You are on page 1of 176

Construction and Operations Management Report

Appendix D
Environmental Management Plan

Project 205783 | File COMR Final 20110726~ 26 July 2011 | Aurecon

Page i

DRAFT ENVIRONMENTAL
MANAGEMENT PLAN
Castle Hill Wind Farm

Genesis Energy
July 2011
Doc Ref (BD-REWE-051, B669537)

Version

Issue Date

Description

Prepared

Authorised

Draft

26/07/2011

Draft lodged with Resource


Consent applications

Tim McKenzie

Kerry Butler

Draft Environmental Management Plan


Castle Hill Wind Farm

Castle Hill Wind Farm


Environmental Management
Plan

DOCUMENT CONTROL
AMENDMENT RECORD

Prepared by:
Genesis Energy
Initial:

Title:

Pages

No:

Genesis Energy
Date

Issue

Description

File name:
Initials

Draft Environmental Management Plan


Castle Hill Wind Farm

Table of Contents
Table of Contents..........................................................................................................i
Tables ......................................................................................................................... iii
Figures ........................................................................................................................ iii
Document Register ..................................................................................................... iv
Project Terminology and Glossary ................................................................................v
1.

The Castle Hill Wind Farm Project...................................................................... 1

2.

Purpose and Scope ........................................................................................... 3

3.

Statutory Requirements ..................................................................................... 4

4.

Genesis Energys Approach to Environmental Management............................... 5

5.

Environmental Management Framework............................................................. 7

6.

Revisions and EMP Evolution........................................................................... 12

7.

EMP Roles and Responsibilities ....................................................................... 18

8.

Construction Environmental Management ........................................................ 21

9.

Erosion and Sediment Control Measures ......................................................... 31

10.

Water Management ......................................................................................... 38

11.

Site Rehabilitation and Reinstatement .............................................................. 40

12.

Air Quality........................................................................................................ 43

13.

Construction Noise Management .................................................................... 44

14.

Traffic and Transport Management................................................................... 45

15.

Concrete Batching Plant Management ............................................................. 46


i

Draft Environmental Management Plan


Castle Hill Wind Farm

16.

Management of Quarries and Crushing Facilities.............................................. 47

17.

Archaeological and Heritage Management ....................................................... 48

18.

Biodiversity Management................................................................................. 49

19.

Visual Mitigation .............................................................................................. 53

20.

Hazardous Material Management..................................................................... 54

21.

Operations and Maintenance Environmental Management ............................... 57

22.

Incidents.......................................................................................................... 63

23.

Inspection, Monitoring and Auditing ................................................................. 67

24.

Complaints and Enquiries................................................................................. 70

25.

EMP Documentation........................................................................................ 71

ii

Draft Environmental Management Plan


Castle Hill Wind Farm

Tables
Table 1: EMP Content
Table 2: SEMP Topics and Location
Table 3: Castle Hill Wind Farm Component Location Consenting Approach
Table 4: EMP Roles and Responsibilities
Table 5: Site Responsibilities
Table 6: Potential Environmental Effects and Environment Management Measures
Table 7: Typical Operations and Maintenance Activities, Effects and Management
Table 8: Environmental Inspections

Figures
Figure 1: Location Map
Figure 2: Layout Overview
Figure 3: External Roads
Figure 4: Wind Farm Component Map A1
Figure 5: Wind Farm Component Map A2
Figure 6: Wind Farm Component Map A3
Figure 7: Wind Farm Component Map A4
Figure 8: Project Organisational Chart

iii

Draft Environmental Management Plan


Castle Hill Wind Farm

Document Register
Copy Number

Held By

Genesis Energy

Genesis Energy

Genesis Energy

Greater Wellington Regional Council

Horizons Regional Council

Masterton District Council

Tararua District Council

Consulting Engineer

Contractor

10

Contractor

This Environmental Management Plan for the Castle Hill Wind Farm must be reissued to all
parties following substantive amendment to its contents.

Advice Note: Instructions or matters subject to update are identified in italics.

iv

Draft Environmental Management Plan


Castle Hill Wind Farm

Project Terminology and Glossary


Central Laydown Area(s)

Areas On-site that may be used to store turbine components for a


sub-set of turbine locations, or on which construction equipment
and materials can be placed. This is an alternative option to storing
components Off-site or at individual Turbine Platforms.

CHWF

Castle Hill Wind Farm.

CHWF Landowners

Owners of the land on which the wind farm will be built. CHWF
Landowners have signed agreements with Genesis Energy.

CHWF Landowners Dwellings

Dwellings within the CHWF Site.

CHWF Site or Site

The area of land defined by the land titles covered by agreements.

Concrete Batching Plant

A facility required for making concrete. Likely to include a concrete


mixer, cement bins, sand and aggregate stockpiles, water storage
tanks and storage areas for equipment and tools.

Construction Traffic Routes

External Roads used for non-OW/OD construction traffic.

Contractor Compound

Centre for construction management and workshop based activities


consisting of offices, workshops, storage, parking and amenities.

Electrical Balance of Plant


(EBoP)

All electrical structures and equipment related to the collection and


reticulation of electrical power around CHWF and required to
connect the CHWF to the External Transmission Line. Plant
includes underground cables, overhead reticulation lines,
transformers, substations and switchgear.

Engineered Fill

Excavated material (excluding top soil) that is incorporated into


engineered earthworks such as road fills, Turbine Platforms and
Central Laydown Areas. Placement and treatment of the
Engineered Fill is designed to meet construction requirements for
such aspects as drainage, strength and stability.

Excess Fill

Soil removed from the ground which is either not suitable or not
needed as Engineered Fill.

Excess Fill Areas

Areas for disposal of Excess Fill.

External Dwellings

Dwellings external to the CHWF Site.

External Roads

Public roads that are planned to be used for traffic associated with
the construction and operation of the CHWF and including roads
used by Over-weight and Over-dimension Vehicles.

External Transmission Line

The electricity transmission line which connects CHWF to the


Transpower national grid.

Draft Environmental Management Plan


Castle Hill Wind Farm

Indicative Turbine Layouts

Turbine layouts that have been created to represent the range of


possible turbine layouts:
80M a turbine layout consisting of 286 Medium Turbines based
on a turbine with an 80m rotor diameter.
90M a turbine layout consisting of 262 Medium Turbines based
on a turbine with a 90m rotor diameter.
100L a turbine layout consisting of 242 Large Turbines based on
a turbine with a 100m rotor diameter.
110L a turbine layout consisting of 186 Large Turbines based on
a turbine with a 110m rotor diameter.

Internal Roads

Roads that will be constructed within the CHWF Site for


transporting wind farm components and materials within the Site
and to allow access around the Site for construction and
operational activities.

Internal Transmission Line

The 220kV electricity transmission line that is On-site and connects


the main substation to the satellite substation.

Internal Transmission Line


Deviation

The deviation of the Internal Transmission Line to connect it to the


Switching Station.

Large Turbine Configuration

Any turbine configuration that consists only of Large Turbines with a


maximum quantity of 242 turbines.

Large Turbines

Turbines that have a maximum tip height greater than 135m but no
greater than 155m.

Lay-by

A passing bay which provides a means for large vehicles to pass


each other on Internal Roads.

Main Substation

The larger of the two substations, located in the southern region of


the wind farm.

Medium Turbine Configuration

Any turbine configuration that consists only of Medium Turbines


with a maximum quantity of 286 turbines.

Medium Turbines

Turbines that have a maximum tip height of 135m.

Mixed Turbine Configuration

Any turbine configuration that consists of a mixture of Large


Turbines and Medium Turbines with a maximum quantity of turbines
limited by the proportion of Medium and Large Turbines.

Off-site

Anywhere outside the CHWF Site.

On-site

Anywhere within the CHWF Site.

OW/OD

Over-weight and/or over-dimension.

OW/OD Route

External Roads used for OW/OD Vehicles.

OW/OD Vehicles

Any vehicle with a gross mass in excess of 40 tonnes and/or over


20 metres in length, 2.5 m in width and 4.25 m in height.

Road Pavement

The top layer of material on the Internal Road that forms a surface
that is designed specifically for traffic to regularly pass over it.

vi

Draft Environmental Management Plan


Castle Hill Wind Farm

Satellite Substation

The smaller of the two substations, located in the northern region of


the wind farm.

Switching Station

Provides an optional connection point for the External Transmission


Line to connect to the Internal Transmission Line as an alternative
to connecting at the Main Substation.

Turbine Clusters

Groupings of turbines for ease of reference.

Turbine Corridor

The area of the CHWF Site in which Turbines can be located.

Turbine Foundations

The underground foundation upon which each turbine is based and


which keeps the Turbine upright and stable.

Turbine Platform

An engineered flat area beside the turbine that will be used for
laying out and assembling turbine components and as a hard
standing area for construction equipment and vehicles, particularly
the construction crane.

Turbines

Wind turbine generators consisting of foundations, tower, nacelle


and rotor and including all equipment for and associated with the
generation of electricity from the wind.

Wind Farm Access Points

Entrances to the CHWF Site where External Roads meet Internal


Roads.

vii

Draft Environmental Management Plan


Castle Hill Wind Farm

1.

The Castle Hill Wind Farm Project

Genesis Energy is proposing to construct and operate a wind farm in northern Wairarapa,
known as the Castle Hill Wind Farm (hereafter referred to as CHWF). The CHWF Site is
located 20km east of Eketahuna and Pahiatua, 20km north-east of Masterton and 15km west of
the Wairarapa coast north of Castlepoint (Figure 1, Appendix A). The CHWF Site covers an
area of approximately 30,000ha.
The CHWF Site is characterised by undulating hills of predominantly pastoral grass, with grazing
by sheep and cattle. Stands of native vegetation are located throughout the Site, particularly in
gullies, with several small forestry blocks scattered across the Site. The topography is varied,
with elevation ranging from 200m to 500m above sea level.
The CHWF Site is located in a remote area that is sparsely populated. There are six small rural
settlements in or around the CHWF area including Tinui, Pongaroa, Alfredton, Makuri, Tiraumea
and Bideford. These six settlements had a combined population in 2006 of around 500 people
in 110 households 1 . Masterton (population 18,000), Pahiatua (population 2,600) and Eketahuna
(population 460) are the larger townships located within 30kms of the CHWF Site 2 (Figure 1,
Appendix A).
Key components and features of the CHWF project include:

1
2

Turbines: plant consisting of foundations, tower, nacelle and rotor for conversion of
wind energy into electricity.

A Turbine Corridor: 3,144ha identified as suitable for turbine placement. Turbines


will be located within this corridor.

Turbine Clusters: groupings of turbines for ease of reference.

Turbine Configurations: up to 286 Medium Turbines (maximum tip height 135m) or


up to 242 Large Turbines (maximum tip height greater than 135m but no greater
than 155m) or a mixture of Medium and Large Turbines installed within the Turbine
Corridor.

Internal Roads: roads constructed within the CHWF Site for transporting wind farm
components, materials and personnel within the Site and to allow access around
the Site for construction and operational activities.

Statistics NZ 2006 Census


Statistics NZ 2006 Census

Draft Environmental Management Plan


Castle Hill Wind Farm

Electrical Balance of Plant (EBoP): All electrical structures and equipment related to
the collection and reticulation of electrical power around CHWF to the point of
connection to the External Transmission Line. Plant includes an Internal
Transmission Line, 33kV overhead lines, 33kV underground cables, a Main
Substation and Satellite Substation, an optional Switching Station and switch gear
huts along with other associated electrical equipment.

Monitoring masts: up to 16 monitoring masts to collect on-going meteorological


information during the operational life of the CHWF.

External Roads: Public roads near the Site that are planned to be used for traffic
associated with the construction and operation of the CHWF and by Over-weight
and Over-dimension Vehicles (OW/OD Vehicles).

Earthworks associated with the construction and maintenance of the CHWF.

Temporary construction infrastructure: components required for construction of the


CHWF including Concrete Batching Plants, Central Laydown Areas, Excess Fill
Areas, Contractor Compound, quarrying and crushing facilities and water storage
and abstraction facilities.

Operations infrastructure e.g. operations and maintenance buildings (O&M


facilities).

The Turbine Corridor, Turbine Clusters, Internal Roads, Substations and the Internal
Transmission Line are shown in Figure 2, Appendix A. External Roads are shown in Figure 3
(Appendix A), and wind farm components are shown on Figures 4, 5, 6, 7 in Appendix A.
The generation capacity of the CHWF is in the order of 600MW. The maximum capacity will be
dependent on the type of turbine eventually selected for the Site but current Site and wind
turbine analysis indicates a potential capacity of up to 860MW.
Development of the CHWF may progress in stages, with any first stage being in the order of
300MW. This capacity depends on the wind turbine model selected, but will also depend on
other commercial and technical factors.

Draft Environmental Management Plan


Castle Hill Wind Farm

2.

Purpose and Scope

In applying for the resource consents to construct and operate the CHWF and associated
structures, Genesis Energy identified how potential environmental effects would be avoided,
remedied, mitigated and ultimately managed. As a means of augmenting the mitigation
measures proposed to address environmental effects set out in the Assessment of
Environmental Effects (AEE), this Environmental Management Plan (EMP) has been prepared to
articulate, and implement those environmental management measures.
This EMP provides an overarching management framework that will manage environmental
effects which arise from the construction, commissioning and operation of the CHWF project. It
identifies roles and responsibilities and includes practical management actions, performance
requirements, and a system of monitoring, reporting and auditing, and corrective action
requirements for the project.

Draft Environmental Management Plan


Castle Hill Wind Farm

3.

Statutory Requirements

Genesis Energy [is seeking/holds] resource consents from Tararua District Council (TDC),
Masterton District Council (MDC), Greater Wellington Regional Council (GWRC) and the
Manawatu-Wanganui Regional Council (MWRC) for the construction, operation, maintenance,
replacement and refurbishment of all structures associated with the CHWF. [These consents
are attached in Appendix B].
The conditions of those consents [sought/held] specify various standards, terms, restrictions
and prohibitions. The purpose of those conditions is to provide certainty in relation to the
effective management and enforceability of the consents, such that in relation to the operation
or development of the CHWF, any adverse effects on the environment are avoided, remedied
or mitigated.

3.1

Consent Timeframes and Implementation

The resource consents Genesis Energy [is seeking/holds] consist of land use consents which
have an unlimited duration and regional resource consents relating to permanent features (for
example bridges and culverts) which have a duration of 35 years. The lapse period or period of
time following the grant of consent where by substantial progress must have been made
towards giving effect to the consent and continues to be made has been [sought/granted] for
10 years. To enable construction of wind farm components, construction related consents have
been [sought/granted] for a period of 20 years.

Draft Environmental Management Plan


Castle Hill Wind Farm

4.

Genesis Energys Approach to Environmental Management

Genesis Energys approach to environmental management is expressed in a suite of


Environmental Values. Genesis Energys intention and principles in relation to its overall
environmental performance are:
We are committed to achieving excellence in all our environmental practices and to ensuring
that environmental and social awareness are the cornerstones of our business. Achieving full
regulatory compliance is considered to be the minimum standard that Genesis Energy must
strive to achieve in the operation of its business 3 .
At Genesis Energy we:

Act with integrity at all times

Foster close relationships with the community and stakeholders, so that their views
can be incorporated into the environmental decision-making processes.

Acknowledge that our activities affect both the environment and the communities
within which we operate.

Respect the role of tangata whenua as kaitiaki of the natural resources and taonga
within their rohe.

Investigate to better understand the nature of the environmental effects and share
this information with the community and stakeholders.

Seek environmental improvements in all aspects of our business.

Genesis Energy understands that all aspects of its business can impact on the environment and
that in order to reduce that impact it must:

Identify those who have responsibility for environmental management.

Identify and document all environmental effects associated with its activities.

Identify environmental objectives and develop associated work programmes to


address the environmental effects of the activities undertaken.

Regularly review how well the company environmental values are being
implemented, whether objectives are being met and which areas require corrective
action.

Report publicly on environmental performance.

Genesis Energy, Environmental Management Manual, Genesis Energy Environmental Values (GEN-ENV-POL-0006)

Draft Environmental Management Plan


Castle Hill Wind Farm

To achieve these objectives, Genesis Energy operates an Environmental Management System


(EMS) which utilises a number of different business systems to manage the companys effects
and requirements for environmental management across all Genesis Energy projects and
operational sites. The EMS provides the necessary controls and instructions to achieve the
companys commitment to environmental excellence and requirement to comply with all
environmental legislation. The EMS applies to all activities involving the use of natural and
physical resources and the environment, from the conceptual stage of any project through to
normal operational activities of Genesis Energy.

Draft Environmental Management Plan


Castle Hill Wind Farm

5.

Environmental Management Framework

The environmental management framework for the CHWF uses the EMP and associated
Supplementary Management Plans (SEMPs) as the primary mechanisms to implement the
measures to manage potential environmental effects. Through the consenting process the EMP,
(in draft form) was prepared and made available to stakeholders and decision makers so that
they could view the objectives of and the proposed approach to environmental management at
the CHWF by Genesis Energy. Specifically the EMP establishes the environmental management
procedures associated with the construction and operation of the CHWF. It sets out Genesis
Energys environmental management activities which shall, as a minimum, meet and comply with
consent requirements.
The EMP will be updated to reflect the requirements and conditions imposed by all resource
consents issued for the CHWF project, and updated in response to any future amendments to
such consents.

5.1

Environmental Management Plan

This EMP has the following objectives:

To provide for the effective management of the environmental effects and


environmental concerns arising from the CHWF project.

To ensure the construction of CHWF is compliant with the relevant statutory


requirements (such as conditions of consent).

To assign management responsibilities and to define reporting requirements.

To implement the mitigation measures.

To identify management strategies for implementation.

To establish a system to assess the effectiveness of environmental management


actions implemented, by way of audits, inspections and monitoring programme set
against acceptable environmental performance criteria.

To ensure the project contractors, construction and operational staff are aware of
the environmental controls of the project, with the expectation that their activities
will be conducted and managed in accordance with the EMP.

To regularly review how well the management objectives are being met and that
they remain appropriate.

To monitor activities and report internally and externally on environmental


performance.

Draft Environmental Management Plan


Castle Hill Wind Farm

The EMP sets out the following matters:


Table 1: EMP Content
Content Topic

Section

The Castle Hill Wind Farm Project

Purpose and Scope

Statutory Requirements

Genesis Energys Approach to Environmental Management

Environmental Management Framework

Revisions and EMP Evolution including adaptive management improvement


approach responding to monitoring and protocols for managing design
finalisation.

EMP Roles and Responsibilities.

Construction Environmental Management measures to be adopted

Erosion and Sediment Control Measures

Water Management

10

Site Rehabilitation and Reinstatement

11

Air Quality

12

Construction Noise Management

13

Traffic and Transport Management

14

Concrete Batching Plant Management

15

Management of Quarries and Crushing Facilities

16

Archaeology and Heritage Management

17

Biodiversity Management

18

Visual Mitigation

19

Hazardous Material Management

20

Operations and Maintenance Environmental Management including measures


to be adopted

21

Incidents (including Incident Response Plan)

22

Inspection, Monitoring and Auditing

23

Complaints and Enquires

24

EMP Documentation for recording and reporting.

25

Draft Environmental Management Plan


Castle Hill Wind Farm

5.2

Supplementary Environmental Management Plans

In addition to the EMP, SEMPs [will be/have been] prepared to ensure a suitable level of
management is implemented for specific locations or activities at the CHWF Site. The process
of preparing the SEMPs is outlined below. Contractors involved with the CHWF project will be
contractually obligated to contribute to, and to implement the EMP and the SEMPs. [A

contractors ability to comply with the EMP/SEMPs will form part of the construction tender
process].
SEMPs [will be/have been] prepared after the resource consent conditions have been finalised
and [will be/have been] developed in conjunction with the draft EMP with input from the
appointed contractor, relevant specialists, Genesis Energy staff and Council representatives.
Final SEMPs [will/have been] submitted to Council for approval prior to construction
commencing.
The following SEMPs [will be/have been] prepared 4 :
Table 2: SEMP Topics and Location

SEMP

Location

Erosion and Sediment Control Plan (ESCP)

Appendix F

Drainage Management Plan (DMP)

Appendix G

Quarry Management Plan (QMP)

Appendix H

Concrete Batching Plant Management Plan (CBPMP)

Appendix I

Baseline Aquatic Monitoring Plan (BAMP)

Appendix J

Construction Aquatic Monitoring Plan (CAMP)

Appendix K

Biodiversity Management Revegetation Plan

Appendix L

Biodiversity Management Weed Hygiene and Surveillance Plan

Appendix M

Construction Noise Management Plan (CNMP)

Appendix N

Construction Traffic Management Framework (CTMF)

Appendix O

Draft Archaeological Accidental Discovery Protocol

Appendix P

Biodiversity Management Habitat Management Plan(s)

Appendix Q

Biodiversity Management Riparian Protection Plan

Appendix R

Biodiversity Management Goat Control Plan

Appendix S

Biodiversity Management Avifauna Monitoring Plan

Appendix T

Biodiversity Management Bat Monitoring Plan

Appendix U

List to be updated and completed prior to construction and in response to conditions of consents

Draft Environmental Management Plan


Castle Hill Wind Farm

SEMP

Location

Biodiversity Management Lizard Monitoring Plan

Appendix V

Biodiversity Management Predator Control Plan

Appendix W

Biodiversity Management Vegetation Management Plan

Appendix X

Operational Noise Management Plan (ONMP)

Appendix Y

Spill Response Plan (SRP)

Appendix Z

5.3

SEMP Preparation and Requirements

Detailed requirements for each of the SEMPs will be determined and agreed with the
contractor, relevant Genesis Energy staff (e.g. environmental manager, project manager),
technical specialists and the relevant Regional or District Council representatives. This will
involve a review of detailed designs and conditions of consent, Site visits and review of other
information required to determine the extent of effects management required.
Preparation of SEMPs follows the general process described below.

A preliminary design or methodology is completed.

A draft SEMP is prepared.

Councils review the SEMP and provide feedback.

SEMP finalised and issued to the Councils and contractors.

SEMPs typically include the following. Outline approaches to SEMPs are set out in Appendix F
Z.

Objectives and purpose.

Roles and responsibilities.

Detailed plans showing location and details of the required management measures.

Construction or implementation methodology if not provided in the EMP.

Design criteria.

Design calculations.

Any details relating to the operation and maintenance of the proposed management
measures.

Construction method statements i.e. method statements for the construction


activities associated with the SEMP.

Any specific requirements for hazardous substances (such as fuels).

Actions and measures implemented to minimise environmental effects.

10

Draft Environmental Management Plan


Castle Hill Wind Farm

Key contact details.

Key environmental considerations.

Construction or implementation programme.

Monitoring and inspection schedule requirements, frequency and reporting.

Health and safety requirements and measures.

11

Draft Environmental Management Plan


Castle Hill Wind Farm

6.

Revisions and EMP Evolution

This section of the EMP establishes the process and approach for documenting changes made
under the adaptive management approach and also the protocol for managing design
finalisation. The adaptive management approach involves regular monitoring and reporting which
creates a continuous improvement feedback loop and ensures that actual On-site effects are
being addressed and managed appropriately.
Genesis Energy will operate a plan-do-check-act adaptive management approach. The
approach enables objectives to be set, actions to be monitored and performance to be
evaluated against those objectives and for this to be communicated to relevant stakeholders. It
will enable reviews of progress to check the effectiveness of actions and to ensure that
improvements are implemented accordingly.

6.1

EMP Evolution and Control

The EMP is subject to revision based on review, experience and changes in technology, thereby
taking an adaptive approach to improve future management. The key mechanisms for this
include the following:

Review of measures utilised to manage effects.

Improvements identified from any incident response.

Consultation with relevant stakeholders.

Undertaking an annual review.

To maintain control over any changes in approach made through the evolution of the EMP, this
EMP has been issued as a controlled document. Any other copies issued in part or full are
deemed not to be controlled copies and will not be updated nor may they be considered a
current document. All copies shall be distributed in accordance to the document register. On
receipt of a revision the copyholder shall discard the superseded copy and adopt the new copy.

6.2

Component Location Consenting Approach

Overall, the environmental effects assessment for the CHWF Project has been undertaken on a
comprehensive, conservative and robust basis.
The AEE, and the supporting technical information, [is/was] provided in such detail as
corresponds with the scale and significance of the effects that the CHWF activities may have on
the environment. As noted, the CHWF Site encompasses some 30,000 ha, with a construction
footprint of 861 ha and an operational footprint of some 226 ha. In order to provide an
assessment of all potential environmental effects (positive and negative), independent experts

12

Draft Environmental Management Plan


Castle Hill Wind Farm

[have undertaken/undertook] both specific and representative effects assessments. Thus, while
not every spatial area of the 30,000 ha Site [has been/was] specifically assessed, the worst
case position for all potential effects [has been/was] assessed regardless of the final location of
all the activities for which resource consent has been [sought/granted].
Optimisation of the CHWF design [is/was] proposed to make the best use of the wind resource
while responding to technological advances, opportunities to minimise environmental effects
and in order to take account of Site conditions following grant of resource consent. When
implementing the CHWF project, Genesis Energy will ensure that final designs fit within the
overall location and extent of effects described in the AEE and authorised by the resource
consents [sought/granted]. It will ensure that the nature and scale of the effects associated with
the final design are no greater than the authorised adverse effects.
In that regard, it is anticipated that the following protocol will form part of the conditions of
consent.

6.2.1

Protocol for Managing Design Finalisation

During the development of the final design, the following protocol will apply:
1. Confirm the final location of the CHWF components.
2. Document the reasons why the final location has been selected.
3. Prepare detailed design drawings.
4. Ensure that exclusion areas where infrastructure shall not be located contain no
infrastructure elements apart from those specific locations sought in the AEE.
5. Undertake a confirmatory process to ensure environmental effects are no greater than
that contained in the AEE.
6. Report the findings of the confirmatory process, to confirm that for the project as a
whole:
a. Areas of legally protected habitats (DOC, QEII) and, rare, threatened or
at risk habitats identified under statutory plans will not be disturbed.
b. Areas of high ecological value as defined in the Ecological Effects
Assessment in support of the AEE will be avoided, except to the extent
already outlined in the CHWF Project Figures shown in the AEE. Clearance
of a limited amount of high ecological value vegetation is described and
this quantity will not be exceeded in construction of the CHWF.
c. Clearance of indigenous vegetation will be minimised and will not cause the
maximum quantity of indigenous vegetation clearance of 66 ha described in
the AEE to be exceeded.

d. Watercourse crossings will not vary in location by more than 100m each
13

Draft Environmental Management Plan


Castle Hill Wind Farm

side of locations identified in the AEE.


e. Gullies with watercourses will be avoided unless it can be demonstrated
that downstream water quality effects are no more than minor.
f.

Seepage areas dominated by indigenous species with an area greater than


0.05ha will be avoided.

g. Total CHWF earthworks volumes described in the AEE are not exceeded.
h. Noise standards will be complied with or effects will be appropriately
mitigated.
Overall, the design of the CHWF has been undertaken to a level sufficient to enable the
environmental effects to be assessed robustly and conservatively. During detailed design and
optimisation, the protocol set out above will ensure that effects are well managed and will not
exceed the nature and scale of effects as described in the AEE.
Table 3, below, summarises the parameters within which Genesis Energy will refine and finalise
the location of the CHWF infrastructure.
Table 3: Castle Hill Wind Farm Component Location Consenting Approach
Component

Rationale

Location Description

Turbines

Siting refinement is important to allow for


variation in spacing between Turbines to
maximise energy output. Spacing varies
depending on the size of the Turbine rotor and
therefore, optimal spacing can only be
determined once the final turbine model(s) are
selected after resource consent acquisition.
Four Indicative Turbine Layouts have been
established to provide a basis for representative
engineering and environmental assessments and
to illustrate how different Turbine sizes may be
placed within the Turbine Corridor.

Turbines may not be sited anywhere


other than in the Turbine Corridor.

Turbine
Corridor

The Turbine Corridor incorporates all areas


within the CHWF Site identified for turbine
placement. The development and refinement of
the Turbine Corridor has incorporated
representative environmental and engineering
assessments to avoid, remedy or mitigate
adverse environmental effects.

The area and location of the Turbine


Corridor is located where indicated
in the CHWF Project Maps.

Internal
Roads

Internal Roads have been designed and


associated earthworks volumes calculated and
will generally be located where indicated.
However the scope sought within the resource
consent will enable the final location of the
Internal Roads to be confirmed during the
detailed design phase. Further refinement may
be required due to the following:

Internal Roads are likely to be


located where indicated in the
CHWF Project Maps but may be
located anywhere within the Site,
subject to the limits presented
below:

(including
Turbine
Foundations
and Turbine
Platforms)

(including
Lay-bys)

Technological advances in transporters or

(1) Areas of legally protected


habitats (DOC, QEII) and, rare,
threatened or at risk habitats

14

Draft Environmental Management Plan


Castle Hill Wind Farm

Component

Rationale

Location Description

components, or construction techniques. This


may enable a more efficient route to be taken
which may reduce earthworks and/or ecological
effects.

identified under statutory plans will


not be disturbed.

Unforeseen ground conditions or environmental


constraints.
Unidentified archaeological sites or features.
The Internal Road design approach is considered
appropriate at this Site because of the large
proportion of the Site consisting of low or
negligible ecological value. The location of the
Internal Roads will be influenced by the fixed
locations of key CHWF infrastructure (Turbines
within the Turbine Corridor and Substations) to
which they will provide access.

(2) Areas of high ecological value


as defined in the Ecological Effects
Assessment in support of the AEE
will be avoided, except to the extent
already outlined in the CHWF
Project Figures and shown in the
AEE. Clearance of a limited amount
of high ecological value vegetation
is described and this quantity will
not be exceeded in construction of
the CHWF.
(3) Clearance of indigenous
vegetation will be minimised and will
not cause the maximum quantity of
indigenous vegetation clearance of
66 ha described in the AEE to be
exceeded.
(4) Watercourse crossings will not
vary in location by more than 100m
each side of locations identified in
the CHWF Project Figures.
(5) Gullies with watercourses will be
avoided unless it can be
demonstrated that downstream
water quality effects are no more
than minor.
(6) Seepage areas dominated by
indigenous species with an area
greater than 0.05ha will be avoided.
(7) Total CHWF earthworks volumes
described in the AEE are not
exceeded.

Main
Substation

Two locations have been identified for the Main


Substation. The key factors that will determine
which location will be most appropriate will be
the final size, location and order of stages of
construction, and the final location of the
External Transmission Line.

The Main Substation will be located


at one of the two locations shown in
the CHWF Project Maps.

Two alternative locations also provide


redundancy in the unlikely event that one
location is found to be unsuitable during detailed
design.
Satellite
Substation

The location of the Satellite Substation was


identified after a thorough assessment of the
overall Site against a range of suitability criteria,
such as area, topography, visibility, distance
from occupied dwellings, and potential for flood

The location of the Satellite


Substation is shown in the CHWF
Project Maps.

15

Draft Environmental Management Plan


Castle Hill Wind Farm

Component

Rationale

Location Description

risk, accessibility and ecology.


Switching
Station

The Switching Station location was identified


after a thorough assessment of the overall Site
against a range of suitability criteria, such as
area, topography, visibility, proximity to
dwellings, potential for flood risk, accessibility,
expected proximity to the External Transmission
Line connection point and ecology.

The location of the Switching


Station is shown in the CHWF
Project Maps.

Internal
Transmissio
n Line

The Internal Transmission Line has been


designed to a reasonably high level of certainty
and apart from micro-siting of towers is not
expected to change.

The location of the Internal


Transmission Line will be within 50m
of the location indicated in the
CHWF Project Maps.

The location indicated in the AEE shows some


alternative arrangements depending on the
location of the Main Substation and whether the
Switching Station is utilised.

The location of the Internal


Transmission towers will be within
50m of the locations indicated in the
CHWF Project Maps and will be
positioned to avoid clearance or
trimming of indigenous vegetation to
the extent practicable.

Wherever practical, the 33kV reticulation


system will follow Internal Roads so the
requirement for variation from the routes
indicated will match that of the Internal Roads.

These components are likely to be


located where indicated in the
CHWF Project Maps but may be
located anywhere within the Site,
subject to the following limitations:

33kV
overhead
lines and
underground
cables

Other EBoP

Excess Fill
Areas

The opportunity arising from refinement, and the


degree of constraint applied is as for the Internal
Roads.
Other EBoP components such as switchgear
huts will generally be located near previously
listed EBoP components (substations, overhead
lines and underground cables) and will vary in
their location as these other components do.
On-site Excess Fill Areas have been identified as
suitable from both an engineering and
environmental perspective. They are located
near or adjacent to Internal Roads to minimise
transport of Excess Fill and so may vary in
location if Internal Roads relocations are
required. Other variations may be required to
achieve engineering or environmental
improvements and additional Excess Fill Areas
may also be identified by the contractor.

Central
Laydown
Areas

Indicative Central Laydown Area locations have


been identified to indicate suitable sites and
demonstrate that the requirement to provide
Central Laydown Areas can be achieved.

Contractor
Compounds

The contractor will identify a suitable location for


the Contractor Compound prior to construction.

Operations
and

The location of O&M facilities will be determined


prior to construction depending on the final size,

(1) Areas of legally protected


habitats (DOC, QEII) and, rare,
threatened or at risk habitats
identified under statutory plans will
not be disturbed.
(2) Areas of high ecological value
as defined in the Ecological Effects
Assessment in support of the AEE
will be avoided, except to the
extent already outlined in the
CHWF Project Figures and shown
in the AEE. Clearance of a limited
amount high ecological value
vegetation is described and this
quantity will not be exceeded in
construction of the CHWF.
(3) Clearance of indigenous
vegetation will be minimised and will
not cause the maximum quantity of
indigenous vegetation clearance of
66 ha described in the AEE to be
exceeded.
(4) Gullies with watercourses will
be avoided unless it can be
demonstrated that downstream
water quality effects are no more

16

Draft Environmental Management Plan


Castle Hill Wind Farm

Component

Rationale

maintenance
facilities

location and order of stages of construction.

Quarries

Quarries will be established at the locations


indicated or additional sites if identified during
construction.

Crushing
Plant

Crushing plant is likely to be located at or near


the quarry sites.

Concrete
Batching
Plants

Concrete Batching Plants will be located either


near current construction sites, or near material
sources such as quarries or water abstraction
sites. Indicative locations have been identified
with specific locations to be determined prior to
construction. The plants will be re-locatable, with
only one or two locations operating concurrently
at any one time and sites being rehabilitated as
soon as the Concrete Batching Plant is
relocated.

Water
abstraction
and storage
areas

Water abstraction and storage locations have


been identified.

Location Description
than minor.
(4) Seepage areas dominated by
indigenous species with an area
greater than 0.05ha will be avoided.
(5) Total CHWF earthworks
volumes described in the AEE are
not exceeded.
(6) Noise standards will be
complied with or effects will be
appropriately mitigated.

The location of water abstraction


and storage facilities is shown in the
CHWF Project Maps.

17

Draft Environmental Management Plan


Castle Hill Wind Farm

7.

EMP Roles and Responsibilities

7.1

General Responsibilities

Whilst Genesis Energy has the ultimate responsibility for the implementation of the EMP, the
Contractor has a responsibility to ensure that the environmental measures provided in the EMP
and SEMPs are implemented. In addition to Council inspections, the EMP implementation is
subject to internal Genesis Energy inspections, auditing and reporting.
Responsibilities for the environmental performance of the CHWF project are outlined in Table 4
below.
Table 4: EMP Roles and Responsibilities
Organisation
Genesis Energy

Contractor

Primary Responsibilities

Overall responsibility for the project, contractors and environmental


performance of the CHWF

Ultimate responsibility for the implementation of the EMP and SEMPs

Undertakes internal Genesis Energy inspections, auditing and reporting to


determine if works are being undertaken in accordance with the EMP and
SEMPs

Authorises all changes to design and contracts

Assists in providing training and inductions

Complaint handling

Incident management and emergency response

Document control

Genesis Energy will assume the ongoing environmental management role


at the CHWF following construction

Contribute to and implement the EMP and SEMPs

Undertake all aspects of environmental management as set out in its


Agreement with Genesis Energy

Have in place appropriate systems and procedures to comply with the


environmental management requirements for the Site

Ensure all reasonable steps have been taken to protect the environment

Comply with all legal and statutory requirements

Operate in accordance with the requirements of resource consents


authorising the proposed activities and in accordance with the EMP and
SEMPs

Contribute to the ongoing improvement and implementation of the EMP


and SEMPs

Adhere to the requirements of any other relevant plans for the CHWF Site

18

Draft Environmental Management Plan


Castle Hill Wind Farm

Organisation

Council

7.2

Primary Responsibilities

Providing training and inductions

Assist in responding to complaints or issues

Support incident management and emergency response procedures

Audit and monitor the Site construction activities to identify that these are
being undertaken in compliance with the conditions of resource consent
and the EMP and SEMPs

Review reports prepared by Genesis Energy in respect of reporting on


implementation mechanisms and monitoring outcomes

Act on advice and information provided by Genesis Energy and


stakeholders

Site Responsibilities

The Site Project Environmental Manager will be responsible for the implementation and
maintenance of the EMP and acts as an interface between the contractors project manager,
Genesis Energy and other stakeholders. Table 5 identifies the Site environmental
responsibilities of project stakeholders.
Table 5: Site Responsibilities
Name

Company

Position

Responsibilities

Genesis Energy

Project Principal

Overall responsibility for the project


Authorises all changes to design and
contracts

Genesis Energy

Project Manager

Overall responsibility for the environmental


performance of the project

Genesis Energy

Project
Environmental
Manager

Audit and inspection to determine if works are


being undertaken with EMP and SEMP
Training and inductions
Complaint handling
Incident management and emergency
response
Prepare, review, revise, distribute and control
the EMP and SEMP documents
Document control

19

Draft Environmental Management Plan


Castle Hill Wind Farm

Name

Company

Position

Responsibilities

Main contractor

Project Manager

Management of all contractors and


subcontractors
Implement mitigation measures and
obligations outlined in the EMP and SEMP
documents
Ensure compliance with EMP, SEMP and
resource consent conditions
Inspections and reporting
Incident management and emergency
response
Training and inductions

Various

Councils

Councils

Various

Staff and Subcontractors

Adhere to EMP and SEMP

Consents
management

Approval of EMP and SEMPs

Compliance and
monitoring officer
(or equivalent)

Approval of EMP and SEMPs

Technical
Specialists

Specialist environmental support

Incident reporting

Auditing to ensure consent conditions are


being met

Auditing to ensure consent conditions are


being met

The project organisational structure [is/will be] outlined in Figure 8 below. The contact details
for key personnel are provided in Appendix B.
Figure 8: Project Organisational Chart

[The Project Organisation Chart will be prepared once roles and responsibilities have been
assigned]

20

Draft Environmental Management Plan


Castle Hill Wind Farm

8.

Construction Environmental Management

This section of the EMP outlines the proposed general environmental management measures to
be implemented to address environmental effects. Detailed methods for specific sites and
issues will be identified within the SEMPs, provided in appendix to the EMP.

8.1

General Operations

Works will not commence On-site until the following actions have been undertaken:

8.2

Pre construction conditions of resource consent have been met and authorised by
Council.

All other approvals required from Council have been received for a given project
area.

Relevant EMPs and SEMPs are have been approved by the relevant authority.

Provision of Information, Training and Inductions

All organisations and individuals working on the CHWF project will be required to complete a
formal Site induction prior to commencing work On-site. The induction will include important
environmental issues pertaining to the Site including environmental management requirements,
accidental discovery of cultural or archaeological sites or material, emergency response
procedures and incident reporting, as well as Health and Safety information and requirements.
Attendees will be provided with a copy of the EMP and any appropriate SEMP to read prior to
commencing work On-site. A register will be maintained by the contractors Project Manager
which needs to be signed prior to an individual commencing work On-site confirming they have
understood the contents of the EMP and relevant SEMPs.
Should any specialised environmental training be identified as being necessary for personnel at
the Site, training will be provided by a suitably qualified person. A record of the training will be
kept by the contractors Project Manager.
Environmental issues and management will be included as an item on the agenda of daily
toolbox meetings to assist in the continuing development and improved performance of
environmental management On-site.

21

Draft Environmental Management Plan


Castle Hill Wind Farm

8.3

Construction Activities

The main construction activities have been identified and described in detail in the COMR.
These include:

Wind Farm Access - Establishment of External Roads and Internal Roads providing
access to the Site.

Establishment of temporary Site presence by contractors. Creation of temporary


Contractor Compounds On-site for the duration of the construction project.

Internal Road establishment and construction.

Formation of Turbine Platforms.

Construction of Central Laydown Areas.

Transport of components (turbines, EBoP) to Site.

Establishment of water storage facilities and water abstraction systems.

Establishment and operation of quarries and crushing facilities.

Establishment and operation of Concrete Batching Plants.

Construction of Operation and Maintenance building(s).

Establishment and construction of Internal Transmission Line access and Internal


Transmission Line structures and conductors.

Establishment of Excess Fill Areas.

Excavation works and formation of Turbine Foundations.

Formation of Substation and optional Switching Station pads and construction of


Substations and optional Switching Station.

Excavation works and laying of underground cabling, earthing and communications


between Turbines and the Substation sites.

Overhead electrical reticulation line works between clusters and the substations.

Formation of wind monitoring mast foundations, construction of monitoring masts.

Turbine tower erection.

Turbine nacelle installation.

Turbine rotor assembly and installation.

Commission Electrical Balance of Plant (connect to external 220kV grid).

Install and commission wind farm communications system (SCADA and external).

Turbine electrical commissioning and reliability runs.

Disestablishment of temporary works.

Revegetation and restoration.

Power performance testing.


22

Draft Environmental Management Plan


Castle Hill Wind Farm

Normal operations and maintenance.

Environmental effects and the identified management measures are summarised in Table 6
below and set out in detail further on.

23

Cause

Creation of
unstable or
disturbed surfaces

Stormwater runoff
over disturbed
surfaces

Potential Environmental
Effect

Accelerated erosion

Accelerated erosion

Use structures to dissipate energy and allow for settlement of


sediments.

Collect stormwater in appropriate detention structure

Ensure sediment controls are maintained and fit for purpose

Use appropriate erosion and sediment control methods

Avoid concentration of water volumes

Create ponding areas to reduce water velocity and settling of


sediments

Install drainage to divert water away from disturbed areas

Mulch slopes

Revegetate surfaces as soon as possible.

Use compaction to stabilise unstable surfaces

Monitor weather

Report monthly

Report weekly

Inspect periodically,
particularly during
inclement weather

24

Use of flocculants

Provide maximum
storage capacity in
advance of forecasted
rainfall

Potential for the


installation of
additional sediment
control measures

Report weekly

Limit the period of time that surfaces are left in an unstable


state.
Report monthly

Re-establishment of
erodible surfaces

Inspect periodically

Minimise the area of erodible surfaces.

Staging of earthworks

Contingency
Measures

Monitoring and
reporting

Measures to Avoid Effects

Table 6: Potential Environmental Effects and Environment Management Measures

Draft Environmental Management Plan


Castle Hill Wind Farm

Cause

Top soils not


recovered or lost
from stock piles

Stormwater runoff
from disturbed
surfaces

Potential Environmental
Effect

Accelerated erosion
Topsoil loss

Sediment loading of local


waterways as a result of
stormwater runoff from
disturbed areas

Draft Environmental Management Plan


Castle Hill Wind Farm

Other structures as necessary

Sediment ponds

Silt fences and improved silt fences

Install erosion and sediment control structures.

Install drainage to prevent water running over disturbed


surfaces (divert clean water)

Use of appropriate machinery and techniques

Adequate supervision

Cover loads

Respread and compact as soon as possible.

Compact soil to reduce losses

Monitor erosion and


sediment control
structures

Monitor weather

Report monthly

Report weekly

25

Use of flocculants

Provide more erosion


and sediment controls

Report monthly

Locate storage sites away from areas of surface water /


overland flows.

Inspect periodically,
particularly prior to and
during inclement
weather

Establish cover on
topsoil stockpiles such
as grassing, mulch or
geotextiles.

Inspect periodically

Careful removal and storage of topsoil at outset of earthworks

Locate storage sites away from prevailing winds

Contingency
Measures

Monitoring and
reporting

Measures to Avoid Effects

Cause

Fuel spills, oils,


concrete wash,
hazardous
substances

Dust discharges
from stockpiles,
roads or
transported
materials

Contaminants from
construction plant

Potential Environmental
Effect

Spills and leaks of


hazardous substances,
oil, fuel or any other
substance harmful to the
surrounding environment

Deterioration of air quality

Deterioration of air quality

Draft Environmental Management Plan


Castle Hill Wind Farm

Monitor weather

Use covers to secure loads

Limit operations to certain areas within the Site.

Restrict Site access to authorised vehicles

Utilise modern construction plant in a good operating


condition

Use of sprinklers and water trucks to dampen sources of dust

Report monthly

Inspect periodically

Report monthly

Enforce appropriate vehicle speeds

Training of operators

Inspect daily

Report Monthly

Inspect risk activities


weekly

Inspect facilities
weekly

Monitoring and
reporting

Minimise the area of erodible surfaces.

Secure storage of fuels

Bunded storage of hazardous materials

Contractor / Supplier required to clean up any spills


immediately

Treat contaminated water appropriately

Remove contaminated sludge to registered landfill

Prohibit fuelling and hazardous material storage within 50m of


a waterway.

Ensure contaminants are handled appropriately

Ensure secure and bunded storage compounds provided

Measures to Avoid Effects

Replace or repair
aging plant.

26

Minimise extent of
stockpile areas.

Revegetate stockpiles
temporarily between
use.

Additional use of
water to dampen
sources.

Prepare and follow a


Spill Response Plan

Alert emergency
response for oil spills /
pollution hotline

Use spill kits On-site

Contingency
Measures

Equipment in poor
condition.

Noise pollution

Loss or damage to
ecologically sensitive or
significant vegetation

Material from
blasting (fly)

Deterioration of air quality

Excessive
earthworking

Unusual climatic
conditions

Cause

Potential Environmental
Effect

Draft Environmental Management Plan


Castle Hill Wind Farm

Revegetation or enhancement of other habitats to mitigate


clearance

Ensure operators are adequately trained.

Maintain awareness of significant vegetation areas

Seek approval from appropriate manager and where


necessary technical expert ecologist prior to commencing
clearance

Delineate maximum areas of clearance by pegging.

Install noise suppression equipment where possible.

Report monthly

Inspect as necessary,
prior to earthworks

Report monthly

Undertake nuisance noise operations during normal working


hours.
Ensure operators are adequately trained.

Inspect periodically

Report monthly

Inspect following blast

Monitoring and
reporting

Maintain all equipment in a good condition

Undertake blasting only in accordance with an approved


blasting plan prepared by a suitably qualified expert

Measures to Avoid Effects

27

Revegetate cleared
areas

Allow for climatic


conditions to improve
before works resume.

Cease works until


equipment repaired or
suppressed.

Remove any fly


material where
appropriate.

Stop work until


appropriate blasting
plan prepared.

Contingency
Measures

Cause

Seeds and other


material capable of
germinating
brought to Site
from dirty
equipment

Seeds and other


material capable of
germinating
brought to Site
within revegetation
seed mixes

Excessive
earthworking

Culverts and
stream crossings

Potential Environmental
Effect

Weed infestations

Weed infestations

Loss of fauna habitat

Impacts on fish movement

Draft Environmental Management Plan


Castle Hill Wind Farm

Report monthly
Monitor ongoing

Vehicle inspection to be undertaken prior to entering Site.


Any plant being relocated from the South Island shall be
checked and treated for didymo.

Relocate trapped fish.

Supervise installations

Ensure culverts and stream crossings are installed to maintain


fish passage

Relocate sensitive fauna

Ensure operators are adequately trained.

Maintain awareness of significant faunal habitat

Seek approval from appropriate manager and where


necessary technical expert ecologist prior to commencing
clearance

Delineate maximum areas of clearance by pegging.

Report monthly

Weeding / spraying where appropriate

Report monthly

Inspect periodically

Aquatic monitoring

Report monthly

Inspect as necessary,
prior to earthworks

Monitor ongoing

Inspect periodically

Use specified and certified seed mixes

Prepare and follow a Weed Hygiene and Surveillance Plan

Weeding / spraying where appropriate

Inspect periodically

Monitoring and
reporting

Ensure all machinery is clean before coming onto Site.

Measures to Avoid Effects

Installation of fish
baffels

Remove perched
culverts

28

Revegetate cleared
areas

Treatment with
appropriate weedkiller

Treatment with
appropriate weedkiller

Contingency
Measures

Cause

Earthworks not
appropriate for the
landform

Earthworks expose
items of
archaeological
interest

Potential Environmental
Effect

Visual impacts

Impacts on Cultural /
Historical features

Draft Environmental Management Plan


Castle Hill Wind Farm

Follow the Accidental Discovery Protocol for items of


archaeological interest discovered.

Ensure operators are adequately trained.

Maintain awareness items of archaeological interest

Seek approval from appropriate manager and where


necessary technical expert archaeologist prior to commencing
earthworks

Assessment of the potential for items of archaeological


interest to be discovered, and avoidance of locations with
archaeological interest.

Use of consistent vegetation patterns

Modify contours to relate to landform

Prompt revegetation and rehabilitation

Ensure operators are adequately trained.

Seek approval from appropriate manager and where


necessary technical expert landscape architect prior to
commencing earthworks

Delineate maximum areas of clearance by pegging.

Report on discovery.

29

Report monthly

Limit extent and height of cuts

Ongoing surveillance.

Recontouring and
revegetation

Inspect periodically

Minimise areas modified

Shape earthworks to relate to the landform

Contingency
Measures

Monitoring and
reporting

Measures to Avoid Effects

Cause

Increases in
volume of vehicles
and size of loads

Careless loss or
discarding of waste
materials and litter

Potential Environmental
Effect

Impacts on local traffic

Unplanned distribution of
construction waste

Draft Environmental Management Plan


Castle Hill Wind Farm

Collect lost waste.

Confirm the Site as litter free

Provide adequate secure facilities for various waste materials.

Limiting traffic during peak periods

Communication Systems

Traffic management

Bridge Replacement

Road Widening

Travel Plans

Construction Traffic Management Plan

Construction Traffic Management Framework

Measures to Avoid Effects

Report monthly

Ongoing surveillance ,
inspect periodically

Close liaison with


NZTA

Close liaison with local


authorities

Construction Traffic
Management Plan

Monitoring and
reporting

30

Engage personnel to
monitor, manage and
collect waste.

Contingency
Measures

Draft Environmental Management Plan


Castle Hill Wind Farm

9.

Erosion and Sediment Control Measures

Exposure of soil during the construction process and the formation of topsoil and weathered
rock stockpiles, means that there is potential for an increase in erosion and sediment
discharges, including airborne dust. Accordingly, erosion and sediment control measures
will form integral components of the construction process for the CHWF, with appropriate
planning and adoption of control measures for all earthworks to minimise the effect on the
receiving environment.
The minimisation of erosion is the most effective way of reducing sediment discharges.
Earthworks activities associated with the construction process will be kept to the minimum
area necessary, and exposed surfaces will be stabilised until the Site is appropriately
revegetated.
The following general objectives underpin erosion control at the CHWF:

Minimising the area disturbed by construction activities.

Progressively completing construction activities on a stage-by-stage basis.

Revegetating and rehabilitating areas disturbed as soon as possible after


earthworks have been completed.

Stabilising material storage areas for future use.

In addition, the potential effects associated with earthworks activities can be prevented and
minimised with the following guiding principles:

Maintain separation of earthworks from watercourses.

Divert clean surface runoff away from areas of earthworks or soil stockpiles.

Reduce the energy of surface flows in areas of potential erosion.

Allow for the passage of extreme flows and protect against blockage of
infrastructure.

Provide containment for sediment entrained in surface flows.

Treat sediment laden water leaving the construction site.

Promptly stabilise or revegetate disturbed areas.

Monitoring to ensure erosion and sediment controls are operating effectively.

A range of erosion and sediment control measures will be implemented as part of the
construction process associated with CHWF. These measures will be contained within
relevant ESCPs and are summarised below. The ESCPs will set out measures to avoid and
minimise potential impacts of construction works on soils and waterways at the Site, and
will be prepared for each phase of development and submitted to Council prior to
construction.
31

Draft Environmental Management Plan


Castle Hill Wind Farm

A draft example of an ESCP identifying the purpose, objectives and content of the ESCP(s)
is provided in Appendix F.

9.1

Erosion Control Measures

A summary of erosion control measures are set out below. These will be implemented in
combination with sediment control measures set out in section 9.2.

9.1.1

Clean Water Diversion Bund

A clean water diversion bund is used to divert clean surface flows away from unstabilised
soils. Bunds are set up around the uphill perimeter of the active works area, constructed of
compacted earth and then stabilised. Existing turf from the active works area should be
used to line the constructed bund where appropriate.

9.1.2

Contour Drains

Contour drains consist of a temporary bund or channel cut across the face of the active
works area to collect runoff and provide a low velocity pathway to either a sediment control
device or a collector drain. Contour drains should be installed at the end of every day, or
when the site is about to be shut down due to impending inclement weather.

9.1.3

Collector Drains

Collector drains consist of a channel cut into the active works area to collect flow from
contour drains and discharge the flow into a sediment control device. These cut channels
are a semi permanent feature, so they must be located along a suitable path. Check dams
and reinforcement may be required under certain circumstances.

9.1.4

Rock Check Dams

Rock dams are placed across steep clean water diversions or collector drains to slow the
water velocity where it exceeds the erosive limit of the soil.

9.1.5

Channel Reinforcement

Channel reinforcement consists of lining clean water diversions or collector drains with
rock, geotextile, or other reinforcement material.

9.1.6

Benched Slopes

Benched slopes involve a reverse slope bench cut into steep and high batters to prevent
stormwater concentrating into erosive rills. Reverse benches are expected to require a
drop pipe to convey the runoff down the subsequent cut slopes.

32

Draft Environmental Management Plan


Castle Hill Wind Farm

9.1.7

Drop Pipes

Drop pipes are temporary structures used to convey runoff from a channel or other type of
collection point down a steep slope without requiring an overland flow. The entrance to the
pipe is flared and constructed of compacted earth reinforced with geotextile.

9.1.8

Flow Dispersal Outlets

Flow dispersal outlets are connected to a section of drainage coil or pipe that has had slots
cut into it fixed perpendicular to the slope in order to promote broad sheet flow rather than
a concentrated flow. This is suitable where flow is being discharged away from a
watercourse. The dispersal device must be laid flat and perpendicular to slope so that flow
will exit from the full length of pipe rather than concentrated at one point.

9.1.9

Rip-rap reinforced Outlets

A basin, wingwall, or other suitable structure based on existing relief to prevent scour and
erosion at and around outlets. This is suitable where flow is being discharged to a
watercourse. Depending on the situation, armouring of the opposite side and/or
downstream channel of the stream bank may also be required.

9.1.10 Stream Flow Diversion


A stream flow diversion diverts perennial water flows around a works area that is located in
a watercourse.

9.2

Sediment Control

In combination with the erosion control measures set out above, a suite of sediment control
measures are proposed for the CHWF Site. A summary of sediment control measures are
set out below.

9.2.1

Silt Fences

Silt fences are a barrier device comprising a geotextile fence used to intercept sediment
laden runoff from areas that are either unable to drain to, or are of a size that does not
warrant a communal sediment control device. Silt fences will be installed on a contour and
service catchment areas below 0.5 ha as required.

9.2.2

Super Silt Fences

Super silt fences are the same as for silt fences but include chain link and tensioned wire for
reinforcement of the geotextile. The fence is reinforced with chain link at 400mm and
800mm above ground, comprising a double layer of geotextile from 400mm above ground

33

Draft Environmental Management Plan


Castle Hill Wind Farm

to 200mm below ground. Super silt fences will be used to service catchments larger than
0.5ha where no other sediment control method is suitable.

9.2.3

Sediment Control Ponds

Sediment control ponds are a temporary pond with storage volume and outlet structure
designed to provide sufficient settling time for sediment to settle out for a range of events
up to the design storm. Ponds require maintenance by way of excavation when 20% of
total volume is lost to accumulated sediments. A level spreader will be used between the
forebay and the pond to ensure infows do not cause sediment re-suspension. Pond
catchments should generally be limited to less than 3 ha in area.

9.2.4

Sediment Control Ponds with Flocculation

Same as for sediment control ponds, but include a flocculation dosing system to aid the
settlement of suspended solids. Bench scale tests will be undertaken to determine the
suitability of flocculation systems, and if suitable, appropriate dosing rates. Dosing systems
include batch dosing, rainfall activated liquid dosing, and flow activated dosing.
Flocculants can be toxic to fauna, so stringent care will be taken to establish and operate
correct dosing regimes that ensure residual levels are safe in the environment. Flocculation
pond catchments should generally be limited to an area less than 5 ha.

9.2.5

Decanting Earth Bunds

A Decanting Earth Bund is a compacted earth bund established to created an impoundment


area where runoff can pond and allow sediment to settle out. This is similar to a sediment
control pond but with a different outlet type and without a forebay. Catchments should
generally be limited to less than 0.3 ha and bunds will be excavated when 20% of total
volume lost to accumulated sediments.

9.2.6

Improved Decanting Earth Bund

Same as Decanting Earth Bund but with improved inlet and outlet systems as used by
sediment control ponds. A level spreader will be used at the inlet to the bund to ensure
inflows do not cause sediment re-suspension. Improved bund catchments will be limited to
less than 1.5 ha and bunds should be excavated when 20% of total volume lost to
accumulated sediments.

9.2.7

Wheel Wash Stations

A wheel wash station is a flooded basin lined with agitators to remove sediments
accumulated on the wheels of trucks prior to them exiting the Site. Daily flushing of basins
will occur, with effluent being discharged into a sediment control device and any
contaminants treated in an appropriate manner. Generally wheel wash stations will be at the
Site exits onto a sealed road, and often used in conjunction with a stabilised entrance.

34

Draft Environmental Management Plan


Castle Hill Wind Farm

9.3

Stabilisation or Surface Treatment Methods

Stabilisation and surface treatment methods will utilised at the CHWF. The use of these
measures will be refined based on site specific requirements and On-site experience. A list
of those methods that will be considered for use in the appropriate circumstances at the
CHWF is set out below.

9.3.1

Surface Roughening

Surface Roughening consists of track rolling to roughen a bare surface to slow the velocity
of sheet flow, prevent runoff concentrating into erosive rills, and aid the establishment of
vegetative cover.

9.3.2

Stabilised Construction Entrance

A stabilised construction entrance is a stabilised pad of aggregate or asphalted to prevent


erosion at a highly trafficked area, and to provide an opportunity for dust accumulated on
the truck scrape to be vibrated off. The drainage from stabilised entrances will discharge to
a sediment control device and contaminants treated in an appropriate manner.

9.3.3

Staging Works and Progressive Stabilisation

Staging or sequencing of construction and progressive stabilization and rehabilitation is a


function of construction planning. Staging requires work areas to be segmented into
separate task areas that can be opened and then completed prior to moving onto
successive areas. These completed areas will be stabilised as they were finished, resulting
in the Site being progressively opened and then stabilised. This ensures that the minimum
area of soils are exposed at any one time and also allows for high risk work to be planned
over summer while lower risk work can be scheduled for winter works.

9.3.4

Top Soiling and Grass Sowing

Spreading topsoil and sowing grass seed to permanently stabilise exposed areas will
receive a minimum thickness of 100 mm topsoil (depending on available supply at the Site).

9.3.5

Mulching

Mulching involves spreading straw or other suitable materials to protect exposed surfaces
from erosion and to promote establishment of vegetative cover. A sufficient quantity of
mulch needs to be applied to form a protective layer over the exposed surface. Mulching
will be used as temporary measure at the Site or will be used in conjunction with top soiling
and grass sowing for permanent stabilisation.

35

Draft Environmental Management Plan


Castle Hill Wind Farm

9.3.6

Geotextile

Geotextiles (woven or other artificial but non-degradable geotextile) will be used for the
protection of exposed areas. The type, thickness, strength and hydraulic performance of the
geotextile used depend on the situation and purpose of use. Common uses include lining
steep channels, providing removable stabilisation overnight or during inclement weather,
and lining excavations prior to placement of riprap or aggregate.

9.3.7

Biodegradable Fibre Matting

Biodegradable Fibre Matting is used to protect exposed areas and to promote


establishment of vegetative cover, often to stabilise topsoil and grass sown on steeper
slopes.

9.3.8

Hydroseeding

Hydroseeding activities will apply a mixture of grass seed, fertiliser and a binding agent
(usually wood or paper pulp) sprayed onto steep or otherwise critical exposed areas.

9.3.9

Tackifier enhanced Mulching or Hydroseeding

Tackifiers are polymers which are added to hydroseeding pulp to improve immediate
erosion protection and to aid adhesion to exposed surfaces. These tackifiers are often also
used as flocculants in sediment control ponds. Any restriction on the use of tackifiers will be
considered before application.

9.3.10 Spray Concrete


Spray concrete is a high cement content grout which is applied to immediately stabilise and
reinforce steep slopes and other critical areas. This will be used to stabilise loose rock on
steep batters adjacent to roads and bridge abutments.

9.4

Maintenance of Erosion and Sediment Control Measures

Ongoing maintenance of erosion and sediment control structures is necessary to ensure


that they remain fit for purpose and functional in a wet weather event. Such devices will be
inspected as part of the supervision duties undertaken by responsible parties and
maintained in working order whilst they are required. Inspections shall occur prior to, during
and after prolonged periods of heavy rain, as appropriate. Any defects will be promptly
rectified.
Intensive monitoring and maintenance will be required to optimise and maintain erosion and
sediment controls during construction. This will include:

Maintaining access to ponds and decanting earth bunds following wet weather;

36

Draft Environmental Management Plan


Castle Hill Wind Farm

Cleaning out ponds and decanting earth bunds following heavy rainfall and high
sediment load events;

Signposting ponds and decanting earth bunds to identify them;

Maintaining open communications and cooperation with Council appointed


compliance staff;

Maintaining electronic records of device condition (including photos and


inspection records);

Providing as built drawings of key ponds and decanting earth bunds and their
catchment areas; and

Monitoring occurrences of and managing stock interference with erosion and


sediment control measures.

In addition to specific measures, topsoil that is to be used in revegetation will be stockpiled


away from drainage lines and watercourses. These areas will be managed to minimise
erosion with surface stabilisation to prevent wind erosion.

9.5

Removal of Erosion and Sediment Control Measures

Erosion and sediment control measures will be monitored and maintained as set out in the
EMP and ESCP(s). When the use of control measures is determined to no longer be
necessary (construction activities are completed and reinstatement and revegetation of the
disturbed area implemented), Council will be advised that the area has been adequately
stabilised and that risks from erosion are low.
For clarity, removal shall only be considered when the area in question is inherently resistant
to erosion or rendered resistant. In terms of revegetation by way of grassing or
hydroseeding, inherent resistance is determined to be when ground cover is in excess of
80%.

37

Draft Environmental Management Plan


Castle Hill Wind Farm

10.

Water Management

General drainage works may be required across the Site to manage any seepages during
the earthworks activities. Surface discharges from seepages and any springs that are
covered by construction earthworks (e.g. Excess Fill Areas) will be diverted beneath the fill
to discharge at a suitable downslope location. This will be achieved by installing underdrainage beneath the fill areas where appropriate
Open excavations (for example Turbine Foundations) may collect either ground or rain
water. If this occurs, the excavation will be dewatered, most likely by pumping. Discharges
generated by this will be treated in accordance with the ESCP(s) and Drainage Management
Plan (DMP).
Some Internal Roads, Central Laydown Areas, turbines, Excess Fill Sites or other site
elements have been sited over an existing On-site pond. Where this occurs the ponds are
usually relatively small locally constructed retention areas used by farmers and do not hold
large volumes of water, or similarly small natural depressions where water has been allowed
to accumulate. If required, ponds will be de-watered in a controlled manner and if
appropriate, treated in accordance with the ESCP and DMP. It is not expected that this
practice will be necessary at many sites.
In addition to the ESCP (Appendix F), a draft example of the DMP is also provided in
Appendix K. This sets out the purpose, objectives and content for the DMP.

10.1

Quarry Water Management

It is estimated that 0.24 m3 of water will be required for each 1m3 of gravel in the crushing
process. Once the gravel aggregate has been sorted it will be transported to the Concrete
Batching Plant for concrete production or it will be stockpiled for use in road formation.
Detailed water management measures for quarries and aggregate processing will be
established and set out in detail in Quarry Management Plan (QMP) located in Appendix H.
Typical arrangements will include:

Quarries will be surrounded by a cut-off nib or bund, and will drain to a multi
stage settling pond.

Recycled water will be drawn off from this.

Excess clean water will discharge in a controlled manner onto grass slopes.

Sludge in settlement ponds is likely to contain a very low level of contaminants.


This will be tested during construction in accordance with the agreed monitoring
approach. Un-contaminated sludge (essentially silt and clay) will be included in
Excess Fill Areas.

38

Draft Environmental Management Plan


Castle Hill Wind Farm

10.2

Any contaminated sludge will be removed off site to a landfill.

Concrete Batching Water Management

General water management measures for concrete batching plants will include:

Full management of sediment and erosion potential in accordance with the


ESCP.

Isolation and capture of runoff from activity areas (cement silo, concrete
batching, load-out, wash-pits, sludge drying and waste concrete) into settling
ponds for recycling.

Water will be recycled for concrete manufacture and washing the inside of the
truck bowls when it is available.

Where storage for flows from within the activity area is full, treatment is
provided.

Stormwater from non activity areas will be collected and treated prior to
discharge.

An outline Concrete Batching Plant Management Plan (CBMP) is provided in Appendix I.

10.3

Water Quality Monitoring

Water quality will be managed through a monitoring plan comprising a Baseline Aquatic
Monitoring Plan (BAMP) which will establish a baseline of receiving water quality at
reference sites prior to construction both during dry periods and in response to rainfall
events. A Construction Aquatic Monitoring Plan (CAMP) will also be used to establish
water quality at reference sites during construction and monitor water discharged from
representative sediment control ponds. This will enable the performance of management
measures against environmental and operational objectives to be evaluated. Detailed
information will be set out in the BAMP (Appendix J) and CAMP (Appendix K).

10.4

Wastewater Management

Toilet facilities will be provided On-site, with holding tanks or septic tanks utilised. Sewerage
will be removed from Site and disposed of at a registered waste treatment facility. Wastes
generated from wash-down activities will be collected and disposed of appropriately.

39

Draft Environmental Management Plan


Castle Hill Wind Farm

11.

Site Rehabilitation and Reinstatement

11.1

Overview

The construction of the CHWF will be progressive in nature and post construction
reinstatement of all disturbed areas will also occur in a progressive manner, and in
accordance with the measures proposed within this EMP and relevant SEMPs. This
sequential reinstatement process will occur from upstream areas moving through to
downstream areas. The reinstatement process will ensure that all areas, including any
earthworks batters, internal roads, channels and sedimentation ponds are appropriately
stabilised before the Contractor demobilises from that particular area within the Site.
Reinstatement and revegetation will focus on providing a stable landform and vegetative
cover promptly after the infrastructure is no longer required, or when the earthworks activity
is complete. Once construction activity is completed in a particular cluster or area, the
following activities shall be undertaken:

All building and construction materials shall be removed from the Site and
disposed at a licensed facility.

Temporary facilities such as contractor compounds, concrete batching plants


and erosion and sediment controls shall be removed from Site

Reinstatement will involve the stabilisation and rehabilitation of disturbed areas


by ripping, top soiling, and revegetating the area.

Follow up maintenance will be undertaken until the area is satisfactorily


stabilised and restored.

The appropriate Council shall be notified.

Retention of topsoil for use in rehabilitation will form an integral component of the
rehabilitation process. In all areas of excavation, topsoil will be removed and stockpiled for
later use in the rehabilitation and revegetation of disturbed areas.

11.2

Revegetation

The objective of revegetation and rehabilitation will (apart from where there are nonvegetated solutions proposed) be to replace vegetation as like-for-like. To assist vegetation
establishment, stock will be excluded from recently established grass and indigenous
plantings, with measures for control of pest animals and weeds undertaken to improve
establishment success. The control of pest animals and weeds will be provided for within
the Revegetation Plan (Appendix L) and within other relevant Biodiversity Management
SEMPs such as the Weed Hygiene and Surveillance Plan (Appendix M). A combination of
methods may be utilised and are identified within this section.

40

Draft Environmental Management Plan


Castle Hill Wind Farm

11.2.1 Hydroseeding
Hydroseeding will comprise the application of a mixture of grass seed, fertiliser and a
binding agent (usually wood or paper pulp) sprayed onto steep or otherwise critical exposed
areas. Surface roughening exposed areas will aid vegetation establishment in hydroseeded
areas. Because hydroseeding does not retain moisture as well as topsoil, grass seed and
mulching, the timing of spraying important.
The benefits of hydroseeding are that it offers a solution to revegetate difficult terrain which
cannot be established by using normal methods. It is anticipated that the seed mix to be
used in hydroseeding will include perennial ryegrass, brown top and clover. The seed mix
must be free of weed seeds and will take account of the preferences and recommendations
of CHWF landowners.
Due to the steepness of the areas proposed for hydroseeding, Genesis Energy will require
that a uniform hydroseeded cover is provided. Areas being hydroseeded shall be inspected
six to eight weeks after the application and any areas that have failed to establish shall be
retreated until in excess of 80% cover is achieved and the area is deemed to be inherently
resistant to erosion

11.2.2 Direct Drilling


Direct drilling is a method of establishing pasture cover over large areas where suitable
contour allows for machinery to manoeuvre. In areas that are to be direct drilled, preparation
may include light cultivation and rolling to assist in pasture establishment. In areas capable
of being direct drilled, the expectation is that the area can be fully reestablished into pasture
cover (100% cover). Depending on the prevailing climatic conditions, the normal timeframes
to observe successful establishment of vegetative cover is approximately six weeks. All
areas will be reviewed six to eight weeks after direct drilling to determine the overall
success of the established pasture and to enable resowing to occur in areas which have not
successfully established. A range of species will be used for revegetating the Site, with
pasture grasses including perennial ryegrass, brown top and clover where appropriate.

11.2.3 Fascining
Fascining involves the laying of seed-bearing slash or mulch branches with viable seed that
has been harvested from plants and placed across the slope to retain sediment. Often this
needs to be held in place with stakes or biodegradable netting. Seed contained on the
material germinates under the protective leaf mulch and establishes. The species likely to
be used for fascining activities at the CHWF Site are manuka and kanuka. Seasonal
considerations are necessary to ensure foliage collected contains viable seed.

41

Draft Environmental Management Plan


Castle Hill Wind Farm

11.2.4 Direct Planting


Direct planting will use plants that are naturally found in the project area and are suited to
the Site. In order to reinstate or provide establishment phase indigenous vegetation cover,
species such as kanuka, toetoe, manuka, karamu, ti kouka, piripiri and coprosma will be
used initially. Secondary phase indigenous species will be planted (known as enrichment) in
the appropriate areas once the initial canopy cover has been established. Slow release
fertiliser and water crystals will be used where necessary to assist vegetation
establishment. The areas proposed to be revegetated will be determined and set out in the
relevant SEMP, with appropriate species, the composition of the planting mix, plant spacing,
plant sizes and maintenance requirements.

11.2.5 Natural Revegatation


Natural Revegetation relies on the existing seed bank within soils and surrounding
vegetation to naturally establish or colonise areas. Natural revegetation of areas can be
enhanced when topsoil is collected from an area with a significant seed bank and spread to
an area identified for revegetation (e.g. not stockpiled).

11.2.6 Maintenance of Revegetated Areas


Ongoing maintenance in the form of pest and weed control, replacement of vegetation
which has failed to establish, and fencing will be determined for specific sites and set out in
the relevant SEMP.
Secure fencing or alternative protection will be necessary to prevent vegetation being eaten
by stock and to allow native plants to grow and or regenerate. Options for control of goats
and deer are being considered as part of a wider control effort within the CHWF properties;
however pests such as possums, hares and rabbits can cause considerable damage to
establishing vegetation and will require more focused control until vegetation has
established.
Weed control will also be undertaken in order to reduce competition from weeds for the
first 3 years following planting / sowing. Weeds will be suppressed by use of an appropriate
mulch or herbicide.

11.2.7 Stock Access and Farm Management


Construction activities will at times conflict with normal farm and stock management
operations within the CHWF, expecting the need to remove fencing and other containment
measures in order to undertake earthworks.
These aspects of the project will be managed in consultation with individual farm managers
and CHWF Landowners. In order to provide for stock containment, stock will be moved to
secure paddocks and fencing will be reinstated as soon as practicable.

42

Draft Environmental Management Plan


Castle Hill Wind Farm

12.

Air Quality

Various activities associated with the construction of the CHWF are expected to result in
the creation and discharge of dust into the air. The effects are expected to be less than
minor; however management measures will be employed as necessary. Management of the
effects caused by dust discharges will be covered in the ESCP(s).

12.1

Dust Control

To manage dust emissions from the CHWF Site during construction the following measures
will be implemented as appropriate:

Temporary sealing of roads at key areas.

Full compliance with the EMP and ESCP (Appendix F) and other relevant
management plans

Temporary water application to suppress dust in certain areas or conditions

Use of cement silos and aggregate bins to avoid aeolian dust.

Provision of wheel washing facilities (where appropriate)

Hydroseeding and other revegetation techniques will be applied to earthworks


sites as quickly as possible post excavation.

Earthworks sites will be limited to areas of immediate construction.

Restriction of traffic speeds.

Vehicle tailgates will be properly sealed.

In addition, all stockpiles will be covered or stabilised to avoid loss of material during high
wind events and where practicable, placed in areas sheltered from the wind. Where a
significant amount of material is lost, a review of storage procedures will be undertaken to
avoid reoccurrence of the event.

12.2

Machinery and Vehicle Condition

Vehicles and machinery are one possible source of air contamination. All construction
machinery and vehicles operating on the CHWF Site will be in a good state of repair and be
well maintained throughout the project.

43

Draft Environmental Management Plan


Castle Hill Wind Farm

13.

Construction Noise Management

The assessment of construction noise for the CHWF elements identified that the
construction of the CHWF would readily comply with New Zealand Standard 6803:1999
Acoustics -Construction Noise. It was noted that during construction of roads, and in the
operation of construction vehicles over these roads there is potential to produce noise
levels which approach the limits of acceptability for construction noise. In order to ensure
compliance within the noise limits, and to address noise issues which may arise upon
commencement of construction a Construction Noise Management Plan (CNMP) shall be
prepared and implemented. The CNMP describes the manner in which noise effects will be
controlled to comply with the construction noise standard (except where appropriate forms
of mitigation have been provided), and to minimise noise effects on residents and other
noise sensitive activities near the Site. This CNMP includes a procedure for responding to
noise complaints. An outline CNMP is located in Appendix N.

13.1

Controlled Blasting

It is anticipated that the excavation work will be able to be undertaken entirely using
excavators and dozers with ripping attachments. However, it is possible that harder material
is encountered and that it may be necessary to undertake controlled blasting operations to
assist excavation activities.
Controlled blasting involves the breaking up of larger rock into smaller, more manageable
pieces. Rock drilling to plant the explosives is undertaken.
Any requirement for controlled blasting will be documented formally by the contractor in a
request to the Project Manager and Project Environmental Manager (or others as
necessary). The request will contain the following information:

Name and qualifications of the responsible person(s)

Current Approved Handlers Certification of the responsible person(s)

Location of the area proposed for the discharge of the explosives

Information on the method and explosive to be used and the depth and spacing
of the charges.

The procedure for site clearance and post blast reoccupation

Storage and handling of explosives.

Occupational health and safety requirements

Noise monitoring requirements.

44

Draft Environmental Management Plan


Castle Hill Wind Farm

14.

Traffic and Transport Management

A Construction Traffic Management Plan (CTMP) is proposed to manage all construction


traffic associated with the development of the CHWF.
In advance of the CTMP being prepared, a Construction Traffic Management Framework
(CTMF) has been prepared and is provided as Appendix O. This CTMF establishes the
purpose, objectives, and process for development of the CTMP. It specifies the minimum
content for the CTMP and the deliverable expectations to be met. The consultative and
approval requirements for the plan provide an assurance about the management, control
and delivery of the proposal.

45

Draft Environmental Management Plan


Castle Hill Wind Farm

15.

Concrete Batching Plant Management

Up to four Concrete Batching Plant locations have been proposed On-site for the CHWF
project. The plants would be re-locatable with one or two locations concurrently operational
at any one time. Concrete Batching Plants may also be located next to water sources Offsite.
A Concrete Batching Plant will consist of a concrete mixer, cement bins, sand and
aggregate stockpiles, water storage tanks and storage areas for equipment and tools.
Sufficient area is required for the use of front end loaders, delivery of materials and entry
and exit of agitator trucks. The Concrete Batching Plants will be approximately 5,600 m2 in
size.
Environmental management measures for the Concrete Batching Plant will be agreed in a
specific Concrete Batching Plant Management Plan (CBMP) (see Appendix I).

46

Draft Environmental Management Plan


Castle Hill Wind Farm

16.

Management of Quarries and Crushing Facilities

Potential gravel sources for concrete production and for construction of roads and other
hardstanding areas have been identified both On-site and Off-site. In order to use the
gravel, it will need to be quarried or excavated from the gravel source site.
An indicative quarry layout can be found in the Quarry Management Plan (QMP) located in
Appendix H.
The typical process for quarrying materials is as follows:

Erosion and sediment controls will be established in accordance with the ESCP
and QMP.

Topsoil will be removed and stockpiled for use in rehabilitation,

Overburden will be removed to On-site Excess Fill Areas

Gravel resources will be excavated using earthmoving equipment. If hard


material is encountered controlled blasting may be necessary under strict
management.

Gravel will be loaded into an adjacent crushing / screening facility.

When the gravel deposit is exhausted, or gravel from that particular quarry is no
longer required the quarry site will be rehabilitated. This may include the use of
the quarry to deposit excess fill.

47

Draft Environmental Management Plan


Castle Hill Wind Farm

17.

Archaeological and Heritage Management

At the time of consent, no archaeological sites were known to be present and it was
considered unlikely that any unrecorded sites would be exposed during construction at the
CHWF Site. However, it is possible that items of archaeological interest may be discovered
as a result of exposing sub surface layers.
To address the potential for discovery items of archaeological interest, a comprehensive
Accidental Discovery Protocol will be developed in consultation with the tangata whenua.
This Accidental Discovery Protocol (ADP) will ensure that if koiwi tangata (human remains),
taonga or sub-surface archaeological evidence is uncovered during construction, work
would cease in the immediate vicinity of the remains so that appropriate action can be
taken.
Should an archaeological site be identified (through the CHWF construction process) and
the modification of such a site become necessary, an Authority to modify an archaeological
site shall be applied for under Section 11 of the Historic Places Act 1993. No further work
shall be carried out that will affect the site until the appropriate permissions are granted.
This is in accordance with legal requirements. In addition, the tangata whenua shall be
consulted regarding the effects on Maori cultural values.
All Contractors working on the Site will be required to go through a Site induction process,
which will include training on the accidental discovery of cultural or archaeological sites or
material
A Draft Archaeological Accidental Discovery Protocol is provided in Appendix P.

48

Draft Environmental Management Plan


Castle Hill Wind Farm

18.

Biodiversity Management

The approach to biodiversity management at the CHWF Site encompasses a


comprehensive suite of measures that address effects to vegetation, habitats, flora, and
fauna through construction and operation of the wind farm. These are set out in a number of
SEMPs, each of which is summarised below and include for the mitigation of operational
effects.

18.1

Revegetation Plan

A Revegetation Plan will be prepared to ensure that rapid reinstatement of vegetation cover
following on from earthworks. The overall objective of this plan will be to ensure that
vegetative cover (or alternative protective measures) is established within 3-6 months of the
completion of Site works. An outline of the Revegetation Plan is provided in Appendix L.

18.2

Habitat Management Plan(s)

A Habitat Management Plan will be prepared for the CHWF, to enhance areas of indigenous
vegetation and habitat to improve the overall quality and productivity of that habitat. This
shall address matters such as legal and physical protection by covenant and fencing,
enrichment planting, revegetation planting (if required), natural regeneration, pest control,
and monitoring and reporting. It will guide the permanent protection and ongoing
improvement of an area of habitat approximately 210 ha in size, in a staged manner. An
outline of the Habitat Management Plan is provided in Appendix Q.

18.3

Riparian Protection Plan

A Riparian Protection Plan will be prepared to guide the physical protection of stream
riparian margins. It will establish the mechanism for the implementation of riparian protection
is achieved in a staged manner as the wind farm is constructed.
An outline of the Riparian Protection Plan is provided in Appendix R.

18.4

Weed Hygiene and Surveillance Plan

A Weed Hygiene and Surveillance Plan shall be prepared to promote good weed hygiene
and a high standard of weed control at the CHWF Site. This will address matters such as
transportation risks from vehicles or equipment and cover both terrestrial and aquatic pest
species. The Weed Hygiene and Surveillance Plan is located in Appendix M and will require:

49

Draft Environmental Management Plan


Castle Hill Wind Farm

All contractors to practice good weed hygiene, cleaning their equipment before
entering the CHWF Site.

Ensuring that aggregates, soil, sand other material brought onto the CHWF Site
is weed-free.

Ensuring that existing weeds present On-site do not have their spread
exacerbated by On-site activities.

Measures to reduce the likelihood of an accidental introduction to the extent


practical.

An annual weed monitoring programme.

Control measures to address invasive species as a result of monitoring.

18.5

Goat Control Plan

As a component of the approach to managing pests across the Site, a Goat Control Plan
will be prepared to provide a coordinated management approach to the control of feral
goats across all properties associated with the CHWF with an aim to reduce goats to very
low levels and eliminate goats over a period of 5 years.
An outline Goat Control Plan is provided in Appendix S.

18.6

Avifauna Monitoring Plan

An Avifauna Monitoring Plan will be prepared to establish the baseline situation (building on
monitoring already undertaken at the Site) and also provide for the monitoring, assessment
and analysis of the impacts associated with the CHWF. The Avifauna Monitoring Plan shall
establish a mechanism for assessment and review by relevant specialists in order to
determine if any effects on avifauna have arisen as a result of the operation of the wind farm
and the process and proposed measures that shall be implemented to manage such effects
in an adaptive manner.
An outline Avifauna Monitoring Plan is provided in Appendix T.

18.7

Bat Monitoring Plan

Long-tailed bats have been found within the CHWF Site. A Bat Monitoring Plan will be
prepared to address the potential presence of bat roost sites within the construction
footprint, the process for relocating bats should the removal of the roosts be deemed
necessary (including seasonal and breeding considerations) and also measures to

50

Draft Environmental Management Plan


Castle Hill Wind Farm

determine collision risks, collision monitoring, and the process and proposed measures that
shall be utilised to manage such effects in an adaptive manner.
An outline Bat Monitoring Plan is provided in Appendix U.

18.8

Lizard Monitoring Plan

A Lizard Monitoring Plan will be prepared to provide a mechanism for managing potential
effects on lizards. This will ensure that likely lizard habitat is identified and searched prior to
construction and that lizards found during construction are handled correctly and if
necessary, translocation to an area of appropriate adjacent habitat be made. Only lizards
which are officially threatened will be the subject of translocation efforts.
An outline Lizard Monitoring Plan is provided in Appendix V.

18.9

Predator Control Plan

Predator control will be undertaken at the CHWF to reduce ecological impacts arising from
introduced predators at specific high value locations within the Site. An outline of the
Predator Control Plan is provided in Appendix W.

18.10 Vegetation Management Plan


A detailed assessment of vegetation clearance requirements and mitigation has been
performed and accounted for in the AEE. Included in this is the requirement for an amount
of vegetation clearance/trimming to reduce flow effects on the wind turbines and to
maintain transmission line clearances. Where trees will be felled, this activity will be
performed by suitably qualified tree felling contractor.
An outline Vegetation Management Plan id provided in Appendix X.

18.11 Aquatic Monitoring Plans


In order to determine any effects from construction of the CHWF, a comprehensive
management programme for avoiding or mitigating effects on in-stream values is proposed.
This comprises a Baseline Aquatic Monitoring Plan (BAMP) and a Construction Aquatic
Monitoring Plan (CAMP).

51

Draft Environmental Management Plan


Castle Hill Wind Farm

The BAMP will be developed to collect pre-construction information on aquatic communities


within the Site and will provide a comparison with subsequent monitoring during
construction.
The CAMP will then be developed, based on the BAMP, and will include compliance
standards and measures to be implemented if standards are not met Any potential effects
will be minimised by adopting best-practice erosion control measures during construction
and prompt post-construction revegetation of disturbed sites according to the ESCP.
It is expected that there will be a combination of culverts and small bridges required for the
Internal Roads to cross watercourses. Conceptual designs for water crossings have been
developed and will be implemented at watercourse crossing sites, to enable fish passage to
be maintained, as discussed in the COMR. Fish located in areas of stream beds which are
likely to become stranded or harmed by construction activities in and around the stream
may be captured and released in a section of stream that will not be affected by
construction activities.
A Draft BAMP is provided in Appendix J and Draft CAMP provided in Appendix K.

52

Draft Environmental Management Plan


Castle Hill Wind Farm

19.

Visual Mitigation

Genesis Energy intends will minimise the landscape and visual effects arising from the
infrastructure at the CHWF by implementing the following:

Siting Turbines within a defined Turbine Corridor which has been identified to
have acceptable environmental effects.

Colour turbines off-white to light grey colour using a low reflectivity paint to
minimise visibility of turbines and reduce the potential for blade glint.

Screen infrastructure (substations, buildings, etc) with appropriate vegetation to


soften built features in the landscape (where practicable).

Use an appropriate colour palette for permanent buildings to assist in their


integration into the landscape using colours recessive in nature, and appropriate
within the rural environment

Investigate and where appropriate, implement site specific landscape mitigation


where it is considered that the occupants are likely to experience high visual
effects from their dwelling area.

Work with the CAA and qualified landscape architect to reduce the effects of
light spillage (type, placement, colour) from turbines and other permanent
facilities.

Once wind turbine positions are finalised the assessment of shadow flicker effects will be
reassessed to confirm that predicted shadow flicker effects are less than the guidelines of
no more than 30 hours per year and/or 30 minutes per day. Landscape mitigation shall be
applied where high visual effects will be experienced from dwelling areas (where
appropriate).
Genesis Energy will minimise the landscape and visual effects arising from the earthworks
of the CHWF by implementing the following:

Briefing construction staff on the desired approach to minimise environmental


impacts and proposed rehabilitation measures.

Minimise extent of earthworks cuts and escarpments in road creation at final


design.

Minimise height of earthworks cuts and escarpments at final design where


practicable.

Engage a qualified landscape architect to assist in minimising visual impacts.

Modify cut and fill to relate to the existing landform and natural features

Store and reuse topsoil on finished earthworks to assist in revegetation.

Revegetate areas on a like-for-like basis

53

Draft Environmental Management Plan


Castle Hill Wind Farm

20.

Hazardous Material Management

A bulk storage facility (or facilities) shall be provided within a suitable location close to Site
offices or active construction areas. Any facilities will not be located within 50m of a
watercourse. The bulk storage facility will be used to provide fuel to service all the vehicles
On-site, probably by way of mini tanker. Towable tankers may also be used in some
circumstances.
The bulk fuel tank will carry a significant capacity of diesel fuel. The tank will be double
skinned providing an additional layer of containment should the inner tank rupture. This
tank shall be supplied and maintained by a specialist fuel supplier. Any towable tankers will
be stored in the bunded facility when these are not in use.
Spill kits will be carried in all fuel delivery vehicles (tanker trucks and towable tankers), and
be located at the contractors compound, project Site office, substations and any other
location deemed necessary.
Any fuels for hand held equipment, oils, lubricants and other hazardous compounds will be
stored in a secure facility within the contractor compound and O & M facility and in
accordance with all relevant guidelines and regulations. The small quantities of these
materials will be stored on bunded trays to prevent spillage. The following measures shall
also be required:

The Contractor will ensure that all personnel using hazardous substances are
trained and qualified to do so.

An incident report shall be prepared in the event of a spill/incident

All unwanted materials and empty containers should be disposed of Off-site at


an appropriate landfill

The Contractor Project Manager (or delegate) shall review and retain copies of
Material Safety Data Sheets (MSDS) which identify the specific requirements in
relation to storage, use and disposal of hazardous substances.

20.1

Contaminated Land

Due to the agricultural setting of the CHWF, there is the possibility of encountering old offal
pits, old sheep dip sites, rubbish pits, metals and other contaminants from historical
pesticide/fertiliser use, spills of fuel or other from storage tanks, effluent pits, and asbestos
in buried building materials. During the various investigations and consultation performed at
the CHWF, no evidence of contaminated land of any type was identified.

54

Draft Environmental Management Plan


Castle Hill Wind Farm

Should contaminated land be encountered then an approach to management and


containment will be developed in alignment with section 22.2 Discharges of Hazardous
Materials and in consultation with the relevant council(s).

20.2

Waste Management

Covered and secure waste bins will be utilised at the Site. Both rubbish and recycling bins
will be provided and they will be clearly marked and emptied regularly to avoid overflowing.
The construction sites and work areas will be kept in a litter free condition.
All waste material will be transported Off-site for disposal at an appropriately licensed
disposal facility. There will be no On-site burial of waste material.
Surplus material and used oils may be collected for recycling; otherwise such material will
be disposed of at a registered facility.
All vehicles involved in the transportation of waste should be well maintained and waste
products on such vehicles will be well secured to avoid spills or loss.
Contractors shall ensure that no litter or debris can be dispersed from any work site, Site
plant or facilities. The dropping of litter On-site will be expressly prohibited and all people
On-site will be made aware of this requirement.

20.3

Fire Management

The following potential ignition sources at the CHWF have been identified:

Hot work (cutting and welding)

Cigarette smoking and disposal of butts

Catalytic converters on petrol driven vehicles when there is a possibility of


contact with combustible material

Ground engaging tools

The actions to be implemented to minimise the risk of fire and employ best practice with
respect to fire management include:

Appropriate signage will be utilised to warn of fire danger

No fires will be allowed On-site unless in accordance with the Forest & Rural
Fires Act 1977, District Council Regulations and Council Bylaws.

No firearms will be allowed On-site without the authorisation of the Project


Manager and Landowner. It is noted that firearms may be necessary to
55

Draft Environmental Management Plan


Castle Hill Wind Farm

implement some Biodiversity Management measures proposed for the CHWF


Site.

Provision of fire fighting equipment (operative fire extinguishers) on all Site


vehicles and water reserves at construction sites.

Access to the construction site will be by controlled access only.

The project manager and NZ Fire Service will be notified when high fire risk
construction work is being carried out on Site.

Dead end roads shall have turn around areas at least 25 metres in diameter to
enable appliance access.

Investigation into the cause of any fire outbreak and implementation of remedial
actions to ensure no reoccurrence of the event will be required.

Security staff will monitor and inspect all contractor compounds and areas
under construction after work hours for fire outbreaks.

56

Draft Environmental Management Plan


Castle Hill Wind Farm

21.

Operations and Maintenance Environmental Management

The CHWF will be operational over an indefinite period. Activities On-site during the
operational phase are of significantly lower intensity than during construction, therefore a
detailed management approach for the operational phase requirements of the wind farm is
not considered to be required at this stage.

21.1

Operational and Maintenance Activities

At the end of construction, works will be stabilised and structures completed or


disestablished, and activities will be limited to those required for the long term operation of
the wind-farm. Key operational activities are identified below.

Wind farm operation i.e. control and scheduling of electrical equipment, and
dispatch of power.

Repairs and maintenance activities:

Turbine maintenance, e.g. regular servicing, including changes of


oils, filters, firmware upgrades, inspections, component
replacements

Electrical balance of plant maintenance e.g. electrical outages for


transformer, switchgear, other plant servicing or upgrades

Civil works periodic repair of Internal Roads, buildings or laydown


areas to accommodate natural deterioration or degradation

Minor quarrying may be required for road/civil maintenance.

Other O&M phase activities:


o

Turbine performance testing

Consent compliance testing and monitoring

Other e.g. educational visits

Typical operations and maintenance activities, effects and management are identified in
Table7 below.

57

Wind farm outages

Operation of the wind farm to produce


electrical power for export into the
transmission network

Normal wind farm


operation

Turbines are temporarily not connected to


grid and are parked and secured safely

Entire wind farm is disconnected from the


grid for major transmission/electrical or
other key plant maintenance

Central point for entry/exit to Site and


starting and finishing day for staff will be at
the operations and maintenance
facility/facilities

Operation staff are likely to commute to Site


from nearby towns. Staffing levels could be
up to 40 full time equivalent personnel.

Operation times and level are mostly


determined by the wind speed and direction,
however some control (e.g. ramping) may
be implemented

Description

Activity

Traffic movements associated with the


normal operation of the wind farm are not
expected to be significantly greater than
baseline levels.

Traffic routing operations and maintenance


staff traffic.

Negligible other effects expected

Visual temporary change to normal


appearance of turbines (e.g. not rotating)

Ecology potential bird or bat strike

Effect is negligable and for relatively short


duration (e.g. <1day)

Potential bird strike will be managed through


biodiversity management measures
including avifauna and bat monitoring plans.

Operational noise effects will be addressed


in the Operational Noise Management Plan

Noise effects noise emissions through


normal operation

Traffic - driver distraction and turbine


viewing

Visual effects have been determined to be


no more than minor

Management measures

Visual effects i.e. the visual impact of the


wind turbines

Effects

Table 7: Typical Operations and Maintenance Activities, Effects and Management

Draft Environmental Management Plan


Castle Hill Wind Farm

58

Unscheduled
maintenance
(turbine)

Regular preventative maintenance on


individual turbine(s)

Scheduled
maintenance
(turbine)

Could involve major component


replacement

Intermittent, and with a good scheduledmaintenance programme infrequent

Response to faults or mechanical


breakdowns in turbines

Could involve major component


replacement

Service periods vary, but can be on a 6


month interval

Typically turbine is shut-down and a team of


service technicians will perform predefined
activities in order to ensure the safe and
sustainable operation of the turbine

Description

Activity

Draft Environmental Management Plan


Castle Hill Wind Farm

Increased potential for hazardous waste


(e.g. oils/greases)

Effects

Compliance with Site environmental


management plan(s) for example Spill
Response Plan

Management measures

59

Other activities

Civil Maintenance
(Internal Roads,
platforms)

Typically involves the removal and


replacement of a major component, e.g.
generator, gearbox, rotor, nacelle,
transformer, electrical line and others

Major component
replacement

Sediment and erosion e.g. caused by any


earthmoving activities

Possible disruption to traffic

Crane usage (minor transport effect, visual)

Transport and traffic e.g. requirement to


import overweight or over-dimension loads

Possible effects including:

Effects

Comply with quarrying management plan

Comply with erosion and sediment control


plan(s)

Compliance with relevant management


plans

Management measures

Other activities, which arise in the operation of the CHWF from time to time, will be managed in full accordance with the relevant
environmental management plan(s)

Possible additional minor quarrying activities


to extract aggregate for civil maintenance

Intermittent, but many activities may be


performed on a regular/scheduled basis

Grading and restoration of roads and


Turbine Platforms or their drainage systems
to maintain the level of intensity required for
normal operations activities

May involve temporary strengthening works


to external bridges and/or traffic/transport
measures

Level of activity and duration will vary


depending on the type of major component
replacement

Can involve the temporary, singular usage


of cranes, transport rigs, increased staffing

Description

Activity

Draft Environmental Management Plan


Castle Hill Wind Farm

60

Draft Environmental Management Plan


Castle Hill Wind Farm

21.2

Transport Activities

Operational transport activities will involve limited day to day access by wind farm staff and
contractors together with occasional delivery of supplies and components. There may also
be times when major turbine component replacement is necessary. At these times, the level
of activity and the duration of those activities will vary depending on the type of major
component replacement. Transport requirements will include a requirement to import
OW/OD loads, involve increased staffing and possible disruption to traffic.
Civil maintenance of Internal Roads and Turbine Platforms are expected to require
infrequent grading and restoration of roads and Turbine Platforms or their drainage systems
to maintain the level of intensity required for normal operations activities. These activities
will be intermittent, internalised and will be performed on a scheduled basis.

21.3

Wastewater Management

Toilet facilities will be provided On-site, with holding tanks or septic tanks utilised. Sewerage
will be removed from Site and disposed of at a licensed waste treatment facility in
accordance with the manufacturers recommendations and the level of utilisation.

21.4

Operational Noise Management

At all dwellings, the sound levels predicted from operational activities from the CHWF can
comply with the limit recommended in NZS6808:2010. To ensure compliance is achieved,
and to address noise issues which may arise upon commencement of the operation of the
wind farm, the following measures are proposed:

That noise emissions assessed by NZS6801, NZS6802 and NZS6808, will


comply with limits in the District Plans and with those derived by the method in
NZS6808:2010 as appropriate.

The noise assessment presented in the AEE will be reviewed prior to the
construction of the CHWF. This will include a recalculation of the CHWF sound
output once the wind turbine selection has been determined and their operating
parameters are known, and their siting location has been determined. The
outcome of this will be the production of an Operational Noise Assessment
Report, in which it shall be demonstrated that the noise limits of NZS6808 or of
resource consent conditions will be met.

The sound character of the selected turbines should also be assessed once the
first turbines are installed and commissioned, to ensure that special audible
characteristics are not present, and to allow the manufacturer to rectify any
such problems before the remainder of the CHWF is constructed.

61

Draft Environmental Management Plan


Castle Hill Wind Farm

21.5

An Operational Noise Management Plan (ONMP) shall be produced, which shall


include a description of the monitoring regime that will be employed to
determine compliance with noise limits (including the location of monitoring
points, duration of measurement, and requirements to report results), and
procedures for handling noise complaints. An outline ONMP is provided in
Appendix Y.

Wind Farm Decommissioning

It is expected that the CHWF will continue to operate with repairs, refurbishments and
replacement indefinitely into the future. If circumstances arise that cause the CHWF to
permanently cease operations, it will be decommissioned. If decommissioning is necessary
in the future, a specific decommissioning plan will be prepared and the appropriate
approvals will be sought from Council at the appropriate time.

62

Draft Environmental Management Plan


Castle Hill Wind Farm

22.

Incidents

All environmental incidents will be recorded and immediately reported to the Project
Environmental Manager within 24 hours of the incident occurring. The Environmental
Manager will determine the need and timing for reporting the incident to the Councils.
The need for and timing of reports will depend on the seriousness of the incident, Where an
incident or potential incident occurs that is likely to cause significant Off-Site effects on
people or the environment a report shall be supplied to the Council detailing the relevant
facts within 48 hours of the incident occurring. A further detailed report outlining
investigations of the causes and identification of additional preventative measures shall be
submitted to the Councils within 14 days of the incident.
All personnel will be made familiar with the CHWF Contingency Response Plan (below),
which identifies objectives and actions to be taken in the event of an environmental
emergency. If a significant ecological, social or heritage event occurs as a result of any
project activity, works in the immediate area will cease and the Project Environmental
Manager will be advised. Consultation with Council will be initiated, experts or individuals
will be engaged to assess the extent of the impact, and a plan for remedial action will be
developed. Remedial work will be undertaken as required and may be subject to inspection
from the Councils.
The incidents register will be kept at the Site office. All personnel working On-site are
required to report any incidents.

22.1

Incident Response Plan

If an environmental emergency or incident occurs On-site, prompt remedial action will be


implemented. Once the situation is controlled and addressed, a review will be undertaken to
assess the effectiveness of the remedial actions employed. The EMP will be updated to
reflect the outcome of any reviews.
Unforeseen events which may result in emergency action being undertaken include:

Natural Hazards such as earthquake, flooding, extreme rainfall and wind events

Pre-existing contamination sites

Operational failures

Equipment failures

Ecological disturbances

Vandalism

63

Draft Environmental Management Plan


Castle Hill Wind Farm

The following sections discuss the potential incidents which may occur On-site and the
expected response.

22.2

Discharges of Hazardous Materials

In the event of a spill or discharge from fuels, lubricants, and hazardous materials the
following procedure should be followed:

Evaluate the type of spill, the risks involved and the volume of material

Stop all operations in the immediate area of concern and remove any ignition
sources

Ensure appropriate Protection Personal Equipment (PPE) is being used

If appropriate, isolate the spill

Contain the spill using a spill kit

Report the incident to the Project Environmental Manager who will instigate the
Incident response including:
o

Notification of the Regional Council Pollution Hotline

Notification of the Consents Manager(s) at the Council(s)

Notification of the Compliance and Monitoring Officer(s) at the


Council(s)

Seek appropriate help

Start cleaning the site

Waste material will be sent to landfill

Contaminated soil will be sent to the appropriate facility

Replace any material used in the spill kit

Review the cause and response procedures. Amend operational procedures as


necessary.

A Spill Response Plan (SRP) has been provided in Appendix Z.

22.3

Sediment Control

Discharges of sediment may occur where there are failures of erosion and sediment control
devices due to a significant or extreme weather event.
In the event of a sediment discharge the following procedure should be followed:

64

Draft Environmental Management Plan


Castle Hill Wind Farm

Identify the issue which is contributing to the discharge.

Take all practicable steps to improve the quality of the discharge, including:

Unblocking any sediment control devices

Use an approved flocculant in accordance with the ESCP

Increase detention time in sediment ponds where practicable

Preventing discharge by blocking discharge outlets

Determine measures to remove deposited sediments

Undertake a review of the failure to identify any requirement for repair,


replacement or redesign such as:
o

Increase size of sediment control devices

Installing additional sediment control devices

Increase diversion of clean water around exposed surfaces

Mulch exposed surfaces

The Environmental Project Manager shall notify Council at the earliest possible convenience
to advise of the incident and the proposed approach to mitigating the discharge should
appropriate mitigating measures be appropriate or available.
Where sediment discharges prevent the use of domestic water supplies, an alternative
temporary water supply will be installed and maintained by Genesis Energy until the original
supply is fit for purpose and consumption. This is likely to consist of providing a tank and
tanker supply to the affected areas.

22.4

Fire

Equipment such as fires extinguishers and fire blankets will be located in the Site office and
within all contractor vehicles. Water carts will be located On-site and will assist with
extinguishing a fire. If a fire cannot be extinguished immediately, the Fire Service shall be
contacted. The Project Manager and Environmental Project Manager will determine the
safety of all persons and property in determining the immediate fire response.
The New Zealand Fire Service will be provided with layout details of the wind farm, including
access points, road network and the location of water sources.

22.5

Noise

Should noise generated from the CHWF and associated operations be the subject of
complaint, the noise generating activity will be reviewed in accordance with relevant

65

Draft Environmental Management Plan


Castle Hill Wind Farm

standards by the Environmental Project Manager and Project Manager and a decision be
made as to weather to stop that activity.
A review will be undertaken to identify why the activity is considered to produce excessive
noise and if there are practical options to reduce the noise generated or remediate the
noise producing activity. Such options to be considered include:

Undertaking the activity under alternative climatic conditions

Undertaking the activity in an alternative location

Reducing the number of activities being undertaken at any one time

Using noise barriers to muffle sound

Repair any damaged or faulty equipment generating the noise.

22.6

Air-borne Particles

Should particles such as dust, cement or other contaminants be identified, measures will be
taken to eliminate the source. This will be achieved by applying water to the source of dust,
covering loads or exposed areas.
Once the situation is remedied, the incident will be investigated to determine how the
situation can be avoided or mitigated going forward.

66

Draft Environmental Management Plan


Castle Hill Wind Farm

23.

Inspection, Monitoring and Auditing

The system for reviewing the environmental performance of the project activities will be
based on regular inspections, audits and sound environmental monitoring programs. These
aspects are discussed in more detail in the following sections.

23.1

Inspections

During construction, weekly inspections will be undertaken by the Contractor and Genesis
Energy Environmental Project Manager to achieve fine scale monitoring of specific
environmental aspects to ensure compliance with the EMP, SEMPs and the relevant
resource consents.
An indication of the environmental aspects requiring monitoring and the frequency of
inspections are presented in Table 8 below. This list is not exhaustive and may be amended
as specific environmental issues arise. In addition to the targeted inspections detailed
below, the contractor will have the responsibility of identifying any non-compliance with the
EMP and SEMPs.
Table 8: Environmental Inspections
Environmental Aspect

Frequency (as
appropriate)

Erosion and sediment controls Ensure there are no significant erosion /


sedimentation events caused by inadequate maintenance of soil / water
control devices

As provided in
the SEMP

Culverts Ensure the culverts On-site remain free from debris and fish
passage is not restricted

Weekly

Hazardous materials and waste Ensure all hazardous material and waste
stored and handled as per the EMP and the statutory requirements

Weekly

Roads Road conditions meet required standards and ensure the safe
transportation of required material On-site.

Weekly

Site remediation Stabilisation and revegetation works are successful with no


significant plant loss

Weekly

Biodiversity Ensure the no-go zones are left undisturbed. Inspections will also
look for signs of dieback due to dust or root compaction, weed infestations
and plant disease.

As provided in
the SEMPs

The effectiveness of the inspections will be reviewed and where necessary, the level, scope
and timing of inspections will be improved through the life of the project to ensure the
project achieves the required environmental performance.

67

Draft Environmental Management Plan


Castle Hill Wind Farm

23.2

Monitoring

Genesis Energy has proposed a range of measures and environmental monitoring to


appropriately address the potential adverse effects of the CHWF development.
Management of the CHWF during both the construction and operation phases revolves
around the establishment of this EMP and the associated SEMPs.
In addition, Genesis Energy or its representative(s) will closely and regularly monitor the
construction works. Work will require formal notice to proceed. This notice will not be
issued to the contractor unless Genesis Energy is satisfied that appropriate, compliant
measures to avoid potential adverse effects are either in place or shall be undertaken in
accordance with the management plans, or if not practicable, planned to occur during the
works.

23.3

Auditing

Auditing of performance is central to confirming that the environmental management


measures proposed are implemented, effective and maintained. It is appreciated that
Council representatives will have a role in monitoring and auditing the project so that it is
proceeding in compliance with resource consents. In addition to Council monitoring and
auditing (where Genesis Energy will work closely with the Council representatives), Genesis
Energy will have its own audit procedures to ensure that the Contractor engaged to
construct the CHWF is undertaking its work in consistency with Genesis Energys
Environmental Values.
The Project Environmental Manager will be the lead Genesis Energy representative to audit
and inspect works to determine if the contractor is undertaking these in accordance with the
EMP and SEMPs. The Genesis Energy Project Environmental Manager will also undertake
periodic audits in response to complaints and incident management.

23.4

Non-compliances

A Non-compliance Report will be generated when:

A complaint is received regarding any environmental impact or aspect caused


by the project, provided initial investigations show the complaint is valid.

A departure from approved or agreed environmental procedures is observed.

A non-compliance is identified as a consequence of any self assessment, formal


audit or other environmental survey or inspection.

68

Draft Environmental Management Plan


Castle Hill Wind Farm

Any individual working On-site may create a Non-compliance Report. If the non-compliance
is considered to be a breach of the resource consent or legislative requirements the
Councils will be notified. Non-compliances and corrective actions will be recorded and kept
at the Site office and included in the weekly and monthly reports.

69

Draft Environmental Management Plan


Castle Hill Wind Farm

24.

Complaints and Enquiries

There are several ways the general public can register complaints about the environmental
performance including:

A dedicated public enquiry line

Direct contact with Genesis Energy (0800 436 946)

Direct contact with On-site staff or Project Manager

CHWF Website by contacting castle.hill@genesisenergy.co.nz

Any complaints received will be recorded by the Project Environmental Manager in the
Public Enquiry Record and registered with the Site Manager. The Record shall include the
details of the complainant, date, nature of complaint, weather conditions at the time of the
event (if relevant), corrective action and follow up with the complainant. The record will be
kept at the Site office and included in the weekly and monthly reports.
If a material complaint is received the Councils will be notified within 5 days.

70

Draft Environmental Management Plan


Castle Hill Wind Farm

25.

EMP Documentation

The following section describes the documentation required to implement and maintain the
EMP. Genesis Energy will prepare a reporting template which will be issued to Council on a
monthly basis during construction and as necessary during operation of the CHWF.
In addition to the documentation described in the preceding sections, the following
documents will be maintained in the Site office:

EMP

SEMPs

Resource Consent documentation

Training and induction records

Any special permits or approvals required to undertake works On-site (e.g.


blasting approvals)

25.1

Work Instructions

The main contractor will prepare Work Instructions where appropriate. Work Instructions will
provide a high level of detail on the environmental aspects and obligations for a specific
work package to guide the relevant personnel or sub-contractors. The scope of the work
instruction will be dependent on the activity being undertaken, and will be prepared at the
discretion of the Project Manager. Examples of environmental aspects requiring Work
Instructions include the following:

Clearing and internal road preparation

Removal of, or works around sensitive ecology

Excavations

Weed control

Traffic management

Waste management

Soil erosion

Handling and storage of hazardous substances

A copy of all Work Instructions will be maintained at the Site office.

71

Draft Environmental Management Plan


Castle Hill Wind Farm

25.2

Inspection and Audit Reports

As outlined in Section 23 regular inspections and audits will be undertaken and


documented. Inspection reports and associated environmental documentation will be
available at the Site office. Subsequent details of corrective action and results will also be
available.

25.3

Weekly and Monthly Reports

Weekly and monthly reports will be prepared by the contactor and be made available to
relevant stakeholders. The contents of the reports would include at minimum:

Monitoring undertaken

Works undertaken in the work period

Mitigating measures / management solutions implemented

Environmental incidents report summaries

Environmental statistics

Environmental non-conformances

Issues, actions

Any audit reports during the period

A copy of the weekly and monthly reports will be maintained in the Site office. Regular
reports will be provided by the contractor outlining details and performance of management
solutions implemented during the reporting period, and also identifying any improvements or
adaptations to the SEMP required to address any site-specific issues which arise.

72

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix A: CHWF Figures


Figure 1: Location Map
Figure 2: Layout Overview
Figure 3: External Roads
Figure 4: Component Location Plan A1
Figure 5: Component Location Plan A2
Figure 6: Component Location Plan A3
Figure 7: Component Location Plan A4

Legend

NAPIER
HASTINGS "

CHWF Site
Palmerston
North
City
Council
Boundary

"

"WANGANUI

"PALMERSTON

Pahiatua

NORTH

"MASTERTON
"WELLINGTON

Manawatu-Wanganui Region

Makuri
Pongaroa

Tararua District

Tiraumea
Eketahuna

Alfredton

Mauriceville

Mataikona

Masterton District

Wellington Region
Bideford
Tinui

Castlepoint

Figure 1: Location Map

12
Kms

W-CHL-GE-001

Legend

Wind monitoring masts (existing)


Turbine Corridor
Turbine Cluster (A-G)
CHWF Site

Electrial Balance of Plant


1
"
)
2
"
)
3
"
)
4
"
)

Main Substation option 1


Main Substation option 2
Satellite Substation
Switching Station (optional)
Internal Transmission Line (220kV)

Internal Transmission Line Deviation


Internal Roads
Turbine access
Substation access
Internal Transmission Line tower access

E
G

Figure 2: Layout Overview

6
Kms

W-CHL-LY-001

To Port of Napier
on SH2

Legend

Port of Napier
NAPIER

CHWF Site

"
"

Council boundary

HASTINGS
"WANGANUI

InternalNorth
Roads City
(indicative)
Palmerston
External Roads

"PALMERSTON

NORTH

it
Ka

Over-weight/Over-dimension route

aR
aw

Additional construction traffic route

"MASTERTON

oa d

"WELLINGTON

one Valle
yR
oa
d

Horowhenua District

Ha
on

Hig

go

hw

ay

aR

Ma
ng
a

mu

Tararua District

Rim
uR
oad

R
oa
d

y
Pa Valle

Sta
te

ai

Paihiatua Road

Ro

Rakaunui (Gandys) Road

Road

A l f re

u te

Waih
oki

dt

52

Valle
y

Road

on

Rout e 52

Ro
ad

aw

d
Ro
a

Puketawa Road

Ng
ar

at

oad

oa

hi
t

iR

Ca
stle
Hi
ll R

W
ai

D ag g
s

Ro

A l fredton

u
Tin

State Highway

ut
Ro

Ro
ad

Ma
rin

ad

nd

Ti
nu

on

iV
al
le
y

ald
R

Ro
a

oa d

gi R o

Gle

or
d

Ro
ad

Wellington Region

Whangaehu

Masterton District

oa d

V alley Road

ri R

ai
ri

re O
Te O

Carterton District

re

Manawa Road

ef
B id

rto n
Maste

R
epo int
st l
a
C

0 1.5 3

o ad

Figure 3: External Roads

9
km

W-CHL-TP-001

"

Pa V
ley
al
a
Ro

ne Valley Ro ad

"

"
"

"

Ro
ute

"

52
"
"

"

r ed t o

Alf

"

"

nR
oa d

"

"
"
"
""
"
"

"

"

""
"

"

""
"
"

egend
Council Boundary

"
"

Indicative Turbine Layout

Indicative Internal Road Design

CHWF Site
Turbine Corridor

80M Turbine Layout

80M Internal Road

90M Turbine Layout

90M Internal Road

Turbine Cluster (A-G)


External Dwellings
CHWF Landowner Dwellings

100L Turbine Layout

100L Internal Road

110L Turbine Layout

110L Internal Road


Internal Substation Access Road

_
^

Internal Transmission Line Access Road

Internal Road Water Course Crossings


Transport Route

Electrical Balance of Plant


Substations
Optional Switching Station

J
"

Electrical Switchgear Huts


220kV Internal Transmission Line Towers
220kV Internal Transmission Line
Optional Internal Transmission Line Deviation
33kV Overhead Internal Electrical Lines
33kV Underground Interal Electrical Cables

Indicative Construction Areas

!L
(
(B
!
Q
(
!
W
(
!

Laydown Areas
Concrete Batching Plant
Quarry Locations

Quarry and Crushing Fac


Excess Fill Areas
Water Take Points
Water Storage Areas

"

"

"

"
""

"

"

aR
atu

"

A aihi
Ri
P
m

!!
!

A
!
!
!!
!!!

Ro
ad

!
!!
!
!
!

"

d
oa

!
!
!

"

!
!

!!!

!!

"
"
"
"

!
!
!

!!!

"
" "

!! !
! !

"
"

"

_
^
Ri m u Ro
ad

!
!

"
" "

"

!
!!

!!

!!
!
!
!
!
!!
!
! !! !!
!
!!
!
!!
!! ! !
! !
!

!
!
"

"

"

!
"

"

!
!

!
!

"
!
!!

!
!

!!
!!

"

!!

al

!
!!
!
!
!
!

!!

^a W a
_
ihok
i
"

l ey

2
e5

!!
!

"
"

"

"

"
" ""

!
!
!
!!
!
!
!

!
!

"
!
!!

!!

!!

!
!

"

_
^
!!

!
!!
!

"

Ro

!
!

!
!
!

!
!
!
!
!
!!

_
^

!
!

Roa
d

ut

"

"

"

!
!

!
!

!
!
!

!
!

!
!

"

!
!!
!

!
!! !
!
!

"
""

"

!!

"

Indicative Turbine Layout

"

a it

Council Boundary

!
""

Indicative Internal Road Design

CHWF Site
Turbine Corridor

hit
80M Turbine Layout
i

90M Turbine Layout

Turbine Cluster (A-G)


External Dwellings
CHWF Landowner Dwellings

100L Turbine Layout

100L Internal Road

110L Turbine Layout

110L Internal Road

R oad

Substations
Optional Switching Station

90M Internal Road

Internal Substation Access Road

_
^

Electrical Balance of Plant

80M Internal Road

Internal Transmission Line Access Road

Internal Road Water Course Crossings


Transport Route

J
"
B

egend

Electrical Switchgear Huts


220kV Internal Transmission Line Towers
220kV Internal Transmission Line
Optional Internal Transmission Line Deviation
33kV Overhead Internal Electrical Lines
33kV Underground Interal Electrical Cables

Indicative Construction Areas

!L
(
(B
!
Q
(
!
W
(
!

Laydown Areas
Concrete Batching Plant
Quarry Locations

Quarry and Crushing Fac


Excess Fill Areas
Water Take Points
Water Storage Areas

"

"

"

"

"

"
"

"
"
"

D
!
!
!

"

"

"

""

" "

"

"
!

!
!

!
!
!

!
!

Ro ad
!

!!!

!! !

!
!!

Ma

"o ad

"

!
"

!
!

gi R

"

"
" ""

!!!
!

"

!!
!

rin

"

!
!
!!

!
!

d
oa
i ri R

!
!
!
!!
!!!

!
!

!!

!!
!

ai r

!
!

!!
! !!
!
!
! !

!
!!

!
!
!

!
!
!!

!
!

"

!!

!!

_
^

^
_
1
_
^

!
!

!
!

!
!
!
!
!
!
!!

!
!

!
!

!
!
!
!
!

!
!

! !

!
!
!

!
!

!
!

!
!

! !!!
!
!
!

"

!!

!
!

!
!

!
!
!!

!
!!

!
!!

!!!
!

!
!
!!

!
!
!
!
!
!
!

"""

!
!
!!
!

!
!

!
!
!

!!

Da
gg

!
!

!
!!

!
!!

"

!!
!

"

"

!
!
!

"

"
"

ald R
oad

"

"

Glen
don
""
"
"

"

Council Boundary

"

"""
"

"

egend

"

""

"

"
Indicative Turbine Layout

Indicative Internal Road Design

CHWF Site
Turbine Corridor

80M Turbine Layout

80M Internal Road

90M Turbine Layout

90M Internal Road

Turbine Cluster (A-G)


External Dwellings
CHWF Landowner Dwellings

100L Turbine Layout

100L Internal Road

110L Turbine Layout

110L Internal Road


Internal Substation Access Road

_
^

Internal Transmission Line Access Road

Internal Road Water Course Crossings


Transport Route

Electrical Balance of Plant


Substations
Optional Switching Station

J
"

Electrical Switchgear Huts


220kV Internal Transmission Line Towers
220kV Internal Transmission Line
Optional Internal Transmission Line Deviation
33kV Overhead Internal Electrical Lines
33kV Underground Interal Electrical Cables

Indicative Construction
Areas
"

!L
(
(B
!
Q
(
!
W
(
!

Laydown Areas
Concrete Batching Plant
Quarry Locations

Quarry and Crushing Fac


Excess Fill Areas
Water Take Points
Water Storage Areas

C
!
!
!
! !
! !! ! ! !
!
!
! ! ! !!
!
!
!
!

!!
!

!
!

!!

!
!

!!

!
!!

D
!

!!!!

!!
!!

!
!!

"

"
" "

!
!
!

"

_
^

"
!!

!!

"

!
!
!

!
!!
!
"

C
"

"

!
!
!!

!
!
!

"

!!

!
!

F
"
" "
"

!
!
!!

"

!
!

!
!!
!
!

"
!
!!

!!

!
!
!!!

!
!
!

!!
!

o ad

"

!
!!

!!

!
!
!! !

!!

_
"" "^
"
"

!!
!

!!

!
!

"

!
!

!!
!
!
!!

!!
!
!
!
!
!

!!
!
!!!
!
!
! ! ! ! !!
!
!! !

"

_
^

!! !
!
!

"

" "

nawa R

! !
!

!!

!
!!

"

!!
!
!
!
!
!

!
!
!

!
!

!
!!!

" "

!!

"

"

"

Tin ui

"

"
"

"

"
"

""

"

"

egend
Council Boundary

"
"

"
Indicative Turbine Layout

"

Indicative Internal Road Design

CHWF Site
Turbine Corridor

80M Turbine Layout

80M Internal Road

90M Turbine Layout

90M Internal Road

Turbine Cluster (A-G)


External Dwellings
CHWF Landowner Dwellings

100L Turbine Layout

100L Internal Road

110L Turbine Layout

110L Internal Road


Internal Substation Access Road

_
^

Internal Transmission Line Access Road

Internal Road Water Course Crossings


Transport Route

Electrical Balance of Plant


Substations
Optional Switching Station

J
"

Electrical Switchgear Huts


220kV Internal Transmission Line Towers
220kV Internal Transmission Line
Optional Internal Transmission Line Deviation
33kV Overhead Internal Electrical Lines
33kV Underground Interal Electrical Cables

Indicative Construction Areas

!L
(
(B
!
Q
(
!
W
(
!

Laydown Areas
Concrete Batching Plant
Quarry Locations

Quarry and Crushing Fac


Excess Fill Areas
Water Take Points
Water Storage Areas

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix B: Resource Consents held relating to the CHWF


[Resource Consents held in relation to the CHWF to be inserted when available]

CHWF Landowners

Department of
Conservation

Tangata Whenua
Representatives

Tararua District
Council

Masterton District
Council

Horizons Regional
Council

Greater Wellington
Regional Council

Other Contractors

Sub Contractor A

Main Contractor

Genesis Energy

Organisation

Areas of Responsibility

Appendix C: Key Project Personnel Details

Draft Environmental Management Plan


Castle Hill Wind Farm

Person

Phone (office)

Phone (mobile)

Email

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix D: CHWF Project Enquiry Form


Date of Enquiry
Time of Enquiry
Name
Address

Phone Number
Nature of Enquiry

Weather Conditions Onsite at the time of Enquiry


Enquiry Received by:
Proposed Action(s)

Date of Action:
Logged in Consultation
Database

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix E: Site Contractor Acknowledgement Form


[Form to work in accordance with the Principles of the EMP and related documentation is to
be prepared]

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix F: Erosion and Sediment Control Plan (ESCP)

Castle Hill Wind Farm


Erosion and Sediment
Control Plan
Prepared for

Genesis Energy

July 2010

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


Castle Hill Wind Farm Erosion and Sediment Control Plan

Quality Control Sheet

Castle Hill Wind Farm Erosion and Sediment Control PlanErosion and

TITLE

Sediment Control Plan

CLIENT

Genesis Energy

VERSION

Draft

DATE

July 2011

JOB REFERENCE

A02337300

SOURCE FILE(S)

A02337300R007 ESCP draftv1

D
R
A
F
T

Prepared by

SIGNATURE

Hayden Easton

Directed, reviewed and approved by

SIGNATURE

Alan Pattle
Limitations:
The report has been prepared for [Click here to type CLIENT], according to their instructions,
for the particular objectives described in the report. The information contained in the
report should not be used by anyone else or for any other purposes.

A02337300R007 Erosion and Sediment Control Plan Draft v2

PATTLE DELAMORE PARTNERS LTD


Castle Hill Wind Farm Erosion and Sediment Control Plan

Executive Summary
An Executive Summary discussing the Erosion and Sediment Control Plan will be
provided.

D
R
A
F
T

A02337300R007 Erosion and Sediment Control Plan Draft v2

ii

PATTLE DELAMORE PARTNERS LTD


Castle Hill Wind Farm Erosion and Sediment Control Plan

Table of Contents

SECTION

PAGE

Executive Summary

ii

1.0

Introduction

1.1

Purpose

1.2

Objectives

2.0

Design Philosophy and Principles

3.0

Planning Framework

4.0

Assessment of Risk

5.0

Overall Erosion and Sediment Control Approach3

5.1

Team Approach

5.2

Erosion and Sediment Control Device and Measures

5.3

Monitoring

5.4

Miscellaneous Activities

6.0

Specific Erosion and Sediment Control Methodology for each


Turbine Cluster

6.1

Development Phase 1

6.2

Development Phase 2

6.3

Development Phase 3

6.4

Development Phase 4

6.5

Development Phase 5

6.6

Development Phase 6

7.0

Activity Details and Methodologies

7.1

Roads in steep topography

7.2

Concrete Batching Plants

7.3

Stream Realignments and Rehabilitation

7.4

Quarries

7.5

Culvert Installation

7.6

Bridge Works

8.0

Planning Considerations

8.1

Assessment against the Statutory Provisions

9.0

Conclusions

10.0

Key References

A02337300R007 Erosion and Sediment Control Plan Draft v2 i i i

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


Castle Hill Wind Farm Erosion and Sediment Control Plan

Appendices
Appendix A: Area Overview Plan
Appendix B: USLE Assessment
Appendix C: Erosion and Sediment Control Design Drawings
Appendix D: Sizing Calculations
Appendix E: Chemical Treatment Report if required
Appendix F: Consent conditions

D
R
A
F
T

A02337300R007 Erosion and Sediment Control Plan Draft v2 i v

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM EROSION AND SEDIMENT CONTROL PLAN

1.0 Introduction
This section will provide a brief introduction to the Erosion and Sediment Control
Plan(s) (ESCP) and its purpose in the context of the Castle Hill Wind Farm (CHWF).
The will include a brief overview of the Project, what the project entails and how
ESCPs play a part in the wider suite of management plans for the Project.
The introduction will include discussion of the process to be followed in development
and implementation of ESCPs:

that Genesis Energys contractor/consultants will prepare the detailed design


plans for erosion and sediment control devices as per the direction provided
by the ESCP and the conditions of Resource Consent(s).

that the ESCP and detailed design plans will undergo a consultation/review
process with Council.

that once agreed and consented, the ESCP will be constructed.

that Genesis Energy and its contractors will be responsible for managing the
operation and maintenance requirements of the ESCP.

1.1

Purpose

The purpose of an ESCP is to describe the method(s) to minimise soil erosion and the
treatment of sediment laden overland flow during construction of the CHWF Project.
This includes, but is not limited to:

Providing an outline of the proposed activities for each phase of development.

Evaluation of, and reporting on, activities and monitoring from the previous
phases of development.

Providing specific details of the earthworks and key associated erosion and
sediment control measures proposed.

The ESCP will be developed in phases consistent with the development of the
Windfarm.

1.2

Objectives

The following operational objectives will be used to develop each ESCP.

The use, as a minimum, of the erosion and sediment control methods


promulgated through the Hydrology Effects Assessment (PDP, 2011) and any
outcomes defined through the required statutory process.

Demonstrate how the erosion and sediment control methods promulgated are
the Best Practicable Option.

A02337300R007 Erosion and Sediment Control Plan Draft v2

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM EROSION AND SEDIMENT CONTROL PLAN

Review of monitoring data and lessons from implementation of previous ESCPs


on site to inform the choice of devices used in different situations.

The ESCP is monitored, evaluated and where necessary modified to manage


or mitigate alterations to the following; the project brief, the project site
conditions or identified risks, or any significant adverse effects identified
within receiving environments.

2.0 Design Philosophy and Principles


The following section will set the context for the development of the ESCP(s). The
principles of an ESCP are defined from Wellington Regional Councils (WRC) Erosion
and Sediment Control guideline (GWRC, 2002). These are:

Minimise Disturbance

Stage Construction

Protect Steep Slopes

Protect Waterbodies

Stabilise Exposed Areas Rapidly

Install Perimeter Controls

Employ Detention Devices

Make Sure the Plan Evolves

Inspect

D
R
A
F
T

These principles will be discussed individually and commentary will also be given how
each should be incorporated within this ESCP.
Reference will also be made to other supporting AEE documentation which outlines the
specific details of each construction location.

3.0 Planning Framework


This is a brief section that will discuss the linkages of the ESCP with the resource
consent(s), required management plans and relevant planning documents.

4.0 Assessment of Risk


The purpose of this section is to provide an analysis of the expected and foreseen
risks that might occur within the area of work being considered.
A project wide risk assessment has been carried out and this would be the starting
point for the site specific assessment for the proposed area of work.

A02337300R007 Erosion and Sediment Control Plan Draft v2

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM EROSION AND SEDIMENT CONTROL PLAN

The Universal Soil Loss Equation (USLE) would be utilized. This assessment will
provide an initial justification to the proposed sediment and erosion control devices
that will be used to manage and mitigate the effects. This would be confirmed with
the operational experience offered by Genesis Energys consultants, contractors and
Council reviewers.
As well as USLE methods, degree of risk can be classified into three key categories,
which are:

Sediment generating potential - this highlights the generation potential of the


area in question and is based on slope, slope length, soils, rainfall and erosion
control factors.

Sediment delivery this relates to the amount of eroded material that is


retained on site in depressions and within the sites natural contours prior to it
entering any sediment treatment devices.

Sediment yields the amount of sediment that actually leaves the site and
enters the receiving environment. It is well recognised that this is the key
area of interest.

Discussion of each of these categories will be provided in relation to the methods


proposed.

5.0 Overall Erosion and Sediment Control Approach


The following section will provide an outline of the key measures that will be
implemented as part of the ESCP for the phase of work being considered and builds on
the principles outlined in Section 2.0.

5.1

Team Approach

This section will outline the parties and personnel involved in developing,
implementing, monitoring and modifying the ESCP. This will include Council, Genesis
Energy consultants/contractor, and Genesis Energy staff. This section is included to
demonstrate that adequate resources, commitment and expertise are provided to
effectively implement erosion and sediment controls from start to finish of the Project
(design through to dis-establishment).
A key focus of this section will be how effective communication will occur. Discussion
on how information, reports, data will be disseminated amongst all the required
parties will be provided.

5.2

Erosion and Sediment Control Device and Measures

This section will provide a brief summary of what erosion and sediment control
measures will be used to minimise the extent of soil erosion and sediment yield in the
area of the site being considered. This will draw from the toolbox of methods set out
in the PDP Hydrology Effects Assessment.

A02337300R007 Erosion and Sediment Control Plan Draft v2

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM EROSION AND SEDIMENT CONTROL PLAN

This section will include both engineered (device orientated) and management options
(such as staged works, timing of works etc). The section will not get into the specific
detail for each individual device (this comes in section 6), the purpose of this section
is more to state how the device designs will generally conform to meet WRCs erosion
and sediment control guideline.

5.3

Monitoring

This section will be broken into two types of monitoring; performance monitoring of
device effectiveness, and site monitoring for assessing current and new risk.
Within each of these types of monitoring, discussion will be provided on how the
monitoring results will be reported, evaluated and where appropriate actioned (either
through changes to the monitoring strategy or site erosion and sediment control
improvement).
For device performance monitoring, discussion will be provided to demonstrate that
the erosion and sediment control devices have been installed correctly and are actually
working as intended. This monitoring section will need to demonstrate what
procedures will be used throughout the entire period of construction.
Discussion of the performance monitoring information of erosion and sediment control
devices will be provided.
Discussion of how monitoring will be undertaken; such as grab samples, laboratory
methods of analysis, reporting of monitoring results, and how monitoring results will
be evaluated and where appropriate, the monitoring methodology altered, will be
provided.
In parallel to device monitoring, receiving environment monitoring of freshwater and
freshwater habitat monitoring will be included.
The monitoring section will also include how continued assessment for risks will be
undertaken i.e. risks that were not identified initially, but may become apparent over
the construction period. This is essential to cover the principle regarding plan
evolution and improvement. Discussion on what mechanisms will be in place to
incorporate newly identified risk into the ESCP will also be provided.
5.3.1

Response to Indicators of Significant Effects

In this section, discussion will be made as to how parties will respond to adverse
events and what measures will be in place if adverse effects are detected.
This section will include discussion that should linkages between the adverse effect
and on-site erosion and sediment control practices be found, then alterations to the
operational methods (including modifications to environmental control measures and
methodologies) will be investigated as a first order response.

A02337300R007 Erosion and Sediment Control Plan Draft v2

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM EROSION AND SEDIMENT CONTROL PLAN

5.4

Miscellaneous Activities

This purpose of this section will be to provide discussion of the effects caused by
miscellaneous activities. Discussion will need to be included how these miscellaneous
activities will be managed. For example, dust management from roads and any
further site specific monitoring will be discussed.

6.0 Specific Erosion and Sediment Control Methodology


for Defined Areas
This section will provide the detailed methodology regarding the erosion and sediment
control methods to be implemented in the area of works under consideration.
Summary information regarding the devices within each phase of development will be
provided. Information such as; catchment area draining to the device,
pond/channel/bund volume, (forebay volume), the number of decants, side slopes,
and associated drawing references, will be provided.

6.1

Development Area 1

6.2

Development Area 2

6.3

Development Area 3

6.4

Development Area 4

6.5

Development Area 5

6.6

Development Area 6

7.0 Activity Details and Methodologies


This section will provide detailed information for the more specific higher risk
activities within the project. For each of the below, discussion will be provided
regarding the activity, and how erosion and sediment control will be undertaken for
these areas.
The following sections provide some of the potential higher risk activities that will be
discussed.

A02337300R007 Erosion and Sediment Control Plan Draft v2

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM EROSION AND SEDIMENT CONTROL PLAN

7.1

Roads in steep topography

7.2

Concrete Batching Plants

7.3

Stream Realignments and Rehabilitation

7.4

Quarries

7.5

Culvert Installation

7.6

Bridge Works

8.0 Planning Considerations


This section is set to link back to the earlier Section 3 where relevant statutory
documents were identified that are associated with this Plan. This section will
therefore discuss the assessment whether the proposed ESCP meets these statutory
provisions within the identified documents.
The purpose of this section is to demonstrate to stakeholders that the ESCP is
satisfactory and meets the relevant statutory documents.

8.1

Assessment against the Statutory Provisions

Commentary for each of the above described assessments will be placed here.

9.0 Conclusions
A conclusion statement will be included.

10.0Key References
List of references used in the plan.

A02337300R007 Erosion and Sediment Control Plan Draft v2

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM EROSION AND SEDIMENT CONTROL PLAN

Appendices

Appendix A - Area Overview Plan


This appendix will provide graphics showing an overview of the project, contour
information, and where erosion and sediment control devices will be implemented.

Appendix B - USLE
This appendix will summarise the results of the USLE and risk assessment for the area
being considered.

Appendix C - Erosion and Sediment Control Design Drawings


This appendix will provide the Erosion and Sediment Control Plans and detailed design
drawings for the proposed devices.

Appendix D Sizing Calculations


Any technical details in regards to of any devices or diversion channels that are
required within the project will be provided.

Appendix E - Chemical Treatment Report


If flocculation ponds are to be implemented, a chemical treatment plan will be
included. The chemical treatment plan provides information regarding the PAC dosing
strategy for the specific soils within the project site.

A02337300R007 Erosion and Sediment Control Plan Draft v2

D
R
A
F
T

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix G: Drainage Management Plan (DMP)

Castle Hill Wind Farm


Drainage Management Plan
Prepared for

Genesis Energy

July 2010

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM DRAINAGE MANAGEMENT PLAN

Quality Control Sheet

TITLE

Castle Hill Wind Farm Drainage Management Plan

CLIENT

Genesis Energy

VERSION

Draft

DATE

July 2011

JOB REFERENCE

A02337300

D
R
A
F
T

A02337R006 DMP v1
SOURCE FILE(S)

Prepared by

SIGNATURE

Hayden Easton

Directed, reviewed and approved by

SIGNATURE

Alan Pattle
Limitations:
The report has been prepared for [Click here to type CLIENT], according to their instructions,
for the particular objectives described in the report. The information contained in the
report should not be used by anyone else or for any other purposes.

A02337300R006 Drainage Mangement Plan Draft v2

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM DRAINAGE MANAGEMENT PLAN

Executive Summary
An Executive Summary discussing the Drainage Management Plan will be provided.

D
R
A
F
T

A02337300R006 Drainage Mangement Plan Draft v2

ii

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM DRAINAGE MANAGEMENT PLAN

Table of Contents

SECTION

PAGE

Executive Summary

ii

1.0

Introduction

1.1

Purpose

1.2

Objectives

2.0

Design Philosophy

3.0

Drainage Effects

3.1

Water Quantity

3.2

Water Quality

3.3

Ecology

4.0

Design and construction of the drainage network

4.1

Culverts

4.2

Bridges

4.3

Long term channels

4.4

Overland Flow Paths

4.5

Secondary Overland Flow Paths

4.6

Water Quality Devices

5.0

Operation and Maintenance Procedures

5.1

Culverts

5.2

Bridges

5.3

Long term channels

5.4

Overland Flow Paths

5.5

Secondary Overland Flow Paths

5.6

Water Quality Devices

5.7

Response to Operational Drainage Problems

5.8

Training

6.0

Plan Review and Evaluation

7.0

References

Tables of Tables
Table 1: Recommended Drainage Design Criteria

A02337300R006 Drainage Mangement Plan Draft v2

iii

2

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM DRAINAGE MANAGEMENT PLAN

Appendices
Appendix A: Site plan map that illustrates the location of the devices and structures of the
drainage network.
Appendix B: Calculations, Detailed drawings, and maintenance inspection check sheets for
culverts
Appendix C: Calculations, Detailed drawings, and maintenance inspection check sheets for
bridges
Appendix D: Calculations, Detailed drawings, and maintenance inspection check sheets for
long term channels
Appendix E: Calculations, Detailed drawings, and maintenance inspection check sheets for
over land flow paths
Appendix F: Calculations, Detailed drawings, and maintenance inspection check sheets for
secondary overland flow paths
Appendix G: Calculations, Detailed drawings, and maintenance inspection check sheets for
water quality devices

A02337300R006 Drainage Mangement Plan Draft v2

iv

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM DRAINAGE MANAGEMENT PLAN

1.0 Introduction
This section will provide a high level discussion summarising the purpose of the
Drainage Management Plan (DMP) and how the DMP plays a part in the wider suite of
management plans for the Castle Hill Wind Farm (CHWF) Project.
The introduction will include discussion of the process to be followed in development
and implementation of the DMP:

that Genesis Energys consultants will prepare the drainage detailed design
plans for each individual device or structure as per the direction provided by
this DMP and the Consent.

that these detailed design plans will undergo a consultation/review process


with Council.

that once agreed and consented, the drainage network will then be
constructed.

that Genesis Energy will be responsible for managing the operation and
maintenance requirements of the drainage network as directed by this DMP.

1.1

Purpose

The purpose of the DMP is to outline the proposed designs for proposed permanent
(operational phase) drainage devices and structures for the Castle Hill Wind Farm
(CHWF) project. This includes, but is not limited to:

Outlining the proposed infrastructure that will used to manage stormwater


effects (flooding and water quality management) during the operational phase
of the CHWF Project.

Provide details as to how the proposed infrastructure will be designed,


operated, maintained, and monitored to ensure that stormwater effects from
the project are appropriately managed.

The DMP may be developed progressively in line with future construction phasing of
the CHWF.

1.2

Objectives

The following objectives will be used in the development of the DMP.

The use, as a minimum, of the methods promulgated through the Hydrology


Effects Assessment (PDP, 2011) and any outcomes defined through the
required statutory process.

Demonstrate how the designs and methods promulgated are the Best
Practicable Option and meet the design requirements.

A02337300R006 Drainage Mangement Plan Draft v2

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM DRAINAGE MANAGEMENT PLAN

Review of any monitoring data and operational lessons from implementation


of previous parts of the DMP on site to inform the choice of devices used in
different situations.

2.0 Design Philosophy


This section identifies the key drainage requirements set out in the Hydrology Effects
Assessment and will set out the methodology used to generate the proposed drainage
works for the Project.
Table 1 below, provides the recommended design criteria for the project.
In addition to the recommended design criteria, linkage to the statutory requirements
of the Resource Management Act 1991, will also be made. Here, as a minimum, the
following objectives can be included:

To minimise any potential adverse environmental effects on water quality and


aquatic ecosystems from the proposed stormwater discharge from the Project.

To minimise any potential adverse environmental effects from flooding or


erosion (inclusive of land or watercourses) from the proposed stormwater
discharge of the Project.

Any specific consent conditions relating to drainage will be identified here.

Table 1: Recommended Drainage Design Criteria


Infrastructure
Culverts

Design Criteria
All culverts shall be designed to pass the peak flow during the 20 year
ARI event. The bank full flow shall be passed without becoming the
culvert becoming inlet controlled.
All culvert designs for watercourse crossings shall allow for the passage
of aquatic fauna (e.g. fish and invertebrates) and fauna (e.g. water
dispersed seeds and pollen).
Culvert structures shall be designed with good practice with respect to;
erosion and sedimentation around outlets, blockage of inlets, provision
of secondary flow paths or secondary inlets, flood hazard, and operation
and maintenance requirements.

Site Drainage

Primary piped systems shall be designed to convey the peak flow from
the 20 year ARI event.
Secondary overland flow paths shall be designed to convey the peak flow
from the 100 year ARI event based on the assumption that the primary
piped system is not operating (i.e. due to blockage, damage etc).

Flooding

All new industrial floors and sub-station yards shall have a minimum
freeboard of 1.0m above the 100 year ARI event water level (measured
to the underside of the floor structure or yard finished level).
Works shall not exacerbate flooding of existing buildings.

A02337300R006 Drainage Mangement Plan Draft v2

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM DRAINAGE MANAGEMENT PLAN

Table 1: Recommended Drainage Design Criteria


Infrastructure
Climate Change

Design Criteria
Climate change shall be factored into the estimation of peak flows from
design events.

3.0 Drainage Effects


The following section will provide discussion and analysis of the surface water effects
the DMP will manage or mitigate. This can be broken down into the following
subheadings.

3.1

Water Quantity

Discussion of the effects of flooding within the project location will be provided.

3.2

Water Quality

Discussion of the effects of contaminant management/mitigation within the project


location will be provided.

3.3

Ecology

Discussion of how that DMP will be used to manage ecological function within the
project location will be provided.
The above discussions will include the need for drainage networks to be cognisant of
aquatic ecological functions. An example of this is to ensure the design of drainage
networks that enable fish passage, stormwater outfall protection etc.

4.0 Design and construction of the drainage network


This section is a significant component of the plan.
This section will firstly state that the design of these drainage devices is aligned with
the design philosophy that was discussed earlier in section 2, and be designed to
achieve management or mitigation of the effects discussed in section 3.
Following this, details of the design and any specific construction requirements for the
relevant type of drainage device or structure will be provided.
In this section, the design discussion is not for each individual device, but should
describe the methodology that was undertaken to design/size the device type.
Similarly, the construction discussion will summarise the fundamental construction
considerations that need to be addressed when constructing each device type within
the project.

A02337300R006 Drainage Mangement Plan Draft v2

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM DRAINAGE MANAGEMENT PLAN

Calculations and detailed design plans for each individual device or structure will be
provided as appendices. Appendices will be titled for each device/structure type.

4.1

Culverts

4.2

Bridges

4.3

Long term channels

4.4

Overland Flow Paths

4.5

Secondary Overland Flow Paths

4.6

Water Quality Devices

5.0 Operation and Maintenance Procedures


This is another significant component of the plan. This section will provide detailed
discussion of how the drainage infrastructure will be operated and maintained over its
lifecycle.
Details regarding inspection frequencies will be provided. Maintenance frequencies will
include scheduled or routine maintenance procedures and also major or reactive
maintenance procedures.
A list of the people with defined roles and responsibilities for operation and
maintenance will be provided and who is going to be people involved to ensure that
the DMP is effectively implemented, monitored and when appropriate modified to
ensure best practice operation and maintenance methods are maintained.

5.1

Culverts

5.2

Bridges

5.3

Long term channels

5.4

Overland Flow Paths

5.5

Secondary Overland Flow Paths

5.6

Water Quality Devices

In the previously discussed appendices, where appropriate, maintenance inspection


check sheets for each device/structure type will be provided.

5.7

Response to Operational Drainage Problems

This section will specifically discuss how operational problems relating to the drainage
network will be mitigated. Here, the strong linkages to the spill response plan and
also the erosion and sediment control plan will be discussed. A listing of key contacts
from outside the operation and maintenance team who can be contacted regarding
significant issues will also be provided.

A02337300R006 Drainage Mangement Plan Draft v2

D
R
A
F
T

PATTLE DELAMORE PARTNERS LTD


CASTLE HILL WIND FARM DRAINAGE MANAGEMENT PLAN

5.8

Training

This section will outline any training that may be required to ensure that the operation
and maintenance requirements of the DMP are achieved.

6.0 Plan Review and Evaluation


This section will set out how the DMP will be monitored, evaluated, and where
appropriately reviewed and modified. This section would have reference back to
Section 3, where the objectives identified there will be used to determine whether the
DMP is being effective or if modification is required. The section will discuss the
frequency this occurs and what procedures will be undertaken.

7.0 References
Any references cited within the plan are to be populated here.

A02337300R006 Drainage Mangement Plan Draft v2

D
R
A
F
T

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix H: Quarry Management Plan (QMP)


Purpose
To provide for effective environmental management of all activities associated with the
establishment and operation of quarries.
Objectives
To identify measures and methods to be implemented to avoid or minimise environmental
effects appropriate for each quarry used for construction of the CHWF.
Proposed Content

Detailed design drawings

Discussion of impacts on stock and drinking water

Construction/establishment methodology, if not included in EMP

Identification of those involved in preparing the SEMP

Calculations for sizing of every sediment pond and culvert

Actions proposed to minimise the discharges of sediment

Actions taken in design to minimise extent and effects of earthworks

A list of the key environmental considerations

Work programme

Plans showing all proposed works and sediment control measures

Schedule of sediment control measures. The purpose of sediment control is to


minimise the amount of silt and clay that will be discharged onto land or into
natural watercourses. The schedule should include, but not be necessarily
limited to, descriptions of proposed bunds, sumps, diversion channels, storm
water treatment ponds, weirs, spillways and vegetated storm water disposal
strips.

Schedule of contamination control measures. The purpose of contamination


control is to minimise the amount of contaminants that will be discharged onto
land, the air, or into natural watercourses.

Schedule of hazardous substance control measures. The schedule shall


include, but not be necessarily limited to, control measures for storage of fuels
and oil.

Schedule of dust control measures. The schedule shall include, but not be
necessarily limited to, descriptions of water spraying or water misting.

Draft Environmental Management Plan


Castle Hill Wind Farm

Procedures for water recycling. The hydraulic connections for water recycling
shall also be shown on the sediment control plan.

Schedule of measures to control rock blasting, if rock blasting is considered


necessary.

Revegetation schedule during, and on completion of, construction works

Monitoring schedule. This shall include, but not be necessarily limited to, a
programme for monitoring storm water discharge for pH and suspended
sediment.

Contact details for Contractors and relevant Genesis Staff

It is anticipated that many (or potentially all) of the concrete batching plants will be adjacent
to, or contained within a quarry. Where this is the case, then the environmental measures
taken in the quarry and concrete batching plant will be closely interlinked. In such
circumstances the QMP shall be prepared, and incorporate environmental measures for the
concrete batching plant.
Where a concrete batching plant is planned separate from a quarry, then a CBMP shall also
be prepared.
An indicative sketch layout of the quarry is provided below.

   
         
  

     

  
    

 




  


  
  

 


  

 





  

    !"#$%!&&'!'(%"

  





     

 



 

 

  

      

  

   

   

      





 






 


Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix I: Concrete Batching Plant Management Plan (CBPMP)


Purpose
To provide for effective environmental management of all activities associated with the
concrete batching plant.
Objectives
To identify measures and methods to be implemented to avoid or minimise environmental
effects appropriate for each concrete batching plant used for construction of the CHWF.
Proposed Content

Detailed design drawings

Identification, consideration and protection of stock and drinking water supplies

Construction/establishment methodology.

Identification of roles and responsibilities

Calculations for sizing of every sediment pond and culvert

Actions to minimise the discharges of sediment

Actions to minimise extent and effects of earthworks

Key environmental considerations

Work programme including program of actions to implement measures

Plans showing all proposed works and sediment control measures

Schedule of sediment control measures. The purpose of sediment control is to


minimise the amount of silt and clay that will be discharged onto land or into
natural watercourses. The schedule should include, but not be necessarily
limited to, descriptions of proposed bunds, sumps, diversion channels, storm
water treatment ponds, weirs, spillways and vegetated storm water disposal
strips.

Schedule of contamination control measures. The purpose of contamination


control is to minimise the amount of contaminants, such as cement or byproducts of concrete batching that will be discharged onto land, the air, or into
natural watercourses. The schedule shall include, but not be necessarily limited
to, descriptions of the arrangement of cement delivery points, batching plant,
concrete loading areas, sludge drying and washing bays; storage of cement; the
proposed methods and extent of testing of concrete batching plant waste
sludge; and the proposed treatment of both contaminated and uncontaminated
concrete waste sludge.

Draft Environmental Management Plan


Castle Hill Wind Farm

Schedule of hazardous substance control measures. The schedule shall


include, but not be necessarily limited to, control measures for storage of
cement, cement admixtures, fuels and oil.

Schedule of dust control measures. The schedule shall include, but not be
necessarily limited to, descriptions of water spraying or water misting.

Dry cement or wet cement spillage procedures.

Procedures for water recycling. The hydraulic connections for water recycling
shall also be shown on the sediment control plan.

Revegetation schedule during, and on completion of, construction works

Monitoring schedule. This shall include, but not be necessarily limited to, a
programme for monitoring storm water discharge for pH and suspended
sediment.

Contact details for Contractors and relevant Genesis Staff

It is anticipated that many (or potentially all) of the concrete batching plants will be adjacent
to, or contained within a quarry. Where this is the case, then the environmental measures
taken in the quarry and concrete batching plant will be closely interlinked. In such
circumstances a QMP shall be prepared, and incorporate environmental measures for the
concrete batching plant.
Where a concrete batching plant is planned separate from a quarry, then a CBPMP shall
also be prepared.
An indicative sketch layout of the concrete batching plant is provided below.

  

   
         

 
 ) 

 
 ) 







  
  

   

    


  



   *




 ) 

 



  







    )






  
 
 

 

  

 
 

 
 

 

 
  

   

      

 
  

 
  











 

    !"#$


!" +,-!"!'(%"

  





   

  )

 


   
  

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix J: Baseline Aquatic Monitoring Plan (BAMP)


Purpose
To guide the collection of pre-construction information on water quality and aquatic
communities within the Castle Hill Wild Farm Site (CHWF) to ensure that standard
compliance can be adequately assessed during construction.
Objective
To provide the information needed for the development of compliance standards for water
quality and biological parameters to be included in the CHWF Construction Aquatic
Monitoring Plan (CAMP).
Proposed content

A review of Council surface water quality and biological parameter standards to


identify those relevant to construction of the CHWF (e.g. current (July 2011)
Horizons and Greater Wellington Regional Council water quality standards are
listed in Tables 1 and 2, below).

Determination of baseline monitoring required allowing assessment of


compliance with standards during construction. This may include a requirement
to collect information on flow rates or rainfall.

The selection of appropriate monitoring sites that are representative of the


receiving water and will allow compliance with standards to be assessed during
construction. This requires information on key construction locations (e.g.
access road routes, watercourse crossings, water intakes, turbine and
infrastructure locations, and spoil disposal sites) to enable sites to be chosen in
the most appropriate locations. Factors to consider in the selection of sites
include ease and safety of access, positioning in relation to Council defined
mixing zones downstream of discharges or instream works, and the inclusion of
unaffected upstream reference sites where possible. Consultation with the
relevant Council is recommended during this process.

A detailed method for the collection of any required baseline monitoring


information. Including the identification of suitably qualified personnel, a
timetable stating when sampling should begin and end and the timing and
frequency of sample collection, a list of parameters to be measured (e.g. pH,
temperature, dissolved oxygen, water clarity, QMCI, etc.), the method of
sample collection and processing to be used, and a format for the recording and
reporting of information.

The requirement for the preparation of a report to be provided to the relevant


Council stating what water quality and biological parameter standards will be
included in the Construction Aquatic Monitoring Plan (CAMP) for assessment

Draft Environmental Management Plan


Castle Hill Wind Farm

of compliance during construction and, where necessary, the baseline values


against which the standards are to be assessed.

Table 1 Horizons proposed One Plan water quality standards for Water Management Sub-zones
within the CHWF (Schedule D, One Plan).

Parameter

Upper Tiraumea

Owahanga

(Mana_7a)

(Owha_1)

The concentration of Escherichia coli


must not exceed 260 per 100
millilitres 1 November - 30 April
(inclusive) when the river flow is at
or below the 50th flow exceedance
percentile.

The concentration of Escherichia coli


must not exceed 260 per 100
millilitres 1 November - 30 April
(inclusive) when the river flow is at
or below the 50th flow exceedance
percentile.

The concentration of Escherichia coli


must not exceed 550 per 100
millilitres year round when the river
flow is at or below the 20th flow
exceedance percentile.

The concentration of Escherichia coli


must not exceed 550 per 100
millilitres year round when the river
flow is at or below the 20th flow
exceedance percentile.

The pH of the water must be within


the range 7 to 8.5 unless natural
levels are already outside this range

The pH of the water must be within


the range 7 to 8.5 unless natural
levels are already outside this range

The pH of the water must not be


changed by more than 0.5

The pH of the water must not be


changed by more than 0.5

The temperature of the water must


not exceed 23 degrees Celsius

The temperature of the water must


not exceed 22 degrees Celsius

Shall not be changed by more than 3

Shall not be changed by more than 3

Dissolved oxygen (%)

The concentration of dissolved


oxygen (DO) must exceed 70% of
saturation

The concentration of dissolved


oxygen (DO) must exceed 70% of
saturation

sCBOD5 (g/m3)

The monthly average five-days


filtered/soluble carbonaceous
biochemical oxygen demand
(sCBOD5) when the river flow is at
or below the 20th flow exceedance
percentile must not exceed 2 grams
per cubic metre

The monthly average five-days


filtered/soluble carbonaceous
biochemical oxygen demand
(sCBOD5) when the river flow is at
or below the 20th flow exceedance
percentile must not exceed 2 grams
per cubic metre

POM (g/m3)

The average concentration of


particulate organic matter when the
river flow is at or below the 50th
flow exceedance percentile must
not exceed 5 grams per cubic metre

The average concentration of


particulate organic matter when the
river flow is at or below the 50th
flow exceedance percentile must
not exceed 5 grams per cubic metre

Periphyton Chl a
(mg/m2)

Chl a less than or equal to 120


mg/m2

Chl a less than or equal to 200


mg/m2

E. coli / 100ml

pH

Temperature (oC)

Draft Environmental Management Plan


Castle Hill Wind Farm

Parameter

Upper Tiraumea

Owahanga

(Mana_7a)

(Owha_1)

The maximum cover of visible bed


by periphyton as filamentous algae
more than 2 cm long must not
exceed 30%

The maximum cover of visible bed


by periphyton as filamentous algae
more than 2 cm long must not
exceed 30%

The maximum cover of visible river


bed by periphyton as diatoms and
cyanobacteria more than 0.3cm
thick must not exceed 60%

The maximum cover of visible river


bed by periphyton as diatoms and
cyanobacteria more than 0.3cm
thick must not exceed 60%

DRP (g/m3)

The annual average concentration of


dissolved reactive phosphorus
(DRP) when the river flow is at or
below the 20th flow exceedance
percentile must not exceed 0.010
grams per cubic metre, unless
natural levels already exceed this
target.

The annual average concentration of


dissolved reactive phosphorus
(DRP) when the river flow is at or
below the 20th flow exceedance
percentile must not exceed 0.015
grams per cubic metre, unless
natural levels already exceed this
target.

SIN 5 (g/m3)

The annual average concentration of


soluble inorganic nitrogen (SIN)3
when the river flow is at or below
the 20th flow exceedance percentile
must not exceed 0.444 grams per
cubic metre, unless natural levels
already exceed this target.

The annual average concentration of


soluble inorganic nitrogen (SIN)3
when the river flow is at or below
the 20th flow exceedance percentile
must not exceed 0.167 grams per
cubic metre, unless natural levels
already exceed this target.

MCI 6

The macroinvertebrate community


index must exceed 100, unless
natural physical conditions are
beyond the scope of application of
the MCI. In cases where the river
habitat is suitable for the application
of the soft-bottomed variant of the
MCI (sb-MCI) the targets also apply.

The macroinvertebrate community


index must exceed 100, unless
natural physical conditions are
beyond the scope of application of
the MCI. In cases where the river
habitat is suitable for the application
of the soft-bottomed variant of the
MCI (sb-MCI) the targets also apply.

QMCI 7

There must be no more than a 20%


reduction in Quantitative
Macroinvertebrate Community Index
(QMCI) score between
appropriately matched habitats
upstream and downstream of
discharges to water

There must be no more than a 20%


reduction in Quantitative
Macroinvertebrate Community Index
(QMCI) score between
appropriately matched habitats
upstream and downstream of
discharges to water

Percentage cover

Soluble inorganic nitrogen (SIN) concentration is measured as the sum of nitrate nitrogen, nitrite nitrogen, and ammoniacal
nitrogen or the sum of total oxidised nitrogen and ammoniacal nitrogen.
6
The Macroinvertebrate Community Index (MCI) target applies only for State of the Environment monitoring purposes to
determine if the aquatic macroinvertebrate communities are adequate to provide for and maintain the values in each WMSZ.
This target is not appropriate for monitoring the effect of activities such as discharges to water on macroinvertebrate
communities upstream and downstream of the activity.

Draft Environmental Management Plan


Castle Hill Wind Farm

Parameter

Ammoniacal Nitrogen
(g/m3)

Toxicants

Visual clarity (m)

Upper Tiraumea

Owahanga

(Mana_7a)

(Owha_1)

The average concentration of


ammoniacal nitrogen must not
exceed 0.400 grams per cubic
metre. The maximum concentration
of ammoniacal nitrogen must not
exceed 2.1 grams per cubic metre.

The average concentration of


ammoniacal nitrogen must not
exceed 0.400 grams per cubic
metre. The maximum concentration
of ammoniacal nitrogen must not
exceed 2.1 grams per cubic metre.

For toxicants not otherwise defined


in these targets, the concentration
of toxicants in the water must not
exceed the trigger values for
freshwater defined in the 2000

For toxicants not otherwise defined


in these targets, the concentration
of toxicants in the water must not
exceed the trigger values for
freshwater defined in the 2000

ANZECC guidelines Table 3.4.1 for


the level of protection of 95% of
species. For metals the trigger value
must be adjusted for hardness and
apply to the dissolved fraction as
directed in the table.

ANZECC guidelines Table 3.4.1 for


the level of protection of 95% of
species. For metals the trigger value
must be adjusted for hardness and
apply to the dissolved fraction as
directed in the table.

The visual clarity of the water


measured as the horizontal sighting
range of a black disc must not be
reduced by more than 30%.

The visual clarity of the water


measured as the horizontal sighting
range of a black disc must not be
reduced by more than 30%.

The visual clarity of the water


measured as the horizontal sighting
range of a black disc must equal or
exceed 2 metres when the river is at
or below the 50th flow exceedance
percentile.

The visual clarity of the water


measured as the horizontal sighting
range of a black disc must equal or
exceed 1.6 metres when the river is
at or below the 50th flow
exceedance percentile.

This target is only relevant for measuring the percentage of change in Quantitative Macroinvertebrate Community Index
(QMCI) between appropriately matched habitats upstream and downstream of activities, such as discharges to water, for the
purposes of measuring the effect of discharges on aquatic macroinvertebrate communities. It is not an appropriate target for
the measurement of the general state of macroinvertebrate communities in each Water Management Sub-zone.
8
Ammoniacal nitrogen is a component of SIN. SIN target should also be considered when assessing ammoniacal nitrogen
concentrations against the targets.

Draft Environmental Management Plan


Castle Hill Wind Farm

Table 2 Greater Wellington Regional Council physico-chemical and microbiological variables and
guideline values (Milne and Perrie 2006 9 ).

Parameter

Guideline value

Reference

Temperature (oC)

<20

Dissolved oxygen (%)

80

RMA 1991 Third Schedule

pH

6.5-9.0

ANZECC (1992)

Conductivity (S /cm)

Visual clarity (m)

1.6

MfE (1994)

Turbidity (NTU)

5.6

ANZECC & ARMCANZ (2000)

Total organic carbon (mg/L)

Nitrite-Nitrate Nitrogen (mg/L)

0.444

ANZECC & ARMCANZ (2000)

Ammoniacal Nitrogen (mg/L)

0.021

ANZECC & ARMCANZ (2000)

Total Nitrogen (mg/L)

0.614

ANZECC & ARMCANZ (2000)

Dissolved Reactive Phosphorus (mg/L)

0.010

ANZECC & ARMCANZ (2000)

Total Phosphorus (mg/L)

0.033

ANZECC & ARMCANZ (2000)

Faecal coliforms (cfu/100mL)

0.100

ANZECC & ARMCANZ (2000)

Milne, J. and Perrie, A. 2006. Freshwater quality monitoring technical report. Greater Wellington Regional Council, February
2006.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix K: Construction Aquatic Monitoring Plan (CAMP)


Purpose
To guide the collection of information on water quality and aquatic communities within the
Site during construction of the CHWF and consequential reporting and contingency action.
Objectives
To provide the information needed to assess compliance with water quality and biological
parameter standards during construction of the CHWF.
Proposed Content

A detailed method for the collection of the information required to assess


compliance with relevant water quality and biological parameter standards in
relation to CHWF construction activities (based on the BAMP).

A requirement to assess compliance with standards during the construction


period (at timeframes appropriate to the standard being assessed), to identify
any instances of non-compliance, and determine if they are as a consequence
of construction activities (this may require additional monitoring).

A requirement that information on standard compliance monitoring is to be


provided to the relevant Council. Including a record of any instances when
monitoring was not possible and an explanation as to why.

A list of contingency measures that are to be implemented to achieve


compliance if non-compliance with the standards occurs that is attributable to
construction activities.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix L: Biodiversity Management Revegetation Plan


Purpose
To ensure rapid reinstatement of vegetation cover following completing earthworks.
Objectives
To ensure that vegetation cover (or another protective measure) is established within 3-6
months of completion of site works.
Proposed Content

Introduction.

Approaches to be used for:


o

Pasture

Indigenous revegetation

Steep cuttings

Methods: Direct sowing of seed, planting, hydroseeding, others.

Eco-sourcing of indigenous species/locally-sourced species that occur naturally


in the Eastern Wairarapa and Puketoi Ecological Districts, on similar landforms,
and at similar altitudes.

Planting guidelines, including timing, numbers and densities of species, infilling,


nurse crops, and species that require initial shelter.

Maintenance of plantings.

Implementation plan.

Stock exclusion.

Management of pest browsers.

Monitoring.

Contingency strategies.

Reporting.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix M: Biodiversity Management Weed Hygiene and


Surveillance Plan
Purpose
To ensure that weed management at the CHWF is undertaken to a high standard.
Objective
To avoid the establishment of new weeds at the Site and to avoid expansion of existing
weeds.
Proposed Content

Introduction.

Statutory framework (RPMS).

Cleaning of machinery.

Aggregate sources/management.

Weed monitoring programme.

Weed control programme.

Roles and responsibilities.

Reporting requirements.

Term of plan.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix N: Construction Noise Management Plan (CNMP)


Purpose
The purpose of this Construction Noise Management Plan (CNMP) is to describe the
means by which noise effects arising from the construction of the Castle Hill Wind Farm
(CHWF) will be avoided, mitigated or remedied, to describe the means of monitoring
compliance with noise conditions, and to describe a mechanism by which any noise
complaints related to Construction will be received and addressed.
The intended outcome is that the CHWF can be constructed without causing unreasonable
noise effects at dwellings surrounding the project.
Objectives
The objectives of this CNMP are as follows:

Describe the noise limits which apply to noise sensitive locations near the
project.

Describe the activities which will produce noise at dwellings, and describe the
likely noise levels and the durations and times for which this will occur

Describe noise mitigations which will be implemented to ensure that noise


received at dwellings is reasonable, and controlled to the lowest level
practicable.

Describe any limits on hours of operation or on particular activities which are


necessary to maintain appropriate protection of dwellings from noise.

Describe the method of monitoring noise levels to ensure that noise limits are
met.

Designate persons responsible for liaising with the community, both to inform
the community of construction activities and to receive and respond to any
complaints.

Describe a procedure for response to complaints.

Describe the responsibilities of contractors in complying with noise limits and


maintaining community goodwill throughout the construction period.

Draft Environmental Management Plan


Castle Hill Wind Farm

Proposed Content
Noise Limits
Limits which apply to this project are:
New Zealand Standard 6803:1999 Recommended Upper Limits (dBA) for Levels of
Construction Work Noise Received in Dwellings in Rural AreasLong Term Project
Duration
Period

Noise Level (dBA)


Weekdays

Sundays and Public


Holidays

Saturdays

Leq

Lmax

Leq

Lmax

Leq

Lmax

0630-0730

55

75

45

75

45

75

0730-1800

70

85

70

85

55

85

1800-2000

65

80

45

75

45

75

2000-0630

45

75

45

75

45

75

Noise Producing Activities

External Road upgrades


o

At dwellings near the xx Site Access point, upgrades to xx road will


produce noise levels of up to xx decibels for xx days while major
earthworks are undertaken, with ongoing roadworks will produce xx
decibels for approximately xx week

Quarrying

Construction of Internal Roads

Construction of Turbine Foundations and Platforms

Construction traffic noise on Internal Roads

Delivery of turbine components

Construction of substations

Construction of Internal Transmission Lines

Any others which may apply at particular stages of construction

Noise Mitigations (Examples)

Blasting (carried out in accordance with AS2187:Part 2) and rock breaking will
be completed during daylight hours only, and completed in as short a time as
practicable.

Draft Environmental Management Plan


Castle Hill Wind Farm

Works which occur within 50 metres of dwellings will be coordinated with


occupants to ensure special needs are met.

All machinery will be well maintained with appropriate engine silencers,


machinery tracks will be kept wet where practicable.

All personnel will be advised that unnecessary shouting or other noise which is
not required to maintain the safety of the site should be avoided in the vicinity of
dwellings.

Speed limits enforced etc.

Music will not be played outside of vehicles.

Others as necessary.

Restrictions on Activities

Construction works within xx metres of dwellings will be restricted to daytime


hours.

Others as necessary.

Monitoring Methods

Stationary activities such as concrete batching and material extraction shall be


measured within x days of the establishment of the infrastructure for these
activities and it shall be demonstrated to Councils that noise limits at dwellings
are met.

Transient activities such as road works will generally comply with construction
noise rules when carried out within the Site. However when such works are
carried out within xxx metres of dwellings, spot checks of sound levels shall be
taken to allow the community to be advised of likely noise impacts, and
appropriate mitigation options be discussed.

Liaison

Designate persons responsible for liaising with the community, both to inform
the community of construction activities and to receive and respond to any
complaints.

The Community Liaison Manager is [xxx] and can be contacted at all times
throughout the construction period on [02x-xxx-xxxx].

Communities will be informed of construction schedules and activities at least 3


months prior to commencement, and shall be informed by monthly letter drop
and community notice board etc of progress and any changes to the program.

Specific dwellings which may experience particular noise impacts will be


contacted directly, and noise mitigation options discussed.

Draft Environmental Management Plan


Castle Hill Wind Farm

Complaints Procedure

Any noise complaints may be directed to the Community Liaison Manager.

Complaints shall be responded to within 24 hours. The response shall include


an investigation of the noise produced at the time of the complaint, and if
compliance with consent conditions is uncertain, shall be accompanied by a
noise assessment to determine what, if any, additional mitigations should be
implemented.

The result of the noise assessment shall be reported back to the complainant
within xx hours of a determination of the response.

Responsibilities of Contractors

Contractors shall be required to comply with the Consent Conditions at all


times, and bear the primary responsibility for ensuring that noise limits are met
and noise is controlled to the lowest practicable level.

Noise mitigation measures (including methods, equipment, maintenance,


scheduling, practices, etc) shall be made part of the tendering process, and
shall form a part of the contractors performance requirements.

Contractors are also responsible for assisting Genesis Energy in maintaining


community goodwill throughout the project, and shall proactively endeavour to
ensure that the community is informed and respected throughout the
construction process.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix O: Construction Traffic Management Framework (CTMF)

GenesisEnergy
Castle Hill Wind Farm

ConstructionTrafficManagement
Framework

July 2011

PO Box1261, Level 6, 11 Garden Pl


Hamilton 3240
P: +64 78395500
www.tdg.co.nz
New Zealand
10311-8ta_version 8 review_v4 final.docx

GenesisEnergy
Castle Hill Wind Farm

ConstructionTrafficManagement
Framework
QualityAssuranceStatement

Prepared by:
Mark Apeldoorn

Director
Reviewed by:
Anna Wilkins
Principal Transportation Engineer
Approved for Issue by:
Mark Apeldoorn
Director
Status:

Final

Date:

July 2011

ctmp

TableofContents

1.

Introduction .............................................................................................................................1

2.

Purpose and Objectives ..........................................................................................................1

3.

CTMP Development Process..................................................................................................2

4.

CTMP Content ........................................................................................................................3

5.

6.

4.1

Consent Conditions ...................................................................................................3

4.2

Construction Programme...........................................................................................3

4.3

Traffic Flows ..............................................................................................................3

4.4

Road Safety Assessment ..........................................................................................3

4.5

Wind Farm Access Points .........................................................................................3

4.6

Travel Routes ............................................................................................................3

4.7

Road Closures, Events and Cyclic Activities .............................................................4

4.8

Travel Plan ................................................................................................................4

4.9

Driver Protocols .........................................................................................................4

4.10

Contractor Parking.....................................................................................................4

4.11

Oversize Loads..........................................................................................................4

4.12

Passenger Transport .................................................................................................5

4.13

Road Improvements ..................................................................................................5

4.14

Pavement Maintenance .............................................................................................6

4.15

Monitoring..................................................................................................................6

4.16

Incident Reporting .....................................................................................................6

4.17

Emergency Services..................................................................................................6

4.18

Contingency Planning................................................................................................6

4.19

Temporary Traffic Management Planning .................................................................7

4.20

Communication Protocols........................................................................................14

Specific Standards ................................................................................................................14


5.1

Traffic Flows ............................................................................................................14

5.2

Wind Farm Access Points .......................................................................................14

5.3

Travel Routes ..........................................................................................................15

5.4

Driver Protocols .......................................................................................................15

5.5

Oversize Transporters .............................................................................................15

5.6

Road Improvements ................................................................................................16

5.7

Monitoring................................................................................................................17

5.8

Incident Reporting ...................................................................................................17

5.9

Communications......................................................................................................18

Presentation..........................................................................................................................19

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

1.

Introduction

This document is the Construction Traffic Management Framework for the Castle Hill Wind Farm.
It has been prepared to set out the purpose, objectives and specific standards to be applied when
preparing the Construction Traffic Management Plan (CTMP) at the detailed design stage.
Some aspects of the construction methodology are to be fixed as specific standards in this
Framework which must be included in the CTMP under the conditions of the resource consent for
the CHWF. Other aspects, such as timing and staging (which influence traffic volumes), are to be
developed at the detailed design stage when contractors are involved. It is not practical to
prepare these details at this stage, and the approach of preparing the full CTMP at the detailed
design stage will enable contractors to bring innovation where appropriate, enabling a
substantially better outcome for other road users, the efficiency of construction, or both.
The CTMP is to be prepared by a Chartered Professional Engineer with specialist skills in Traffic
Engineering and Transportation Planning, appointed by the consent holder. Preparation of the
CTMP will involve input from the principal civil engineering contractor, the turbine transport
contractor, Tararua and Masterton District Councils, residents on the transport route who wish to
be involved, emergency services and local transport operators (such as the school bus operator
and livestock transporters). It will be required to meet the purpose, objectives, and specific
standards set out in this Framework. The Plan is to be submitted to the Councils to be assessed
and certified as meeting the requirements of the Framework.

2.

PurposeandObjectives

2.1

Purpose

The purpose of the CTMP is to set out in detail the manner in which construction traffic will be
managed to ensure the safe and efficient performance of the road network, to minimise adverse
effects on the existing community arising from construction traffic, and to provide the community
with information about Genesis Energys traffic arrangements.

2.2

Objectives

The objectives of the CTMP are to:


(i)

ensure the specific requirements of Acts, Regulations, Bylaws and consent


conditions in relation to construction traffic, are adhered to;

(ii)

encourage a culture of road safety awareness and commitment;

(iii)

ensure best practice in transport safety;

(iv)

ensure emergency services are not obstructed;

(v)

minimise disruption to the community, farming operations and rural services;

(vi)

minimise traffic generation; and

(vii)

encourage the participation of the community in maximising safety and minimising


disruption.

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

These objectives will be achieved by the methods set out in the CTMP.

3.

CTMPDevelopmentProcess

Preparation of the CTMP will be facilitated by a Chartered Professional Engineer, specialising in


Traffic Engineering and Transportation Planning, appointed by the consent holder.
Its
preparation is to begin approximately four months before construction.
In preparing a first draft CTMP, the Chartered Professional Engineer shall:
(i)

review this Construction Traffic Management Framework;

(ii)

review the CHWF Transportation Assessment and relevant evidence;

(iii)

review the approved consent conditions;

(iv)

liaise with the consent holder, the lead civil engineer, the principal civils
contractor, the turbine transport contractor, Tararua and Masterton District
Councils, residents on the transport route who wish to be involved, NZ Police, NZ
Fire Service, St Johns Ambulance, the school bus operator, rural transport
operators (identified by residents), and vets.

Liaison may involve such meetings and conversations as are appropriate to ensure effective
consultation with the parties listed above, and others considered appropriate by the Engineer.
The first draft will be circulated to the above parties for comments and suggestions. A period of
at least four weeks will be allowed for comments and suggestions. These will be evaluated by
the Chartered Professional Engineer and incorporated into the completed CTMP, as the Engineer
determines appropriate.
The completed CTMP will be submitted to the Tararua and Masterton District Councils at least
four weeks before construction of the CHWF begins along with a report outlining the comments
and suggestions made on the first draft, and the extent to which they have been included. The
Tararua and Masterton District Councils will assess the completed CTMP with a view to certifying
it as meeting the purpose, objectives, and specific standards set out in this Framework.
Any changes required to achieve that certification will be discussed between the Councils and the
Engineer and made, enabling the final CTMP to be distributed to:
(i)

the consulted parties;

(ii)

rural transport operators and rural service providers who regularly use the primary
access roads; and

(iii)

made available to residents and others who have an interest via electronic media.

Updates will likely be required from time to time as a result of project changes or issues arising,
which may be identified by the consent holder, its contractors, Tararua or Masterton District
Councils, or to address matters relating to residents or other road users. Suggested changes to
the CTMP or issues arising will be referred to the Chartered Professional Engineer who will
consider the matter and make a recommendation to the Tararua and Masterton District Councils.
If the Councils certify the recommended changes to the CTMP, revised copies will be made
available via digital media for the above referenced parties.

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

4.

CTMPContent

The CTMP is to include, as a minimum, the following content.

4.1

ConsentConditions

The CTMP shall record the full set of consent conditions relating to traffic and transportation
conditions in this section. The following specific actions and responses shall be developed
having regard for the consent condition requirements and the bases on which the Transportation
Effects Assessment has been made.

4.2

ConstructionProgramme

The CTMP is to present the confirmed construction programme, setting out the start and end
dates for the key traffic generating activities. From this, all parties will be able to understand the
type of activities that are occurring and therefore the types of vehicles to expect on the road
network.

4.3

TrafficFlows

Based on the programme and construction methodology, the CTMP will set out the expected
profile of average daily truck and light vehicle movements from month to month during
construction. It will also address the expected spread of traffic throughout the day, considering
the arrangements for transporting materials and people to the Site, including the geographic
spread of sources and accommodation.

4.4

RoadSafetyAssessment

An assessment of the road safety record as contained on the Land Transport New Zealand Crash
Analysis Database for the most recent five year period shall be provided, and commentary given
on any particular road safety matters that warrant consideration. Where relevant, this may be
taken from the Transportation Assessment Report and updated.
A visual assessment shall also be made of the Local Roading environment to determine the
nature of road safety. Any potential notable risk areas shall be identified and recorded in this
report along with the mitigation planning to be implemented.

4.5

WindFarmAccessPoints

The CTMP will provide details of the individual points where the Site will be accessed from the
public road network including how security will be managed.

4.6

TravelRoutes

The CTMP will map the travel route(s) to be used by construction vehicles and for oversize loads
travelling from the receiving Port.

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

4.7

RoadClosures,EventsandCyclicActivities

The CTMP shall be prepared in consultation with event organisers and Councils. It shall have
regard for but not be limited to considering the following:

4.8

(i)

car rally and/or cycling events;

(ii)

other activities and works within the road environment that may occur from time to
time;

(iii)

the movement of stock along or across the roadways;

(iv)

ram sales and mustering which typically occurs in November;

(v)

lamb sales which typically occur around February; and

(vi)

fertilising activities in autumn and spring. Of note in this regard is the Daggs Road
access to the airstrip, which appears to service up to about seven farms.

TravelPlan

A Travel Plan shall be developed to minimise contractor generated traffic and construction traffic
movements to and from the Site. This shall consider for example alternative travel modes, off-set
travel times, ride sharing and opportunities for back loading of construction vehicles.

4.9

DriverProtocols

In addition to the driving standards imposed by law, all drivers involved in the project will be
subject to additional protocols when travelling along the district roads. The objective of these
protocols will be to ensure the safe operation of roads and to minimise existing user delay during
construction.
The CTMP will set out these protocols along with the monitoring and disciplinary procedures to be
followed in the event of any breaches.

4.10

ContractorParking

Contractor parking is to be planned to be wholly accommodated On-Site and clear of the public
roads. The location, quantity and provision of parking is to be specified in the CTMP to
demonstrate the suitable provision and location of the activity.

4.11

OversizeLoads

The CTMP will address the movement of Over-weight and Over-dimension loads. While this
work will be undertaken by specialist contractors operating under permits specific to the project,
the details will be repeated in the CTMP to inform interested parties in understanding what to
expect.
This part of the CTMP is to include:

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

(i)

the over-size transport route(s);

(ii)

times and locations when movement is prohibited, and an indication of the times
of day when deliveries are anticipated;

(iii)

procedures for working around stock movements;

(iv)

operating restrictions for bridge crossings;

(v)

piloting procedures;

(vi)

contingency plans for breakdowns, bridge or pavement failures, severe weather


conditions, accidents, or roadworks;

(vii)

provisions for co-ordination with other parties, including emergency services; and

(viii) provisions for communication with school bus drivers.


Copies of the permits themselves are to be appended to the CTMP.

4.12

PassengerTransport

Specific management plans shall be prepared to show the planning provisions for reliable travel
time, movement and operation of passenger transport, including stopping areas.
This is to include scheduled passenger services, scheduled community or health services (the
Local or Regional Councils may be able to advise contacts or provisions in this regard) and any
school services that have the potential to be affected.

4.13

RoadImprovements

An appropriately detailed schedule describing the road improvement works and the temporary
traffic management provisions to be put in place will be separately submitted to Council for
approval under the Local Government Act. This schedule will include road improvements to
facilitate movement of oversize loads, pavement upgrades, pavement maintenance obligations,
and the provision of traffic management facilities at regularly used stock crossings along the
transport route.
A summary of those plans will be contained in the CTMP, including:
(i)

the physical extent and nature of the works;

(ii)

a schedule of start and finish dates;

(iii)

details for sourcing materials and disposal of spoil;

(iv)

provisions for advisory signage;

(v)

arrangements for temporary traffic management and supervision; and

(vi)

contact telephone numbers.

Depending on the timing of these works, this component of the CTMP may be prepared and
circulated in advance of the rest.

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

4.14

PavementMaintenance

The CTMP will summarise the key aspects of regular pavement maintenance on roads identified
in the resource consent, including:
(i)

service contract arrangements

(ii)

triggers for intervention (eg: size of pothole);

(iii)

intervention treatments (including materials specifications); and

(iv)

response times.

The CTMP will also include requirements for monitoring the oversize vehicle route from SH2 to
the Site, during the turbine component delivery phase, to ensure any road damage is identified
and repaired.

4.15

Monitoring

The CTMP will provide a detailed schedule of the various elements of monitoring relating to public
roads and transport.
The schedule will also include the specific data to be measured, the method of monitoring, the
frequency with which monitoring will be undertaken, triggers for intervention, and the
corresponding response.

4.16

IncidentReporting

The CTMP will set out requirements and procedures for incident reporting.

4.17

EmergencyServices

The plan shall set out emergency service planning provisions including those related to:

4.18

(i)

Site access and operations;

(ii)

local environment servicing and access;

(iii)

strategic network continuity; and

(iv)

communications provisions.

ContingencyPlanning

The provisioning for contingency shall be set out. It shall outline key risk areas, such as traffic
congestion, potential for storm damage in construction zones, vehicle crash instances (and
others) and describe what management / communication and planning provisions are to be
established to avoid / minimise or mitigate potential adverse situations.

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

4.19

TemporaryTrafficManagementPlanning

The planning requirements set out in COPTTM and provided for within the following pro-forma sheets
shall be completed.

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

Traffic
Management Plan
Reference

For Office Use Only


Contractor

Client

Organisation
RCA Consent Reference

N/A

Contract
Name/Number

Road Name(s)
Location

Road Level

Speed
Limit

From - To RP

Description of
Activity

Work Programme

Proposed/
Restricted Work
Hours
AADT

Traffic Details
(Main Route)

Peak Hour Flow

Active:

Proposed Traffic
Management
Method

General Procedures

Unattended:

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

Traffic
Management Plan
Reference

For Office Use Only


Night:

Proposed Speed
Restrictions

Lane Restrictions

Restricted Speed

Positive Traffic
Management
Measures

Minimum Lane Width

Delineation

Pedestrians

Cyclists

Contingency Plans

Public Notification

Personal Safety

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

10

Traffic
Management Plan
Reference

For Office Use Only

On-Site Monitoring

Other Information
(eg. delay calcs, EED
issues, temporary speed
issues, etc)

Layout Diagrams

EED Applicable?

Y/N - YES
Name (STMS)

Attached Y/N
Phone (24 hours)

Traffic Controllers
Name (TC)

Phone (24 hours)

Cert No:
TMP prepared
accurately to
represent Site
conditions and
submitted by

Contractor/Applicant

Date

Cert No:
Engineer

Date

Requires
Amendment
Cert No:

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

11

Traffic
Management Plan
Reference
1.
2.

For Office Use Only


This TMP is Approved on the Following Basis

To the best of the approving Engineers judgment this TMP conforms to the requirements of Transit New Zealands
Code of Practice for Temporary Traffic Management.
This plan is approved on the basis that the activity, the location and the road environment have been correctly
represented by the applicant.Any inaccuracy in the portrayal of this information is the responsibility of the applicant.
The STMS for the activity is reminded that it is the STMSs duty to Postpone, cancel or modify operations due to the
adverse traffic, weather or other conditions that affect the safety of this Site (reference A4.5).

Approving Engineer:

...........................................................................................................................................................
(Name and Certificate Number)

...........................................................................................................................................................
(Signature)

Acceptance by:

TMC:

.................................................................

Cert No:

.................................................................

Signature:

.................................................................

Date:

..............................................

.................................................................................................................................. (Signature)
Acceptance by:

.........................................................................................................................................(Name)
........................................................................................................................................... (Title)
...........................................................................................................................................(Date)

...................................................................................................................................(Signature)
Acceptance by:

.........................................................................................................................................(Name)
........................................................................................................................................... (Title)
...........................................................................................................................................(Date)

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

12

Traffic
Management Plan
Reference

For Office Use Only

...................................................................................................................................(Signature)
Acceptance by:
Applicant

.........................................................................................................................................(Name)
........................................................................................................................................... (Title)
...........................................................................................................................................(Date)

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

13

4.19.1

TemporarySpeedRestrictions

Application for temporary speed restrictions shall be made on the following form (also included in
COPTTM).
APPLICATION FOR TEMPORARY SPEED RESTRICTION
Pursuant to Section 23(1) of the Traffic Regulations .

Sought by (Contractor)

For (Client)

Contract No. (if appropriate)

Road Name / State Highway

Situated at

From Route Position

From the date of

To the date of

Between the hours of:

Approval granted by:

Name:
Position:
Signature: .
Date:

Special Conditions to apply:


..
..
..
..
..

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

14

4.19.2

COPTTMVariations

Variations from the provisions within COPTTM (and the Local Authority supplement) shall be
made in accordance with the relevant COPTTM provisions and necessary approvals from the
relevant Territorial Authority.

4.19.3

EngineeringExceptionDecisions

Application for an Engineering Exception Decision, as provided for within COPTTM shall be made
on the pro-forma form within COPTTM.

4.20

CommunicationProtocols

Communication protocols are important to the success of the CTMP. Primary contact details will
be clearly recorded as the point of contact for road users.
Specific contact arrangements will be made for farmers to advise the project team of planned
stock movements. These will then be communicated to project drivers enabling them to avoid
that time or otherwise modify their travel as appropriate.
Finally, the CTMP will record a list of people and organisations that the CTMP will be distributed
to. All amendments and updates to the CTMP, as approved by the Councils, will then be made
accessible to those named on the list.

5.

SpecificStandards

A number of specific standards have been identified as necessary components of construction


traffic management and are therefore mandatory standards to be included in the CTMP. They
are:

5.1

TrafficFlows
(i)

5.2

contractor vehicle movements to and from the Site shall be minimised by adopting
shared travel, return waste carriage, and other vehicle number minimisation
techniques.

WindFarmAccessPoints
(i)

the primary Wind Farm Access points shall be located and constructed as
described in the application or as otherwise approved;

(ii)

all CHWF construction traffic must use the primary access points, with the
exception of:
-

(iii)

specific exception sites to be listed once confirmed

other Site access transport conditions of consent to be identified here once


established.

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

15

5.3

TravelRoutes
(i)

5.4

All conditions of consent relating to the management and control of travel on the
defined routes are to be recorded here.

DriverProtocols
(i)

drivers travelling to or from the Site must do so safely, in full compliance with the
law, including in respect of speed limits, following distances, forward sight when
overtaking, being able to stop within the length of road visible (or half the length
on roads without centrelines), and not driving carelessly or dangerously;

(ii)

drivers with CB radios must radio in to the gatehouse when leaving the nearest
town for traffic updates or notifications;

(iii)

when aware of any emergency vehicles (including vets responding to emergency


calls), approaching from in front or behind, drivers must pull over well in advance
to provide unimpeded movement;

(iv)

drivers must reduce their speed to 20km/h when passing a school bus which is
slowing down, stopped, or accelerating in relation to picking up or setting down
children;

(v)

drivers must reduce their speed to a maximum of 30km/h when:


-

passing children walking, cycling or waiting on the side of the road

passing an oncoming school bus (which isnt slowing down, stopped or


accelerating such that the 20km/h limit applies)

passing someone riding or leading a horse along the road

approaching a stock crossing with the amber flashing light operating

approaching an area where a stock shift is known to be occurring

(vi)

truck drivers must not use engine brakes (particularly Jacobs Brakes) on define
relevant sections of road here, except where the load being carried and the grade
of the road make use of such braking absolutely necessary for safe driving.

(vii)

truck drivers travelling on school bus routes at the same time as an oncoming
school bus must use their CB radio to identify the location of the bus and pull over
in a safe location before the school bus reaches and passes them;

(viii) truck drivers must let traffic behind them pass at regular locations including those
opportunities that occur at intersections, wide driveways, sections of road with
adequate forward sight distance, gravel pits etc;
(ix)

5.5

disciplinary procedures shall include consideration of a requirement that a vehicle


tracking system (with driver behaviour functionality) be installed in the vehicle of
any project driver who is the subject of a credible complaint or identified breach of
the road rules or Construction Traffic Management Plan. Any subsequent
breaches identified by the system shall result in disciplinary action.

OversizeTransporters
(i)

the arrangements for the delivery of overweight and Over-dimensioned loads and
turbine components to the Site should avoid peak periods of traffic on the network

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

16

and minimise as far as practicable disruption and disturbance to the residents.


This shall include:
-

5.6

list travel time restrictions here

(ii)

overweight and Over-dimension load permits for turbine components shall be


appended to the CTMP;

(iii)

pilots shall be in radio contact with other trucks to ensure passing occurs at safe
and convenient locations;

(iv)

in the event of a breakdown, accident or road failure, the transporter crew shall do
the following:
-

park the pilot vehicles in locations where they maximise safety, considering
overhanging components, and blind bends on approaches

contact emergency services (including Police) in the case of an accident;

contact the project manager

contact the road controlling authority (Tararua District Council, Masterton


District Council or NZ Transport Agency)

contact the security gate to advise all other project traffic, and local traffic via
CB radio

follow all instructions from Police and the road controlling authority

in the case of an accident, the vehicles involved should not be moved until
instructed by Police.

RoadImprovements
(i)

List the road improvement and maintenance requirements here from the
conditions of consent;

(ii)

any damage to the roads on the oversize vehicle route between SH2 and the Site
caused by oversize vehicles travelling to the Site shall be repaired by the Consent
Holder, with intervention triggers, response modes and response times as set out
in the relevant Tararua and Masterton District Council road maintenance
contracts;

(iii)

close liaison shall occur with Tararua and Masterton District Council engineers in
designing and planning Local Road improvements to maximise the benefit to the
district road network;

(iv)

the management of traffic at road improvement sites shall be in accordance with


the NZTA Code of Practice for Temporary Traffic Management, including the
Local Roads Supplement;

(v)

subject to the approval of individual farmers, the Consent Holder shall supply and
install remotely operated flashing amber lights at regularly used stock crossings
on the roads defined for maintenance in the conditions of consent. The Consent
Holder shall not be responsible for the operation of the lights, but shall be required
to maintain them for the duration of the construction project;

(vi)

signs shall be erected advising all drivers of a channel for CB communication in


the area east of Alfredton;

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

17

(vii)

5.7

subject to monitoring, additional pull over bays may be constructed where


required on the turbine component transport route to facilitate passing.

Monitoring

Monitoring of public roads and traffic management is to be undertaken as indicated in Table 1.

MONITORING

FREQUENCY

REPORTING

Traffic movements through Wind Farm


Access Points, including date, time,
driver,
vehicle
type,
number
of
passengers, Wind Farm Access Point
used

Continuously

Monthly, to Tararua and Masterton District


Councils

Safety and effectiveness of temporary


traffic management at public road
improvement sites

Daily when working

Weekly, to Project Manager

Safety and effectiveness of temporary


traffic management at public road
improvement sites and management of
construction traffic as a whole

Weekly

Monthly, to Tararua and Masterton District


Councils

Condition of Waitahora Valley Road


between Waitahora Road and Site,
including checks for ruts, pot holes,
flushing and bleeding, and the condition
of the whole oversize vehicle route
between SH2 and the Site during the
turbine component delivery phase

Weekly

Monthly, to Tararua and Masterton District


Councils

Safety and effectiveness of oversize load


piloting procedures

Once, at start of turbine


delivery

Within a week to Project Manager, NZTA


and Tararua and Masterton District Councils

Structural condition of bridges

As
required
by
overweight load permits

As required by permits, to NZTA and


Tararua and Masterton District Councils

Register of incidents
comments/complaints
Serious
incidents,
involving any injuries

and

public

Continuously

Weekly, to Tararua and Masterton District


Councils

including

those

As they arise

Immediately to Project Manager and


Tararua and Masterton District Councils

Table 1: Public Road and Traffic Management Monitoring

5.8

IncidentReporting
(i)

road incidents must be reported, including:


-

any road crashes, including damage only;

any near misses, which includes occurrences where evasive action was
required by one or more parties and/or where heavy braking was required;
and

any breakdowns or similar requiring a recovery vehicle;

(ii)

incidents shall be recorded in the register along with all comments and feedback
received from the public;

(iii)

serious incidents, including those involving any injuries, must be reported


immediately to the project manager and Tararua and Masterton District Councils;

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

18

(iv)

5.9

the register shall be reviewed weekly by the project manager and any corrective
actions recorded. The register shall then be forwarded to Tararua and Masterton
District Councils weekly.

Communications
(i)

the Consent Holder shall ensure the relevant provisions of the CTMP and road
safety issues are included in the Site induction and regular toolbox talks;

(ii)

subject to the approval of school bus service operators and individual residents,
the Consent Holder shall supply and install CB radios for school buses on roads
subject to a maintenance or traffic management control due to the CHWF, to
enable communication with construction traffic and the gate house;

(iii)

a freephone number shall be established for public enquiries relating to any


aspect of the project including comments on driver behaviour;

(iv)

vehicles which are committed to the CHWF construction project shall have the
freephone number displayed, along with a vehicle identification number for use in
any public feedback regarding driver behaviour;

(v)

the freephone number shall also be available to be used:


-

to note any issues relating to temporary traffic management at public road


improvement sites, oversize vehicle movement, or construction traffic
management in general;

to notify the project team of any planned stock movements along or across
Waitahora Road or Waitahora Valley Road; and

to notify the project team of any events or activities around which construction
traffic should be arranged

(vi)

where information is to be relayed back to project drivers, it shall be done by


notifying the security guard at the gate house (Siteaccess point), who will in turn
advise drivers when they radio in from the town departure, or when they drive out
of the Site;

(vii)

copies of the CTMP shall be provided to at least the following:


-

consents manager, Tararua and Masterton District Councils;

roading manager, Tararua and Masterton District Councils;

regional state highways manager, NZ Transport Agency;

NZ Police;

NZ Fire Service ;

St Johns Ambulance;

Alfredton primary school;

List other identified schools here;

List VET Services here;

List commercial carriers here;

Rural Fuel;

Allied Petroleum;

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

19

BP;

Transport Officer, School Support Ltd, Napier;

Castle HillCHWF Community Liaison Group; and

shall be made available on a digital media site for general access.

(viii) any updates to the plan, as approved by Tararua and Masterton District Councils,
shall be provided to the above.

6.

Presentation

The CTMP is to be well presented in a format that clearly and efficiently conveys the information
to the range of recipients included on the distribution list.
If appropriate, a summary shall also be prepared for wider distribution.

Traffic Design Group Ltd


July 2011

Genesis Energy, Castle Hill Wind Farm: Construction Traffic Management Framework
ctmp

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix P: Draft Archaeological Accidental Discovery Protocol


The overarching approach to Accidental Discovery of Archaeology is outlined below:
1. Genesis Energy will, in consultation with Rangitane o Tamaki Nui a Rua, Rangitane o
Wairarapa, Ngati Kahungunu ki Wairarapa and Kahungunu ki Tamaki Nui A Rua
prepare an Accidental Discovery Protocol prior to the commencement of any
earthworks activities for the wind farm. The protocol shall be in place for any
earthmoving or ground modification that occurs during the construction and
operation of the wind farm. The protocol shall clearly set out the steps to be taken
(in accordance with 2), including any site walkovers, inspections or ceremonies that
may be carried out by representatives of Rangitane o Tamaki Nui a Rua, Rangit ne o
Wairarapa, Ngati Kahungunu ki Wairarapa and Kahungunu ki Tamaki Nui A Rua prior
to any works authorised by this consent commencing, or in the event of any
archaeological sites, taonga (treasured or prized possessions, including Maori
artefacts) or koiwi (human remains) being discovered at any time.
2. If any archaeological site, taonga or koiwi is discovered during the works authorised
by this consent, Genesis Energy shall immediately cease work at the affected site.
Genesis Energy shall notify Rangitane o Tamaki Nui a Rua, Rangitane o Wairarapa,
Ngati Kahungunu ki Wairarapa and Kahungunu ki Tamaki Nui A Rua the Historic
Places Trust, and in the case of koiwi, the Police, and shall not recommence works
in the area of the discovery until the relevant Historic Places Trust and Rangitane o
Tamaki Nui a Rua, Rangitane o Wairarapa, Ngati Kahungunu ki Wairarapa and
Kahungunu ki Tamaki Nui A Rua approvals to damage, destroy or modify such sites
have been obtained, and Tararua District Council and Masterton District Council (in
consultation with Manawatu-Wanganui Regional Council and Greater Wellington
Regional Council) has given authorisation to recommence the activities.
A draft outline of the protocol is set out as follows:

Evidence of archaeological sites can include oven stones, charcoal, shell


middens, ditches, banks, pits, and old building foundations, artefacts of Maori
and European origin or human burials.

Is any archaeological site(s) are uncovered during physical works, Genesis


Energy will require the Contractor to adopt the following protocol.

Work shall cease immediately at that place (the affected area)

The contractor must shut down all machinery, secure the Site and advise
Genesis Energy.

Genesis Energy shall advise the project archaeologist, Historic Places Trust,
relevant iwi authorities, Tararua District Council, Masterton District Council,
Manawatu-Wanganui Regional Council and Greater Wellington Regional
Council.

Draft Environmental Management Plan


Castle Hill Wind Farm

If skeletal remains are uncovered, the Genesis Energy will also advise the
Police.

A site inspection will be undertaken with relevant iwi authorities.

Materials discovered will removed by relevant iwi authorities responsible for the
tikanga appropriate to their removal and preservation, or re-interment.

Works affecting the site shall not resume until the NZ Historic Places Trust, the
Police, (if skeletal remains are involved) and Iwi Authority representatives have
each given the appropriate approval for work to continue.

Contact details are included in Table X.


Table [X]: Organisation Contact Details
Organisation and Representative

Contact Details

Genesis Energy Project Manager


Project Archaeologist
Historic Places Trust
Rangitane o Tamaki Nui a Rua
Rangitne o Wairarapa
Ngati Kahungunu ki Wairarapa
Kahungunu ki Tamaki Nui A Rua
Tararua District Council
Masterton District Council
Manawatu-Wanganui Regional Council
Greater Wellington Regional Council.

Training Procedures for All Contractors


All people (main contractors staff, sub-contractors, Genesis Energy staff and technical
advisors, and Council staff) working on the Site will be required to go through a Site
induction process, which will include training on the accidental discovery of cultural or
archaeological sites or material.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix Q: Biodiversity Management Habitat Management Plan(s)


Purpose
To guide the permanent protection and ongoing improvement of an area of approximately
210 ha of early successional indigenous vegetation in a staged manner.
Objectives
To achieve ongoing successional development of an area of indigenous vegetation set aside
as mitigation for vegetation clearance as a result of development of the CHWF (to be
subject to permanent legal protection).
Proposed Content

Introduction.

Objectives.

Site(s) to be protected.

Legal protection mechanism(s).

Fencing: Construction, monitoring, maintenance.

Pest Animal Control: Species to be controlled, control targets, monitoring,


reporting requirements.

Pest Plant Control: Species to be controlled, control targets, monitoring,


reporting requirements.

Enrichment Planting: Species, maintenance, monitoring.

Vegetation Monitoring: Walk-through inspections, vegetation RECCE plots.

Contingency strategies.

Reporting requirements.

Other relevant matters.

Term of plan.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix R: Biodiversity Management Riparian Protection Plan


Purpose
To guide the physical protection of stream riparian margins required to minimise aquatic
effects.
Objectives
To ensure that implementation of riparian protection is achieved in a staged fashion as the
wind farm is constructed.
Proposed Content

Introduction.

Priority catchments for riparian protection.

Criteria for selection of riparian protection sites.

Standards for riparian fencing, including minimum riparian buffers.

Minimum lengths of stream to be protected.

Reporting requirements.

Term of plan.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix S: Biodiversity Management Goat Control Plan


Purpose
To provide coordinated management of feral goats across all properties associated with the
CHWF.
Objectives
To reduce feral goats to very low levels within five years, with an overall objective of
eradication.
Proposed Content

Introduction.

Scale of problem.

Strategic approach.

Hunting programme.

Monitoring.

Roles and responsibilities.

Reporting requirements.

Term of plan.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix T: Biodiversity Management Avifauna Monitoring Plan


Purpose
To provide and implement a technically rigorous monitoring programme for birds at the
CHWF site.
Objective
To assess potential collision effects resulting from construction and operation of the CHWF.
Proposed Content

Introduction.

Methods.

Pre-construction monitoring:

Flight paths;

Five-minute bird counts.

Post-construction monitoring:
o

Flight paths.

Five-minute bird counts.

Carcass searches (discuss the use of search dogs).

Searcher efficiency checks.

Bird removal trials


decomposition).

Protocols for dealing with injured birds (including contacts).

Protocols for dealing with threatened or banded birds (including


contacts).

(checking

on

rate

of

scavenging

and

New Zealand Falcon.


o

Protocols for dealing with nests found during construction.

Peer review process.

Contingency strategies (to be triggered if targets and/or timelines are not


achieved).

Reporting.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix U: Biodiversity Management Bat Monitoring Plan


Purpose
To provide and implement a technically rigorous monitoring programme for bats at the
CHWF site.
Objective
To assess potential collision effects resulting from construction and operation of the CHWF,
and manage construction activities near identified bat roosts.
Proposed Content

Introduction.

Methods.

Protocols for dealing with any bat roosts discovered.

During construction.

During post-construction monitoring, such as implementing targeted


predator control.

Carcass searches (if search dogs are used for avifauna monitoring then it may
be possible to locate bat carcasses)
o

Protocols for dealing with injured or deceased bats (including


contacts).

Automatic batbox deployment in lower Pati Tapu Bush (suggest annual for first
3 years during Dactylanthus flowering, and then every 2 years for next 3
occasions and then 5 yearly thereafter for duration of windfarm operation the
detection rate would give an indication as to how the bat population is
changing).

Peer review process.

Contingency strategies.

Reporting.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix V: Biodiversity Management Lizard Monitoring Plan


Purpose
To ensure that development of the CHWF minimises effects on lizards.
Objectives
To minimise construction effects by identifying and manage lizards and lizard habitats.
Proposed Content

Introduction.

Methods.

Protocols.
o

Pre-construction searches of likely sites

Lizards found during construction.

Handling permits.

Translocation protocols.

Reporting.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix W: Biodiversity Management Predator Control Plan


Purpose
To undertake intensive predator control to enhance the prevalence and success of forest
bird species.
Objectives
To achieve intensive predator control over specific high value areas of indigenous forest
over the life of the CHWF.
Proposed Content

Introduction.

Species to be controlled.

Monitoring.

Target levels for species to be controlled.

Bird counts (annual for first three years then two yearly for next three
occasions)

Contingency strategies.

Reporting.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix X: Biodiversity Management Vegetation Management Plan


Purpose
To guide the implementation of vegetation clearance or trimming required to maintain
transmission line clearances or for wind flows (one turbine only).
Objectives
To minimise clearance requirements and adverse effects for indigenous vegetation.
Proposed Content

Introduction.

Sites to be affected.

Objectives.

Transmission lines - approach to be used.

Clearance for wind flows (potentially one site only) - approach to be applied.

Reporting.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix Y: Operational Noise Management Plan (ONMP)


Purpose
The purpose of this Operational Noise Management Plan (ONMP) is to describe the means
by which noise effects arising from the operation of the Castle Hill Wind Farm (CHWF) will
be avoided, mitigated or remedied, to describe the means of monitoring compliance with
noise conditions, and to describe a mechanism by which any noise complaints related to
Operation will be received and addressed.
Objectives
The objectives of this ONMP are as follows:

Describe the noise limits which apply to noise sensitive locations near the Wind
Farm.

Describe the activities which will produce noise at dwellings, and describe the
likely noise levels times for which this will occur.

Describe the method of monitoring noise levels to ensure that noise limits are
met.

Designate persons responsible for liaising with the community, both to inform
the community of operational activities and to receive and respond to any
complaints.

Describe a procedure for response to complaints.

Describe the responsibilities of the Wind Farm operator in reporting to the TDC
and MDC.

Proposed Content
Noise Limits
The noise limits which apply to this Wind Farm are described in detail in the Final
Operational Noise Assessment Report (FONAR). In general the limit on noise from wind
turbines is 40 dB LA95 at the notional boundary of dwellings, although at x specific
locations this limit rises with increase wind speeds as discussed in the FONAR.
Noise from vehicles on Site and fixed plant including substations and etc are those
described in the Conditions of Consent, which relate to the permitted activity noise limits in
the District Plans.
Noise Producing Activities
Wind Turbines

Draft Environmental Management Plan


Castle Hill Wind Farm

Noise is produced by wind turbines when they operate, with noise output level depending
on wind speed. The wind turbines used in the CHWF are xxx model yyy which produce a
peak noise output of xx dB Lw. The turbine operate in the wind speed range of xx and yy.
The operational mode of the turbines are xx during condition A and yy during condition B.
Substations
On-site Vehicles
Maintenance Facility Activities
Others as Applicable
Noise Monitoring
Noise monitoring for compliance testing purposes shall be carried out within xx months of
the completion of the Wind Farm, [or of each stage of the wind farm details to be
determined]. All noise monitoring shall be carried out in accordance with the relevant
clauses of NZS6808:2010, and compliance testing shall be reported in accordance with the
requirements of that standard.
Liaison
Ongoing communication between the Council and the Community and Genesis Energy
forms a useful part of the management of noise effects and provides input into any future
review of consent conditions.
Complaint history shall be maintained by TDC and MDC and made available for
consideration upon request.
A 6-monthly newsletter shall be placed in the local newspaper by Genesis Energy during the
first two years of operation. The newsletter shall include updates on the development and
operation of the wind farm, results of compliance testing, and shall provide contact details
for the Community to communicate with Genesis Energy.
Complaints Procedure
Any noise complaints may be directed to the Community Liaison Manager.
Complaints shall be responded to within 24 hours. The response shall include an
investigation of the noise produced at the time of the complaint, and if compliance with
consent conditions is uncertain, shall be accompanied by a noise assessment to determine
what, if any, additional mitigations should be implemented.
The result of the noise assessment shall be reported back to the complainant within xx
hours of a determination of the response.

Draft Environmental Management Plan


Castle Hill Wind Farm

Procedures for Investigation of Complaints


Prior to the receipt of Compliance Testing Report
Complaints may be received in the first months of operation of the Wind Farm, prior to the
completion and reporting of compliance testing. These complaints may be relevant to
compliance testing, and Genesis Energy shall direct its noise consultant to have regard for
these complaints and the conditions in which they arise in the compliance assessment.
Within three working days of receipt of such a complaint Genesis Energy shall provide a
written or emailed response to MDC and TDC advising that this information has been
provided to its noise consultant, and an estimate of the date of completion of the
Compliance Testing Report, or any other relevant information about the status of
compliance testing.
The Compliance Testing Report when submitted to the Councils shall include a section
discussing complaints received, and describing the actions taken to incorporate these
complaints into the assessment methodology.
Following the receipt of Compliance Testing Report (demonstrating compliance)
Complaints received after the Wind Farm has been demonstrated to be compliant with
Consent Conditions may arise from one of two causes:
1. Operational conditions exist which were not considered in the assessment of
compliance. This may include a change in noise emissions due to wear or failure of
turbine components, or meteorological conditions which were not foreseen, or
some other change to the wind farm.
2. Resident satisfaction is not addressed by confirmation of compliance with consent
conditions.
On receipt of a complaint it may not be possible for the Council to determine which of these
two categories the complaint falls into. When each complaint is passed to Genesis Energy,
its first response shall be to report the wind direction, wind speed, and number of
operational turbines at the time of the complaint to the Council, and to provide a statement
as to whether this set of conditions has been demonstrated to be compliant.
Where conditions arise which have not been considered in the Compliance Testing Report,
a suitably qualified and experienced person shall be engaged to assess compliance under
these conditions. The results of this assessment shall be provided to TDC and MDC. If noncompliance is demonstrated, remedial steps shall be undertaken as described in the
following section. If compliance is demonstrated, then this condition shall not be required to
trigger such an investigation following future complaints under similar conditions.

Draft Environmental Management Plan


Castle Hill Wind Farm

If a number of complaints are received during a specific period under a condition which has
previously been shown to comply, the Council may request Genesis Energy to provide
evidence (for instance by comparing sound levels near the turbines to those levels
produced during compliance testing) that the wind farm noise output has not increased after
compliance testing was carried out.
If a significant increase is demonstrated under the wind conditions in question, the Council
may request that compliance testing be repeated for that wind condition. If the sound level
has not increased by more than 2 dB, then the relevant complaints may be considered to
belong to category 2 above. In this latter case the complainants shall be informed that the
wind farm has been deemed to be operating within its consent conditions, but that the
complaints have been permanently logged and will form part of the complaints record.
Following receipt by Councils of the required description of operational conditions and
intended actions by Genesis Energy (including a timeframe for these actions), a written
response shall be provided to each complainant describing this action. This response shall
be provided within one week of the complaint. It is acknowledged that if the noise event is
caused by unusual meteorological conditions, the timeframe for assessment of that
condition may be dependent upon these conditions re-occurring.
Remediation Measures
Should non-compliance be demonstrated, the operation of the wind farm shall be ceased or
modified until modifications are made to reduce noise. These modifications may include
modifications to turbines, cessation or modification of operation of certain turbines during
certain wind conditions, or improvements to sound insulation at affected properties, or
other treatments.
Resumption of operation shall be subject to the demonstration of compliance. Prior to the
re-commencement of operation, a report shall be provided by Genesis Energy to
TDC/MDC describing the remedial steps taken and demonstration of compliance.
This information shall be reported to the complainant(s) who were affected by the original
noise event.

Draft Environmental Management Plan


Castle Hill Wind Farm

Appendix Z: Spill Response Plan (SRP)


Purpose
To manage any spills of hazardous substances during construction of the CHWF.
Objectives
To provide the information needed to be prepared for, respond to and clean up any spills of
hazardous substances during construction of the CHWF.
Proposed Contents

A list of hazardous substances (and associated quantities) that will be stored or


transported as part of construction of the CHWF.

MSDS sheets for the substances.

Plan(s) showing storage locations and location of spill kits.

Plan(s) showing potentially sensitive receiving environments on-site (e.g.


waterways).

Level 3 Emergency Response Plans (ERP) in compliance with HSNO


(emergency management) regulations 2001 for any On-site bulk storage of
substances that exceed HSNO (quantity) thresholds. Any ERP required for the
site would be prepared in accordance with the ERMA/Department of Labour
Approved Emergency Procedures and would comply with the requirements of
HSNO (emergency management) regulations 2001 as well as the Responsible
Care NZ Draft Code of Practice for Preparing for Chemical Emergencies.

Substance-specific spill response plans (SRP) for small and medium scale spills
(refer to attached examples for small scale diesel/oil spill and medium scale
concrete spill).

Spill event reporting/notification requirements.

Draft Environmental Management Plan


Castle Hill Wind Farm

SPILL RESPONSE PLAN SMALL DIESEL/OIL SPILL (LESS 10 L)


(1) BE SAFE

1. Turn off all ignition sources.


2. Put on gumboots or suitable footwear.
3. Wear Nitrile or appropriate chemical resistant gloves (i.e. PVC)
from spill response kit.
4. Obtain MSDS for product for specialist advice.

(2) STOP THE SOURCE

(3) PROTECT
WATERWAYS

Quickly control the spill by stopping or securing the spill source. This
could be as simple as up-righting a container, turning off the equipment,
plugging the leak or using absorbent pads to soak up any spilled material.
1. Identify nearest waterway (see xxxxx plan).
2. Determine if spill could potentially enter waterway.
3. Place booms or sorbent pads/material (sawdust, zeolite, etc) over
top of spilt material to soak it up.

(4) NOTIFY

1. Notify your supervisor/site foreman/ manager of spill.


2. If Spill has entered waterway contact Horizons Regional Council
3. 0508 800 800 (ask for Pollution Hotline)
4. Contact xxxx for any specialist advice or assistance call:Xxx xxxx
xxxxx
5. Contact sucker truck contractors (Call xxxxxxxxxxx) remove any
spill material in contaminant system or waterways.

(5) CLEAN UP

Place contaminated soil and absorbents into secure containers.


Use spade or shovel to remove any stained soil from the ground.
NEVER wash diesel into waterways.

(6) DISPOSE
RESPONSIBLY
(7) RESTOCK AND
REVIEW

Spill material and used absorbent material and pads are hazardous waste.
Arrange for hazardous waste contractor (<insert name of company>
<insert contractor phone>) to dispose of material.
1. Immediately replace all used clean-up material (<insert name and
contact details of company supplying spill kit>)
2. Assess the cause of spill and take any steps necessary steps
necessary to prevent re-occurrence.
3. Have a site meeting to discuss the reason of spill. File Health,
Safety and Environment Alert Notice to other contractors of
incident.

Draft Environmental Management Plan


Castle Hill Wind Farm

SPILL RESPONSE PLAN MEDIUM CONCRETE SPILL (up to 200 kg)


(1) BE SAFE

1. Put on gumboots or suitable footwear.


2. Wear Nitrile or appropriate chemical resistant gloves (i.e. PVC)
from spill response kit.
3. Obtain MSDS for product for specialist advice.

(2) STOP THE SOURCE

(3) PROTECT
WATERWAYS

Quickly control the spill by stopping or securing the spill source. This
could be as simple as up-righting a container, turning off the equipment,
plugging the leak or using absorbent material (sand, sawdust, earth,
zeolite) to soak up any spilled material.
1. Identify nearest waterway (see xxxxx plan).
2. Determine if spill could potentially enter waterway.
3. Place sorbent material over top of spilt material to soak it up.
4. Consider making a cut off ditch and/or earthen bunds to protect
water courses.
5. If concrete has entered waterways call sucker truck to remove
material.

(4) NOTIFY

1. Notify your supervisor/site foreman/ manager of spill.


2. If spill has entered waterway contact Horizons Regional Council
3. 0508 800 800 (ask for Pollution Hotline).
4. Contact xxxx for any specialist advice or assistance call:
xxxxxxxxx
5. Contact sucker truck if waterway contaminated or to remove
diesel/oil in cut off ditches or contaminate systems.

(5) CLEAN UP

Place contaminated soil and absorbents into secure containers for off-site
disposal.
Use spade or shovel to remove any stained soil from the ground.
NEVER wash diesel into waterways.

(6) DISPOSE
RESPONSIBLY
(7) RESTOCK AND
REVIEW

Spill material and used absorbent material and pads are hazardous waste.
Arrange for hazardous waste contractor (<insert name of company>
<insert contractor phone>) to dispose of material.
1. Immediately replace all used clean-up material (<insert name and
contact details of company supplying spill kit>)
2. Assess the cause of spill and take any steps necessary steps
necessary to prevent re-occurrence.
3. Have a site meeting to discuss the reason of spill. File Health,
Safety and Environment Alert Notice to other contractors of
incident.

You might also like