You are on page 1of 3

Activity ID

Activity Name

Original Early Start


Duration

Early Finish

Late Start

Late Finish

Total Float

2015

2016

319 18-Feb-15

03-Jan-16

04-Mar-15

11-Feb-16

39

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul g
03-Jan-16, Port Buildings and Infrastru

293 16-Mar-15

03-Jan-16

15-Jun-15

11-Feb-16

39

03-Jan-16, Section 2 CP 14 Port Marin

293 16-Mar-15

03-Jan-16

15-Jun-15

11-Feb-16

39

03-Jan-16, Milestone 8 & 10

Infrastructure and External Works


Engineering
Material Submittals
Submittals
Utility Buildings
Electrical
Substation 13
57.S2.M8.IE.S13.E052 Material Submittals for S13

293
25
25
5
5
5
5
5

16-Mar-15
16-Mar-15
16-Mar-15
16-Mar-15
16-Mar-15
16-Mar-15
16-Mar-15
16-Mar-15

03-Jan-16
09-Apr-15
09-Apr-15
20-Mar-15
20-Mar-15
20-Mar-15
20-Mar-15
20-Mar-15

15-Jun-15
15-Jun-15
15-Jun-15
15-Jun-15
15-Jun-15
15-Jun-15
15-Jun-15
15-Jun-15

11-Feb-16
15-Jul-15
15-Jul-15
19-Jun-15
19-Jun-15
19-Jun-15
19-Jun-15
19-Jun-15

39
97
97
91
91
91
91
91

Approvals
Utility Buildings
Electrical
Substation 13
57.S2.M8.IE.S13.E054 Material Approvals for S13

15
15
15
15
15

22-Mar-15
22-Mar-15
22-Mar-15
22-Mar-15
22-Mar-15

09-Apr-15
09-Apr-15
09-Apr-15
09-Apr-15
09-Apr-15

25-Jun-15
25-Jun-15
25-Jun-15
25-Jun-15
25-Jun-15

15-Jul-15
15-Jul-15
15-Jul-15
15-Jul-15
15-Jul-15

69
69
69
69
69

Orders for S13

45
5
5
5
5
5

10-Apr-15
10-Apr-15
10-Apr-15
10-Apr-15
10-Apr-15
10-Apr-15

24-May-15
14-Apr-15
14-Apr-15
14-Apr-15
14-Apr-15
14-Apr-15

16-Jul-15
16-Jul-15
16-Jul-15
16-Jul-15
16-Jul-15
16-Jul-15

29-Aug-15
20-Jul-15
20-Jul-15
20-Jul-15
20-Jul-15
20-Jul-15

97
97
97
97
97
97

Manufacturing and Fabrication for S13

20
20
20
20
20

15-Apr-15
15-Apr-15
15-Apr-15
15-Apr-15
15-Apr-15

04-May-15
04-May-15
04-May-15
04-May-15
04-May-15

21-Jul-15
21-Jul-15
21-Jul-15
21-Jul-15
21-Jul-15

09-Aug-15
09-Aug-15
09-Aug-15
09-Aug-15
09-Aug-15

97
97
97
97
97

@@Delivery of S13

20
20
20
20
20

05-May-15
05-May-15
05-May-15
05-May-15
05-May-15

24-May-15
24-May-15
24-May-15
24-May-15
24-May-15

10-Aug-15
10-Aug-15
10-Aug-15
10-Aug-15
10-Aug-15

29-Aug-15
29-Aug-15
29-Aug-15
29-Aug-15
29-Aug-15

97
97
97
97
97

04-Jul-15
04-Jul-15
04-Jul-15
04-Jul-15

03-Jan-16
04-Jul-15
04-Jul-15

30-Aug-15
30-Aug-15
30-Aug-15
30-Aug-15

11-Feb-16
30-Aug-15
30-Aug-15

39
57
57
57

Port Buildings and Infrastructure DTP Rev.03


Section 2 CP 14 Port Marine Unit Area ecluding the Control Tower Buildin
Milestone 8 & 10

Procurement
Orders
Utility Buildings
Electrical
Substation 13
57.S2.M8.IE.S13.P005
Manufacturing and Fabrication
Utility Buildings
Electrical
Substation 13
57.S2.M8.IE.S13.P014
Delivery
Utility Buildings
Electrical
Substation 13
57.S2.M8.IE.S13.P023
Construction
Utility Buildings
SCH35-Substation 13
57.S2.M8.35.C000
Infrastructure
SCH45-Electrical works
57.S2.M8.45.C000

c Jan Feb Mar Apr May Jun

03-Jan-16, Infrastructure and External


09-Apr-15, Engineering
09-Apr-15, Material Submittals
20-Mar-15, Submittals
20-Mar-15, Utility Buildings
20-Mar-15, Electrical
20-Mar-15, Substation 13
Material Submittals for S13
09-Apr-15, Approvals
09-Apr-15, Utility Buildings
09-Apr-15, Electrical
09-Apr-15, Substation 13
Material Approvals for S13
24-May-15, Procurement
14-Apr-15, Orders
14-Apr-15, Utility Buildings
14-Apr-15, Electrical
14-Apr-15, Substation 13
Orders for S13
04-May-15, Manufacturing and Fabrication
04-May-15, Utility Buildings
04-May-15, Electrical
04-May-15, Substation 13
Manufacturing and Fabrication for S13
24-May-15, Delivery
24-May-15, Utility Buildings
24-May-15, Electrical
24-May-15, Substation 13
@@Delivery of S13
03-Jan-16, Construction
04-Jul-15, Utility Buildings
04-Jul-15, SCH35-Substation 13
Submittals Completion SCH35, 04-Jul-15

Submittals Completion SCH35

183
0
0
0

03-Jan-16
03-Jan-16

16-Dec-15
16-Dec-15
14-Jan-16

11-Feb-16
11-Feb-16

Submittals Completion SCH45

127 29-Aug-15
127 29-Aug-15
0 29-Aug-15

39
39
138

42 29-Oct-15
14 26-Nov-15

10-Dec-15
10-Dec-15

16-Dec-15
13-Jan-16

02-Feb-16
26-Jan-16

55
48

10-Dec-15, Distribution Transformers, 22kV


Installation of MDB Potable Water Pump Station

Distribution Transformers, 22kV


2
& LV Switchboards, Isolators and Battery & UPS S
57.S2.M8.I.C.45.0001
Installation of distrib transf, 22kV distrib & LV switchboard

03-Jan-16, Infrastructure
03-Jan-16, SCH45-Electrical works
Submittals Completion SCH45, 29-Aug-15
Installation of distrib transf, 22kV distrib & L

57.S2.M8.I.C.45.0002

Installation of MDB Potable Water Pump Station

14 29-Oct-15

12-Nov-15

16-Dec-15

29-Dec-15

48

57.S2.M8.I.C.45.0003

Installation of MDB Fire Fighting / Fresh Water Pump Sta

14 12-Nov-15

26-Nov-15

30-Dec-15

12-Jan-16

48

57.S2.M8.I.C.45.0004

Installation of MDB Land Fuel Control Room

20 29-Oct-15

17-Nov-15

14-Jan-16

02-Feb-16

77

7 10-Dec-15
7 10-Dec-15

17-Dec-15
17-Dec-15

27-Jan-16
27-Jan-16

02-Feb-16
02-Feb-16

48
48

Roads power cables laying

14 06-Dec-15
14 06-Dec-15

19-Dec-15
19-Dec-15

28-Jan-16
28-Jan-16

11-Feb-16
11-Feb-16

54
54

Road excavation of electrical trenches

25 28-Oct-15
10 28-Oct-15

21-Nov-15
06-Nov-15

22-Dec-15
22-Dec-15

02-Feb-16
31-Dec-15

73
55

Road excavation of electrical trenches

Diesel Generator Set


57.S2.M8.I.C.45.0008
Power Cables
57.S2.M8.I.C.45.0009
Duct Banks
57.S2.M8.I.C.45.0010

Installation of diesel generator set Substation 13

Installation of MDB Fire Fighting / Fresh Wate


Installation of MDB Land Fuel Control Room
17-Dec-15, Diesel Generator Set
Installation of diesel generator set Substat
19-Dec-15, Power Cables
Roads power cables laying
21-Nov-15, Duct Banks

57.S2.M8.I.C.45.0011

Installation of conduit spacers

8 31-Oct-15

07-Nov-15

25-Dec-15

01-Jan-16

55

Installation of conduit spacers

57.S2.M8.I.C.45.0012

Conduit laying

8 31-Oct-15

07-Nov-15

26-Jan-16

02-Feb-16

87

Conduit laying

Actual Level of Effort

Milestone

Primary Baseline

summary

Actual Work
Remaining Work
Critical Remaining Work

Detailed Classic Schedule Layout (UCE)

IA 15/16C 008G
Revision

Page 1 of 3
Date
21-Jun-15

Rev 00

Checked
FBM

Approved

Activity ID

Activity Name

Original Early Start


Duration

Early Finish

Late Start

Late Finish

Total Float

2015
c Jan Feb Mar Apr May Jun

2016

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Jul g

57.S2.M8.I.C.45.0013

Installation of formwork

8 02-Nov-15

09-Nov-15

27-Dec-15

03-Jan-16

55

Installation of formwork

57.S2.M8.I.C.45.0014

Concrete pouring

5 06-Nov-15

10-Nov-15

31-Dec-15

04-Jan-16

55

Concrete pouring

57.S2.M8.I.C.45.0015

Curing duration

7 11-Nov-15

17-Nov-15

05-Jan-16

11-Jan-16

55

Curing duration

57.S2.M8.I.C.45.0016

Backfilling of electrical trenches

4 18-Nov-15

21-Nov-15

30-Jan-16

02-Feb-16

73

Road excavation of electrical manholes

29 28-Oct-15
10 28-Oct-15

25-Nov-15
06-Nov-15

05-Jan-16
05-Jan-16

02-Feb-16
14-Jan-16

69
69

Road excavation of electrical manholes

57.S2.M8.I.C.45.0018

Construction of electrical manholes

10 31-Oct-15

09-Nov-15

08-Jan-16

17-Jan-16

69

Construction of electrical manholes

57.S2.M8.I.C.45.0019

Curing duration of electrical manholes

7 10-Nov-15

16-Nov-15

18-Jan-16

24-Jan-16

69

57.S2.M8.I.C.45.0020

Backfilling of electrical manholes

4 17-Nov-15

20-Nov-15

25-Jan-16

28-Jan-16

69

57.S2.M8.I.C.45.0021

Installation of manhole covers and fittings

7 19-Nov-15

25-Nov-15

27-Jan-16

02-Feb-16

69

14 20-Dec-15
14 20-Dec-15

03-Jan-16
03-Jan-16

02-Jan-16
02-Jan-16

16-Jan-16
16-Jan-16

13
13

311 18-Feb-15

25-Dec-15

04-Mar-15

05-Feb-16

42

Setting-up the SCS/PMS and FO cable


25-Dec-15, Section 3 CP 12 Coast Gua

311 18-Feb-15

25-Dec-15

04-Mar-15

05-Feb-16

42

25-Dec-15, Milestone 6

311
27
27
6
6
6
6
6

18-Feb-15
18-Feb-15
18-Feb-15
18-Feb-15
18-Feb-15
18-Feb-15
18-Feb-15
18-Feb-15

25-Dec-15
16-Mar-15
16-Mar-15
23-Feb-15
23-Feb-15
23-Feb-15
23-Feb-15
23-Feb-15

04-Mar-15
04-Mar-15
04-Mar-15
04-Mar-15
04-Mar-15
04-Mar-15
04-Mar-15
04-Mar-15

05-Feb-16
09-Apr-15
09-Apr-15
16-Mar-15
16-Mar-15
16-Mar-15
10-Mar-15
10-Mar-15

42
24
24
21
21
21
14
14

5 18-Feb-15
5 18-Feb-15

22-Feb-15
22-Feb-15

12-Mar-15
12-Mar-15

16-Mar-15
16-Mar-15

22
22

23-Feb-15
23-Feb-15
23-Feb-15
24-Feb-15
24-Feb-15

16-Mar-15
16-Mar-15
16-Mar-15
16-Mar-15
16-Mar-15

15-Mar-15
15-Mar-15
15-Mar-15
15-Mar-15
15-Mar-15

09-Apr-15
09-Apr-15
09-Apr-15
05-Apr-15
05-Apr-15

18
18
18
13
13

15 23-Feb-15
15 23-Feb-15

15-Mar-15
15-Mar-15

22-Mar-15
22-Mar-15

09-Apr-15
09-Apr-15

19
19

46
6
6
6
5
5

16-Mar-15
16-Mar-15
16-Mar-15
16-Mar-15
17-Mar-15
17-Mar-15

30-Apr-15
21-Mar-15
21-Mar-15
21-Mar-15
21-Mar-15
21-Mar-15

05-Apr-15
05-Apr-15
05-Apr-15
05-Apr-15
05-Apr-15
05-Apr-15

25-May-15
15-Apr-15
15-Apr-15
15-Apr-15
10-Apr-15
10-Apr-15

24
24
24
24
19
19

5 16-Mar-15
5 16-Mar-15

20-Mar-15
20-Mar-15

10-Apr-15
10-Apr-15

15-Apr-15
15-Apr-15

25
25

Manufacturing and Fabrication for S11

21
21
21
20
20

21-Mar-15
21-Mar-15
21-Mar-15
22-Mar-15
22-Mar-15

10-Apr-15
10-Apr-15
10-Apr-15
10-Apr-15
10-Apr-15

10-Apr-15
10-Apr-15
10-Apr-15
10-Apr-15
10-Apr-15

05-May-15
05-May-15
05-May-15
30-Apr-15
30-Apr-15

24
24
24
19
19

Manufacturing and Fabrication for S12

20 21-Mar-15
20 21-Mar-15

09-Apr-15
09-Apr-15

15-Apr-15
15-Apr-15

05-May-15
05-May-15

25
25

@#@Delivery of S11

21
21
21
20
20

10-Apr-15
10-Apr-15
10-Apr-15
11-Apr-15
11-Apr-15

30-Apr-15
30-Apr-15
30-Apr-15
30-Apr-15
30-Apr-15

30-Apr-15
30-Apr-15
30-Apr-15
30-Apr-15
30-Apr-15

25-May-15
25-May-15
25-May-15
20-May-15
20-May-15

24
24
24
19
19

20 10-Apr-15

29-Apr-15

05-May-15

25-May-15

25

Manhole
57.S2.M8.I.C.45.0017

Power Management System (PMS)


57.S2.M8.I.C.45.0023
Setting-up the SCS/PMS and FO cables Substation 13

Section 3 CP 12 Coast Guard Area


Are
Milestone 6
Infrastructure and External Works
Engineering
Material Submittals
Submittals
Utility Buildings
Electrical
Substation 11
57.S3.M6.IE.S11.E062 Material Submittals for S11
Substation 12
57.S3.M6.IE.S12.E062 Material Submittals for S12
Approvals
Utility Buildings
Electrical
Substation 11
57.S3.M6.IE.S11.E064 Material Approvals for S11
Substation 12
57.S3.M6.IE.S12.E064 Material Approvals for S12
Procurement
Orders
Utility Buildings
Electrical
Substation 11
57.S3.M6.IE.S11.P005
Substation 12
57.S3.M6.IE.S12.P005
Manufacturing and Fabrication
Utility Buildings
Electrical
Substation 11
57.S3.M6.IE.S11.P014
Substation 12
57.S3.M6.IE.S12.P014
Delivery
Utility Buildings
Electrical
Substation 11
57.S3.M6.IE.S11.P025
Substation 12
Actual Level of Effort

Milestone

Primary Baseline

summary

Actual Work
Remaining Work
Critical Remaining Work

Orders for S11


Orders for S12

16
16
16
15
15

Detailed Classic Schedule Layout (UCE)

Backfilling of electrical trenches


25-Nov-15, Manhole

Curing duration of electrical manholes


Backfilling of electrical manholes
Installation of manhole covers and fittings
03-Jan-16, Power Management Syste

25-Dec-15, Infrastructure and External W


16-Mar-15, Engineering
16-Mar-15, Material Submittals
23-Feb-15, Submittals
23-Feb-15, Utility Buildings
23-Feb-15, Electrical
23-Feb-15, Substation 11
Material Submittals for S11
22-Feb-15, Substation 12
Material Submittals for S12
16-Mar-15, Approvals
16-Mar-15, Utility Buildings
16-Mar-15, Electrical
16-Mar-15, Substation 11
Material Approvals for S11
15-Mar-15, Substation 12
Material Approvals for S12
30-Apr-15, Procurement
21-Mar-15, Orders
21-Mar-15, Utility Buildings
21-Mar-15, Electrical
21-Mar-15, Substation 11
Orders for S11
20-Mar-15, Substation 12
Orders for S12
10-Apr-15, Manufacturing and Fabrication
10-Apr-15, Utility Buildings
10-Apr-15, Electrical
10-Apr-15, Substation 11
Manufacturing and Fabrication for S11
09-Apr-15, Substation 12
Manufacturing and Fabrication for S12
30-Apr-15, Delivery
30-Apr-15, Utility Buildings
30-Apr-15, Electrical
30-Apr-15, Substation 11
@#@Delivery of S11
29-Apr-15, Substation 12
IA 15/16C 008G
Revision

Page 2 of 3
Date
21-Jun-15

Rev 00

Checked
FBM

Approved

Activity ID

Activity Name
57.S3.M6.IE.S12.P025
Construction
Infrastructure
SCH25-Electrical works
57.S3.M6.25.C000

@#@Delivery of S12

Submittals Completion SCH25

Distribution Transformers, 22kV


2
& LV Switchboards, Isolators and Battery & UPS S
57.S3.M6.I.C.25.0053
Installation of MDB Firefighting/Fresh Water Pump Statio

Original Early Start


Duration
20 10-Apr-15

Early Finish

Late Start

Late Finish

Total Float

2015
c Jan Feb Mar Apr May Jun

2016

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Jul g

29-Apr-15

05-May-15

25-May-15

25

30-Jun-15
30-Jun-15
30-Jun-15
11-Dec-15

25-Dec-15
25-Dec-15
25-Dec-15

08-Nov-15
08-Nov-15
08-Nov-15
24-Dec-15

05-Feb-16
05-Feb-16
05-Feb-16

42
42
42
13

25-Dec-15, Construction
25-Dec-15, Infrastructure
25-Dec-15, SCH25-Electrical works
Submittals Completion SCH25, 11-Dec-15

178 30-Jun-15
14 09-Sep-15

24-Dec-15
22-Sep-15

09-Nov-15
24-Dec-15

07-Jan-16
07-Jan-16

13
106

24-Dec-15, Distribution Transformers, 2

179
179
179
0

@#@Delivery of S12

Installation of MDB Firefighting/Fresh Water Pump Station

57.S3.M6.I.C.25.0054

Installation of MDB Potable Water Pump Station

14 11-Dec-15

24-Dec-15

24-Dec-15

07-Jan-16

13

Installation of MDB Potable Water Pump

57.S3.M6.I.C.25.0055

Installation of distrib transf, 22kV distrib & LV switchboard

14 12-Oct-15

25-Oct-15

24-Nov-15

08-Dec-15

43

Installation of distrib transf, 22kV distrib & LV switchb

57.S3.M6.I.C.25.0056

Installation of distrib transf, 22kV distrib & LV switchboard

14 30-Jun-15

13-Jul-15

09-Nov-15

22-Nov-15

132

107 15-Jul-15
7 23-Oct-15

29-Oct-15
29-Oct-15

08-Nov-15
03-Jan-16

09-Jan-16
09-Jan-16

72
72

7 15-Jul-15

21-Jul-15

08-Nov-15

15-Nov-15

116

Power cables laying

14 05-Oct-15
14 05-Oct-15

19-Oct-15
19-Oct-15

22-Jan-16
22-Jan-16

05-Feb-16
05-Feb-16

109
109

Backfilling of electrical trenches

28 11-Sep-15
4 05-Oct-15

09-Oct-15
09-Oct-15

15-Nov-15
03-Jan-16

07-Jan-16
07-Jan-16

89
89

Diesel Generator Set


57.S3.M6.I.C.25.0025

Installation of diesel generator set Substation 12

57.S3.M6.I.C.25.0026

Installation of diesel generator set Substation 11

Power Cables
57.S3.M6.I.C.25.0030
Duct Banks
57.S3.M6.I.C.25.0031

Installation of distrib transf, 22kV distrib & LV switchboards, isolators an


29-Oct-15, Diesel Generator Set
Installation of diesel generator set Substation 12
Installation of diesel generator set Substation 11
19-Oct-15, Power Cables
Power cables laying
09-Oct-15, Duct Banks
Backfilling of electrical trenches

57.S3.M6.I.C.25.0038

Curing duration

7 28-Sep-15

05-Oct-15

02-Dec-15

09-Dec-15

64

Curing duration

57.S3.M6.I.C.25.0043

Concrete pouring

5 23-Sep-15

28-Sep-15

27-Nov-15

02-Dec-15

64

Concrete pouring

57.S3.M6.I.C.25.0044

Installation of formwork

12 16-Sep-15

28-Sep-15

20-Nov-15

02-Dec-15

64

57.S3.M6.I.C.25.0046

Conduit laying

12 14-Sep-15

26-Sep-15

26-Dec-15

07-Jan-16

102

57.S3.M6.I.C.25.0047

Installation of conduit spacers

12 14-Sep-15

26-Sep-15

18-Nov-15

30-Nov-15

64

Installation of conduit spacers

57.S3.M6.I.C.25.0049

Excavation electrical trenches

14 11-Sep-15

25-Sep-15

15-Nov-15

29-Nov-15

64

Installation of manhole covers and fittings

33 11-Sep-15
7 07-Oct-15

14-Oct-15
14-Oct-15

15-Nov-15
31-Dec-15

07-Jan-16
07-Jan-16

84
84

Excavation electrical trenches


14-Oct-15, Manhole

4 05-Oct-15

09-Oct-15

29-Dec-15

02-Jan-16

84

Manhole
57.S3.M6.I.C.25.0029

Installation of formwork
Conduit laying

Installation of manhole covers and fittings

57.S3.M6.I.C.25.0032

Backfilling of electrical manhole

57.S3.M6.I.C.25.0042

Curing duration of electrical manholes

7 28-Sep-15

05-Oct-15

02-Dec-15

09-Dec-15

64

57.S3.M6.I.C.25.0045

Construction of electrical manholes

14 14-Sep-15

28-Sep-15

18-Nov-15

02-Dec-15

64

Construction of electrical manholes

57.S3.M6.I.C.25.0050

Excavation of electrical manholes

14 11-Sep-15

25-Sep-15

15-Nov-15

29-Nov-15

64

120 28-Aug-15
14 28-Aug-15

25-Dec-15
10-Sep-15

24-Dec-15
24-Dec-15

07-Jan-16
07-Jan-16

12
118

Excavation of electrical manholes


25-Dec-15, Power Management System

14 12-Dec-15

25-Dec-15

24-Dec-15

07-Jan-16

12

84 03-Oct-15

25-Dec-15

23-Dec-15

23-Jan-16

29

Testing & Commissioning of electrical and earthing system

84
18
18
18

03-Oct-15
03-Oct-15
03-Oct-15
03-Oct-15

25-Dec-15
21-Oct-15
21-Oct-15
21-Oct-15

23-Dec-15
23-Dec-15
23-Dec-15
23-Dec-15

23-Jan-16
09-Jan-16
09-Jan-16
09-Jan-16

29
81
81
81

Testing & Commissioning of electrical and earthing system

14 12-Dec-15
14 12-Dec-15
14 12-Dec-15

25-Dec-15
25-Dec-15
25-Dec-15

10-Jan-16
10-Jan-16
10-Jan-16

23-Jan-16
23-Jan-16
23-Jan-16

29
29
29

Power Management System (PMS)


57.S3.M6.I.C.25.0001
Setting-up the SCS/PMS and FO cables Substation 11
57.S3.M6.I.C.25.0003

Setting-up the SCS/PMS and FO cables Substation 12

Milestone 10
Infrastructure and External Works
SCH12-Substation 11
Testing and Commissioning
57.S3.M6.I.C.12.0063
SCH13-Substation 12
Testing and Commissioning
57.S3.M6.I.C.13.0063

Actual Level of Effort

Milestone

Primary Baseline

summary

Actual Work
Remaining Work
Critical Remaining Work

Detailed Classic Schedule Layout (UCE)

Backfilling of electrical manhole


Curing duration of electrical manholes

Setting-up the SCS/PMS and FO cables Substation 11


Setting-up the SCS/PMS and FO cables
25-Dec-15, Milestone 10
25-Dec-15, Infrastructure and External W
21-Oct-15, SCH12-Substation 11
21-Oct-15, Testing and Commissioning
Testing & Commissioning of electrical and earthing s
25-Dec-15, SCH13-Substation 12
25-Dec-15, Testing and Commissioning
Testing & Commissioning of electrical an

IA 15/16C 008G
Revision

Page 3 of 3
Date
21-Jun-15

Rev 00

Checked
FBM

Approved

You might also like