Wanda Alexander
ITMG627 IT Project Management HR and Procurement
Dr. Glenda Holcomb, Instructor
June 28, 2015
1. According to PMBOK Guide, what steps are included in the process of planning
procurements?
When a project manager is planning for procurements there are four processes that he will have
to execute because it is a formal process. The project procurement management processes consist
of: the Plan Procurement Management - which is the process that documents the decisions
related to project procurement, it specifies what approach will be used and identifies the vendors;
Conduct Procurement - which is the process of issuing a RFI, RFQ, RFP, etc. to get responses
from vendors, and making a selection and then the awarding of a vendor the contract; Control
Procurements which is the process of maintaining and monitoring procurement relationships
and contracts and making any adjustments if needed and Close Procurements - which is the
process of closing out the procurement project (PMBOK, 2008).
3. List three reasons why the project manager should buy scope from a seller.
In trying to fulfill project goals, organizations and project managers will from time to time be
faced with make or buy decisions to determine what can be made internally and what to buy
from an outside seller in order to maximum profits and achieve project goals. When making the
make or buy decision the project manager must consider, the volume, the fixed price of making,
the per unit price when buying and the per unit direct price when making. Some of the reasons
for making are: concerns about cost, need for control over the product, concerns about
intellectual property, not enough quality suppliers and organizational pride. Some of the reasons
to buy scope: technical expertise is lacking, cost concerns, unable to produce in-house and
strategic partnerships. The Cost to Buy and the Cost to Make formulas will determine which
solution would be the best to go with. The higher value will be the loser and the project manager
can go with the least expensive solution (Bajec & Jakomin, 2010).
4. What is the main difference in a Request for Proposal (RFP) and a Request for Quote (RFQ)?
The Request for Proposal (RFP) specifies the scope of work that needs to be performed and
solicits responses to the proposal from vendors describing how they would execute the scope of
work along with cost estimates. The buyer will have to specify all the requirements for the
vendor in great enough detail so that the vendor can design and develop an approach for the
project. The RFP is a clear, concise and complete document whose minimum components will
consist of a cover letter, Statement of Work (SOW) and the technical specifications which could
consist of any special requirements such as their top sells individuals along with their
biographies and cost estimates (Fleming, 2003). The Request for Quotation (RFQ) is used to
engage the vendor to provide specifics for what they can offer in regards to completing the
project. The RFQ will focus on a bids and quotes for a specified time frame for standard items
that the buyer has clearly defined in the document. A RFQ is quicker to execute than a RFP and it
does not take as long to prepare and get responses back from the vendors (Schwalbe, 2011).
agreement must be of sound mind in order to understand the seriousness of the contract and what
is required. The parties entering into the agreement must be of legal age, sober and mentally
competent. If either party is mentally incompetent the contract will be invalid and the contract
can be disavowed. The contract must be clear, concise, in writing and used for legal purposes
(AllBusiness Editors, n.d.).
7. List all methods that are used to terminate a contract.
The Control Procurements process manages the details for early termination of contract work
due to default, cause or convenience, which is associated with the termination clause that is in
the agreement (PMBOK, 2008). An organization has the right to terminate a contract based on a
default in performance which is a breach of contract. The federal government has provisions in
place which will allow for terminating a contract based on convenience or clause. Termination
for convenience gives the government the right to end part or all of contract based on
performance of work and to enter into settlement agreements. Termination for cause allows the
government to terminate a contract due to breach of contract because the party did not live up to
its obligations which may include failure to comply the terms and conditions of the contract or
the inability to provide adequate reassurance for future performance (FAR, 2013).
8. What is the difference between mediation and arbitration?
Mediation and arbitration are two forms of Alternate Dispute Resolution (ADR), which can be
inserted into a contract. Mediation and Arbitration are similar in that they are alternatives to
litigation. Both processes use a neutral third party to command the procedure and the outcomes
are legally binding (Soskin, 2014). Mediation is conducted with a mediator who facilitates the
discussions and the final resolution to the dispute. Arbitration is conducted with an arbitrator or a
panel of multiple arbitrators, to make decisions about a dispute that is presented and provide a
written opinion that can be legally binding. The process can be informal and not subjected to
common law evidence such a pre-trial discovery and the final rulings can be kept confidential
and not made public (Fleming, 2003).
References
AllBusiness Editors (n.d.), What Must a Contract Contain to Be Legally Binding?, Retrieved
June 26, 2015, http://www.allbusiness.com/what-must-a-contract-contain-to-be-legally-binding731-1.html
Assets and Supply Management and Control Division (n.d.), Bidding and Award Procedures,
Retrieved June 26, 2015,
http://www.dpwh.gov.ph/doing_business/procurement/supplies/procedures.htm#Section 1.0
INTRODUCTION
Bajec, P. & Jakomin, I. (2010), A Make-or-Buy Decision Process for Outsourcing, Promet
Traffic & Transportation, Vol. 22, 2010, No. 4
FAR -- Part 49 (2013), Termination of Contracts, Retrieved June 26, 2015,
http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/49.htm
Fleming, Q. W. (2003), Project Procurement Management: Contracting, Subcontracting,
Teaming. Tustin, CA: Quentin W. Fleming
Project Management Institute (2008), A Guide to the Project Management Body of Knowledge
(PMBOK Guide) Fourth Edition, Newtown Square, PA, Project Management Institute
Schwalbe, K. (2011), Information Technology Project Management. (6th ed.). United States of
America: Course Technology Cengage Learning.
Soskin, L. (2014), Wondering What The Difference Is Between Mediation and Arbitration?,
Retrieved June 26, 2015, http://www.huffingtonpost.com/lance-soskin/wondering-what-thediffer_b_5291286.html