Professional Documents
Culture Documents
1.0
1.1That the Contractor agrees to provide and supply all labor and equipment required to
complete the construction of the building as described in this construction contract;
1.2
That the Contractor agrees to provide all materials required to construct the Sulu
Electric Cooperative Board Conference Hall as per approved plans and specifications.
The Project is to be located at Suleco Compound, Bus-bus St., Jolo, Sulu (see Site
Development Plan);
1.3
That the Contractor agrees to provide full-time Site Engineer and other relevant
construction personnel to assure quality of the construction;
1.4
The Owner assures that the property where the building is to be constructed is owned
by SULECO and that it is free from liens or encumbrances on the property.
Page 1
3.4
That should an installment amount has not been paid within (15) Fifteen days after the
due date the contractor has the right to stop work and may proceed until after the payment
has been made and the funds have been verified and cleared;
3.5
That should the Owner cease making payment the Contractor has the right to seek
legal action against the Owner only until after all meetings and negotiations has been
exhausted.
4.0
4.1
That the Contractor agrees to complete the construction within 120 Calendar days
from date of the receipt of 30% mobilization retainer per item 3.2 under payments;
4.2
That request for extension of turn-over date may be granted should the grounds be
heavy rains due to typhoon and other natural calamities that are classified as Acts of God.
5.0
Site Preparation
5.1
Per this construction contract the Owner shall ensure there is a cleared area for a
bunkhouse as staff house and for storage of construction materials and equipment. Access for
the deliveries of materials and all of the equipment shall be granted;
5.2
The Owner also ensures the construction site is properly zoned and cleared for the
construction and the boundaries of the property identified;
5.3
Permits for construction and other Government clearance and documents shall be paid,
obtained and expedited by the Owner unless otherwise specified in this Contract.
6.0 Utilities
6.1
In order for construction to begin and continue the Owner shall provide waterlines to
the construction site, however bills for volume used for the construction shall be for the
account of the Contractor.
6.2
As per this construction contract the Owner will also ensure electricity access with at
least one 220 amp outlets.
6.3
The Owner agrees to temporarily connect gas, oil, electrical and water to the new
construction prior to connecting permanent lines. The Contractor will add utility facilities for
an extra fee as an addendum to the original contract.
7.0
Completion
7.1
Per item 4.1, the project shall be completed in 120 days. The Owner will not take
possession of the completed construction until all payments relative to this contract
agreement has been made.
7.2
Should the owner occupy the new building site prior to completion of the construction
contract, the Contractor shall assume that the Owner has decided the construction is
complete and satisfactory for occupancy.
8.0
Workmanship Guaranty
MBTUTTUH ARCHITECTS+PARTNERS
Page 2
8.1
The contractor shall guaranty the workmanship (e.g. roof leaks, masonry cracks, paint
chalking or flaking, sanitary and waterlines) from any defects for a period of (240) Two
Hundred Forty days from completion/turnover date. The same however shall be subject to
verification if the said defect/s were caused by faulty installation/fabrication or of excessive
abnormal use.
For the Owner :
Ms. Peraida T. Jalani
General Manager, SULECO
Date___________________
Date___________________
______________________________________________________________________________________________
NOTARY PUBLIC
MBTUTTUH ARCHITECTS+PARTNERS
Page 3