What the code allows, and supplemental findings by researchers
hat can you do if rebars partially embedded in
concrete have been fabricated incorrectly
have been placed incorrectly
have become accidentally misaligned, or are no longer properly located because there has been a design change? Should such rebars be bent or rebent in the field? If so, should they be bent cold or hot, and what are the limitations on such bending? Some answers to these questions are offered in the Concrete Reinforcing Steel Institute Engineering Data Report, Number 12. The report refers to the provisions of ACI 318-77, Building Code Requirements for Reinforced Concrete Structures. In Section 7.3 (bending), the Code requires only that: 7.3.1All reinforcement shall be bent cold, unless oth erwise permitted by the Engineer. 7.3.2Reinforcement partially embedded in concrete shall not be field bent, except as shown on the design drawings or permitted by the Engineer. ACI 318R-77, the commentary on the code, howe ve r, provides additional information and instruction: 7.3.1All bends must be made cold unless otherwise permitted by the Engineer. In this sense the Engineer may be the design engineer or architect or the engineer or architect employed by the owner to perform inspec tion. For unusual bends with inside diameters less than ASTM bent test requirements, special fabrication may be required. 7.3.2Construction conditions may make it necessary to bend bars that have been embedded in concrete, and it usually is not possible to provide a pin of the minimum diameter specified in the Code at the point of bend. Such field bending should not be done with out authorization of the inspecting engineer. The in specting engineer must determine whether the bars can be bent cold without damage, or if heating is nec essary. If heating is required it must be controlled to avoid splitting of the concrete or damage to the bars. Partially embedded reinforcing bars can be successfully rebent (or bent for the first time, which should be
less critical) if they are first pre-heated to 1100-1200 F
and then bent as gently and in as gradual an arc as possible. If there is no failure at the bend area, the reworked bars should perform as originally intended. Heating must be performed in a manner that will avoid damage to the concrete. If the bend area is within 6 inches or so of the concrete, some protective insulation may have to be applied. The heating operation should be done in such a manner that the temperature of the steel does not exceed 1200 F as measured by temperature indicating c ra yons or the other suitable means.The heated bars should not be artificially cooled (such as by water or forced air) until after cooling to at least 600 F. The above recommendations from the commentary include provisions for preheating the partially embedded rebar before bending. These were based on a study by William C. Black (Reference 1). Two other investigators, J.R. Lalik and R. L. Cusick, came to a different viewthat partially embedded rebars could be bent and straightened successfully in the field without using heat (Reference 2). Howe ve r, since their tests were run on #8 bars only, they cautioned that these conclusions needed substantiation for bar sizes larger than #8. Later, L.G. Erasmus warned in Reference 3 that it is hazardous to restraighten partially embedded bars while cold. He supported the ACI 318R-77 commentary recommendation of preheating to 1100 to 1200 F.. There have been a number of other studies that have thrown further light on the subject. In one of them The Associated Reinforcing Bar Producers Concrete Reinforcing Steel Institute, under a program to study cold versus hot bending: effects of the type, degree and axis bend; effect of bar size and deformation pattern; effect of cold temperature bending; and the differences between accidental and deliberate bending. As a result of this and earlier studies the Concrete Reinforcing Steel Institute concluded essentially that: Reworking of the bars partially embedded in concrete entails some risk. Bars of #8 or smaller size can be successfully field bent or straightened at temperatures above about 32 F. Bar sizes #9, #10 and #11 have a better change of being
successfully bent or straightened
if the bend area is uniformly preheated to 1400 to 1500 F and extreme care is excercised in the bending or straightening operation. the applicability of these conclusions to size #14 to #18 bars is uncertain. References 1. Black, William C., Field Corrections to Partially Embedded Reinforcing Bars, ACI Journal, October 1973, pages 690-691. 2. Lalik, J. R. and Cusick, R. L. Cold Straightening of Partially Embedded Reinforcing Bars, Concrete International, July 1979, PAges 26-30. 3. Erasmus, L. A. Cold Straightening of Partially Embedded Reinforcing BarsA Different View, Concrete International, June 1981, pages 47-52.
PUBLICATION #C830244 Copyright 1983, The Aberdeen Group All rights reserved