Professional Experience
1) CLIENT: OIL and NATURAL GAS CORPORATION, INDIA
COMPANY: TATA PROJECTS LTD, MUMBAI, INDIA
POSITION HELD: E&I ENGINEER
PERIOD: Feb 2013 Till date
PROJECT EXECUTED: FIRE WATER NETWORK, ONGC URAN.
Responsibilities: (INSTRUMENTATION)
Review of P & IDs, Cable Schedules and Instrument Installation Drawings and review of
Interfaces between PLCand Electrical switch gears, Fire & Gas and vendor Package PLCs.
Erection and Commissioning of PLC (Honeywell) Panel.
Loop checking & Functional checking as per Cause&Effect, Control Philosophy
Cable termination as per Cable schedule &JB schedule.
Calibration of Field Instruments like LT, PT Etc.
Supervise & monitor Contractors installation of Field Instrument & equipments.
Installation and Commissioning of Deluge System.
Resolving technical issues with Contractor related to Instrument Installations where
required.
Preparation of Documentation like RFI, Checklist, and Reports related all construction
Activity.
Preparing Bill of Material require for day to day construction activity for project execution.
Leading the contractor from construction phase to commissioning phase to complete the
systems and priority wise sub systems.
Hand on experience of HART (375/475) Communicator for Calibration & loop checking..
Supervising cable Tray Installation Activities
Responsibilities: (FIRE&GAS DETCTION SYSTEM)
Installation, Assembling &Commissioning of Siemens fire alarm panel.
Installation of Smoke Detector (HFP-11), MCP (HTRI-S), HTRI-R, RPM Fire Fighting
Telephone as Per Construction documents.
Understand the construction documents like Cable schedule, Loop Diagram.
Supervising the cable laying Activities as per Drawing and Cable Schedule.
Programming for Smoke Detector & Control Module Using DPU.
Loop checking & Functional checking as per Cause Effect, Control Philosophy.
Responsibilities: (Electrical)
Review of Electrical Drawings &SLD.
Installation & Internal wiring of 22Kv Isolator panels.
Installation & Internal Wiring of 6.6Kv Switchboard.
Installation & Internal Wiring of PMCC Panel.
Installation of DBs like PDB, UDB etc.
Installation of 7.5, 1MVA Transformers.
No Load Test & MRT of LT and HT Motors.
Testing of LT, HT Panels.
Cable lying as per SLD&Cable Schedule.
Termination of Control Cable as per Interconnection Schedule.
Documentation like RFI, Checklist, Reports.
Prepared cable cutting scheduled for 50 KMs.
Supervising installation activities.
Known the Operation of 22Kv/6.6Kv Panels
Responsibilities: (Instrumentation)
Cable tray installation under access floor
MCT frame installation
Laying of internal earthing, power, signal and field cables as per schedule
Installation of Cabinets and consoles
Testing& Termination of all cables
Preparing materials according to drawing
Installation of cable tray supports and tray routing as per given and typical drawing
Stub up installation as per given and typical drawing
Jbs installation as per given and typical drawing
Installation of field instruments as per P&I drawings
Involved in preparing for cable cross section.
Loop checking & Functional checking.
Preparation of cable drum cutting schedule.
Preparation of Bill of Material.
Key skills
MS OFFICE.
Microprocessor & microcontroller
Personal Skills
Excellent Leadership Skills
Personal Particulars
Father name
Date of birth
Passport no
: Ottapanavilai,
Ritapuram (P.O)
K.K.Dist,
Pin No 629159.
Kanyakumari District.
Declaration
I hereby assure that all the information furnished above is true to the best of
my knowledge.
Place :
Date
Yours faithfully,
: