Background
The TA will (i) prepare a bulk water supply master plan; (ii)
prepare an option study for the bulk water supply; (iii)
feasibility study (FS), which includes investigative surveys,
preliminary designs, cost estimates, technical, financial,
and economic analysis, environment analysis, social
impact assessment, a baseline survey for project
indicators, and a project administration manual; (iv)
preparation of TOR and tender documents for detailed
design of the selected options and initiate the tender
process with consultants; (v) groundwater management
plan for Bandung Basin, (vi) upper catch management and
development program, and (vii) scope for PFR 3 as well as
a preparation facility for PFR 3.
The TA will also (i) identify priority reforms in provincial
water supply system ; (ii) prepare a situation and gaps
analysis of the raw water supply in the targeted areas
based on need and poverty alleviation; and (iii) prepare a
feasibility study, which include investigative surveys,
preliminary designs, preliminary engineering design of
some 5 subprojects, cost estimates, technical, financial,
economic and socioeconomic analysis, environment
analysis, social impact assessment, a study for initial
benchmark indicators, and a project administration
manual. The sequencing of the TA to prepare PFR 2
includes the bulk water supply master plan for the
metropolitan Bandung areas, feasibility studies for
selected water supply options, tender documents for
detailed design, and preparation of groundwater
management and upper watershed management. The
activities to be included into PFR 2 should be also reflected
into the Pola and Rencana for Citarum, which is under
preparation with the support of TA 7189 Package B
consulting services.
Results
Senior staff and
functions