Federal Register / Vol. 73, No.

20 / Wednesday, January 30, 2008 / Notices 5537

operated in a run-of-river mode would filed, either a preliminary permit comments within the time specified for
consist of: (1) One new 400-foot-long, application or a development filing comments, it will be presumed to
120-inch-diameter steel penstock; (2) a application (specify which type of have no comments. One copy of an
new powerhouse and switchyard; (3) application). A notice of intent must be agency’s comments must also be sent to
two turbine/generator units with a served on the applicant(s) named in this the Applicant’s representatives.
combined installed capacity of 4 public notice.
p. Proposed Scope of Studies Under Kimberly D. Bose,
megawatts; and (4) appurtenant
facilities. The proposed Wickiup Dam Permit—A preliminary permit, if issued, Secretary.
project would interconnect with does not authorize construction. The [FR Doc. E8–1629 Filed 1–29–08; 8:45 am]
Midstate Electrical Cooperative’s term of the proposed preliminary permit BILLING CODE 6717–01–P
existing distribution system at the would be 36 months. The work
project site, and would have an average proposed under the preliminary permit
annual generation of 16 gigawatt-hours. would include economic analysis, DEPARTMENT OF ENERGY
l. This filing is available for review at preparation of preliminary engineering
the Commission in the Public Reference plans, and a study of environmental Federal Energy Regulatory
Room or may be viewed on the impacts. Based on the results of these Commission
Commission’s Web site at http:// studies, the Applicant would decide [Project No. 12974–000]
www.ferc.gov using the ‘‘eLibrary’’ link. whether to proceed with the preparation
Enter the docket number excluding the of a development application to Wright Patman Hydro, LLC; Notice of
last three digits in the docket number construct and operate the project. Application Accepted for Filing and
field to access the document. For q. Comments, Protests, or Motions To Soliciting Comments, Motions To
assistance, call toll-free 1–866–208– Intervene—Anyone may submit Intervene, and Protests
3676 or e-mail comments, a protest, or a motion to
intervene in accordance with the January 24, 2008.
FERCONLINESUPPORT@FERC.GOV.
For TTY, call (202) 502–8659. A copy is requirements of Rules of Practice and Take notice that the following
also available for inspection and Procedure, 18 CFR 385.210, .211, .214. hydroelectric applications have been
reproduction at the address in item h In determining the appropriate action to filed with the Commission and are
above. take, the Commission will consider all available for public inspection:
m. Competing Preliminary Permit— protests or other comments filed, but a. Type of Application: Preliminary
Anyone desiring to file a competing only those who file a motion to Permit.
application for preliminary permit for a intervene in accordance with the b. Project No.: P–12974–000.
proposed project must submit the Commission’s Rules may become a c. Date Filed: August 31, 2007.
competing application itself, or a notice party to the proceeding. Any comments, d. Applicant: Wright Patman, LLC.
of intent to file such an application, to protests, or motions to intervene must e. Name of the Project: Wright Patman
the Commission on or before the be received on or before the specified Dam Hydroelectric.
specified comment date for the comment date for the particular f. Location: The project would be
particular application (see 18 CFR 4.36). application. located on the Sulphur River in Bowie
Submission of a timely notice of intent r. Filing and Service of Responsive County, Texas. The Wright Patman Dam
allows an interested person to file the Documents—Any filings must bear in is owned and maintained by the U.S.
competing preliminary permit all capital letters the title Army Corps of Engineers.
application no later than 30 days after ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT g. Filed Pursuant to: Federal Power
the specified comment date for the TO FILE COMPETING APPLICATION’’, Act, 16 U.S.C. 791a–825r.
particular application. A competing ‘‘COMPETING APPLICATION’’, h. Applicant Contact: Mr. Brent
preliminary permit application must ‘‘PROTEST’’, and ‘‘MOTION TO Smith, Symbiotics, LLC, P.O. Box 535,
conform with 18 CFR 4.30 and 4.36. INTERVENE’’, as applicable, and the Rigby, ID 83442, Phone (208) 745–0834.
n. Competing Development Project Number of the particular i. FERC Contact: Patricia W. Gillis,
Application—Any qualified application to which the filing refers. (202) 502–8735.
development applicant desiring to file a Any of the above-named documents j. Deadline for filing comments,
competing development application must be filed by providing the original protests, and motions to intervene: 60
must submit to the Commission, on or and the number of copies provided by days from the issuance date of this
before a specified comment date for the the Commission’s regulations to: The notice.
particular application, either a Secretary, Federal Energy Regulatory All documents (original and eight
competing development application or a Commission, 888 First Street, NE., copies) should be filed with: Kimberly
notice of intent to file such an Washington, DC 20426. An additional D. Bose, Secretary, Federal Energy
application. Submission of a timely copy must be sent to Director, Division Regulatory Commission, 888 First
notice of intent to file a development of Hydropower Administration and Street, NE., Washington, DC 20426.
application allows an interested person Compliance, Federal Energy Regulatory Comments, protests, and interventions
to file the competing application no Commission, at the above-mentioned may be filed electronically via the
later than 120 days after the specified address. A copy of any notice of intent, Internet in lieu of paper; see 18 CFR
comment date for the particular competing application or motion to 385.2001(a)(1)(iii) and the instructions
application. A competing license intervene must also be served upon each on the Commission’s Web site under the
application must conform with 18 CFR representative of the Applicant ‘‘e-Filing’’ link. The Commission
4.30 and 4.36. specified in the particular application. strongly encourages electronic filings.
mstockstill on PROD1PC66 with NOTICES

o. Notice of Intent—A notice of intent s. Agency Comments—Federal, state, Please include the project number (P–
must specify the exact name, business and local agencies are invited to file 12974–000) on any comments or
address, and telephone number of the comments on the described application. motions filed.
prospective applicant, and must include A copy of the application may be The Commission’s Rules of Practice
an unequivocal statement of intent to obtained by agencies directly from the and Procedure require all intervenors
submit, if such an application may be Applicant. If an agency does not file filing documents with the Commission

VerDate Aug<31>2005 18:49 Jan 29, 2008 Jkt 214001 PO 00000 Frm 00044 Fmt 4703 Sfmt 4703 E:\FR\FM\30JAN1.SGM 30JAN1
5538 Federal Register / Vol. 73, No. 20 / Wednesday, January 30, 2008 / Notices

to serve a copy of that document on must submit to the Commission, on or ‘‘PROTEST’’, and ‘‘MOTION TO
each person in the official service list before a specified comment date for the INTERVENE’’, as applicable, and the
for the project. Further, if an intervenor particular application, either a Project Number of the particular
files comments or documents with the competing development application or a application to which the filing refers.
Commission relating to the merits of an notice of intent to file such an Any of the above-named documents
issue that may affect the responsibilities application. Submission of a timely must be filed by providing the original
of a particular resource agency, they notice of intent to file a development and the number of copies provided by
must also serve a copy of the document application allows an interested person the Commission’s regulations to: The
on that resource agency. to file the competing application no Secretary, Federal Energy Regulatory
k. Description of Project: The later than 120 days after the specified Commission, 888 First Street, NE.,
proposed project would utilize the comment date for the particular Washington, DC 20426. An additional
existing U.S. Army Corps of Engineers’ application. A competing license copy must be sent to Director, Division
Wright Patman Dam and would consist application must conform with 18 CFR of Hydropower Administration and
of: (1) A proposed 339-foot-long, 144- 4.30 and 4.36. Compliance, Federal Energy Regulatory
inch-diameter steel penstock; (2) a p. Notice of Intent—A notice of intent Commission, at the above-mentioned
proposed powerhouse containing one must specify the exact name, business address. A copy of any notice of intent,
generating unit with an installed address, and telephone number of the competing application or motion to
capacity of 5-megawatts; (3) a prospective applicant, and must include intervene must also be served upon each
switchyard; (4) a proposed 2-mile-long, an unequivocal statement of intent to representative of the Applicant
25-kV transmission line; and (5) submit, if such an application may be specified in the particular application.
appurtenant facilities. The proposed filed, either a preliminary permit t. Agency Comments—Federal, state,
project would have an estimated annual application or a development and local agencies are invited to file
generation of approximately 16- application (specify which type of comments on the described application.
gigawatts and would be sold to a local application). A notice of intent must be A copy of the application may be
utility. served on the applicant(s) named in this obtained by agencies directly from the
l. Location of Application: A copy of public notice. Applicant. If an agency does not file
the application is available for q. Proposed Scope of Studies Under comments within the time specified for
inspection and reproduction at the Permit—A preliminary permit, if issued, filing comments, it will be presumed to
Commission in the Public Reference does not authorize construction. The have no comments. One copy of an
Room, located at 888 First Street, NE., term of the proposed preliminary permit agency’s comments must also be sent to
Room 2A, Washington, DC 20426, or by would be 36 months. The work the Applicant’s representatives.
calling (202) 502–8371. This filing may proposed under the preliminary permit
also be viewed on the Commission’s would include economic analysis, Kimberly D. Bose,
Web site at http://www.ferc.gov using preparation of preliminary engineering Secretary.
the ‘‘eLibrary’’ link. Enter the docket plans, and a study of environmental [FR Doc. E8–1631 Filed 1–29–08; 8:45 am]
number excluding the last three digits in impacts. Based on the results of these BILLING CODE 6717–01–P
the docket number field to access the studies, the Applicant would decide
document. For assistance, call toll-free whether to proceed with the preparation
1–866–208–3676 or e-mail of a development application to DEPARTMENT OF ENERGY
FERCOnlineSupport@ferc.gov. For TTY, construct and operate the project.
call (202) 502–8659. A copy is also r. Comments, Protests, or Motions To Federal Energy Regulatory
available for inspection and Intervene—Anyone may submit Commission
reproduction at the address in item h comments, a protest, or a motion to [Docket No. CP08–52–000]
above. intervene in accordance with the
m. Individuals desiring to be included requirements of Rules of Practice and Caledonia Energy Partners, L.L.C.;
on the Commission’s mailing list should Procedure, 18 CFR 385.210, .211, .214. Notice of Application
so indicate by writing to the Secretary In determining the appropriate action to
of the Commission. take, the Commission will consider all January 24, 2008.
n. Competing Preliminary Permit— protests or other comments filed, but Take notice that on January 14, 2008,
Anyone desiring to file a competing only those who file a motion to Caledonia Energy Partners, L.L.C.
application for preliminary permit for a intervene in accordance with the (Caledonia), 2001 Timber Creek Road,
proposed project must submit the Commission’s Rules may become a Flower Mound, TX 75028, filed in
competing application itself, or a notice party to the proceeding. Any comments, Docket No. CP08–52–000, an
of intent to file such an application, to protests, or motions to intervene must application under section 7(c) of the
the Commission on or before the be received on or before the specified Natural Gas Act (NGA), to expand the
specified comment date for the comment date for the particular Caledonia Storage Facility by
particular application (see 18 CFR 4.36). application. developing a depleted production
Submission of a timely notice of intent Comments, protests and interventions reservoir as an additional gas storage
allows an interested person to file the may be filed electronically via the field; constructing a pipeline lateral to
competing preliminary permit Internet in lieu of paper. See 18 CFR connect the new field with the existing
application no later than 30 days after 385.2001(a)(1)(iii) and the instructions storage facility; and installation of a
the specified comment date for the on the Commission’s Web site at http:// total of 10,000 Hp of additional
particular application. A competing www.ferc.gov under the ‘‘e-Filing’’ link. compression which will allow
mstockstill on PROD1PC66 with NOTICES

preliminary permit application must s. Filing and Service of Responsive Caledonia to increase its maximum
conform with 18 CFR 4.30 and 4.36. Documents—Any filings must bear in allowable operating pressure to 2,518
o. Competing Development all capital letters the title psia. The expanded facilities will
Application—Any qualified ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT increase Caledonia’s maximum total
development applicant desiring to file a TO FILE COMPETING APPLICATION’’, storage capacity from 11.7 Bcf to 16.9
competing development application ‘‘COMPETING APPLICATION’’, Bcf and its maximum daily withdrawal

VerDate Aug<31>2005 18:49 Jan 29, 2008 Jkt 214001 PO 00000 Frm 00045 Fmt 4703 Sfmt 4703 E:\FR\FM\30JAN1.SGM 30JAN1