Forecast TXT :FCST which has been released from APO DP to APO SNP

Sales Order TXT :- Sales order transferred from ECC to APO via CIF.
Distribution Demand (Planned) TXT :- Dependent demand coming from other location to this location for same product. Network
planning
Distribution Demand (Confirmed) TXT :- In case deployment , we confirm the Distribution Demand (Planned) will appear her.
DistrDemand (TLB-Confirmed) TXT :- Mainly used in case of TLB.
Dependent Demand TXT :- Dependent demand coming from parent product in case of BOM
Total Demand TXT :- The sum of all above demands is called as Total Demand.
Distribution Receipt (Planned) TXT :- SNP created Purchase req will appear in this key figure.
Distribution Receipt (Confirmed) TXT :- In case of deployment Distribution Receipt (Planned) will be get confirmed in the
Distribution Receipt (Confirmed) key figure.
Distribution Receipt (TLB-Confirmed) TXT :- Mainly used in case of TLB.
In Transit TXT :- In will contain the in transit stock which will transfer for ECC via CIF.
Production (Planned) TXT :- Planned order will get created via SNP in case of domestic mfg.
Production (Confirmed) TXT :- In case of SNP deployment Production (Planned) will be get confirmed in the Production
(Confirmed)) key figure.
Total Receipts TXT :- Total of all the receipt elements as been used.
Stock on Hand TXT :- Stock has transferred from ECC or R3 via CIF.
Supply Shortage TXT :- This will be calculated with macro based on total demand and total receipt.
Safety Stock TXT :- Based on SNP master data, safety stock will get calculated during planning run.
Reorder Point TXT :- Based on SNP master data, Reorder Point will get calculated during planning run. . There are different
methods of calculating safety stock.
Target Days Supply D :- The safety stock defined in number of days appears based on SNP master data in APO.
Target Stock Level TXT :- Get calculated by macro based on Target Days Supply D and total demand in future.
ATD Receipts TXT :- Mainly used for Deployment.
ATD Issues TXT :- Mainly used for Deployment