Professional Documents
Culture Documents
7-1
May 2005
7
7.1
Roadside Features
General
General
(ii)
Ditches
Figures 7.1 (a) and 7.1 (b) show design details for abrupt and
gradual slope change ditch designs. Ditch cross sections
which fall within the shaded regions of these figures are
considered traversable, not hazardous and do need not be
constructed at, or beyond, the clear zone distance.
7-2
May 2005
7-3
May 2005
This diagram is applicable to Rounded Ditches with bottom widths of $ 2.2 m, and
Trapezoidal Ditches with bottom widths $ 1.2m.
Revised Draft: 12 May 2005
7-4
May 2005
If the ditch bottom and side slopes are free of fixed objects a
non-preferred ditch cross section may, however, be
acceptable:
(b)
Back Slopes
(a)
The distance from the edge of the traffic lane to the start
of the ditch is 4.8 m. From Table 6.10 the clear zone
required for a 1:4 fill slope on a straight level section of
road is 6.0 to 7.5 m. This is 1.2 to 2.7 m less than what
is available.
From Table 6.10 the clear zone required for a 1:5 cut
slope on a flat, straight section of road is 3.5 to 4.5 m.
The distance available between the edge of the traffic
lanes and the start of the cut slope face is 3.6 m, which
is 0.1 m more to 0.9 m less than the clear zone required.
If the section of road has a history of accidents related
to vehicles hitting the back slope face, or the face of the
slope is rough and has the potential to cause snagging or
overturning of an impacting vehicle, then shielding it
with a longitudinal barrier should be considered as a
safety improvement.
7-5
May 2005
Structural Adequacy
Occupant Risk
7.3.4
(a)
(b)
Median Barriers
General
7.3.3
(c)
Special Conditions
Designers must apply engineering judgement to the nature
of all roadside hazards that require shielding by safety
barriers and specify higher performance barrier s whenever
they
are
considered
necessary.
Revised Draft: 12 May 2005
7-6
May 2005
Figure 7.4:
7.3.5
Standard Section
Transition
(km/h)
Nearside
(Left)
Offside
(Right)
# 70
1.5
1.0
80
2.0
1.0
90
2.5
1.5
$ 100
3.0
2.0
7-7
May 2005
Deflection Distance
7-8
May 2005
Characteristics
Type
Flexible
Application
Post spacing
Deflection
Mounting height
TL - 3
Varies with
type of barrier
Longitudinal
roadside/median
barrier
( typically 2.4
to 5.0 m)
TL - 3
Semi-rigid
Longitudinal
roadside barrier
Semi-rigid
Longitudinal
roadside barrier
1905 mm
1905 mm
1905 mm
1905 mm
TL - 3
TL - 4
Semi-rigid
Longitudinal
roadside barrier
Semi-rigid
Longitudinal
median barrier
TL - 3
TL - 4
Semi-rigid
Longitudinal
median barrier
1905 mm
Longitudinal
roadside barrier
N/A
N/A
TL - 4/5
Rigid
Longitudinal
median barrier
If height is reduced to
less than 725 mm by
pavement overlays
vehicles may roll over
the barrier.
7-9
May 2005
7.3.9
(a)
Terrain Effects
General
Kerbs
Figure 7.5:
Figure 7.6:
(c)
Side Slopes
7 - 10
May 2005
7.3.10
Flare Rates
7.3.11
(a)
General
Where:
Flare Rate
Inside Shy Line
Non-rigid
# 60
1:18
1:12
1:10
70
1:21
1:14
1:11
80
1:24
1:16
1:12
90
1:26
1:18
1:14
$100
1:30
1:20
1:15
L ADVANCE
L HAZARD
L OPPOSING
=
=
Figure 7.7: Length of Barrier Needed to Shield a Hazard on a Two-way Two-lane Road
7 - 11
May 2005
(b)
Runout Length
The runout lengths, LR, shown in Table 7.4 are from the
AASHTO Roadside Design Guide - Table 2.6.6. These
are based on actual field studies.
Design Speed
(km/h)
2000 - 6000
50
40
45
50
50
60
50
55
60
70
70
60
65
75
80
80
75
80
90
100
90
85
95
105
110
100
100
105
120
130
110
110
120
135
145
X
Over 6000
Runout Length - L R
(m)
Table 7.4:
(c)
800 - 2000
X
LA [ (b / a) x L1 ] L2
(b / a) (LA / LR )
Traffic Volume
(AADT)
Under 800
L1
LA L2
(LA / LR )
L
Y = LA A X
L
R
L1
L2
=
=
L3
LA
LC
LS
b/a
LR
X
Y
=
=
=
=
=
Figure 7.8: Length of Barrier Needed in Advance of a Hazard for Adjacent Traffic
Revised Draft: 12 May 2005
7 - 12
May 2005
(d)
2.
3.
Figure 7.9:
7 - 13
May 2005
(e)
(v)
(ii)
Figure 7.10:
(f)
Me t a l
beam
g u a r dra i l
is
manufactured in nominal 3.8 m
lengths so the length of rail scaled
should be rounded up to the nearest
multiple of this length.
7 - 14
May 2005
(g)
Figure 7.11:
(h)
Length of Barrier Needed to Shield a Hazard on a One-way Section of a Dual Carriageway Road
(i)
Figure 7.12:
Revised Draft: 12 May 2005
Recovery Area
7 - 15
May 2005
7.3.12
(a)
Median Barriers
AADT 5+
1.
2.
General
NOTES:
the design speed for new roads and the and the
85 th percentile operating speed on existing roads,
(i)
(ii)
1.
2.
AADT is:
2.
3.
4.
0.7 x K g x K C x AADT 5+
Where:
Kg
KC
7 - 16
May 2005
Figure 7.13:
Figure 7.14:
7 - 17
May 2005
7 - 18
May 2005
(c)
Given:
Median width
Design speed
=
AADT (two-way) =
Traffic Growth rate =
AADT 5+
=
=
% Trucks in AADT =
Minimum radius
=
Grade
=
Barrier offset
(i)
10
450 m (left hand curve)
- 3% (in the direction of
travel on the left hand
curve)
1.0 m (median shoulder)
Up Grade Direction
K C,
AADT 5M+
0.7 x K g x K C x AADT 5+
27,400
(d)
K G,
K C,
AADT 5M+
0.7 x K g x K C x AADT 5+
54,900
Section I
General
(iii) Section 2:
7 - 19
May 2005
(ivi) Section 3:
Figure 7.15:
7 - 20
May 2005
2.
3.
Figure 7.16:
(e)
Barrier Type
7 - 21
May 2005
7.3.13
(a)
X
LA ((b / a) x L1 ) L2
(b / a) (LA / LR )
Problem:
31.2 m
LA
Y LA
LR
14
145
14
70.5
(i)
Figure 7.17:
Bridge Piers on a
Two-lane Two-way Road
Given:
Barrier type
Design speed
AADT
Embankment slope
(i)
=
=
=
=
Opposing Traffic
W-beam
100 km/h
2850 vpd
Flat
Adjacent Traffic
Figure 7.19:
X
LA L2
(LA / LR )
6.5 6.1
(6.5 / 120)
7.4 m
7 - 22
May 2005
(b)
Problem:
Determine the roadside safety barrier requirements on
the outside of a horizontal curve to shield the hazard
shown on Figure 7.20.
vpd
Figure 7.20:
Given:
Design Speed
AADT
Embankment slope
Curve radius
Type of barrier
=
=
=
=
=
90 km/h
500 vpd
1:4
500 m
W-beam
Figure 7.21:
Revised Draft: 12 May 2005
7 - 23
May 2005
(c)
Problem:
Determine the length of barrier needed on the left hand
side for the one-way carriageway bridge approach
shown in Figure 7.22.
110 km/h
9000 vpd
1:4
Graphical Solution:
14 m
145 m
10.6 m (7.6 m plus 3 m of
bridge rail from line L A = L C )
Barrier offset L 2
Flare rate
=
=
3.2 m
15:1
Straight installation:
Figure 7.21:
Mathematical solution:
Clear zone L C = L A =
Runout length L R
=
Tangent section L 1 =
Given:
Bridge over river
Design speed =
AADT
=
Fill slope
=
X
LA L2
(LA / LR )
14 3.2
(14 / 145)
Flared installation:
X
LA ((b / a) x L1 ) L2
(b / a) (LA / LR )
14 ((1 / 15) x 10.6 ) 3.2
(1 / 15) (14 / 145)
14
LA
LR
14
145
70.5
2.
Length of Roadside Safety Barrier Required to Shield a Hazard Extending Beyond the Clear Zone
Revised Draft: 12 May 2005
7 - 24
May 2005
7.4
Breakaway Designs
7.4.1
Introduction
7 - 25
May 2005
Traffic Signs
Sign Components
7 - 26
May 2005
7.4.3
(a)
General
Rigid Support
(c)
Slip-base Poles
7 - 27
May 2005
7.4.4
(d)
7 - 28
May 2005
(b)
7.5.1
Introduction
7.5
(c)
7 - 29
May 2005
7.5.2
Drainage Concerns
7.5.3
Kerbs
Design Speed
Roadside Barriers
7 - 30
May 2005
7.5.4
(b)
7.5.6
(a)
General
7 - 31
May 2005
(b)
(c)
Structure Extension
7 - 32
May 2005
Figure 7.31 (a): Details of Nested W-beam Wood Post Guardrail over 3.8m Clear Span
7 - 33
May 2005
Figure 7.31 (b): Details of Nested W-beam Wood Post Guardrail over 5.7m Clear Span
7 - 34
May 2005
7.5.7
(b)
(a)
(c)
7 - 35
May 2005
Figure 7.32: Example of Inlet / Outlet Design for Parallel Drainage Structures
7 - 36
May 2005