You are on page 1of 12

CONTENTS

Item

Subject

Page No.

1.

SCOPE

REFERENCES

RESPONSIBILITIES

RESOURCES

Materials
Equipment
Personnel
5

DEFINITIONS AND ABBREVIATIONS

PROCEDURE

Method and Sequence of Construction


Installation procedure of uPVC Pipe Work Water Treatment

Plant
Installation for Pressure Testing
Pump Room Equipment Installation

7
8
9
10

Method of statement for Testing & Commissioning


QUALITY CONTROL
SAFETY
ATTACHMENT

8
10

10
12
12
12

1. Inspection Test Plan


2. Risk Assessment
3. Manufacturers Manual
4. Checklist for Mechanical Installation
5. WIR format

1. SCOPE
This method of statement specifies the sequences and methodology for the
installation of MEP system for Water Treatment Plant.
2.

REFERENCES:
a. Project HSE Plan
b. Project Quality Plan
c. Approved Shop Drawing
d. Approved Material submittal
e. Manufacturer recommended installation procedures.

3.

Responsibilities

3.1

All works associated with above mentioned project limited to the installation
of MEP for Water treatment plant and will be the responsible in accordance with the
contract.

3.2

Resources for Personnel is as follows:

3.2.1 Site Engineer


He is responsible to carry out the work as per the Project
Specification, approved shop drawings, method statements,
co-ordinates with the MEP contractor and ensures all works are
provided, inspected & approved by the consultant.
He/she is also responsible to ensure the specialized sub-contractor has
adequate equipment, tools, materials, manpower are in place before
starting the works.

3.2.2 QA/QC Engineer


He/she is responsible to ensure work has been done as per the specification
and drawings, inspections are done as per Quality Control Procedure and
offer works for (CONSULTANT/CLIENT) inspection.

3.2.3 Supervisor/Foreman

Carrying out the work and the proper distribution of all the
available resources in coordination with the site engineer on a
daily basis.

Daily reports of the works achieved and coordinate for the future
planning with the Site engineer.

Incorporate all the QC and Safety requirements as requested


by the concerned Engineer.

Met with any type of unforeseen incidents or requirements and


reporting to the site engineer immediately

4.

RESOURCES:
4.1

Materials
a. Activated Carbon Filter
b. Pumps
c. Dosing System
d. Cartridge filter
e. UV System
f. UF System
g. RO System
h. Pipes
i.

Cable Tray

j.

Pipe and Cable Tray Supports

k. Electrical Cables
l.

Tanks
3

m. Valves
n. Fittings
o. Control Panel

4.2

Equipment
a. Tool Box
b. Measuring Tape
c. Hacksaw
d. Spirit Level
e. Drill Machine / Grinder
f. Pressure Gauges
g. Hand Pump/Electric Pressure Pump
h. Ammeter/Voltmeter
i.

4.3

Welding Machine

Personnel
a. Site Engineer
b. QA/QC Engineer
c. Supervisor/Foreman
d. Skilled workers

5.

DEFINITIONS & ABBREVIATIONS

SE

Site Engineer

QC

Quality Engineer

FR

Foreman

WIR

Work Inspection Request

6.

PROCEDURE

6.1

METHOD AND SEQUENCE OF CONSTRUCTION

(MEP WORKS)

Any material delivered to the site not confirming to the approved


material submittal shall be returned to the supply and replaced with
approved material.

No materials will be permitted to enter the work locations without


being inspected on arrival to the site.

Work shall be carried out by the site personnel under strict supervision
and guidance of the concerned engineers/ supervisors/ foreman.

QA/QC inspector/ engineer shall check all the installations as per the
installation/Test check sheets.

WIR will be prepared, signed by the subcontractor and shall be submitted


without delay to Contractor/Consultant for their inspection and approval as
per approved ITP.

REE is responsible for all the installation activities for getting the work
inspected and approved by Contractor/Consultant.

6.2

Installation procedure of uPVC Pipe Work for Water Treatment Plant

6.2.1

General Requirements

All the materials received at site will be inspected, upon receipt.

Any discrepancies, damages, etc. should be notified and report


to the supplier for further action.

All construction/ inspection/ testing works shall be carried out in


accordance with specifications. Work shall be carried out by the
site foreman staff under the guidance of site engineer and shall
further be checked and approved by consultant.

If any damage for the material has been happened on the site, the site
persons will be responsible for the damage.

6.2.2 Handling
During transportation pipes must be handled with care.
Do not drop or drag pipes especially on hard surfaces.
This is particularly important where the pipe ends have been
pre- prepared in the form of spigots (e.g. chamfered ends)
and integral sockets.
Where ever possible the loading and unloading of pipes to be
carried safely. When mechanical fitting equipment is to be used,
no metallic slings, hooks or chains should be used in direct contact
with the pipe. Ropes or web slings are preferred, as they will not
damage the pipe wall.

6.2.3 Storage (for uPVC Pipes)

uPVC Pipes should be stored on a flat dry level surface free


from sharp projections, stones or other objects likely to cause point
loading or pipe deformation. Timber supports spaced 1.5m apart
along the pipe can be used to support the pipe stack should not
exceed 3m.

Pipes of different sizes should be stacked separately or where


this is not possible, hose with larger diameters and/ or thicker walls
should be placed at the bottom of the stack.

The height of the stack should never exceed 7 layers or maximum


2m high. If prolonged storage is needed (more than one month) or
where the temperature exceeds 23C then the stack should not
exceed 4 layers or maximum 1m high.

All pipes and fittings should be properly covered with tarpaulins


to protect them from UV rays. The tarpaulins are to be fixed to
the wooden supports, which allow a free passage of air around
the pipes.

Fittings will be stored in sheltered conditions in the boxes as


supplied to protect them from weathering and accidental damage.

6.2.4

Cleaning of Pipes

Prepare water hose at site.

Connect the hose to clean water connection available at the site.

Flush water through the pipe in order to remove any debris, dust, and any
other unwanted material which will result in pipe blockage.

6.2.5

Installation

Mark the routing of pipe work according to approved shop drawings.

6.2.5.1 Pipe Work (for uPVC Pipes)

Measure length of pipe required, making due allowance for any


pipe fittings to be used. Cut the pipe to the measured length.

Ensure that the ends are cut square and clean all burs.

A chamfer to the depth of half wall thickness to be applied to


each spigot.

The spigot and socket to be jointed should be carefully examined


for any damage which could impair the jointing procedure.

The spigot insertion depth should be measured as the depth form


the mouth to the shoulder of the socket.

The insertion depth should be marked on the spigot using marker.


The jointing system for piping system is Solvent weld.
The mating areas of the spigot and the socket should be thoroughly
cleaned using the pipe cleaner and a clean rag.
Using a brush apply an even layer solvent cement to the spigot
and socket mating surfaces. The glue should be applied in a
lengthwise direction and not with a circular motion.
The glue should be applied simultaneously to the spigot and
socket by two people.
Immediately following gluing application ensure that the pipe
is suitably anchored, and push the spigot home in the socket
without turning the pipe.
The spigot should be inserted with a steady, continuous motion
and held in place for 20 seconds.
Remove the surplus glue from around the mouth of the socket.
Leave the joint undisturbed for five minutes, and then handle with
reasonable care.

6.2.5.2 Pipe Supports (for uPVC Pipes)

For the pipes above ground supports will be given of ring type pipe

clamps with rubber packing and for pipes at more height will be given
standard galvanized channel support with pipe clamps.
6.3

Installation for Pressure Testing


6.3.1

Procedures for Installation:

Check first the approve drawing submitted for the location


and marking of the pipes.

Prepare the necessary materials for installation

Start layout of the pipe as per coordinated marking and levels.

After the layout make a support for all the pipes using thrust block,
rubber clamp and steel bar.

Prepare the materials for the pressure testing such as plugs,


pressure pump, pressure gauges and other equipment / tools required.

Clean the edge of the pipe and put plug on locations where valves are
not required.

After putting plug, install the pressure pump with threaded nipples,
connect to the valve for the purpose of bleeding to the part you
can remove the air inside the pipelines then connect a G.I Tee to
interlink between the calibrated pressure and the pipe to be tested.

Fill entire system with water through any water supply faucet by means
of pail and put it on the pressure hand pump.

Check for any leak in the connection /layout. If so, modify/ rectify
first before applying the pressure.

The working pressure of the pipe is 4 bars; however, for testing


Pressure the lines until it reaches the test pressure of 6 bars which is
1.5 times of the working load.

Check the points / connections again for leakage. If there is no leak close
the valve and remove the pressure hand pump.

Maintain pressure in the pipe line for at least 4 hours.

Prepare the necessary documents such as drawings, pressure test


9

certificate indicating the start and end, together with the pressure rated
and losses and get signature from Consultant

After checking the bar rating passed, remove the pressure of the pipes
up to 1 bar by experience person.

After remove the end plugs and valves.

Remove the water and flushed the lines.

Close all the end points using masking tapes.

6.4. Pump Room Equipment Installation


6.4.1 Mark out the location of the plinths for the pumps and filters as per
approved shop drawings and cast the plinths in place up to the required
thickness.
6.4.2 Fix the interconnected pipe work between the pumps, filters and
the suction and delivery lines as per the approved drawings.
6.4.3 Route and level shall be as per the approved drawing and clearance to
be maintained as required.
6.4.4 After installation of equipments & pipings in pump room are
completed and raise stage by stage WIR for getting approval
from the consultant as per approved ITP.
6.4.6 Installation of cable tray and trunking shall be carried out as per
specification and approved shop drawing.
6.4.7 Cable tray and cable trunking and related accessories shall be by an
approved manufacturer and the material should be inspected prior to
the installation of work.
6.4.8 Route and level shall be as per the approved drawing and clearance to be
maintained as required.
6.4.9 Support spacing to be executed as per the approved drawing and site
condition.
6.4.10 Spacing between others services shall be coordinated on the site.
6.4.11 Remove burrs and sharp edges from cable trays/trunking.
6.4.12 Fasten cable tray/ cable trunking to building structure.

10

6.4.13 Any cutting or drilling support channel, threaded rod, tray/trunking


edges shall be cleaned up and painted with zinc paint.
6.4.14 Install cable tray/trunking with enough space to permit access for
installing cables. Install the cable tray/trunking with proper
alignment with other services.
6.4.15 After installation clean and cover it properly to avoid any mechanical
damages from other services.
6.4.16 Install cables only when cable tray/trunking installation has been
completed and raise stage by stage WIR for getting approval
from the consultant as per approved ITP.
6.4.17 Install the control panel.
6.4.18 Terminate the cables at the control panel as well as the equipment
and pumps.

7.0

METHOD STATEMENT FOR TESTING AND COMMISSIONING


Scope:

To test and commission the water treatment plant system.

TESTING & COMMISSIONING PROCEDURES

1. Check for fresh water supply line in the pump room for filling and make up.
2. Check for incoming power supply for the control panel
3. Verify the connection and termination of control panel
4. The water has to be filled to the required level in the raw water tank.
5. After that close and open all the necessary valves to start the system
6. First set to open the butterfly valve on the suction line and discharge line.
7. Run the filtration pump on HAND position to start the operation
8. Check the direction of rotation of pump is proper
9. The chemical system is filled with appropriate reagents and working properly.
10. Check for any leakage in the piping, if there is turn OFF the pump
and close all the valves to rectify the fault.
11. If there is no leakage or fault in the system, continue the operation.
11

8.0

Quality Control
8.1

Check all the materials delivered to site are inspected properly as per
approved MAR (Material Approval request) and proper storage.

8.2

Work shall be carried out by the site personnel under strict supervision
and guidance of the supervisors/foreman / engineers.

8.3

Work inspection Request (WIR) will be submitted for witness and hold
points as detailed in the attached Inspection and Test Plan for MEP.

8.4

Pressure gauges for testing will be calibrated and certificates will be provided
during testing.

9.0

Safety
9.1

All workers shall wear PPE

9.2

Proper access, sign board and barriers shall be provided as required

9.3

Sufficient illumination and ventilation should be available at working


Areas.

10.0

Attachments
10.1

Inspection Test Plan

10.2

Risk assessment

10.3

Manufacturers Manual

10.3

Checklist for Mechanical Installation

10.3

WIR format

12

You might also like