & Officer:

- Implementing the HSE Plan and reviewing safety performance on the project. Maintain a safety pro
activities at the Shop Fabrication and in site installation.
- Preventing and stopping any unsafe practice in the yard and setting up safety standards procedures w
the level of safety awareness in any area within the construction facility.
2.7

Supervisor:

- The Supervisor will instruct & manage The works directly to working teams, he shall assign The wo
control what they have performed or not yet done and help them in technical matters. he shall work wi
and foreign specialist to execute The work properly as required by design drawings, prepare quantity a
The Owner for payment, make report to Site Manager frequently so that he can adjust The planning if
of completion The project timely and with high quality of work.
2.8

QC Supervisor:

- QC Engineer has responsibilities for the coordination of the QA/QC surveillance effort at the faciliti
with correspondence and queries arising forms these activities. In addition he prepares the Shop Inspe
the procured materials and equipment.
3

The working relation between the managing office and the managing work at the Site.

- The Departments at the Head Office of LILAMA 18, LILAMA 45.4 should support the Site constru
demand from them quickly and effectively concerning to man power, material supply, working machin
- The concerning department will base on the requisition sheet sent from the working site to solve the
requisitions have been prepared in advanced before or right after starting work so that the company ca
material, labor, machinery etc from the site.
- All relating manager shall contact with the Site Manager permanently to know what is going on and
execution of the Contract will always be controlled well.

Bidders Official Repre


Signature:
Name: Trn S Qunh
Position: General Direc
Date:
Company: LILAMA 18
Company Stamp:

anization Chart and Manning Schedule

45.4 JOINT VENTURE

anagement Board - to be in charge of management of the whole works of the

contracts, budgets, and service performance.


f project.
de information to the construction team.

ed by Project Management Board - to be in charge of management of technical

SC. - to be charge of management of the design & document works.


o review the technical documents and design consultancy.

nagement team at site. The Site Manager is responsible to conduct periodic


stem is effective and valid for the project, that non-conformance is being identified
k affecting quality are qualified for the task. The review may be delegated,
ck to Site Manager for action.
s & concerning Parties at site to check up the time schedule which has been
works.

responsible for all fabrication and construction activity. Control the manpower
progress meeting with the project team to review status of project schedule
nt and delivery schedule, safety and other associated project issues.

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

quality assurance plan and for the activities affecting quality within the project
edule and works with others to identify and control non-conforming product. Heads
action to ensure the proper co-ordination of project quality activities.
ineering information received from Owners Engineer and ensures that information
te section of Owners Engineer.

ety performance on the project. Maintain a safety program covering construction


allation.
the yard and setting up safety standards procedures where necessary to improve
he construction facility.

orks directly to working teams, he shall assign The work even to each worker and
e and help them in technical matters. he shall work with The Owner representatives
rly as required by design drawings, prepare quantity acceptance report to submit to
nager frequently so that he can adjust The planning if necessary to reach The target
quality of work.

ination of the QA/QC surveillance effort at the facilities of vendors and for dealing
hese activities. In addition he prepares the Shop Inspection and Test Plan (SITP) for

office and the managing work at the Site.

MA 18, LILAMA 45.4 should support the Site construction team to solve any
rning to man power, material supply, working machinery & tools
quisition sheet sent from the working site to solve the matter. Normally, the
ore or right after starting work so that the company can fulfill the request of

Manager permanently to know what is going on and what the site need so that the
ed well.

Bidders Official Representative:


Name: Trn S Qunh
Position: General Director
Company: LILAMA 18 Joint Stock Company.
Company Stamp:

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

SCHEDULE T-9-1 Head Office Organization Chart


Name of Bidder:

LILAMA 18/LILAMA 45.4 JOINT VENTURE


Owner
PMB (Joint Venture)
Project Manager
QA/QC Dept.
HSE Dept.
Administration Dept.

Bussiness & Tech. Dept.


Procurement Dept.
Finance & Accounting Dept.
Const. Machinery Dept.
Technical Management Specialist

Chief Design Engineer

Design Unit (IHR)

Site Manager

LILAMA 18
Purchasing of Steel PenStock
Fabrication of Steel PenStock
Sand blasting & Painting Work for Steel
PenStock

Bidders Official Representative:


Signature:
Name: Trn S Qunh
Position: General Director
Date:

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

Company: LILAMA 18 Joint Stock Com


Company Stamp:

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

ad Office Organization Chart

ENTURE

LILAMA 45.4
Purchasing and Logistics of
Equipments
Fabrication of Equipments
Transportation, Installation &
Adjustment Work
Sand blasting & Painting Work for
Equipments
Commisioning Work

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

Company: LILAMA 18 Joint Stock Company.

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

SCHEDULE T-9-1b Head Office Organization Chart


Name of Bidder:

LILAMA 18/LILAMA 45.4 JOINT VENTURE


Institute for Hydropower and
Renewable energy
CONSULTANT CENTER

Design at IHR

Works design

Mechanical Design

Design and fabricate the hydro- mechanical equipment and intake water
gate and gate of plant downstream suction chamber

At Site

Inspect document

Design and fabricate the penstock

Supervising

Supervise the manufacturing of Intake


hydro-mechanical equipment and
valve gate

Supervise the manufacturing of


penstock

Bidders Official Representative:


Signature:
Name: Trn S Qunh
Position: General Director
Date:
Company: LILAMA 18 Joint Stock Compan
Company Stamp:

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

ead Office Organization Chart

VENTURE

Design at Site

Supervise the erection of vale gate,


open/close machine and penstock

Company: LILAMA 18 Joint Stock Company.

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

SCHEDULE T-9-2 Site Organization Chart


Name of Bidder:

LILAMA 18/LILAMA 45.4 JOINT VENTURE


Site Management Board
1-Site manager
2-Deputy Site manager
QA/QC Dept. (04 per.)
HSE Dept.

Material Control Team


Mat. Supervisor: 01 per.
Safety officer: 01 per.
Foremen: 02 per.
Worker: 20 per.

Chief Site Engineer for


Fabrication of Equipment
<LLM 45.4>

Chief Site Engineer for


Installation & Adjustment
Work
<LLM 45.4>

Equipment Fabrication Team

Penstock Erection Team

Tech. Supervisor: 01 per.


Safety officer: 01 per.
Foremen: 02 per.
Worker: 30 per.

Tech. Supervisor: 02 per.


Safety officer: 03 per.
Foremen: 04 per.
Worker: 96 per.

Equipment Erection Team


Tech. Supervisor: 01 per.
Safety officer: 01 per.
Foremen: 01 per.
Worker: 25 per.

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

E T-9-2 Site Organization Chart

T VENTURE

Administration Dept.
Const. Machinery Dept.

Chief Site Engineer for


Fabrication of Steel PenStock
<LLM 18>

PenStock Fabrication Team


Tech. Supervisor: 03 per.
Safety officer: 01 per.
Foremen: 02 per.
Worker: 140 per.

Scaffolding Team
Scaff. Supervisor: 01 per.
Safety officer: 01 per.
Foremen: 01 per.
Worker: 20 per.

Bidders Official Representative:


Signature:
Name: Trn S Qunh
Position: General Director
Date:
Company: LILAMA 18 Joint Stock Company.
Company Stamp:

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

SCHEDULE T-9-3 Manning Schedule


Name of Bidder:

LILAMA 18/LILAMA 45.4 JOINT VENTURE


6th

7th

8th

9th

10th

11th

12th

13th

14th

Time Schedule
15th
16th
17th

Jan-16

Feb-16

Mar-16

Apr-16

May-16

Jun-16

Jul-16

Aug-16

Sep-16

Oct-16

Nov-16

1 Head office
1.1 Project Manager

###

###

###

###

1.2 Deputy Project Manager

###

###

###

###

###

###

###

###

1
1

1
1

1
1

###
###

1
1

###
###

1
1

1
1

###
###

1
1

1
1

###
###

1
1

1
1

###

###

###

###

###

###

###

###

1
2
4
4
4
4
5

1
2
4
4
6
8
7

1
2
4
4
8
11
10

1
2
4
4
8
11
12

###
###
###
###
###
###
###

1
2
4
4
8
11
12

1
2
4
4
8
11
12

###
###
###
###
###
###
###

1
2
4
4
8
11
12

1
2
4
4
7
11
8

###
###
###
###
###

1
2
3
4
7

1
2
3
4
7
8
8

No.

1.3
1.4
1.5
1.6
1.7
2
2.1
2.2
2.4
2.5
2.6
2.7
2.8

Description

Technical Management
Specialist
HSE Manager
QA/QC Manager
Purchasing and Logistics
Manager
Chief Design Enginner
Construction Site
Site manager
Deputy Site manager
Chief Site Engineer
QA/QC Supervisor
Safety officer
Supervisor
Foremen

###
###
###
###
###
11
12

Dec-16

8
###

18th

19th

Jan-17

Feb-17

###
8

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

No.

Description

6th

7th

8th

9th

10th

11th

12th

13th

14th

Time Schedule
15th
16th
17th

18th

19th

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

T-9-3 Manning Schedule

VENTURE
Time Schedule
20th

21st

22nd

23rd

24th

25th

26th

Mar-17

Apr-17

May-17

Jun-17

Jul-17

Aug-17

Sep-17

###

###

###

###

###

###

###

###

###

1
1

###
###

1
1

###
###

1
1

1
1

###
###

###

###

###

###

###

###

1
2
3
4
7
8
8

###
###
###
###
###
###
###

1
2
3
4
7
8
8

###
###
###
###
###
###
###

1
2
3
4
7
8
8

1
1
3
4
3
3
5

###
###
###
###
###
###
###

Bidders Official Representative:


Signature:
Name: Trn S Qunh
Position: General Director

Remark

Da Nhim Hydropower Plant Expansion Project


Bidding documents Package 12.02 (DNE-D2)

Time Schedule
20th

21st

22nd

23rd

24th

25th

Date:
Company: LILAMA 18 Joint Stock Company.
Company Stamp:

26th