You are on page 1of 2

Capacity Leveling

Call up the transaction as follows:


From the Capacity Planning node, choose Leveling Work Center View Planning

Menu Path

Table (Graphical)
Transaction

CM21

Code
Enter the following data:
Field

Data

Work center

1320-01

Plant

1000

Choose

The current orders whose operations result in capacity loads at the selected work center are displayed.
By scrolling through the different charts in the planning table, you can analyze the information provided.
For a better view, choose Settings Scale Monthly period split.
To automatically dispatch one or several operations of an order, click the red rectangle in the order's
diagram section to select the order and choose

The order disappears from the order pool and reserves a time segment in the work center section.
To manually dispatch one or more operations of an order, select the order in the diagram section, drag
it to the work center section with the mouse, and place it in a time period that you select.
To deallocate an order, select it in the work center's diagram section and choose

The order is again displayed in the order pool.


To analyze the changes made in scheduling, select an order in the order's diagram section and choose
Order.
Choose

and write down the start and finish dates of the operation you selected.

Choose

until the Planning Table: SAPSFCG001 Finite Scheduling Forw./All Functs.Active screen

appears.
Drag the order to a valid section in the work center's diagram section. Make sure that you move the
order to a valid and defined start and finish date.
Select the order in the work center's diagram section and choose
Choose

and compare the new start and finish date.

Choose

until the overview tree appears.

Order.

Do NOT save.

I agree with you Cap. Levlling is not frinedly in R/3 or ECC.


However we use Capacity levelling for our collective order scheduling as it helps schedule
parent & child orders as needed by planner.

For this I use cutomised profile ZSAPPSG001 copy of SAP standard SAPSFCG001 - SFC: View
work center/capacity (2 graf.).The agreed capacity overall profile is then called in your prod.
schduling profile tcode : OPKP.
You can customize user required Capacity levelling Overall profile in tcode : OPD0
From there you can select any subprofile that meets user needs or further customize subprofiles
as needed.
Selection profile

SAPSFCS009 SFC: View Center -> Capacity (2 graf.) ( tcode : OPD1

Control profile

SAP___C002 Gen: Planning table ( tcode : OPDE

Time profile

SAPSFCZ002 SFC: graph. medium-term (3 months) ( tcode : OPD2

Evaluation profile

SAP___A001 Gen: Standard evaluation profile ( tcode : OPD3

Strategy prof.

SAP___T001 Finite scheduling forw./all functs.activ ( tcode : OPDB

Period profile

SAP___P002 Gen: Daily period split ( tcode : OPD4

Planning tab.profile ZSAPPSL001 SFC: only main caps. (2 graf.) ( tcode : OPG0
List profile

SAPSFCI001 SFC: Production planning ( tcode : OPDH)

CM21/CM25 transactions