STANDARD EQUIPMENT CAPABILITY ESTIMATES

ITEM NO.

TYPE OF WORK

EQUIPMENT USED

CAPABILITY ADOPTED

100

Clearing and Grubbing

Bulldozer

3200 - 4000 sq.m./day

102

Excavation
Compaction

Bulldozer
Road Roller

200 cu.m./day
240 - 320 cu.m./day

104

Embankment
Compaction
Quarrying

Payloader
Road Roller
Bulldozer

240 - 320 cu.m./day


240 - 320 cu.m./day
400 cu.m./day

105

Sub-grade Preparation
Compaction

Grader
Road Roller

2400 sq.m./day
240 - 320 cu.m./day

200

Aggregate Sub-Base Course Grader


Road Roller
Water Truck

2400 sq.m./day
240 - 320 cu.m./day
8000 sq.m./day

STANDARD MANUAL CAPABILITY ESTIMATES


ITEM NO.

TYPE OF WORK

MANPOWER REQT.

CAPABILITY ADOPTED

100

Canal Excavation
Backfilling

3.00 cu.m./day
2.00 cu.m./MD

103

Structure Excavation

1.5 cu.m./MD

200

Agg. Sub-Base Course


Spreading

2.50 cu.m./MD

500

504

RC Pipe Culverts
12"
18
24
30
36

Grouted Riprap

Stone Masonry
Laying of Materials
Concreting

Crew Foreman
Mason
Carpenter/Steelman
12 Laborers
1 bagger mixer
10 mins/bag

16 pcs/day
14 pcs/day
12 pcs/day
10 pcs/day
8 pcs/day

Crew Foreman
2 - mason
10 - Laborers
1 bagger mixer

7.50 cu.m./day

Boulders
Crew Foreman
2 - Mason
10 - Laboreres
1 bagger mixer

1.50 cu.m./day
6.00 cu.m./day

STANDARD SPECIFICATIONS FOR HIGHWAYS, BRIDGES AND AIRPORTS


PART I EARTHWORKS:
Item 100
Item 101
Item 102
Item 103
Item 104
Item 105
Item 106
Item 107

Clearing and Grubbing


Removal of Structures and Construction
Excavation
Structure Excavation
Embankment
Sub-grade Preparation
Compaction Equipment and Density Control Strips
Overhaul

PART II SUB-BASE & BASE COURSE:


Item 200
Aggregate Sub-base Course
Item 201
Aggregate Base Course
Item 202
Crushed Aggregate Base Course
Item 203
Portland Cement Stabilized Road Mix Base Course
Item 204
Asphalt Stabilized Road Mix Base
Item 205
Portland Cement Treated Plant Mix Base Course
Item 206
Aggregate Stockpile
PART III SURFACE COURSE:
Item 300
Item 301
Item 302
Item 303
Item 304
Item 305
Item 306
Item 307
Item 308
Item 309
Item 310
Item 311
-

Aggregate Surface Course


Bituminous Prime Coat
Bituminous Tack Coat
Bituminous Seal Coat
Bituminous Surface Treatment
Bituminous Penetration Macadam Pavement
Bituminous Road Mix Surface
Bituminous Plant Mix Surface Course-General
Bituminous Plant Mix Surface Course-Cold Land
Bituminous Plant Mix (Stocking Maintenance Mix)
Bituminous Concrete Surface Course, Hot Land
Portland Cement Concrete Pavement

PART IV BRIDGE CONSTRUCTION:


Item 400
Item 401
Item 402
Item 403
Item 404
Item 405
Item 406
Item 407
Item 408
Item 409
Item 410
Item 411
-

Piling
Railing
Timber Structures
Metal Structures
Reinforcing Steel
Structural Concrete
Pre-Stressed Concrete Structure
Concrete Structure
Steel Bridges
Welded Structural Steel
Treated and Untreated Timber
Paint

PART V DRAINAGE AND SLOPE PROTECTIONS STRUCTURES:


Item 500
Pipe Culverts and Storm Drains
Item 501
Under Drains
Item 502
Manholes, Inlets, and Catch Basin
Item 503
Metal Structures
Item 504
Riprap and Grouted Riprap
Item 505
Stone Masonry
Item 506
Hand Laid Rock Embankment
Item 507
Sheet Piles
Item 508
Concrete Slope Protection
Item 509
Gabions
PART VI MISCELLANEOUS:
Item 600
Item 601
Item 602
Item 603
Item 604
Item 605
Item 606
Item 607
Item 608
Item 609
Item 610
Item 611
-

Curb & Gutter


Side Walk
Monuments Marker and Guide Posts
Guard Rail
Fencing
Road Sign
Pavement Markings
Reflecting Pavement Stud
Top Soil
Springing
Sodding
Tree Plant

PART VII MATERIAL DETAILS:


Item 700
Item 701
Item 702
Item 703
Item 703-A
Item 704
Item 705
Item 706
Item 707
Item 708
Item 719
Item 710
Item 711
Item 712
Item 713
Item 714
-

Hydraulic Cement
Construction Lime
Bituminous Materials
Aggregates
Mineral Filler
Masonry Limit
Joint Minerals
Concrete Clay, Plastic & Fiber
Metal Pipe
Concrete Curing Materials & Admixture
Paints
Reinforcing Steel & Wide
Fence and Guard Rail
Structural Metal
Treated & Untreated Timber
Water

MANPOWER REQUIREMENT AND MINIMUM QUANTITY SURVEY


1. Formworks

Team:

1 Senior Carpenter
3 Junior Carpenter

for every 10 Teams provide 1 Supervisor

MQS: 20.16 sq. m./day/team for Fabrication


8.29 sq. m./day/team for Installation
2. Steelwork

Team:

1 Lead man
4 Helpers (Benders and Cutters)

MQS: 25 mm. Dia. = 5 to 6 m. length/day


10 mm. Dia. = 10 to 16 m length/day
3. Tileworks

Team:

1 Senior Mason (Places Tiles)


1 Laborer/Jr. Mason (Mixer/Placer)

MQS: 2 sq.m./day/team
4. Welding Works (structural steel/penetration)

Team

1 Senior Welder
2 Junior Welder

MQS: 200 kg. Or 0.20 metric tons/day/team

MANPOWER AND EQUIPMENT CAPABILITY/PROJECT PARAMETERS

Compaction of Existing Ground After Stripping

Production: 350 cu. m. hr

Equipment:

1 DG Cat Dozer
1 GT Dyna CC-20 Vibro Roller
Water Truck (3000 Gals.)
1 3 dia. Water Pump

crew

1 Operator
2 Drivers
2 Helpers

Excavation and Earthmoving


A. Excavation along Earth cuts

Production: 20 cu. m./hr


Equipment: 1 DG Dozer
Crew

1 Operator
6 10 Helper

Manual Labor: 2.50/cu.m./manday (soft)


1.50/cu.m./mandy (rock)
B. Filling with Compaction
Production: 120 cu. m./hr
Equipment: 1
1
1
1
Crew

Grader (120 G Cat)


GT Dyna CC-20 Vibro Roller
Water Truck (3000 gals.)
2 dia. Water Pump

5 Operators
2 Drivers

C. Hauling/Disposal of Stripped Earth


1) Distance: 320 300m

Production: 57 cu. m./hr


Equipment: 1 2 cu. yd. 950 Loader
2 6 to 8 cu. yd. Dump Trucks

2) Distance: 1 km

Production: 45 cu. m./hr


Equipment: 1 2 cu. yd. 950 Loader
2 6 to 8 cu. yd. Dump trucks
3) Distance: 2 km

Production: 35 cu. m./hr


Equipment: 1 2 cu. yd. 950 Loader
2 6 to 8 cu. yd. Dump Trucks
4) Distance: 3 km.

Production: 57 cu. m./hr.


Equipment: 1 2 cu. yd. 950 Loader
3 6 to 8 cu. yd. Dump Trucks
5) Distance: 4 km.

Production: 35 cu. m./hr.


Equipment: 1 - 6 to 8 cu. yd. 950 Loader
3 6 to 8 cu. yd. Dump Trucks
6) Distance: 5 km.
Production: 57 cu. m./hr.
Equipment: 1 2 cu. yd. 950 Loader
4 6 to 8 cu. yd Dump Trucks

CAPABILITIES OF EQUIPMENT
ITEM

TYPE OF WORK

CAPABILITY

1. Dozer

a)
b)
c)
d)
e)

2. Grader

a) sub-grading
b) spreading

300 sm/hr
50 cm/hr

3. Pay Loader

a) loading

30 cm/hr

4. Crane Shovel

a) loading

35 cm/hr

5. Sheep foot
Roller

a) static rolling (12 passes-15 cm lift)


b) vibratory rolling (4 passes-15 cm lift)

45 cm/hr
135 cm/hr

6. No. 3 Road
Roller

a) static rolling (6 passes-15 cm lift)

24 cm/hr

7. Tractor-drawn
Roller (1-D)

a) vibratory rolling (6 passes 2 cm lift)

240 cm/hr

8. Tander Roller

a) static rolling 96 passes-20 cm lift)

24 cm/hr

9. 5-T Dump truck

a) Hauling Common Borrow


b) Hauling
SEBC
(Selected
basecourse)
c) Hauling Concrete batch class A

10. 2 DT

Clearing
Stripping
Quarrying
Excavation
Pushing

a) Hauling Common Borrow


b) Hauling
SEBC
(Selected
basecourse
c) Hauling concrete batch class A

500 sm/hr
200 sm/hr
50 sm/hr
25 sm/hr
3 cm/hr

borrow,

3.5 cm /hr
5 cm/trip
3 batch/trip

borrow,

2.5 cm/trip
2 cm/trip
2 batch/trip

11. Buggy

a) Hauling concrete mix

6 cm/trip

12. Wheel Borrow

a) Hauling aggregate
b) Hauling concrete mix

2.5 cm/trip
1.7 cm/trip

13. Water Truck

a) Watering

1000 sm/hr

14. Asphalt
Distributor

a) Spraying asphalt prime coat

300 sm/hr

15. 165 Conc. Mixer

a) Mixing concrete

9 cm/hr

16. Rock Crusher

a) Crushing mixed sand and gravel

30 cm/hr

17. Conc. Vibrator

a) Vibrating concrete mix

40 cm/hr

18. Conc. Floor


Finisher

a) Finishing concrete floor

140 sm/hr

19. Scraper lowed

a) Hauling heap capacity

11 cm/trip

20. Percussion

a)
b)
c)
d)
e)

Drilling
Drilling
Drilling
Drilling
Drilling

hard rock
loose rock
lime stone
sticky clay
loose clay

0.75 f/hr
1 f/hr
1.25 f/hr
1.60 f/hr
2.50 f/hr

CONSTRUCTION WORK CAPACITIES IN MANHOUR

ITEM

TYPE OF WORK

CAPABILITIES

1. Earth works

a) Excavation
b) Backfill

2. Formworks

a)
b)
c)
d)
e)
f)
g)
h)
i)

Footings, gradeboams & columns


Beams, bond beams & floor slabs
Roof beams and bond beams
Roof slab
Edging (100) for roof
Grade slab edging (4)
Retaining walls
Stairs and landings
Form oil application

22 manhours/100 sf
26 manhours/100 sf
28 manhours/100 sf
31 manhours/100 sf
16 manhours/100 sf
14 manhours/100 sf
28 manhours/100 sf
23 manhours/100 sf
0.60 manhours/100 sf

3. Reinforcement

a) Reinforcement of footing up to
roofing____take an ave. of_____
b) floor slab
c) floor membrane

4 manhours/100 lbs
1.2 manhours/100 sf
1.4 manhours/100 sf

4. Concrete Work

a) Column, footings, wall


grade beams, grade slabs
b) Floor beam & bond beams
c) Floor slabs (suspended)
d) Roof beam & bond beams
e) Stairs
f) Roof slabs
g) Curing (water)
h) Equipment
1. Vibrator
2. Crane

3.13 4.10 manhours/cm


2.29 manhours/cm

footings,
1.31 manhour/cm
2.84 manhour/cm
2.62 manhour/cm
2.41 manhour/cm
2.62 manhour/cm
2.93 manhour/cm
2 manhour/day for 7 days
15 manhour/cm
3 cm/manhour

CAPABILITIES OF MANUAL LABOR

TYPE OF WORK

UNIT
1. One Man

a)
b)
c)
d)
e)
f)
g)
h)
i)

Excavation loam or sand


Excavation clay or heavy soil
Excavation of rock
Backfilling
Spreading, tampering & grading
Placing scramble fill
Placing binders
Clearing undergrowth and small brush
Clearing undergrowth and truss

CAPABILITY
0.76 cm/hr
0.61 cm/hr
0.33 cm/hr
1.22 cm/hr
2.09 cm/hr
4.78 cm/hr
9.56 cm/hr
40 sm/hr
20 sm/hr

2. One Mason & One a) Laying CHB and Adobe


helper
b) Cement finish

2 sm/hr
2.80 sm/hr

3. One Carpenter & a) Erecting forms


One helper
b) Removing forms

1.86 sm/hr
1.86 sm/hr

4. One Mechanic & a) Operational maintenance and repair of


One helper
engineering equipments

EMPIRICAL REQUIREMENTS FOR VARIOUS STRUCTURES


I.

Box Culverts
Forms
Bars
Nails
Tie Wire

=
=
=
=

60 bf/cm of concrete
80 kg/cm of concrete
1.5 kg/cm of concrete
0.80 kg/cm of concrete

=
=
=
=

60 bf/cm of concrete
120-150 kg/cm of concrete
2 kg/cm of concrete
1.1 kg/cm of concrete

II. Bridges
Forms
Bars
Nails
Tie Wire

III. Grouted Riprap


4 bags cement/cm of riprap
0.68 cm of sand/cm of riprap

3 equipments

DIESEL
FUEL

ENGINE OIL

GREASE

GEAR OIL

1. Payloader

10 liters/hr

3 liters/day

1 lb./day

1 liter/day

2. Bulldozer

12 liters/hr

3 liters/day

1 lb./day

1 liter/day

3. Road Grader

10 liters/hr

3 liters/day

1 lb./day

1 liter/day

2 liters/day

2 lbs./week

EQUIPMENT

4. Road Roller
(5 tons)

6 liters/hr

5. Road Roller
(5-8 tons)

5 liters/hr

2 liters/day

2 lbs./week

1 liter/week

6. Road Roller
(10-12 tons)

5 liters/hr

2 liters/day

1
liters/week

1 liter/week

4 liters/day

7. Crane Truck

GASOLINE

1 liter/day

12 liters/hr

1 liter/week

6 liters/hr

1 liter/week
brake fluid1pint/week

8 liters/hr

2 lbs./day
1 liter/day

8. Pneumatic
Tractor
9. Truck Tractor
with trailer

lb./day
2 kms./liter

1 lb./week
1 .5 liters/day

10. Water Truck


with Pump

11. Pave

1 liter/day

1 lb./day

6 liters/day

2 litters/day
1 lb./day

12. Dump truck

3 kms./liter

1 liter/day
1 lb./week

13. Tractor
Crawler (D-7)
14. Stake Truck 8
tons

80 liters/day

2 liters/day

2 liter/week
brake fluid1 pint/week
1 liter/day

2 lbs./day
1 liter/km

1 liter/day

liter/day
1 lb./day

15. Conc. Mixer 4


Bagger

liter/day

16. Jeep 4 wheel


drive

1 liter/day

60 liters/day
lb./day
lb./day

1 liter/day

30 liters/day

AVERAGE POL CONSTRUCTON FOR VARIOUS CONSTRUCTION EQUIPMENT/DAY


ACCOUNT & CONTRACT WORKS GUIDELINE

I. MECHANIZED ASPECT:
A. Clearing & Grubbing

PRODUCTION
DOZER
BOFSE
POWER

120
140
160
180
200

( SQ. M. /HR.

DENSE OF VEGETATION (NO. OF TREES/HAS.

0-50

51 100

101 - 200

201 - 250

251 & >

360
420
480
540
600

250
290
330
375
420

190
220
255
285
310

160
185
210
240
265

130
150
170
195
215

B. Excavation
B.1. CRANE

Common Materials

Pro. (cu. m/hr.) Bank Volume

Tonnages

10 15
15 20
20 25
25 - 30

Canal

Structure

Creek

15
25
30
35

10
15
20
25

10
15
20
25

B. 2. DOZER
Horse Power
120
140
160
180
200

Pro. (cu. m/hr.) Bank Volume


Canal
Structure
30
40
50
60
70

10
15
20
25
30

B. 3. BACKHOE
Production (cu. m/hr.) Bank Volume

Bucket

0.50
0.75
1.00
1.25
1.50

Canal

Structure

Creek

20
30
35
40
50

15
20
25
30
35

15
20
25
30
35

C. Quarrying
Production (cu. m/hr.) Bank Volume

Dozer
( H. P.)

Common

Aggregate

Col/Bol

140
160
18
200

40
50
60
75

30
40
55
70

10
15
20
25

Loose
Excavated Mat.
( cu .m.)
70
80
90
100

D. Loading
Bucket (cu. m.)
1.0-1.5
1.5-2.0
2.0-2.5
2.5-3.0

Production (cu.m/hr.) Bank Volume


Common
Aggregate
Cobbles/Boulders
70
100
130
150

80
110
140
160

30
40
50
60

E. Spreading
Grader (H.P)
80 100
100 125
125 150
150 - 175

Production (cu. m/hr.) Cmp.


Common
Aggregate
60
70
90
100

70
80
100
110

F. Side Borrow (Common Mat.)


Dozer (H.P)
80 100
100 125
125 150
150 175

Production (cu. m/hr.) Compacted Vol.


35
40
45
55

G. STR. BACKFILL w/Comp.

Dozer (H.P)

Production (cu. m/hr)


Compacted Vol.

140
160
180
200

50
70
80
90

H. Embankment Compaction
Cap. Cu. m/hr Comp. Volume
Tons
35
6 10
11 15

Vibratory

Static

60
70
80

40
50
60

I. Loading, Spot & Maneuver & Delay Time


Used Loader : 1.00 cu. m. Bucket

Dump Truck Capacity

Common Materials

Road Surface
Materials

4.00 cu. m.
6.00 cu. m.
8.00 cu. m.

10 min.
12 min.
17 min.

12 min.
15 min.
17 min.

Cobbles/
Boulders
15 min.
17 min.
20 min.

J. Average Speed of Dump Truck (Kilometer per hour)


Haul dist.
Good
Poor
Haul dist.
Good
Km.
Maintained Maintained
Km.
Maintained
Road
Road
Road
0.30
18.00
13.00
11.00
46.00
0.40
19.00
14.00
12.00
47.00
0.50
20.00
15.00
13.00
48.00
0.60
21.00
16.00
14.00
49.00
0.70
22.00
17.00
15.00
50.00
0.80
23.00
18.00
16.00
51.00
0.90
24.00
19.00
17.00
52.00
1.00
25.00
20.00
18.00
53.00
2.00
27.00
21.00
19.00
54.00
3.00
30.00
22.00
20.00
55.00
4.00
32.00
23.00
21.00
55.00
5.00
35.00
25.00
22.00
55.00
6.00
37.00
26.00
23.00
7.00
39.00
27.00
24.00
same speed
8.00
41.00
28.00
24.00
to all
9.00
43.00
29.00
26.00
succeeding
10.00
45.00
30.00
27.00
haul distance

Poor
Maintained
Road
30.50
31.00
31.50
32.00
32.50
33.00
33.50
34.00
34.50
35.00
35.00
35.00

NOTE: Free haul dist. is limited to 200m.

H. Demolition of Concrete:
300 CFM Compressor & two (2) Jackhammer
Cap. = 15.00 cu. m. /day for massive concrete
= 20.00 cu. m./day for slab & wall
160 CFM Compressor & two (2) Pavement Breakage
Cap. = 8.00 cu. m. /day for massive concrete
= 12.00 cu. m./day for slab & wall
L. Diving of Piles:
Steel Piles
: Crane 25 tons w/ 2-tons drop Hammer: Cap. = 20ml/hr
Conc. Piles
: Crane 25 tons w/ 7500 kgs. - m pile hammer
Cap
: 2.00 mt/hr. & 4.00 m/hr. for thick & thin concrete piles
M. Fuel & Oil Consumption
Equipment
Fuel
Liter/hr

Oil & Lub


road

DOZER
55 84HP
85 114HP
132 159HP
180 200 HP

12
15
17
23

0.24
0.33
0.40
0.50

BACKHOE
.10 45 m
.70 1.0cm
1.1-1.5cm

10
18
32

0.68
0.76
0.94

Equipment

GRADER
60-75hp
110-130hp
180-200hp

CRANE
10-15 tons
16-20 tons
21-25 tons
D. TRUCK
4-6 cu.m.
7-8 cu.m.

Fuel Liter /
hr.

Oil & Lub


Liter /hr.

14
15
18

0.25
0.28
0.50

6
10
12

0,25
0.40
0.50

7
9

0.25
0.30

Wh. Loader
.75 1.0cm
1.1 - 1.5cm
1.5 2.0cm

7
11
16

0.35
0.38
0.50

Compactor
Static
5 10 tons
11 20TC

5
7.5

0.25
0.40

Vibrator
1 3 tons
4 6 tons

4
8

0.30
0.50

Water Pump
2
4
6
8

1.5
4.0
6.5
9.0

0.05
0.08
0.10
0.15

MIXER
1 Bagger
2 Bagger
C. Vibrat.
Compressor
(cf m)

1
2
1

0,05
0.06
0.05

350-450
251-315

9
8

0.25
0.20

Water Truck

0.25

Cargo Truck
6-7 tons
8-10 tons

7
8

0.25
0.30

Farm Truck

0.20

II. MANUAL ASPECT


A. EXCAVATION
A.1. Common Material

TYPE OF WORK

Cap. (cu.m.) Depth of less


2m

Bank Volume excavation


more than 2m

3.50
3.00
1.5

3.00
2.50
2.00

Farmditche
Canal
Structure
A.2 Slight hd. Matl (Ind)

TYPE OF WORK

CAP. (cu. m/day/man) Bank


Volume

Canal
Structure

1.00
0.75

B. LOADING: Util. five (5) LABORERS

Total time per cubic meter

Sand & gravel


15 min.

Cobles
17 min

Boulder
20 min

C. UNLOADING: Util. 5 LABORER

Total time per cubic meter

Sand & gravel


11 min.

Cobles
12 min

Boulder
15 min

D. CUT, BEND & PLACE RSB

Structure

1 Steel man & 1 Helper


with bar cutter

Dam
Siphon
Bridge
Other

96 kgs/day
112 kgs/day
100 kgs/day
80 kgs/day

E. QUARRYING

Cu. m/day/man

Capability
Sand & Gravel
3.50

Cobles
2.50

Boulder
2.00

F. DEMOLITION OF CONCRETE
Slab & Wall
Massive Conc.

0.35 cu/day/man
0.20 cum/day/man

G. SCREENING OF AGGREGATES
Gravel
Sand
H. MANUAL BACKFILL
Cap :
2.00 cu.m./day/man
I. LAYING OF MATERIALS (cum/day/man)
Cobbles=2
Boulders=1.50
J. SPREADING OF AGGREGATE (cum/day/man)
Cap :
2.50

4.00 cum/day/man
6.00 cum/day/man

K. RUBBLE MASONRY (Concreting)


Crew:1-foreman, 2 mason
10-Laborer & L.E. Operator
Cap. = 6.00 cum/day
L. GROUTED RIPRAP
Crew:
1-Foreman, 2-Mason
10-Lab. & 1-L.E. Operator
Cap.:
7.50 cum./day
M. C.H.B. : Setting Cap. (sqm/d)
Crew:
1-Mason, 2 Laborer
: Fence : Building
4 CHB
: 14
: 10 = 125 pcs/day
6 CHB
: 10
: 8 = 100 pcs/day
N. CONCRETE LINING:
Crew: 1-foreman, 2 mason, 1
L.E. Operator 10-lab. w/ 1 Bagger mixer
Capability = 4.50 cu. m./day
O. INSTALLATION OF STEEL GATES
Crew 1-manson & 5 - Laborer
16x16 to 24x24
: 2 assy/day
above 24x24
: 1 assy/day
P. CONCRETE WORKS
P 1. Fabrication, Placing & dismantling of forms
Crew
: 2 - carpenter & 4 laborer : Cap. = 2.00 cu. m./day for 3000psi
:1 carpenter & 1 laborer : Cap. = 4.50 cu.m./day Canal lining
P 2. Concreting & Curing
P 2a With concrete mixer
Crew
: 1 1 foreman, 2 mason, 1 - L.E. Operator & 8 laborer
Cap.
= 3.50 cu. m./day for Class A : 4.50 cu. m./day for Class B.
=3.50 cu. m./day for Class C : 4.50 cu. m./day for Lean Concrete
P 2b. Without concrete mixer
Crew
: 1 foreman, 2 mason, and 10 laborer
Cap.
= 2.50 cu. m./day for Class A : 3.20 cu. m./day for Class B
=3.50 cu. m./day for Class C : 4.50 cu. m./day for Lean Concrete
Q. PLASTERING OF C.H.B. WALL
Crew : 2 mason and 2 laborer
Capability = 12 sq. m./day (one side only) = 150 pcs/day
Both sides
= 75 pcs/day

R. Reinforced Concrete Pipes

CREW
1 Foreman
1 Mason
1 Carp./Steel man
12 Laborers
with 1 Bagger Mixer

Capability

DIAMETER
In.

cm.

Fabrication

12
18
24
30
36
48

30
46
61
76
91
122

15
11
9
6
5
3

Installation

NOTE:
TIME OF MIXER/DAY=BAGS OF CEMENT /DAY X 10 MIN./BAG
60 MINUTES/HOUR

16
14
12
10
8
6

III. MATERIAL ASPECT


CLASS STRENGTH

A. CONCRETE
a) 3000 psi
b) 2400 psi
c) 2400 psi
Canal Lining
2400 psi

Max.
Aggregate
inches

Cement
bag/cum

Sand
Cum/cum

Gravel
Cum/cum

Boulder
Cum/cum

1.50
2.00
3.00

9.00
7.00
6.50

0.45
0.50
0.52

0.90
1.00
1.04

1.00

7.50

0.48

0.96

4.25

0.25

0.375

0.95

4.00

0.22

0.05

1.00

5.00

0.50

1.00

0.20

1.00

0.90

0.40

Tie wr.
Kgs/cum

Nail
Kgs/cum

B. Rubble Masonry
w/3000 psi
C. Grouted Riprap
D. Lean Concrete
1000 psi

E. Gravel Blanket
F. Filter Drain

G. Other Materials
C
L
A
S
S

A
A
A
A
A
C
A
A

TYPE OF STR

Strength
Psi

E. lumb.
Bdft/cum

1/2pl. wd
pcs/cum

Bridge/Flume
Siphon/box culvert
Other Struc. MC
Other Struc. T.Fac.
Rubble Masonry
Canal Lining
Dam
Dam

3000
3000
3000
3000
3000
2400
3000
2400

40
25
20
15
5
5
15
5

1.00
1.00
1.25
1.15
0.15
0.10
0.10

1.25%
1.20%
1.10%
1.10%
1.00%
1.00%

RSB
RSB
RSB
RSB

RSB
RSB

2.25
2.00
1.75
1.50
0.75
0.25
1.00
1.00

F. REINFORCE CONCRETE PIPES


Fabrication Materials
Diameter Cement
Inches
bag

12
18
24
30
36
42

Sand cu.m.

Gravel
cu.m.

G.I.
Sheet
L.F.

F. Lumber
bd.ft.

R.S.B.
kgs.

0.02
0.05
0.08
0.11
0.14
0.18

0.05
0.10
0.15
0.21
0.28
0.36

0.12
0.19
0.24
0.30
0.34
0.40

0.24
0.36
0.48
0.60
0.72
0.84

5.28
7.72
9.77
23.22
50.43
60.84

F. Lumber
Bdft.

CWN. &
TWIRE
Kgs

0.58
1.22
1.82
2.52
3.33
4.28

F.a Installation of R.C.PIPES


Diameter
inches

Cement
bag

12
18
24
30
36
42

0.21
0.45
0.72
0.93
1.11
1.32

Sand
Cu.m.

Gravel
Cu. m.

0.01
0.02
0.03
0.04
0.05
0.06

0.02
0.04
0.06
0.08
0.10
0.12

R.S.B.
kgs

3.65
4.52
5.26
6.01
6.79

2.00
2.00
3.00
3.00
4.00
4.00

G. PLASTERING C.H. BLOCK


SIZE

Materials per sq. m.


(for two side)
Sand
Cement
0.038
0.45

4&6
G.1. LAYING OF C.H.B.
SIZE

CEMENT
Bag/sqm.

SAND
Cu/sq.m.

4
6

0.55
1.07

0.047
0.091

0.20
0.20
0.30
0.30
0.40
0.40

IV. COSTING ASPECT:


A. Computation of Gross Rates for Agency Manual Labor per Day
G. R. = BRI + COLA + AA + IA + M + TI + EFSA + MA
Where
: GR=Gross rate per day BR1 = Basic Current Rate/day
BR2 = Basic Previous Rate per day

COLA :
AA
:
A1
:

T1
:
EL
:
EFSA :
NA
M
G.R

:
:
:

Cost of Living Allo. Per day=(P550/m)/(22d/m)=P25.00/day


Allowance per pay =0.10 BR1/day
Incentive Allo. Day=(( BRX30 + o.10BR x 30 + 550/Y))/
(12M/Y x 22DAY/MO.)
= P.01875BR1 + P3.125
Term Insurance/day = (P12.00/y)/(12m/yx22d/m) = P0.05/day
Earned Leaves/day = (BR1/dx30d/m)/ (12/yx22d/m) = P0.11bri1/d
Emergency Food Subsidy Allowance per day
= (P200/m (BR1-BR2) (22d/m) /(22d/m)/(22d/m) = P9.09/day BR1 + BR2
Medical Allowance per day = (P200/m)/(22d/m) = P9.09/day
Medicare (Govt. Share) per day = (P7.50/m)/(22d/m)=P0.34/d
BR1 + P25 +P0.10BR1 + P0.187BR1 + P3.125 + P0.05+P0.11BR1
+ P9.09 BR1 + BR2 + P9.09 + P0.34
= P0.3975BR1 + BR2 + P46.695