You are on page 1of 7

Public Disclosure Copy

The World Bank

Implementation Status & Results Report

Regional Development Project (P126033)

Regional Development Project (P126033)


EUROPE AND CENTRAL ASIA | Georgia | Urban Development Global Practice |
IBRD/IDA | Specific Investment Loan | FY 2012 | Seq No: 4 | ARCHIVED on 09-Feb-2015 | ISR16295 |
Implementing Agencies:

Key Dates
Key Project Dates
Board Approval date:20-Mar-2012

Effectiveness Date:31-May-2012

Planned Mid Term Review Date:14-Oct-2013

Actual Mid-Term Review Date:26-May-2014

Original Closing Date:31-Dec-2016

Revised Closing Date:31-Dec-2016

Project Development Objectives


Project Development Objective (from Project Appraisal Document)
The Project Development Objective is to improve infrastructure services and institutional capacity to support the development of tourism-based
economy and cultural heritage circuits in the Kakheti region

Has the Project Development Objective been changed since Board Approval of the Project Objective?
No

PHRPDODEL

Components
Name
Infrastructure Investment:(Cost $56.90 M)
Institutional Development:(Cost $3.10 M)

Overall Ratings
Name

Previous Rating

Current Rating

Progress towards achievement of PDO

Satisfactory

Satisfactory

Overall Implementation Progress (IP)

Satisfactory

Satisfactory

Overall Risk Rating

--

Moderate

Implementation Status and Key Decisions


2/9/2015

Public Disclosure Copy

Page 1 of 7

Public Disclosure Copy

The World Bank

Implementation Status & Results Report

Regional Development Project (P126033)

The Project is on track to achieve its development objective. The overall implementation is assessed as satisfactory. The Project Implementation Entity
(MDF) almost completed its reorganization process to improve its quality of supervision, contract management and coordination with various agencies
involved. Considerable amount of works have been completed. The mission acknowledged not only the outputs achieved under the project, but also the
outcomes already visible on the ground. In sites in which the project provided financing for physical investments, as well as in their proximity, a number
of small businesses have opened, creating permanent job opportunities for Georgians, while offering services to both the resident population and
tourists (main streets of Telavi, road to David Gareji, road segments per PPP sub-projects completed, etc.). A review of the Intermediate Results
Indicators after 29 months (almost 2.5 years) of implementation presents good results.

Risks
Systematic Operations Risk-rating Tool
Risk Category

Rating at Approval

Previous Rating

Current Rating

Political and Governance

--

--

Moderate

Macroeconomic

--

--

Low

Sector Strategies and Policies

--

--

Low

Technical Design of Project or Program

--

--

Substantial

Institutional Capacity for Implementation and


Sustainability

--

--

Low

Fiduciary

--

--

Low

Environment and Social

--

--

Moderate

Stakeholders

--

--

Low

Other

--

--

--

Overall

--

--

Moderate

Results
Project Development Objective Indicators
PHINDPDOTBL

Increase weighted average number of hours per day of piped water services in project areas (Number, Custom)

2/9/2015

Public Disclosure Copy

Page 2 of 7

Public Disclosure Copy

The World Bank

Implementation Status & Results Report

Regional Development Project (P126033)

Baseline

Actual (Previous)

Actual (Current)

End Target

Value

8.00

12.00

12.00

24.00

Date

30-May-2012

06-Jun-2014

24-Dec-2014

31-Dec-2016

PHINDPDOTBL

Reduce weighted average vehicle operating cost due to improved urban roads (Percentage, Custom)
Baseline

Actual (Previous)

Actual (Current)

End Target

Value

100.00

92.00

90.00

75.00

Date

30-May-2012

06-Jun-2014

24-Dec-2014

31-Dec-2016

PHINDPDOTBL

Increase volume of private sector investments (Amount(USD), Custom)


Baseline

Actual (Previous)

Actual (Current)

End Target

Value

0.00

10.00

10.00

50.00

Date

30-May-2012

06-Jun-2014

24-Dec-2014

31-Dec-2016

PHINDPDOTBL

Increase number of hotel beds in circuit route areas (Number, Custom)


Baseline

Actual (Previous)

Actual (Current)

End Target

Value

1610.00

2511.00

2719.00

1932.00

Date

30-May-2012

31-Oct-2013

24-Dec-2014

31-Dec-2016

PHINDPDOTBL

Increase points of sales (tickets, souvenirs shops, restaurants, hotels, guesthouse and family houses) in renovated culture
heritage sites and cities (Number, Custom)

Baseline

Actual (Previous)

Actual (Current)

End Target

Value

248.00

282.00

300.00

323.00

Date

30-May-2012

31-Oct-2013

24-Dec-2014

31-Dec-2016

2/9/2015

Public Disclosure Copy

Page 3 of 7

Public Disclosure Copy

The World Bank

Implementation Status & Results Report

Regional Development Project (P126033)

Overall Comments

Intermediate Results Indicators


PHINDIRITBL

Piped household water connections that are benefiting from rehabilitation works undertaken by the project (Number, Core)
Baseline

Actual (Previous)

Actual (Current)

End Target

Value

0.00

4258.00

4258.00

500.00

Date

30-May-2012

06-Jun-2014

24-Dec-2014

31-Dec-2016

PHINDIRITBL

Number of people in urban areas provided with access to all-season roads within a 500 meter range under the project
(Number, Core)

Baseline

Actual (Previous)

Actual (Current)

End Target

Value

0.00

40400.00

40400.00

50000.00

Date

30-May-2012

06-Jun-2014

24-Dec-2014

31-Dec-2016

PHINDIRITBL

Number of private investment proposals approved (Number, Custom)


Baseline

Actual (Previous)

Actual (Current)

End Target

Value

0.00

9.00

10.00

10.00

Date

30-May-2012

06-Jun-2014

24-Dec-2014

31-Dec-2016

PHINDIRITBL

Number of redeveloped culture heritage sites along the the tourist circuit (Number, Custom)
Baseline

Actual (Previous)

Actual (Current)

End Target

Value

0.00

5.00

11.00

11.00

Date

30-May-2012

06-Jun-2014

24-Dec-2014

31-Dec-2016

2/9/2015

Public Disclosure Copy

Page 4 of 7

Public Disclosure Copy

The World Bank

Implementation Status & Results Report

Regional Development Project (P126033)

PHINDIRITBL

Production/Distribution of new maps based on geotourism database (Number, Custom)


Baseline

Actual (Previous)

Actual (Current)

End Target

Value

0.00

2000.00

19449.00

10000.00

Date

30-May-2012

06-Jun-2014

24-Dec-2014

31-Dec-2016

PHINDIRITBL

Number ofstablished and operating of destinataion management offices (Number, Custom)


Baseline

Actual (Previous)

Actual (Current)

End Target

Value

0.00

0.00

0.00

3.00

Date

30-May-2012

06-Jun-2014

24-Dec-2014

31-Dec-2016

PHINDIRITBL

Number of buildings restored in Telavi, Kvareli and Dartlo (Number, Custom)


Baseline

Actual (Previous)

Actual (Current)

End Target

Value

0.00

210.00

210.00

150.00

Date

30-May-2012

06-Jun-2014

24-Dec-2014

31-Dec-2016

Baseline

Actual (Previous)

Actual (Current)

End Target

Value

0.00

54500.00

54900.00

30800.00

Date

30-May-2012

06-Jun-2014

24-Dec-2014

31-Dec-2016

PHINDIRITBL

Direct project beneficiaries (Number, Core)

2/9/2015

Public Disclosure Copy

Page 5 of 7

Public Disclosure Copy

The World Bank

Implementation Status & Results Report

Regional Development Project (P126033)

PHINDIRITBL

Female beneficiaries (Percentage, Core Supplement)


Baseline

Actual (Previous)

Actual (Current)

End Target

Value

0.00

28504.00

28504.00

16140.00

Date

30-May-2012

06-Jun-2014

24-Dec-2014

31-Dec-2016

Overall Comments

Data on Financial Performance


Disbursements (by loan)
Project

Loan/Credit/TF

Status

Currency

P126033

IBRD-81480

Effective

USD

Original

Revised

Cancelled

Disbursed

Undisbursed

Disbursed

60.00

60.00

0.00

52.37

7.63

87%

Key Dates (by loan)


Project

Loan/Credit/TF

Status

Approval Date

Signing Date

Effectiveness Date

Orig. Closing Date

Rev. Closing Date

P126033

IBRD-81480

Effective

20-Mar-2012

28-Mar-2012

31-May-2012

31-Dec-2016

31-Dec-2016

Cumulative Disbursements

2/9/2015

Public Disclosure Copy

Page 6 of 7

Public Disclosure Copy

The World Bank

Implementation Status & Results Report

Regional Development Project (P126033)

Restructuring History
There has been no restructuring to date.

Related Project(s)
There are no related projects.

2/9/2015

Public Disclosure Copy

Page 7 of 7