CALENDARIO VALORIZADO

MEJORAMIENTO E IMPLEMENTACION DEL PUESTO DE SALUD DE HUANCA HUANCA,DE LA PROVINCIA DE ANGARAES-HUANCAVELICA


MUNICIPALIDAD DISTRITAL DE HUANCA HUANCA
NOEMI BELINDA RIVEROS IZARRA
JUNIO DE 2015
01-06-15 AL 30-06-15
30 DIAS
UND

DIAS

METRADO

PRECIO
UNIT. S/.

PARCIAL S/.

METRADO

CARTEL DE IDENTIFICACION DE LA OBRA


ALMACEN Y CASETA DE GUARDIANIA
MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS
SEGURIDAD Y SALUD EN EL TRABAJO
LIMPIEZA DEL TERRENO MANUAL
TRAZO,NIVELACION Y REPLANTEO PRELIMINAR
TRAZO,NIVELACION Y REPLANTEO DURANTE EL PROCESO DE LA OBRA
MOVIMIENTO DE TIERRAS
EXCAVACION PARA ZAPATAS EN TERRENO NORMAL
EXCAVACION PARA CIMIENTOS HASTA 1.00m TERRENO NORMAL
EXCAVACION PARA SARDINEL EN TERRENO NORMAL
EXCAVACION PARA CUNETAS EN TERRENO NORMAL
RELLENO COMPACTADO MANUAL MATERIAL PROPIO
NIVELACION INTERIOR APISONADO MANUAL
ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m)
ELIMINACION DE DESMONTE CON EQUIPO
OBRAS DE CONCRETO SIMPLE
SOLADO CONCRETO e=4" M=1:12
CIMIENTOS CORRIDOSMEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA
CONCRETO 1:8+25%PM PARA SOBRECIMIENTOS

m2
m2
und

120
120.00
120.00

1.00
5.00
1.00

151.10
100.00
1800.00

151.10
500.00
1800.00

0.25
0.25
0.25

m2
m2
m2

3.00
2.00
2.00

230.24
230.24
230.24

1.07
6.43
6.66

246.36
1480.44
1533.40

1.00
1.00
0.09

m3
m3
m3
m3
m3
m2
m3
m3

2.00
4.00
1.00
1.00
1.00
1.00
6.00
2.00

3.25
42.20
1.79
4.59
4.36
237.51
171.64
171.64

21.37
14.98
13.10
26.12
19.68
1.15
318.98
26.12

1.00
1.00

m2
m3
m3

1.00
1.00
1.00

3.25
38.00
7.36

11.34
202.54
228.39

69.45
632.16
23.45
119.89
85.80
273.14
54749.73
4483.24
0.00
36.86
7696.52
1680.95

ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO HASTA 0.30 m

m2

6.00

67.36

40.41

2722.02

0.17

CONCRETO EN FALSO PISO MEZCLA 1:8 CEMENTO-HORMIGON E=4"


VEREDAS
CONCRETO 1:8 CEMENTO-HORMIGON E=4"
ENCOFRADO Y DESENCOFRADO EN VEREDAS
SARDINEL
CONCRETO f'c=175 kg/cm2 PARA SARDINEL
ENCOFRADO Y DESENCOFRADO EN SARDINEL
CUNETAS
CONCRETO f'c=175 kg/cm2 PARA CUNETAS
ENCOFRADO Y DESENCOFRADO EN CUNETAS
CONCRETO ARMADO
ZAPATAS
CONCRETO PARA ZAPATAS f'c=210 kg/cm2
ACERO fy=4200 kg/cm2 GRADO 60 EN ZAPATAS
COLUMNAS
CONCRETO PARA COLUMNAS f'c=210 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS
ACERO fy=4200 kg/cm2 GRADO 60 EN COLUMNAS
COLUMNETAS
CONCRETO EN COLUMNETAS f'c=175 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS
ACERO fy=4200 kg/cm2 GRADO 60 EN COLUMNETAS
VIGAS
CONCRETO EN VIGAS f'c=210 kg/cm2
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS
ACERO fy=4200 kg/cm2 GRADO 60 EN VIGAS
VIGUETAS DE AMARRE
CONCRETO f'c=210 kg/cm2 PARA VIGAS
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS
ACERO fy=4200 kg/cm2 GRADO 60 EN VIGA
VIGA CANAL
CONCRETO f''c=210 kg/cm2 PARA VIGAS
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS
ACERO fy=4200 kg/cm2 GRADO 60 EN VIGA
LOSA ALIGERADA
CONCRETO f'c=210 kg/cm2 PARA LOSAS ALIGERADAS
ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS
ACERO fy=4200 kg/cm2 GRADO 60
LADRILLO HUECO DE ARCILLA h=12cm PARA TECHO ALIGERADO
MUROS Y TABIQUES DE ALBAILERIA
MURO DE LADRILLO KK 18 HUECOS CABEZA
MURO DE LADRILLO KK-18 HUECOS SOGA
REVOQUES ENLUCIDOS Y MOLDADURAS
TARRAJEO PRIMARIO RAYADO CON CEMENTO-ARENA
TARARJEO EN MUROS INTERIOR
TARRAJEO EN MUROS EXTERIORES
BRUAS DE 1"
CIELORRASOS
CIELORRASOS CON MEZCLA DE C:A CINTAS e=1.5cm
CIELO RASO SUSPENDIDO DE BALDOSA ACUSTICA
PISOS Y PAVIMENTOS
CONTRAPISO DE 40mm BASE 3 cm mezc. 1:5 acab 1cm,pasta 1:2
PISO CERAMICO 30 X 30 DE ALTO TRANSITO
CONTRAZOCALOS
CONTRAZOCALO DE CERAMICO 20 X 30 CM A 45
CONTRAZOCALO SANITARIO DE LOSETA COLOR CLARO 10X30 cm
ZOCALOS
ZOCALO DE CERAMICO DE 20X30CM

m2

3.00

127.60

34.94

m2
m2

1.00
1.00

95.52
8.41

23.47
37.59

m3
m2

1.00
5.00

2.69
36.84

354.11
49.27

m3
m2

1.00
3.00

3.88
36.84

338.96
37.89

m3
kg

1.00
1.00

1.62
150.98

318.98
5.64

m3
m2
kg

1.00
6.00
4.00

3.48
55.70
1234.87

318.98
37.89
5.64

m3
m2
kg

1.00
6.00
2.00

2.57
53.44
574.00

318.98
37.89
5.64

m3
m2
kg

1.00
8.00
6.00

10.49
107.66
1480.02

318.98
37.89
5.64

m3
m2
kg

1.00
1.00
2.00

0.49
7.28
57.16

318.98
37.89
5.64

m3
m2
kg

1.00
5.00
2.00

3.87
60.30
581.20

318.98
37.89
5.64

m3
m2
kg
und

1.00
4.00
1.00
1.00

2.57
53.44
374.18
467.98

318.98
37.89
5.64
3.42

m2
m2

8.00
2.00

167.09
26.48

132.66
12.77

m2
m2
m2
m

6.00
9.00
9.00
16.00

70.87
206.66
98.11
349.84

10.50
12.77
17.46
11.82

m2
m2

7.00
6.00

44.09
158.65

43.75
12.17

m2
m2

6.00
1.00

125.95
32.89

12.17
130.00

m
m

5.00
5.00

98.40
98.40

11.82
11.82

m2

4.00

66.03

43.75

4458.34
0.00
2241.85
316.13
0.00
952.56
1815.11
0.00
1315.16
1395.87
0.00
0.00
516.75
851.53
0.00
1110.05
2110.47
6964.67
0.00
819.78
2024.84
3237.36
0.00
3346.10
4079.24
8347.31
0.00
156.30
275.84
322.38
0.00
1234.45
2284.77
3277.97
0.00
819.78
2024.84
2110.38
1600.49
0.00
22166.16
338.15
0.00
744.14
2639.05
1713.00
4135.11
0.00
1928.94
1930.77
0.00
1532.81
4275.70
0.00
1163.09
1163.09
0.00
2888.81

m2

3.00

38.08

12.17

463.43

m2

1.00

13.26

110.00

m2
m

4.00
1.00

190.61
17.25

110.00
11.82

m2
m2

1.00
1.00

3.43
7.94

110.00
130.00

pza
und

2.00
1.00

40.00
4.00

15.62
42.00

m2

1.00

23.70

6.55

m2
m2
m2

7.00
4.00
1.00

174.22
98.11
6.67

6.55
6.55
6.55

pto
pto
pto

7.00
3.00
7.00

13.00
5.00
13.00

62.07
62.08
64.95

m
m

3.00
47.00

55.25
185.97

11.82
11.82

0.00
1458.60
0.00
20967.10
203.90
0.00
377.30
1032.20
0.00
624.80
168.00
0.00
155.24
0.00
1141.14
642.62
43.69
0.00
806.91
310.40
844.35
0.00
653.06
2198.17

m
m
m

5.00
3.00
4.00

85.90
44.95
75.90

11.82
11.82
11.82

1015.34
531.31
897.14

pto
pto

7.00
2.00

14.00
3.00

62.07
62.08

868.98
186.24

m
m

47.00
47.00

8.00
34.36

11.82
11.82

94.56
406.14

0.06
0.06

pza
pza

47.00
47.00

17.00
4.00

15.62
15.62

265.54
62.48

0.06
0.06

pza
pza

47.00
47.00

3.00
2.00

15.62
15.62

46.86
31.24
221410.34

0.06
0.06

NOMBRE DE TAREA

JULIO DE 2015
01-07-15 AL 31-07-15
31 DIAS

PARCIAL

METRADO

PARCIAL

AGSTO DE 2015
01-08-15 AL 31-08-15
31 DIAS
METRADO

PARCIAL

SETIEMBRE DE 2015
01-09-15 AL 28-06-15
28 DIAS
METRADO

PARCIAL

MEJORAMIENTO E IMPLEMENTACION DEL PUESTO DE SALUD DE HUANCA


HUANCA,DE LA PROVINCIA DE ANGARAES-HUANCAVELICA
PUESTO DE SALUD
OBRAS PROVISIONALES

ZOCALO DE CEMENTO SIN COLOREAR H=0.80 PULIDO,e=2.0cm, mezcla 1:5 c:a


ENCHAPES
ENCHAPE DE MAYOLICA 0.20X0.30
CUBIERTAS
COBERTURA ARTICULADA TIPO TEJA ANDINA
CUMBRERA ARTICULADA PARA TEJA ANDINA
CARPINTERIA METALICA Y HERRERIA
MAMPARA DE ALUMINIO SEGUN DISEO
PUERTA METALICA SEGUN DISEO
CERRAJERIA
BISAGRA ALUMINIZADA CAPUCHINA DE 4"X4"
CHAPA PARA BAO CON SEGURO INTERIOR Y PERILLA O MANIJA
VIDRIOS,CRISTALES Y SIMILARES
SC VIDRIOS 6mm COLOR BRONCE CRUDO C/ACCESORIOS SISTEMA NOVA
PINTURA
PINTURA AL LATEX EN MUROS INTERIOTES C/LATEX LAVABLE
PINTURA LATEX EN MUROS EXTERIORES
PINTURA LATEX EN CIELO RASO
INSTALACION ELECTRICA
SALIDA DE TECHO (CENTRO DE LUZ)
SALIDA PAAR TECHO PARA ARTEFACTOS TIPO SPOT-LIGHT
SALIDA PARA INTERRUPTOR SIMPLE
CANALIZACION Y/O TUBERIA
CANALIZACION DE TUBERIA ENTERRADA 20X30cm
TUBERIA DE PVC-SEL 3/4"
CONDUCTORES Y/O CABLES
CONDUCTOR EN TUBERIA
CONDUCTOR TW 2.5MM2
CONDUCTOR TW 6.0 MM2
CONDUCTOR DE COBRE A POZO TIERRA
INSTALACIONES SANITARIAS
DESAGUE Y VENTILACION
SALIDA DE DESAGUE DE PVC 2"
SALIDA DE DESAGUE DE PVC 4"
REDES DE DISTRIBUCION
TUBERIA DE PVC SAL 4"
TUBERIA PVC SAL 2"
ACCESORIOD
CODOS
CODO PVC SAL 2"X90
CODO PVC SAL 2"X45
YESS
YEE PVC SAL 2"X2"
YEE PVC SAL 4"

0.33

1.00
1.00

1.00
1.00

1.00

1.00

37.78
125.00
450.00
246.36
1,480.44
139.40
69.45
632.16
18,248.08
36.86
7,696.52
453.74
516.75
851.53
6,964.67
3,237.36
-

25.83%
25.83%
25.83%

31.31%

100.00%
100.00%
33.33%
100.00%

100.00%
83.33%

100.00%
100.00%

100.00%
100.00%

40.00%

100.00%
100.00%

39.03
129.17
465.00
480.15
85.80
273.14
18,248.08
4,483.24
1,680.95
2,268.27
1,110.05
2,110.47
819.78
2,024.84
1,631.69
22,166.16
338.15
-

31.31%

100.00%
100.00%

33.33%

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
60.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%
100.00%
28.58%

39.03
129.17
465.00
480.15
23.45
119.89
18,248.08
4,458.34
2,241.85
316.13
952.56
1,815.11
1,315.16
1,395.87
3,346.10
2,447.54
8,347.31
156.30
275.84
322.38
1,234.45
2,284.77
3,277.97
819.78
2,024.84
2,110.38
1,600.49
744.14
2,639.05
1,713.00
4,135.11
551.24
-

28.28%

71.42%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%

35.26
116.67
420.00
433.69
1,377.70
1,930.77
1,532.81
4,275.70
1,163.09
1,163.09
2,888.81
463.43

COSTO ACUMULADO MENSUAL


GASTOS GENERALES (10.00%)
UTILIDAD (7%)
SUBTOTAL
IGV(18%)

48,419.61
8,715.53

70,670.28
12,720.65

97,151.36
17,487.25

42,802.43
7,704.44

TOTAL PRESUPUESTO
COSTOS ACUMULADOS TOTAL

57,135.14
57,135.14

83,390.94
140,526.07

114,638.61
255,164.68

50,506.87
305,671.55

COSTOS ACUMULADOS TOTALCD


PORCENTAJE MENSUAL
PORCENTAJE ACUMULADO

41,384.28
18.69%
18.69%

101,786.23
27.28%
45.97%

184,821.59
37.50%
83.47%

221,404.86
16.52%
100.00%

65.96%

65.96%
65.96%

65.96%
65.96%
65.96%
65.96%

100.00%
50.00%
100.00%

27.66%

27.66%
27.66%

27.66%
27.66%
27.66%
27.66%

1,458.60
10,483.55
203.90
608.01
26.15
112.33
73.45
17.28
12.96
8.64
83,035.35
8,303.54
5,812.47

23.33%
23.33%
23.33%

140.31
6.04
25.92
16.95
3.99
2.99
1.99
41,384.28
4,138.43
2,896.90

0.06

1,449.85
62.37
267.88
175.14
41.21
30.91
20.61
60,401.95
6,040.20
4,228.14

25.83%
25.83%
25.83%

50.00%

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%

100.00%
100.00%
100.00%

100.00%
100.00%

10,483.55
377.30
1,032.20
624.80
168.00
155.24
1,141.14
642.62
43.69
806.91
310.40
844.35
653.06
1,015.34
531.31
897.14
868.98
186.24
36,583.28
3,658.33
2,560.83