Professional Documents
Culture Documents
INDICATIVE
Asof30September2014
Rated
TargetTesting& TargetCommercial
Project
Committed/
Location
Capacity
ProjectStatus
NameoftheProject
Commissioning
Operation
Proponent
Indicative
(MW)
COAL
1,230.00
Indicative
Indicative
DavaodelNorte20MW
CirculatingFluidizedBed
FDCUtilities,Inc.
BiomassCoalFired
ThermalPowerPlant
ZAM100MW
CirculatingFluidizedBed SanRamon
(CFB)CoalFiredPower PowerInc.
Station
Maco,Davaodel
Norte
SitioSanRamon,Bgry.
Talisayan,Zamboanga
City
20
AwaitingapprovalofsalefromERConproposedplantconnectionatDANECO69/13.2kVCanocotanSubstation;
Ongoingofsecuringofpermits;
ClearancetoUnderatakeGISfromDOEissuedon7June2012;
ProjectcostisPhp4.8B
March2015
March2015
(TargetTestingand
Commissioning)
100
Ongoingsecuringpermits;
OngoingnegotiationswithZAMCELCOforbaseloadsupply;PowerSalesAgreementforZAMCELCOis85MW,andZAMSURECO1is10MW;
AwaitingfortheERCapprovalofPSALwithZAMCELCO;
EPCContractbetweenOwnerandDaelimPhilippines,Inc.executedon27December2012;
LandLeaseAgreementwithZamboEcozonesignedon28January2013;DENRhadissuedECCinApril2012;
Ongoingsourcingoffinancingtheproject;
Groundbreakinglast27January2013;
NoticetoProceedtargetedonQ42013;
Projectcostis$292M
December2015
June2016
PRIVATESECTORINITIATEDPOWERPROJECTS(MINDANAO)
INDICATIVE
Asof30September2014
Committed/
Indicative
Indicative
NameoftheProject
600MWSMCDavao
PowerPlantProject
PhaseIII
Indicative
SibugueyPowerPlant
Project
Indicative
2x55MWBalingasag
ThermalPowerPlant
(CirculatingFluidized
BedCombustion(CFBC)
CoalFiredPowerPlant
Plant)
Indicative
300MWCoalFired
PowerPlant
Phase12x100MW
Phase21x100MW
Project
Proponent
SanMiguel
Consolidated
Power
Corporation
Location
Brgy.Culaman,
Malita,DavaodelSur
Philippine
NationalOil
Sibugay,Zamboanga
Company(PNOC
EC)
MinergyCoal
Corporation
OzamizPower
Generation,Inc.
Brgy.Mandangoa,
Balingasag,Misamis
Oriental
Brgy.Pulot,Ozamiz
City,Misamis
Occidental
Rated
Capacity
(MW)
600
ProjectStatus
Landacquisitioncompleted;
SecuredDENRECC(ECCCO13040010)on18June2013;
Ongoingsecuringofpermitsandotherregulatoryrequirements;
Ongoingnegotiationsforfinancingarrangements;
Ongoingcivilworksconstruction/installation;
ProjectStatusasof20March201420%completed;
TargetTesting& TargetCommercial
Commissioning
Operation
PhaseI
Unit1(150MW)
January2016
Unit2(150MW0
June2016
PhaseII
300MWDec
2018
PhaseI
Unit1(150MW)
January2016
Unit2(150MW0
June2016
(Testingand
Commissioning)
PhaseII
300MWDec
2019
100
TechnicalandeconomicfeasibilitystudywascompletedinJuly2011;
EligiblebidderforTransactionAdvisoron8August2012;
OngoingbidprocessingfortheEISconsultancyleadingtoECCapplicationandotherpermits;
ClearancetoUnderatakeGISfromDOEissuedon14October2011;
September2016
September2016
(TargetTestingand
Commissioning)
110
SECRegisteredonFebruary2013;CertificateofEndorsement(No.201307007)issuedon1August2013;
SiteEvaluationcompletedon14August2002;
OngoingsecuringofpermitsandotherregulatoryrequirementssuchasEIS/ECC;
Technicalreviewongoing;OfftakerCEPALCO(embeddedviadoubleckt138kVline);
MainEPCContractor:MitsubishiCorporation;MainSubcontractor:ToshibaPlantsSystemes*ServicesCorp.(TPSC);
TotalprojectcostP14,553B
January2017
January2017
(TargetTestingand
Commissioning)
300
PresentedplantotheLGUofOzamizandwasendorsedtheprojectthroughSangguniangPanglungsodResolutions;
iMinorrevisionsonFeasibilityStudy;TargetcompletionofFeasibilityStudybySeptember2014;
TopographicandBathymetricSurveyoftheproposedsiteaswellasthefirstTechnicalReviewbyEMBarecompletedonJune2014;CAAPapplication,NCIPCertificateof
NonOverlap,BOIapplicationanddetaileddevelopmentplansareallongoing;GeologicaldrillingwillbecompletedbyAugust2014;
Securingofrequiredlandandconversionis50%completed;
OngoingrequestforaCertificateofLandUseCompatabilityfromtheCityPlanningandDevelopmentOfficeofOzamizCity;Finalreportonthe1sttechnicalreviewwas
completedlast18August2014;CompletingrequirementsforCAAPapplication,EndorsementfromDOEtoNCIPfortheissuanceoftheCNOon9September2014,BOI
applicationanddetailedsitedevelopmentplansarestillonprocess;ClearancetoundertakeGISreleasedon6August2014;
1stPublicScopingwasalreadycompletedon28May2014;Landaquisitionandconversionisstillongoing.1stPhaseTargetCompletiononAugust2014;2ndPhaseand
LandConversionTargetCompletionOctober2014;
TargetCompletionofDENRrequirements(EnvironmentalImpactAssessment,EnvironmentalComplianceCertificateandAreaClearanceCertificateonSeptember2014;
DENRECCtobestarted;TargetdateofGroundbreakingforsitedevelopmentworksmov
BarangayandCityEndorsementacquiredlast7March2014and10March2014,respectively;
SECRegistrationobtained11Nov.2013;
TargetdateofGroundbreakingforsitedevelopmentworksmovedonDecember2014;
Negotiationswithprospectiveofftakersareongoing,1stphasetargetcompletionOctober2014;2ndPhaseTargetCompletionFebruary2015;
Negotiationswithforeignpartnersforfinancingarrangementsongoing;DetailedSiteDevelopmentPlansongoing;
SelectionofEPCContractorongoing;TargetawardingofEPCcontractbyDecember2014;
Phase12x
100MWMarch
2018
Phase21x
100MW2018
Phase12x
100MW
September2018
Phase21x
100MW2018
PRIVATESECTORINITIATEDPOWERPROJECTS(MINDANAO)
INDICATIVE
Asof30September2014
Committed/
Indicative
Indicative
NameoftheProject
300MWSMCDavao
PowerPlantProject
PhaseII
Project
Proponent
SanMiguel
Consolidated
Power
Corporation
Location
Rated
Capacity
(MW)
Brgy.Culaman,
Malita,DavaodelSur
300
ProjectStatus
Landacquisitioncompleted;
Ongoingsecuringofpermitsandotherregulatoryrequirements;Ongoingnegotiationsforfinancingarrangements
TargetTesting& TargetCommercial
Commissioning
Operation
December2018
December2018
(TargetTestingand
Commissioning)
PRIVATESECTORINITIATEDPOWERPROJECTS(MINDANAO)
INDICATIVE
Asof30September2014
Committed/
Indicative
NameoftheProject
Project
Proponent
Location
GEOTHERMAL
Indicative
Energy
Mindanao3Geothermal
Development
PowerProject
Corporation
Kidapawan,North
Cotabato
Rated
Capacity
(MW)
50.00
50
ProjectStatus
TargetTesting& TargetCommercial
Commissioning
Operation
Ongoingfeasibitystudy,resourceassessmentandstudiesinoptimalpowerplantcapacity;
TheprojectiswithintheDOEServiceContractGRESC#00910004;DENRECCobtained;
Landusepermitsobtained;LGUEndorsementongoing;Waterrightsecured;OngoingpreparationofDENRrequirementsforTLFLAg;TurnkeyContractspendingresultof
December2017
feasibilitystudy;TargetofcommissioningonDecember2017;
ClearancetoUnderatakeGISfromDOEissuedon7June2012;
Projectcostissubjecttotheresultofthefeasibilitystudy;
December2017
(TargetTestingand
Commissioning)
PRIVATESECTORINITIATEDPOWERPROJECTS(MINDANAO)
INDICATIVE
Asof30September2014
Committed/
Indicative
NameoftheProject
Project
Proponent
Location
HYDROPOWER
Indicative
Indicative
TagoloanHydropower
Bubunawan
HydroelectricPower
Project
FirstGen
Mindanao
Hydropower
Corp.
FirstGen
Mindanao
Hydropower
Corp.
Impasugong&
Sumilao,Bukidnon
BaungonandLibona,
Bukidnon
Rated
Capacity
(MW)
148.20
ProjectStatus
TargetTesting& TargetCommercial
Commissioning
Operation
39
IssuedConfirmationofCommercialityon02July2013;
Submissionoflackingrequirementse.g.permitsinprogress;
OngoingPreconstructionactivities;PreConstructionstage(93%completedasof30September2014)
October2015
October2015
(TargetTestingand
Commissioning)
23
IssuedConfirmationofCommercialityon02July2013;
AlreadysecuredLGUEndorsements,DENREnvironmentComplianceCertificate,NCIPCertificateandNWRBPermit;
AlsosubmittedFeasibilityStudyand5YrWorkPlan;
ClearancetoUnderatakeGISfromDOEissuedon28September2012;
BidsandtenderingfortheEPCstartedonApril2014;
Constructionissettostartonthe3rdquarterof2014;
OngoingPreconstructionactivities;
Ongoingconstruction(Preconstruction0%,Construction0%,Interconnection0%)completedasof30September2014;
October2015
October2015
(TargetTestingand
Commissioning)
PRIVATESECTORINITIATEDPOWERPROJECTS(MINDANAO)
INDICATIVE
Asof30September2014
Committed/
Indicative
NameoftheProject
Project
Proponent
Location
Rated
Capacity
(MW)
Baungon,Bukidnon
October2015
October2015
(TargetTestingand
Commissioning)
IssuedConfirmationofCommercialityon03July2013.
AlreadysecuredLGUEndorsements,DENRCertificateofNonCoverage,NCIPCertificateandNWRBPermit;
AlsosubmittedFeasibilityStudyand5YrWorkPlan;
ClearancetoUnderatakeGISfromDOEissuedon28September2012;
OngoingPreconstructionactivities;PreConstructionstage(20%completedasof30September2014);
Forimprovementofexistingaccessroad(logging)
December2015
December2015
(TargetTestingand
Commissioning)
January2017
January2017
(TargetTestingand
Commissioning)
IssuedConfirmationofCommercialityon09January2014;
Submissionoflackingrequirementse.g.permitsinprogress;
OngoingPreconstructionactivities;
Ongoingconstruction(Preconstruction0%,Construction0%,Interconnection0%)completedasof30September2014;
March2017
March2017
(TargetTestingand
Commissioning)
10
IssuedConfirmationofCommercialityon03June2013;
ClearancetoUnderatakeGISfromDOEissuedon5October2012;
Submissionoflackingrequirementse.g.permitsinprogress;
OngoingPreconstructionactivities;PreConstructionstage(93%completedasof30September2014)
June2018
June2018
(TargetTestingand
Commissioning)
ManoloFortich,
Bukidnon
10
IssuedConfirmationofCommercialityon03September2014;
Submissionoflackingrequirementse.g.permitsinprogress;
OngoingPreconstructionactivities;PreConstructionstage(93%completedasof30September2014)
TBD
TBD
Clarin,Misamis
Occidental
5.00
'IssuedConfirmationofCommercialityon09April2014;
Submissionoflackingrequirementse.g.permitsinprogress;
OngoingPreconstructionactivities;
Ongoingconstruction(Preconstruction0%,Construction0%,Interconnection0%)completedasof30September2014;
TBD
TBD
TBD
TBD
FirstGen
Mindanao
Hydropower
Corp.
Cabadbaran
HydroelectricPower
Project
FirstGen
Mindanao
Hydropower
Corp.
Cabadbaran,Agusan
delNorte
Indicative
NewBataan
EuroHydro
Power(Asia)
Holdings,Inc.
NewBataan,
CompostelaValley
Indicative
Pasonanca
Philcarbon,Inc.
ZamboangaCity
0.05
Indicative
OrientalEnergy
CulamanHydroelectric andPower
PowerProject
Generation
Corporation
ManoloFortich,
Bukidnon
Indicative
PhilnewHydro
MangimaHydroelectric
Power
PowerProject
Corporation
Indicative
Clarin
PhilnewHydro
Power
Corporation
PuyoHEP
FGENPuyo
HydroProject
Indicative
Indicative
TargetTesting& TargetCommercial
Commissioning
Operation
IssuedConfirmationofCommercialityon2July2013;
AlreadysecuredLGUEndorsementsDENRCertificateofNonCoverage,andConditionalWaterPermit;
AlsosubmittedFeasibilityStudyand5YrWorkPlan;
OngoingPreconstructionactivities;PreConstructionstage(93%completedasof30September2014)
Tumalaong
HydroelectricPower
Project
Indicative
ProjectStatus
9.75
IssuedConfirmationofCommercialityon24April2014;
Submissionoflackingrequirementse.g.permitsinprogress;
2.40 OngoingPreconstructionactivities;
Ongoingconstruction(Preconstruction0%,Construction0%,Interconnection0%)completedasof30September2014;
'IssuedConfirmationofCommercialityon12July2013;
Submissionoflackingrequirementse.g.permitsinprogress;
Jabonga,Agusandel
30.00 OngoingPreconstructionactivities;
Norte
Ongoingconstruction(Preconstruction100%,Construction10%,Interconnection0%)completedasof30September2014;
Groundbreakingheldon17April2013;
PRIVATESECTORINITIATEDPOWERPROJECTS(MINDANAO)
INDICATIVE
Asof30September2014
Committed/
Indicative
NameoftheProject
Project
Proponent
MatiI
PhilnewHydro
Power
Corporation
Indicative
Mati2
PhilnewHydro
Power
Corporation
Indicative
Mati3
PhilnewHydro
Power
Corporation
Indicative
Location
Rated
Capacity
(MW)
ProjectStatus
TargetTesting& TargetCommercial
Commissioning
Operation
IssuedConfirmationofCommercialityon09April2014;
Submissionoflackingrequirementse.g.permitsinprogress;
Claveria,Cagayande
2.00
OngoingPreconstructionactivities;
Oro
Ongoingconstruction(Preconstruction0%,Construction0%,Interconnection0%)completedasof30September2014;
TBD
TBD
CagayandeOro,
MisamisOriental
IssuedConfirmationofCommercialityon3September2014;
Submissionoflackingrequirementse.g.permitsinprogress;
4.00
OngoingPreconstructionactivities;
Ongoingconstruction(Preconstruction0%,Construction0%,Interconnection0%)completedasof30September2014;
TBD
TBD
CagayandeOro,
MisamisOriental
4.00
IssuedConfirmationofCommercialityon3September2014;
Submissionoflackingrequirementse.g.permitsinprogress;
OngoingPreconstructionactivities;
Ongoingconstruction(Preconstruction0%,Construction0%,Interconnection0%)completedasof30September2014;
TBD
TBD
PRIVATESECTORINITIATEDPOWERPROJECTS(MINDANAO)
INDICATIVE
Asof30September2014
Committed/
Indicative
NameoftheProject
Project
Proponent
Location
SOLAR
Indicative
CentrallaSolarPower
Project
Brgy.Centralla,
NVVogt
PhilippinesSolar Surallah,South
EnergyOne,Inc. Cotabato
Indicative
KirahonSolarPower
ProjectPhase1
KirahonSolar
Energy
Corporation
Indicative
Enfinity
DigosSolarPhotovoltaic Philippines
PowerProject
Renewable
Resources,Inc.
Brgy.
Kirahon,Villanueva,Mi
samisOriental
DigosCity,Davaodel
Sur
BIOMASS
Rated
Capacity
(MW)
28.75
6.25
12.5
10
ProjectStatus
AwardedwiththeSolarEnergyServiceContract(SESCNo.201310043)on05December2014;
NonFITProject,EmbeddedtoSOCOTECOI;
AcquiredECCfromDENR,CNOfromNCIP,ResolutionsofSupport(Barangay,Municipal,andProvincial),LandOwnership,MunicipalOrdinanceforLandUseConversion
fromAgriculturaltoCommercial/Industrial,ThirdPartyDistributionImpactStudy,andPowerPurchaseAgreementwithSOCOTECOI;
DeclarationofCommercialitywassubmittedon11April2014;
AcquiredtheDOECertificateofConfirmationofCommercialityon18June2014;
FiledforERC'sCertificateofCompliance;
SecuredClearancefromDOEfortheconductofGISon9October2013;
AwardedwiththeSolarEnergyServiceContract(SESCNo.201203004)on3May2012;
FiledDeclarationofCommercialityon09September2014;
AwardedwiththeSolarEnergyServiceContract(SESCNo.201209033)on12October2014;
AcquiredECCfromDENR;
AcquiredtheDOECertificateofConfirmationofCommercialitysubjecttoexecutionofAmendmentContracton11March2014;
ClearancetoUnderatakeGISfromDOEissuedon7August2013;
OngoingacquisitionofrelevantpermitsunderPreConstructionStageasperWorkPlan;
Ongoingconstruction;ConstructionStageasof30September2014(PreConstruction0%completed,Construction0%,Interconnection0%);Ongoingacquisitionof
relevantpermitsunderPreConstructionStageasperWorkPlan;
TargetTesting& TargetCommercial
Commissioning
Operation
March2015
March2015
(TargetTestingand
Commissioning)
May2015
May2015
(TargetTestingand
Commissioning)
October2015
October2015
(TargetTestingand
Commissioning)
9.00
MisamisOriental
BioEnergy
Corporations
MisamisOriental
10.80
Forconstruction;
ClearancetoUnderatakeGISfromDOEissuedon6June2014;
2015
2015
10MWKalilanganBio
KalilanganBio
EnergyCorporation
Energy
MultiFeedstockPower
Corporation
GeneratingFacility
Bukidnon
9.00
Forconstruction;
ClearancetoUnderatakeGISfromDOEissuedon28January2014;
2016
2016
10MWDonCarlosBio
DonCarlosBio
EnergyCorporation
Energy
MultiFeedstockPower
Corporations
GeneratingFacility
Bukidnon
9.00
Forconstruction;
2016
2016
Indicative
12MWBiomassPower
PlantProject
Indicative
Indicative
TotalIndicativeRatedCapacity
1,465.95