You are on page 1of 12

IPASJ International Journal of Management (IIJM)

Web Site: http://www.ipasj.org/IIJM/IIJM.htm


Email: editoriijm@ipasj.org
ISSN 2321-645X

A Publisher for Research Motivation........

Volume 3, Issue 6, June 2015

Lean Office applied to ICT Project


Management: Autoparts Company Case Study
Pedro Domingos Antoniolli, Carlos Roberto Camello Lima, Ana Rita Tiradentes Terra Argoud,
Joo Batista de Camargo Junior
Pedro Domingos Antoniolli
UNIMEP, Brazil
Carlos Roberto Camello Lima
UNIMEP, Brazil
Ana Rita Tiradentes Terra Argoud
UNIMEP, Brazil
Joo Batista de Camargo Junior
UNIMEP, Brazil

ABSTRACT
As result of Globalization, enterprises should act properly on very aggressive and competitive markets. To achieve this goal, not
only product development cycles should be decreased, but also new added value services and products must be created, which,
in turn, are delivered as a result of successful projects. Besides, ongoing processes have to be continuously reviewed, in order to
eliminate losses of efficiency and/or effectiveness. Lean Thinking principles are indicated to achieve better processes
performance, through reduction of delays, waste, inventory levels, over processing and over production, also improving
information quality, essential for competitiveness (WOMACK and JONES, 2003). Yet, as a result of markets globalization, new
levels of competitiveness are in place, marked by quick and deep changes in cultural, social, economic and technological basis,
forcing organizations to find more effective ways to respond to these requirements. In this sense, projects become foundation to
implement new goods and services, being important to conclude them successfully. Festa and Assumpo (2012) argue that
projects that involve ICT (Information and Communication Technology) applied to logistics businesses result in "changes in
processes with improved asset utilization, yielding higher productivity and quality / consistency in operations, reducing waste
and delivery times". Additionally, Hartman and Ashrafi (2002) point out that ICT is one of the fastest growing sectors in
emerging countries. Thus, it is mandatory that projects be concluded within predefined conditions of time, cost, quality and
scope (PMBOK, 2013). Besides, project management has been consolidated into companies due to its high potential value they
provide, allowing that project results are delivered on time, budget, scope and quality, which is especially important for ICT
projects, for which innovation is usually present. For such, the correct resource allocation, and effective application of project
management techniques and methodologies improve success chances. This work presents a case study of project management
processes, based on the PMBOK (Project Management Body of Knowledge) practices into Latin America Information
Technology initiatives of an Autoparts Company. Additionally, this paper presents the relationship among these practices with
Lean Office elements, which causes positive impacts.

Keywords: Information Technology, Lean Office, PMBOK, Project Management

1. INTRODUCTION
Market globalization raised new sharpened competition level, based on rapid technologic, economic, commercial and
cultural challenges, directing companies to answer quickly and precisely to these threats, to keep sustainable on these
markets.
Douglas and Craig (1989) and Yip (1989) state that globalization in business context can be understood as the
development of internationalization strategies of companies". Hilletofth et al. (2009), on the other hand, argue that
because of competitiveness increase, enterprises are forced to offer greater variety of customized products, with
increasingly smaller life cycles, thus achieving better value for the enterprise resources usage.
Abdulmalek et al. (2007) define value as equivalent to something that the consumer is willing to pay for a product or
service. For Hansen and Mowen (2001), competitive advantage can be defined as "the creation of a better value to the
customer by an equal or lower cost, than that offered by competitors".
As response to this increased competitiveness, enterprises generally give two kinds of answers to this increased
competition: operational efficiency, which represents optimized management of scarce resources; and small and
continuous improvements of its business processes. Lima, Garbuio and Costa (2009) say that continuous improvement
has been frequently linked to Total Quality concept, and it can also be applied to other circumstances. Caffyn (1999)

Volume 3, Issue 6, June 2015

Page 9

IPASJ International Journal of Management (IIJM)


A Publisher for Research Motivation........

Volume 3, Issue 6, June 2015

Web Site: http://www.ipasj.org/IIJM/IIJM.htm


Email: editoriijm@ipasj.org
ISSN 2321-645X

complements, considering continuous improvement as an incremental innovation process, which involves the
enterprise as a whole.
An important application of continuous improvement approach is given by Lean Thinking principles, which are
focused on efficiency search, and on avoidance of activities that do not add value to the process, means that these
activities become constraints for organizational performance.
Souza and Carpinetti (2014) argue that enterprises competitiveness requires not only innovation, but also processes
optimization and cost reduction initiatives, which represents operational improvements, resulting in high quality
products to increasingly demanding markets. Taj and Morosan (2011) and Gurumurthy and Kodali (2011)
complements, explaining that the approach to implement lean production gains importance as a mechanism for
achieving organizational effectiveness. This happen due the fact that lean focus relies in the operational efficiency and
effectiveness, reduction of non-value added activities, thus becoming crucial for enterprises.
Thus, lean thinking can be understood as a generalization of Lean Production that, based on Rebelato et al. (2009),
became important source of quality. This concept was initially applied to Toyota Corp, in the 1950s, by the engineer
Taiichi Ohno. Piercy and Rich (2009) complement, explaining that both concepts and lean production techniques has
been increasingly used in administrative processes, called lean office, or lean service.
Womack and Jones (2003) stated that "the essential starting point for lean thinking is the value, that can be defined
only by the final customer. And it is only meaningful when expressed in a specific product that meets customer needs,
at a specific price and time". For Rother and Shook (2003), a value stream comprises all necessary and essential activity
for which a product or service passes, and which result in a monetary benefit that outweighs this activity costs. The
authors state that, when considering the prospect of the value stream, the context is broader, leveraging the whole
process, not only individual tasks. Rudberg and Olhager (2003) extend the concept to the value network, which consists
of facilities in which the usefulness of time, place and/or manner are added to the product in several stages, so that the
perceived value by customer is greater. Thus, value creation comes from the set of activities performed in a particular
case for which lean principles can be applied.
Regarding constraints, to Womack and Jones (2003), there are seven classic inefficiency types: waiting, defects,
transportation, movements, inventory, overproduction, and super processing. Additionally, the authors propose five
principles that guide the implementation of lean principles: (1) define value from the customer perspective; (2) identify
the value stream for each product family; (3) create a flow through the value adding activities; (4) extract value from
subsequent activities; (5) eliminate waste and pursue perfection.
As so important as the process, the management is also essential. In this sense, Lima, Pereira and Souza (2009) argue
that management models include contemporary projects within the company. Thus, projects are, in various areas,
essential to implement new goods and services. With the increasing competitiveness of industrial complexity, and the
difficulties of business decisions, the pressures for successfully complete projects, and thus results, increase.
In terms of innovation, Van Ark (2001) explain that the ICT diffusion in all economy areas constitutes a prerequisite
for the technology potentially generate positive impacts into economic growth and productivity.
This paper aims to relate the Lean Office principles present in PMBOK (Project Management Book of Knowledge)
practices, and verify the results obtained by Project Management Office (PMO) implementation, at Autoparts industry.

2. METHODOLOGY AND JUSTIFICATION


Marconi and Lakatos (2002) argue that a problem must be clearly and objectively defined. Thus, the problem being
investigated in this article is described by the question:
Which Lean Office principles are addressed in the PMBOK project management practices of a Project Office
(PMO) in an Autopartss industry?
Based on this context, basic assumptions include:
Performance of ICT projects might be positively influenced by the use of lean thinking techniques and processes;
PMO is responsible to share good practices in order to improve project management activities;
Lean thinking has been proved, based on the reviewed literature, important component to processes improvement;
Sila and Menezes (2000) argue that a research can be classified under four dimensions: nature, approach, objectives
and technical procedures.
These authors indicate that, with respect to its nature, a research can be considered basic or applied. This article is
classified as an applied research because it focuses theoretically in discussing the concepts and applications of lean
thinking on ICT project management, based on the PMBOK.
With regard to how to approach the problem, Silva and Menezes (2000) explain that research can be classified as
quantitative or qualitative. This article is classified as qualitative research due to the method of interpreting the data,
being its main focus on the process and its meaning.
Silva and Menezes (2000) argue that, in relation to the objectives, research can be classified as exploratory, descriptive
or explanatory. This work is characterized as a descriptive survey because it involves the available literature review,

Volume 3, Issue 6, June 2015

Page 10

IPASJ International Journal of Management (IIJM)


A Publisher for Research Motivation........

Volume 3, Issue 6, June 2015

Web Site: http://www.ipasj.org/IIJM/IIJM.htm


Email: editoriijm@ipasj.org
ISSN 2321-645X

and proposition of lean thinking principles to support ICT projects management.


Talking about technical procedures, Silva and Menezes (2000) indicate that a research can be categorized as:
bibliographic, documentary, experimental, survey, case study, research, ex-post-facto, action research or participatory
research. This research is based on concepts and techniques described in the literature, and these techniques application
in an ICT project, within an auto parts manufacturing company, being therefore classified as bibliographic.
Additionally, the characteristic of the application of these concepts in a particular case falls into the procedures of case
study.
The choice of case study is contingent and convergent with the nature of the problem, and the current state of
knowledge. The following considerations justify the chosen method:
This study focus in the lean thinking principles applied to ICT projects management, specifically on PMO (Project
Management Office) establishment, being the available literature on this topic scarce;
The knowledge level lies on development early research stages. Thus, case study proves to be the most appropriate
approach for the proposed research. As suggested by McCutcheon and Meredith (1993), Yin (1989) and Eisenhardt
(1989), this approach is typical in the early stages of the development of theory, where events or phenomena, have
little or no cataloged knowledge;
There are not yet published a precise idea of which lean thinking principles, techniques and variables that
contribute to improve potential success of ICT projects. Thus, these elements should be clarified during the
research process, with continuous comparisons between the evidence of the case and the literature. As a result, the
problem detailing will be refined during the study (EISENHART, 1989);
Research of the lean thinking application to ICT projects requires the researcher to place the events in a
chronology, to determine causal connections. By doing this, the case study becomes the initial basis for such causal
references (YIN, 1989).
Thus, this article aims to corroborate the relevance of the concepts presented in the literature and in the industry about
the PMBOK, to improve projects success on ICT projects, supported by lean thinking principles.

3. LEAN OFFICE
Lean Office is considered an application of lean manufacturing, where is their source, and maintain its principles,
minimizing and, where possible, eliminate losses / inefficiencies in business processes.
To Womack and Jones (2003), the main sources of losses are:
Over processing: that includes greater use of effort to a service / process / information that required, for what
customers are not willing to pay;
Transport and movement: Are unnecessary movements of people, materials or resources, throughout the process;
Stocks: Although stocks are used as protection mechanisms against variability of the process, to Lean any stock
above what is necessary for customer service should be avoided, because it is translated in cost and additional
processing;
Wait Times: The expression here considers all delays or times when a material / service have to wait to be
processed. It can also be categorized as expected delays in processing slower than the standard;
Defects: Defects are considered all aspects of the product or service that does not conform to customer needs
internal or external to the process. This category includes missing information, non-compliance of terms and
conditions that result in additional work;
Over Production: Production above what is required for immediate use. The over production may be result of a lack
of priority setting, or visibility of customer demand. Overproduction has another downside, which is the use of
resources for priority processing elements, and consequent lack of focus, which cause unavailability of these
resources to essential activities.
For Lareau (2002) losses in administrative processes (Lean Office) are classified into:
Lack of goals alignment: This includes the time spent by poorly defined goals and the effort required to fix any
problems / produce effective results;
Over-allocation: employee effort to complete a task inappropriate / not required;
Waiting: Time lost by waiting for information on meetings, for signatures / approvals, and returns of phone calls;
Movements: Time and effort employed in unnecessary movements;
Reprocessing: Results of a work conducted inefficiently;
Excessive control: Every activity and effort used to control and monitor, but did not produce improvements in
performance;
Variability: This includes the use of resources used to compensate or correct results that vary beyond the expected;
Lack of Standardization: Requires additional energy used in a job, because this was not done the best possible way,
by all those responsible;

Volume 3, Issue 6, June 2015

Page 11

IPASJ International Journal of Management (IIJM)


A Publisher for Research Motivation........

Volume 3, Issue 6, June 2015

Web Site: http://www.ipasj.org/IIJM/IIJM.htm


Email: editoriijm@ipasj.org
ISSN 2321-645X

Irregular Flow: Effort or resources applied to information or materials accumulated between the work centers,
which causes waste due to irregular flow;
Lack of Focus: Occurs when the energy and attention of an employee are not focused on organizational critical
objectives.
According to Rebelato et al. (2009), initially processes should be mapped for identifying sources of inefficiency, and
then taking actions to correct the lower performance. Additionally, setting performance targets helps to maintain
current and increasing level of performance, informing where the company can reduce waste.
Picchi (2002) highlight some Lean tools:
Value Stream Mapping or VSM: It is a fundamental tool to map the flow of materials and information. He supports
the identification of essential activities (value added), and activities that consume resources, preferable to be
eliminated;
Standardized Work: This includes the establishment of standardized procedures and documentation in order to
improve the results achieved, and the possibility of using metrics to measure performance, thereby optimizing it
when needed;
Pulled Systems: The administrative environment is crucial to understand the processes subsequent to an activity, so
the service can flow properly, and the result is available in time and as expected, neither before nor after.
Hunter and Westerman (2009) reported that alterations in processes require more than simply eliminating activities and
/ or redirect task flows. Authors state that it is important that entire organization be mobilized this direction, since
behavior change and roles, through internal structures review, and establishing a system of recognition (or not based on
monetary rewards), linked to reduction targets waste.
For Souza and Carpinetti (2014), during processes evaluation, the transformation of the current state to the future
comprises a continuous improvement process, which considers the existence of many Kaizen projects for elimination
and / or reduction of all types of waste, that becomes a barrier to obtaining lean processes. According to the authors, a
fundamental aspect of lean production implementation plan is to decide what types of waste should be prioritized.
Imai (1986) defines Kaizen as "occasional or continuous improvement in social, family, and professional. In the
workplace, Kaizen means continuous improvement in the participation of all, managers and other employees. Newitt
(1996) complements, explaining that Kaizen word is derived from two Japanese kanji, KAI = change, and ZEN = good
(for the better).
Surez-Barraza and Miguel-Dvila (2011), by the other hand, indicate that the Kaizen is "a set of personal principles
that make you grow as a person, and that assumes that your way of life - whether at work, social, or family - deserve to
be constantly improved ".
Oduoza (2008), on the other hand, adds that lean systems enable that best practices be incorporated into business
processes, such as JIT (Just in Time), TQM (Total Quality Management), continuous improvement, resource planning
and management of SCM - Supply Chain Management.
According to Peters (2010), due the fact that the lean have their focus both on increasing the value of processes, and in
the waste avoidance, it has become one of the most important approaches to improving business performance in recent
decades. Ballard and Tommelein (2012) argue that lean is a management approach that had its origin in the automotive
industry, started to be applied initially in other forms of repetitive manufacturing, and most recently in services
processes and companies.
Hines and Taylor (2000) define five steps to eliminate waste, serving as a set of actions to be taken in order to
obtain lean processes:
Map, in the processes, activities undertaken and identify in these tasks, the degree of value added (for client and
enterprise);
Search processes redesign, in their flow operations, eliminating interruptions, detours, delays and other non-value
added activities;
Perform only activities that contribute to the addition value, based on the perception of the end user, without the
use of additional efforts (overproduction);
Constantly evaluate the flow and removing new sources of inefficiencies, as far as they are discovered.
Liker and Meyer (2007) define four (4) "Ps", representing lean principles:
Philosophy: It constitutes the basis for the long-term vision, in which managers perceive the organization as a
means of adding value to stakeholders;
Process: These are the core elements of adding business value, which means, if adjusted they produce relevant
results;
People and Partners: Represent the elements with which the Organization should keep long-term relationship and
requiring ongoing development;
Problem solving (Troubleshooting): The search for the root cause of the problems, and the correct treatment of
these problems lead to organizational learning;

Volume 3, Issue 6, June 2015

Page 12

IPASJ International Journal of Management (IIJM)


A Publisher for Research Motivation........

Volume 3, Issue 6, June 2015

Web Site: http://www.ipasj.org/IIJM/IIJM.htm


Email: editoriijm@ipasj.org
ISSN 2321-645X

Based on the four (4) "Ps" of the lean, Liker (2006) proposes the following principles:
1st Principle: administrative decisions should be based on long-term philosophy, even if sometimes the financial
goals have to be despised;
2nd Principle: should be established a continuous process flow so that problems can be identified;
3rd Principle: should be used "pulled" systems to avoid overproduction and over processing. The JIT and Kanban
allow the reduction of inventories. In addition, the problems are visible and there are conditions to eliminate them
at their source;
4th Principle: heijunka - The workload must be leveled;
5th Principle: the company culture must be molded / built / adapted to stop and solve problems as they arise, to
obtain the desired quality the first time - jidoka;
6th Principle: standardization is the basis of continuous improvement, and training employees;
7th Principle: visual control must be applied, so that problems are apparent (not hidden);
8th Principle: reliable and fully tested technology that meets employees and processes must be used;
9th Principle: search developing leaders who understand the work and its subsystems, living the lean philosophy,
and feel good in teaching others;
10th Principle: pursue the development of people and high-performance teams, and that follow the company
philosophy and culture;
11th Principle: see and understand fully the situation and its implications (Gemba);
12th Principle: take decisions slowly, by consensus, and consider all options. However, implements them quickly.
Other authors, however, consider that these principles are components of a enablers structure, which if applied
correctly, have great influence for the company to create streams of lean business processes, maximizing value for
customer and company. These enablers are techniques, practices, and methodologies that support lean principles
(LEAN ENTERPRISE INSTITUTE, 2007; MARRAS, 2005; RIBEIRO and MEGUELATI, 2002; SIMO, 2003;
SLACK et al., 2002; SODERQUIST and MOTWANI, 1999), and are compounded by:
a) Just in Time (JIT): JIT comprises the supply of materials required for a process step at the time, quantity, and
quality required. It assumes processes with low disturbance and high internal reliability, so it can avoid the usage
of stocks, as protection mechanism. In addition, due to agility and less material handling, and also the use of
smaller lots, JIT provides flexibility and shorter lead times;
b) Kanban: this is a mechanism that authorizes and guides the production or output items in a pull production system.
So, the consumer is the one who starts the production cycle, and the work is pulled to the extent necessary;
c) Program leveling (heijunka): It applies in cases where there is a definite cycle, since it uses a balanced mix of the
daily production schedules that are set for the production of each product. Thus, it is easier to monitor compliance
with production orders avoiding, at the same time, excess inventory and increased costs / lead times;
d) Setup Time Reduction: The time of set up is conceptually a waste because there is a temporary interruption in
production. The smaller the setup time, greater is the flexibility and productivity of the system. One can reduce
waste in activities like searching tools, and pre-preparation tasks;
e) Involvement: the commitment of employees to enable them to feel part of the process to take on more
responsibilities and more fully use their skills. They are trained and motivated to take on new responsibilities in
carrying out their work;
f) Visual management: mechanisms that are used to facilitate understanding of the operations statuses. The content
and form vary, but the most common are the performance measures, indicator lights charts, control charts,
checklists and visible improvement techniques, among others;
g) Streaming: The purpose is to produce and move one item at a time throughout the process, that is, each step carries
out only what is demanded by their "client", the next phase of the process. Assembly lines or work cells may be
used;
h)Poka-yoke: These are devices or systems foolproof, which means, implemented methods that prevent that
employees make mistakes in the execution of their activities, such as choice of part, assembly, activity sequencing,
etc;
i) 5S: Which consist of organizational practices, housekeeping and discipline in the workplace. Are useful for the
visual management and lean production (sense of use, organization, cleanliness, standardization, and selfdiscipline);
j) Workforce multi skilled: is the working practice that considers the constant development of employees, that is, they
can acquire skills and abilities to work in more than one process;
k) Total Productive Maintenance (TPM): Includes the constant and effective maintenance of production facilities to
ensure that the production process are available and with maximum effectiveness to accomplish their tasks;
l) Value stream mapping (VSM): Process mapping that considers all stages of the flow, containing the information

Volume 3, Issue 6, June 2015

Page 13

IPASJ International Journal of Management (IIJM)


A Publisher for Research Motivation........

Volume 3, Issue 6, June 2015

Web Site: http://www.ipasj.org/IIJM/IIJM.htm


Email: editoriijm@ipasj.org
ISSN 2321-645X

needed to serve customers in the delivered period. They can be drawn at different times in order to reveal
improvements opportunities;
m)Empowerment: aims to give greater autonomy to employees to make decisions in times and places where they
occur and are needed, which can prevent time losses on decisions process escalation to higher hierarchical levels.
Empowerment also increases employees commitment.
Panizzolo et al. (2012) and Jadhav et al. (2014) state that in the last ten years, even industrial companies located in
emerging countries such as China and India, are working to transform their low cost and intensive labor production
processes into high production value added, more flexible and productive, based on lean production systems.
Stone (2012), on the other hand, explains that over the last decades, lean principles are applied beyond the boundaries
of manufacturing, in processes such as performance enhancing mechanisms. Bhasin. (2012) complements, pointing
lean as a business model that delivers superior performance for customers, employees, and stakeholders in general. For
Chual et al. (2010), lean operations enable the company to reduce waste and optimize, in general, the activities of its
value chain.
Malmbrandt and Ahlstrom (2013) state that, although service companies search to adopt lean practices, research
involving lean applications in services is still at an early stage. In this sense, preliminary studies of Bowen and
Youngdahl (1998) relate the applicability of lean practices in service enterprises. Later were released conceptual studies
with contributions to adapt lean practices, originally designed for manufacturing, into services (AHLSTROM, 2004).
Balle and Regnier (2007), and Proudlove et al. (2008) also presented several cases of successfully adopted lean
practices by service companies, especially in healthcare industry. However, rigorous and systematic empirical research
is scarce (MALMBRANDT and AHLSTROM, 2013). Some authors, like Pilkington and Fitzgerald (2006), indicate
that the reasons for this lack includes: lack of conceptual clarity, and definition of operational measures of attendance.
Thus, lean principles are adherent to administrative procedures. Thus, for this paper scope, they are related to project
management activities, given the importance they have on business, as a tool for empowering the delivery of new
products and services.

4. PROJECT MANAGEMENT
One project, according to Kerzner (2002), is a unique venture, which has identifiable goal, which consumes resources,
and operates at pressures of deadlines, costs and quality. For PMBOK (20013) project is "a temporary endeavor
undertaken to create a product, service or single result".
Carton et al. (2007) argue that in practice, is the project management the agent of the changes, since "every change is a
project" and that the translation of strategy inevitably results in projects. Authors state that project management
support leaders to standardize processes and tasks, and ensure that available resources are effectively allocated. In this
sense, project management principles application enables managers and leaders to establish and properly use metrics
for achieving these projects success, measured by comparing the project value added with the cost it spends. Yet,
according to Carton et al. (2007), project management is a recent management discipline, with little more than fifty
years. During this period, successful and good practices and techniques have been included in the PMBOK (Project
Management Book of Knowledge), now on its fifth edition (PMBOK, 2013).
Carton et al. (2007) explain that the PMI (Project Management Institute), organization globally recognized, is the
entity that consolidates such practices in the PMBOK. PMI has branches (chapters) worldwide, as well as thousands of
associated professionals.
A benchmarking survey conducted in 2007 by PMI (Project Management Institute) with 185 companies operating in
the Brazilian market segments, found that 78% of organizations reported problems running their projects, 64% had
problems of cost, 44% identified quality problems and 39% issues related to customer satisfaction. Additionally, about
problems found, 66% of companies reported problems with not meeting deadlines, 64% had communication problems
and 62% faced constant changes in scope (PMI, 2013).
The PMBOK (2013) defines the basic cycle of project management composite of five processes groups, which are:
Initiation: Set of performed processes to define a new project, or new phase of an existing project;
Planning: Processes required to establish the scope of the project, refine goals, and set the course of action required
to achieve the desired results;
Execution: Are the processes carried out iteratively to complete the work defined in the project management plan,
to meet design specifications;
Monitoring and Control: Processes required to track, review, control progress and project performance, and to
identify areas where a change of plan is required;
Closing: Consist of processes undertaken to complete all activities along the process groups, in order to formally
conclude the project or phase.

Volume 3, Issue 6, June 2015

Page 14

IPASJ International Journal of Management (IIJM)


A Publisher for Research Motivation........

Volume 3, Issue 6, June 2015

Web Site: http://www.ipasj.org/IIJM/IIJM.htm


Email: editoriijm@ipasj.org
ISSN 2321-645X

An important aspect of the PMBOK (2013), adherent to Lean practices, is that during all project cycle phases, lessons
learned can be recorded. These records are facts to be evaluated, avoided, solved, or applied for future projects.
According to Kerzner (2006) "every time a company not register lessons learned, it may rapidly return from maturity to
immaturity in project management. Knowledge is lost, and past mistakes are repeated".
To manage properly the forty-two processes included on five groups in the project cycle, ten knowledge areas should be
considered: integration, scope, time, cost, quality, communication, human resources, risk, purchasing, and stakeholders
(PMBOK, 2013).
Santos and Carvalho (2006) argue that project management includes a set of management procedures aimed at
planning, organization, direction and control of the aspects involved in a project, to safely achieve predefined specified
conditions and proposed objectives. The PMBOK (2013) offers nearly four hundred good market practices to support
these procedures.
Additionally, the PMBOK (2013) says it is important to measure the degree of maturity of the organization in project
management, not only to identify improvement opportunities, but also to standardize project management practices.
Neves et al. (2009) shows the five maturity levels, based on CMM (Capability Maturity Model) and OPM3
(Organizational Project Management Maturity Model).
Level 1 = Common Language: Process without standardization. Basic knowledge. Repetitions happen by accident,
without formal process management;
Level 2 = Common Processes: There is managerial support. Common goals are established for the project
management teams. Formal training occurs;
Level 3 = Singular Methodology in Place: Process control. Integrated project management and business processes.
Advanced techniques exist;
Level 4 = Benchmarking: Process Improvement. Objectives and roles defined. Well-defined metrics. Participation
of all stakeholders. Culture of risk management expertise and established project management stated;
Level 5 = Continuous Improvement: Proactive Prevention of defects. Implementing a strategy of continuous
improvement. High level of performance on projects.
Kerzner (2006) state that "the project management maturity is the development of systems and processes that are
repetitive in nature, and guarantee a high probability that each is a success".
ICT (Information and Communication Technology) projects normally involve any degree of innovation. Within this
perspective, Henderson and Clark (1990) classify innovation into four groups: incremental, architectural, modular and
radical. Authors consider that incremental innovations consolidate the enterprise competitive position. Radical
innovation, otherwise, can generate real industry change, probably because there is an effectiveness decrease of current
business skills, during the first moment.
Additionally, Dey et al. (2007) argue that project delays not only add costs for any penalties imposed by customers, but
also add costs from higher prices for goods and services, loss of company image / product, and incurred opportunity
costs.
Still concerning with innovation projects, Keegan and Turner (2002) argue that new approaches combining the existing
theory on project management, with the innovation process management are required. Lau e Kong (2006), on the other
hand, state that can be found five common constraints categories in projects: legal, economic, technical, environmental,
and social. These restrictions may, in certain conditions, lead to risks to the project objectives.
Thus, the pursuit of excellence in project management helps the company make viable products and processes, with
higher added value and thereby increasing their competitiveness.

5. CASE STUDY: THE AUTOPARTS INC


The Autoparts Inc., as it is named in this paper, to preserve the identity of the enterprise, is one American Autoparts
centenary industry, employing more than 60,000 direct workers. It has about thirty factories throughout the world.
Autoparts Inc. main product has an annual production estimated at 150 million units.
Latin America's seven strategic business units are located in Argentina, Chile, Brazil, Colombia, Venezuela, Peru, and
Mexico.
In Brazil, the Autoparts Ltd has been present since late 1930s, and currently has two plants, four sales subsidiaries, five
automotive centers, and approximately 4.000 direct employees. It has a distribution network comprising 150
distributors and about 560 sales points.
The PMO was required, once the Information and Communication Technology (ICT) area was responsible for
maintaining running the infrastructure and systems, with about 3,500 active users, 22 servers, applications, more than
60 different applications, and monthly demand of, in average, four different ICT projects.
Initially, in 2011, has hired a certified (PMP) project manager, to act inside Latin America ICT structure, reporting to
the Global PMO, that was, at this time, on its beginning, start defining a small and customized PMBOK, to fit the
company specificities.

Volume 3, Issue 6, June 2015

Page 15

IPASJ International Journal of Management (IIJM)


A Publisher for Research Motivation........

Volume 3, Issue 6, June 2015

Web Site: http://www.ipasj.org/IIJM/IIJM.htm


Email: editoriijm@ipasj.org
ISSN 2321-645X

In the sequence, a project management maturity level assessment was done, with the participation of the sixteen project
managers allocated on Latin America subsidiaries. Results showed that the ICT maturity level was 2, as ranked
accordingly to Neves et al. (2009).
Thus, Autoparts lacked standardized procedures for project management and this led, consequently, to projects
implementation failures, not only to meet deadlines, but also to achieve established targets:
Only twenty five percent of the projects met the requirements of time, quality and scope, but costs were, on
average, about 30% higher, mainly due to additional required time;
Fourty percent of the ICT projects were delivered out of time, and above the stipulated budget, mainly due to
incorrect scope and re planning recurrent issues;
Thirty five percent of these projects were cancelled, or partially implemented. Project deliverables did not meet
customer requirements.
These facts corroborate the need of performance improvements, and effectiveness to complete ICT projects, which was
adherent to the conditions reported by Lareau (2002), in which there is additional effort, re-work, excessive waiting
times, and defects, among others.
After the diagnosis, was proposed, and accepted by upper management, the establishment of a Latin America Project
Management Office (PMO), with respective process-oriented organizational structure, and allocation of project leaders
to attend the major functional business areas: manufacturing, finance, marketing, and logistics.
According to PMBOK (2013), a PMO is an organizational entity, which is marked for various responsibilities, like
projects coordination and management, ranging from the provision support functions of management, as methodology,
to direct management of a project. PMO is a point of reference for project managers, and also the source of cultural
change in project management (KERZNER 2002).
Thus, the creation of a PMO within Autoparts Inc. aims for the dissemination, capacity building and establishment of
best market practices with regard to project management. This fact, according to Crawford (2002), is directly associated
with the minimization and avoidance of major project failures.
Throughout 2012, the PMO team, along with an external advisory firm, held several training sessions for IT
professionals. Were also implemented several procedures, software, forms and techniques, including risk management
and communications.
In analyzing the main causes of project failures, was identified that imprecise scope definition is one of the sources of
inefficiencies, generating conflicting expectations by stakeholders, and execution of many and additional activities,
without added value.
As one of the first actions was to set up a formalized procedure for drawing up the scope of projects, using as basis the
Project Charter, which according to the PMBOK (2013), is the initial document that formalizes the project start, and
contains the key elements needed for a correct definition of the project.
Additionally, project development process was formalized, considering the interactions between the different areas of
design and IT stakeholders. For this analysis, Lean tool VSM (Value Stream Mapping) was selected, which allowed
that non added value tasks were identified and removed. This fact alone has brought an average reduction of 15% in
development time of projects.
Metrics and performance results were generated, and a knowledge base of projects was created. This database records
main difficulties and solutions found in the development cycle of projects. Lessons learned could be registered for
subsequent projects.
The communication process was improved. During the planning phase of the project was drawn up a spreadsheet for
the identification and registration of all stakeholders, considering their main characteristics, expectations, levels of
influence, form and frequency of communication. This document served as a basis to formalize the follow-up meetings
of the project, as described in the PMBOK (2013).
Besides, was implemented an approach called Stage & gates, which consists of gates reviews during the project cycle
life, to fulfill two targets: validate all concluded tasks and deliverables; and to formally authorize the next phase. This
was adherent of lean principle, to check all production steps as soon as possible, to avoid work on defective pieces,
generating inefficiencies, and rework, as stated by Lareau (2002).
Was also established a tool to help manage risks in projects, consisting of quality and quantity risk evaluations. This
tool calculates, through statistical formulas, the evolution of risks as the project conditions change. Thus, the risks are
managed appropriately, and contingency plans are developed for cases where risks can not be transferred, or avoided.
In status meetings are presented main achievements and constraints of the project, which require specific actions and
decisions.
At the middle of 2012, implemented actions began to deliver results, and the index of completed projects within the
requirements increased to about 70%.

Volume 3, Issue 6, June 2015

Page 16

IPASJ International Journal of Management (IIJM)


A Publisher for Research Motivation........

Volume 3, Issue 6, June 2015

Web Site: http://www.ipasj.org/IIJM/IIJM.htm


Email: editoriijm@ipasj.org
ISSN 2321-645X

Furthermore, with the implementation of the Project Charter scope improvements, the average time for completion of a
project fell by more than 30%, and the budget for these projects decreased by 30%.
The number of projects with re-planning tasks also fell below 25%, and yet for changes requested by customers after
the signing of the Project Charter, and not for inaccuracy in the planning of the project scope.
Due to project management procedures standardization, maturity level rose to 3, according to the classification of
Neves et al. (2009) because there are unique and repeatable methodology, and establishment of project management
best practices (PMBOK, 2013).
Generally, in accordance with Lean principles described by Lareau (2002) and Womack and Jones (2003), practices
implemented in the process decreased losses.
Table I is an attempt to relate the phases of project management PMBOK (2013) with the main sources of loss
described on Lean, submitted by Lareau (2002), and it is based on observation of developed projects within Autoparts
Inc., from August, 2011 to June, 2012. This analysis requires, however, further investigation, considering each
particular process within groups in the development cycle of projects.
Table 1: Lean Opportunities on Project Management Cycle

6. FINAL CONSIDERATIONS
This paper started with a literature search about Lean concepts and principles, as well as its applicability to business
processes in order to reduce losses and therefore, increase effectiveness.
In the sequence, were identified concepts and principles to be applied to ICT project management, which were
consolidated into PMO (Project Management Office) roles and responsibilities.
As stated by Womack and Jones (2003) and Rother and Shook (2003), the main objective of the implementation of lean
practices is to eliminate inefficiencies. The contribution of lean principles to guide PMO tasks in order to improve
projects success, generates added value in conducting projects, especially in avoiding rework, delays and defects, with
impacts on cost, time and scope the project.
In this sense, as argued by Prado (2004), project management is one of the viable ways that make projects possible to
achieve results, and to deliver value to the enterprise, and to the customer.
As presented by the case study of Project Management Office (PMO) implementation in an Autoparts industry, was
possible to identify positive results on project management discipline inside the company.
With the use of the PMBOK (2013) practices, as well as the application of Lean principles, significant results were
obtained in project management, which enabled gains in productivity, assertiveness in delivering results, investments
reduction and, therefore, increased competitiveness for Autoparts Inc.
Thus, there is positive correlation between the practices and tools of the PMBOK (2009), with the Lean principles.
Results, however, point to additional correlations between the practices of the PMBOK (2009) found in processes
groups, with Lean techniques.
This study, however, does not intend to close the subject, rather it is an empirical analysis, which requires further
clarification, since it is a descriptive research within the field of project management, with application to a single case,
and under specific conditions.

REFERENCES
[1]. ABDULMALEK, F.; RAJGOPAL, J.; NEEDY, K. L. (2007), A classification scheme for the process industry to
guide the implementation of lean. International Journal of Production Economics. Vol. 8, n.2, p.223-236, 2007.
[2]. AHLSTROM, P., Lean service operations: translating lean production principles to service operations,

Volume 3, Issue 6, June 2015

Page 17

IPASJ International Journal of Management (IIJM)


A Publisher for Research Motivation........

Volume 3, Issue 6, June 2015

Web Site: http://www.ipasj.org/IIJM/IIJM.htm


Email: editoriijm@ipasj.org
ISSN 2321-645X

International Journal of Services Technology and Management, Vol. 5 Nos 5/6, p. 545, 2004.
[3]. BALLARD, G.; TOMMELEIN, I., Lean management methods for complex projects, Engineering Project
Organization Journal, Vol. 2 Nos. 1/2, pp. 85-96, 2012.
[4]. BHASIN, S., An appropriate change strategy for lean success, Management Decision, Vol. 50 No. 3, pp. 439458, 2012.
[5]. CAFFYN, S. Development of a continuous improvement self-assessment tool. International Journal of Operations
& Production Management, Vol. 19, n. 1, p. 1138-1153, 1999.
[6]. CARTON, F.; ADAM, F.; SAMMON, D., Project management: a case study of a successful ERP
implementation, International Journal of Managing Projects in Business, Vol. 1 No. 1, pp. 106-124, 2007.
[7]. CHUAL, J. L. Y., EZE, U. C.; GOH, G. G. G., Knowledge sharing and total quality management: a conceptual
framework, Proceedings of the IEEE International Conference on Industrial Engineering and Engineering
Management (IEEM), China, pp. 1107-1111, 2010.
[8]. CRAWFORD, J. K. The Strategic Project Office A Guide to Improving Organizational Performance. New York:
Marcel Dekker, 2002.
[9]. DEY, P. K.; KINCH, J.; OGUNLANA, S. O., Managing risk in software development projects: a case study,
Industrial Management & Data Systems, Vol. 107 No. 2, pp. 284-303, 2007.
[10]. DOUGLAS, S. P.; CRAIG, C. S., Evolution of global marketing strategy: scale, scope and synergy, Columbia
Journal of World Business, Vol. 24 No. 3, pp. 47-59, 1989.
[11]. EISENHART, K. M. (1989), Building theories from case resea
[12]. EISENHART, K. M., Building theories from case research. Academy of Management Review, Vol. 14, No. 4,
pp. 532-550, 1989.
[13]. FESTA, E.; ASSUMPO, M. R. P., Uso da Tecnologia de Informao e Desempenho Logstico na Cadeia
Produtiva de Eletroeletrnicos. Revista Cincia e Tecnologia. Vol. 17, No. 33, pp. 7-23, 2012.
[14]. GURUMURTHY, A.; KODALI, R., Design of lean manufacturing systems using value stream mapping
simulation, Journal of Manufacturing Technology Management, Vol. 22 No. 4, pp. 444-473, 2011.
[15]. HANSEN, D. R.; MOWEN, M.M., Gesto de Custos, Contabilidade e Controle. So Paulo: Thomson Pioneira,
2001.
[16]. HARTMAN, F.; ASHRAFI, R. A., Project management in the information systems and information technologies
industries, Project Management Journal, Vol. 33 No. 3, pp. 4-14, 2002.
[17]. HENDERSON, R.; CLARK, K., Architectural innovation: the reconfiguration of existing product technologies
and the failure of established firms, Administrative Science Quarterly, Vol. 35 No. 1, pp. 9-30, 1990.
[18]. HILLETOFTH, P.; ERICSSON, D.; CHRISTOPHER, M., Demand chain management: a Swedish industrial case
study, Industrial Management & Data Systems, Vol. 109 No. 9, pp. 1179-96, 2009.
[19]. HINES, P.; TAYLOR, D., Guia para Implementao da Manufatura Enxuta. So Paulo: IMAN, 2000.
[20]. HUNTER, R.; WESTERMAN, G., The real business of IT. Harvard Business Press. Boston, MA. pp. 95-104,
2009.
[21]. IMAI, M., Kaizen-The key to Japans Competitive Success, Random House, New York, NY, 1986.
[22]. JADHAV, J. R.; MANTHA, S.; RANE, S. B., Exploring barriers in lean implementation, International Journal
of Lean Six Sigma, Vol.5, No 2, pp. 122-148, 2014.
[23]. KEEGAN, A.; TURNER, J. R., The management of innovation in project-based firms, Long Range Planning,
Vol. 35 No. 4, pp. 367-88, 2002.
[24]. KERZNER, H. procura da excelncia em gerenciamento de projetos. So Paulo: Willey, 2002.
[25]. KERZNER, H. Gesto de Projetos: as melhores prticas. Porto Alegre: Bookman. 2006.
[26]. LAU, E.; KONG, J., Identification of constraints in construction projects to improve performance, Proceedings
of the Joint Conference on Construction, Culture, Innovation and Management, Dubai, November 26-29, pp. 65563, 2006.
[27]. LANDMANN, R.; BITTENCOURT, E.; SCHWITZKY, M.; WYREBSKI, J. Lean Office: Aplicao da
Mentalidade Enxuta em Processos Administrativos de Uma Empresa do Setor Metal-Mecanico. ENEGEP.
Salvador, 2009.
[28]. LAREAU, W. Office Kaizen: transforming office operations into a strategic competitive advantage. USA: ASQ
Quality Press, 2002
[29]. LEAN ENTERPRISE INSTITUTE., Lxico Lean: glossrio ilustrado para praticantes do pensamento Lean. So
Paulo: Lean Institute Brasil, 2007. 2.ed.
[30]. LIKER, J., O modelo Toyota, 14 Princpios de Gesto do Maior Fabricante do Mundo. Porto Alegre: Bookman,
2006.
[31]. LIKER, J.; MEYER, D., Modelo Toyota - Manual de Aplicao: Um Guia Prtico Para a Implementao dos 4Ps
da Toyota. Porto Alegre: Bookman, 2007.

Volume 3, Issue 6, June 2015

Page 18

IPASJ International Journal of Management (IIJM)


A Publisher for Research Motivation........

Volume 3, Issue 6, June 2015

Web Site: http://www.ipasj.org/IIJM/IIJM.htm


Email: editoriijm@ipasj.org
ISSN 2321-645X

[32]. LIMA, E. P,; GARBUIO, P. A. R.; COSTA, S. E. G. Proposta de Modelo Terico-Conceitual Utilizando o Lean
Seis Sigma na Gesto de Produo. ENEGEP. Salvador, 2009.
[33]. LIMA, J. F. G.; PEREIRA, S. L.; SOUZA, E. V., Gerenciamento de Projetos Baseada na Gesto por
Competncias: Um Estudo de Caso no Setor de Artigos Esportivos de uma Indstria Manufatureira. ENEGEP.
Salvador, 2009.
[34]. MALMBRANDT, M.; AHLSTROM, P., An Instrument for Assessing Lean Service Adoption, International
Journal of Operations & Production Management, Vol. 33 No. 9, pp. 1131-1165, 2013.
[35]. MARRAS, J. P., Administrao de recursos humanos: do operacional ao estratgico. So Paulo: Futura, 2005.
[36]. MCCUTCHEON, D. M.; MEREDITH, J. R., Conducting case study research in operations management,
Journal of Operations Management, Vol. 11 No. 3, pp. 239-56, 1993.
[37]. MARCONI, M. A. , LAKATOS, E. M. Tcnicas de Pesquisa. So Paulo:Editora Atlas. 5 edio, 2002.
[38]. NEVES, S. M.; SILVA, C.S.; TURRIONI, J. B. Melhoria Contnua em Gesto de Projetos: Anlise de Uma
Incubadora de Base Tecnolgica. ENEGEP. Salvador, 2009.
[39]. ODUOZA, C. F., Lean thinking constrains in traditional batch manufacturing environments, Advances in
production Engineering and Management Journal, Vol. 3 No. 4, pp. 181-192, 2008.
[40]. PANIZZOLO, R.; GARENGO, P.; SHARMA, M. K.; GORE, A., Lean manufacturing in developing countries:
evidence from Indian SMEs, Production Planning and Control: The Management of Operations, Vol. 23 Nos.
10/11, pp. 769-788, 2012.
[41]. PETERS, A., Your Journey to Lean: Continuous Improvement Supported by Tools, Forrester Research,
disponvel em www.forrester.com. Acesso em 24/09/2014, 2010.
[42]. PICCHI, F.A. Lean na administrao. In: LEAN SUMMIT 2002, Gramado, RS, 17-19 nov. Apresentaes.
Gramado: Lean Institute Brasil, 2002.
[43]. PIERCY, N.; RICH, N., Lean transformation in the pure service environment: the case of the call service centre,
International Journal of Operations & Production Management, Vol. 29 No. 1, pp. 54-76, 2009.
[44]. PILKINGTON, A.; FITZGERALD, R., Operations management themes, concepts and relationships: a forward
retrospective of IJOPM, International Journal of Operations & Production Management, Vol. 26, No. 11, p. 1255,
2006.
[45]. PMBOK Project Management Body of Knowledge. 5a ed. Project Management Institute - PMI, 2013.
[46]. PROJECT MANAGMENT INSTITUTE. Estudo de Benchmarking em Gerenciamento de Projetos Brasil 2007.
Project Management Institute Chapters Brasileiros, 2007. Disponvel em: http://www.pmi.org.br Acesso em 15
may. 2013.
[47]. REBELATO, M. G.; RODRIGUES, A. M.; RODRIGUES, I. C. Anlise das Lacunas Presentes na Integrao da
Manufatura Enxuta com a Metodologia Seis Sigma. ENEGEP. Salvador, 2009.
[48]. RIBEIRO, J. F. F & MEGUELATI, S. (2002), Organizao de um sistema de produo em clulas de
fabricao. Revista Gesto e Produo. Vol. 9, n.1, p. 62-77, 2002.
[49]. ROTHER, M.; SHOOK, J. Aprendendo a Enxergar: Mapeando o Fluxo de Valor para agregar valor e eliminar o
desperdcio. So Paulo: Lean Institute Brasil - Verso 1.3, 2003
[50]. RUDBERG, M.; OLHAGER, J. Manufacturing Networks and Supply Chains: an operations strategy perspective.
International Journal of Production Research. (2003).
[51]. SANTIAGO, L.P.; SILVA, D.C.; JUNIOR, L.C.; MOURA, A.M. Potencializando o Planejamento de Projetos:
Abordagem de uma Metodologia de Planejamento no Contexto do Padro PMBOK. ENEGEP. Rio de Janeiro,
2008.
[52]. SANTOS, J. A.; CARVALHO, H. G. Referencial Brasileiro de Competncias em Gerenciamento de Projetos.
Curitiba, Brasil: Associao Brasileira de Gerenciamento de Projetos, 2006.
[53]. SILVA, E. L., MENEZES, E. M., Metodologia da pesquisa e elaborao de dissertao. Programa de Ps
Graduao em Engenharia de Produo, Universidade Federal de Santa Catarina, Florianpolis, 118p. 2000.
[54]. SIMO, L. A. P. M., Estruturao das lies aprendidas na implantao da produo enxuta na Alcoa de Poos
de Caldas. Dissertao (Mestrado em Engenharia de Produo) - Universidade Federal de So Carlos, So Carlos,
2003.
[55]. SLACK, N.; CHAMBER, S.; HARDLAND, C.; HARRISON, A.; JOHNSTON, R. (2002), Administrao da
Produo. So Paulo: Atlas, 2002.
[56]. SDERQUIST, K.; MOTWANI, J., Quality issues in lean production implementation: a case study of a French
automotive supplier. Total Quality Management. Vol.10, n.8, p.1107-1122, 1999.
[57]. SOUZA, F. B. et al., Aplicao do Sistema Logstico da Teoria das Restries na Gesto da Cadeia de
Suprimentos. Publicado no 2 Simpsio Internacional (O Transporte e sua importncia na Cadeia Produtiva
Global: Polticas e Aes para Exportao) realizado na UNIMEP, 2002.

Volume 3, Issue 6, June 2015

Page 19

IPASJ International Journal of Management (IIJM)


A Publisher for Research Motivation........

Volume 3, Issue 6, June 2015

Web Site: http://www.ipasj.org/IIJM/IIJM.htm


Email: editoriijm@ipasj.org
ISSN 2321-645X

[58]. SOUZA, R. V. B.; CARPINETTI, L. C. R., A FMEA-based approach to prioritize waste reduction in lean
implementation, International Journal of Quality & Reliability Management, Vol. 31 No. 4, pp.346-366, 2014.
[59]. STONE, K. B., Lean transformation: organizational performance factors that influence firms Leanness,
Journal of Enterprise Transformation, Vol. 2 No. 4, pp. 229-249, 2012.
[60]. SUREZ-BARRAZA, M. F.; MIGUEL-DVILA, J. A., Implementacin del Kaizen en Mxico: Un estudio
exploratorio de una aproximacin gerencial japonesa en el contexto Latinoamericano, INNOVAR, Journal of
Administrative and Social Sciences, Vol. 21 No. 41, pp. 19-37, 2011.
[61]. TAJ, S.; MOROSAN, C., The impact of lean operations on the Chinese manufacturing performance, Journal
ofManufacturing Technology Management, Vol. 22 No. 2, pp. 223-240, 2011.
[62]. VAN ARK, B., The Renewal of the Old Economy: An International Comparative Perspective, OECD, Paris,
2001.
[63]. YIN, R. K., Case Study Research: Design and Methods, Sage, Newbury Park, CA, 1989.
[64]. YIP, G. S., Global strategy. . .in an world of nations?, Sloan Management Review, Vol. 31, No. 1, pp. 29-41,
1989.
[65]. WOMACK, J. P.; JONES, D. T., Lean Thinking Banish Waste and Create Wealth in Your Corporation, The
Free Press, New York, NY., 2003.

AUTHORS
Pedro Domingos Antoniolli: Doctor in Production Engineering, Post Graduate in Information Technology and an
MBA in Business Management, Master in IT Management and Production Engineering, Bachelor in Business
Administration. Acting in business Projects and Process. Teacher of Stricto Sensu, Professional Masters in
Management UNIMEP, and MBA Project Management. Certified in Project Management (PMP and Scrum Master),
ITIL and COBIT.
Carlos Roberto Camello Lima: Lecturer of EESC - USP (2014). PhD in Mechanical Engineering from UNICAMP State University of Campinas (1996). Master in Mechanical Engineering from the same university (1993). Post doctorate in Engineering and Materials Science from SUNY - State University of New York, USA (1998-1999). Post PhD in Materials Science and Metallurgical Engineering at UB - University of Barcelona, Spain (2004-2005). Degree
in Mechanical Engineering from UNESP - Universidade Estadual Paulista (1977) and Economics from the UFS Federal University of Sergipe (1984). Professor at UNIMEP - Methodist University of Piracicaba, where he has worked
since 1994 as a researcher and mentor teacher. Member of ASM International, TSS - Thermal Spray Society, ABEPRO
- Brazilian Association of Production Engineering, ABRAMAN - Brazilian Association of Maintenance.
Ana Rita Tiradentes Terra Argoud: Production Engineer (1994) and Master in Production Engineering (2000) by
UFSCar, and PhD (2007) in Mechanical Engineering from the EESC-USP, Manufacturing area. She iis permanent
professor at the Graduate Program in Business Administration from the Methodist University of Piracicaba - UNIMEP.
Areas of research interest: supply chain management, operations management, process integration, quality
management, project management, innovation.
Joao Batista de Camargo Junior: Doctor in Business Administration and Master in Business Administration from
Methodist University of Piracicaba (Universidade Metodista de Piracicaba - UNIMEP). Currently is Assistant Professor
of the Professional Master's Program in Business Administration from UNIMEP. Also acts as a business consultant in
the areas of business organization, corporate governance, optimization of administrative processes, information
technology, logistics processes and Supply Chain Management.

Volume 3, Issue 6, June 2015

Page 20

You might also like