51420 Federal Register / Vol. 72, No.

173 / Friday, September 7, 2007 / Notices

Everglades Restoration Plan sets forth prepare an Environmental Impact prepared by the Charleston District,
the process for establishing the interim Statement (EIS) to assess the potential Corps of Engineers.
goals for the Comprehensive Everglades social, economic and environmental 1. Description of Proposed Project.
Restoration Plan. This section provides effects of the proposed construction of The project proposed by the South
that the Interim Goals Agreements be a coal-fired electrical generating station Carolina Public Service Authority
developed by the Secretary of the Army, with associated facilities, a rail line (Santee Cooper) is to construct a coal-
the Secretary of the Interior, and the extension and transmission corridor by fired electrical generating station with
Governor of the State of Florida in the South Carolina Public Service associated facilities on the Great Pee
consultation with the Miccosukee Tribe Authority (Santee Cooper), in the Dee River, in Florence County, SC. The
of Indians of Florida, the Seminole vicinity of the Bostic Landing on the proposed facility will involve the
Tribe of Florida, the Environmental Great Pee Dee River, in Florence installation of an intake and discharge
Protection Agency, the Department of County, South Carolina. The EIS will structure in the Great Pee Dee River in
Commerce, other Federal, State, and assess potential effects of a range of the vicinity of the Bostic Landing and
local agencies, and the south Florida alternatives, including an alternative this Notice of Intent will refer to the
Ecosystem Restoration Task Force. In proposed in the Federal permit proposed project as the Pee Dee Station.
considering the interim goals to be application. The Pee Dee Station development will
indicated in the Interim Goals DATES: General Public Scoping
include the generating station structure
Agreement, the Secretary of the Army, Meetings: Two Public Scoping meetings and facilities that include intake and
Secretary of the Interior and the are being planned. The first will take discharge structures, solid waste
Governor of the State of Florida are place on Tuesday, September 25, 2007 landfills, ash ponds, onsite-rail, rail
required to consider the technical from 6 p.m. to 9 p.m. at Coastal Carolina switchyard, transmission lines, cooling
recommendations of RECOVER and any University located in Conway, South towers, and roads. In total,
modifications to those Carolina in the Recital Hall of the approximately 93.75 acres of
recommendations by the Corps of Edwards College of Humanities and jurisdictional and non-jurisdictional
Engineers, the Department of the Fine Arts. The second Public Scoping wetlands may be impacted to construct
Interior or the South Florida Water meeting will be held on Thursday, the proposed Pee Dee Station.
Management District. The programmatic September 27, 2007 from 6 p.m. to 9 Construction of the Pee Dee Station may
regulations required that the Secretary p.m. in the Commons Area and require filling an estimated 9.45 acres of
of the Army afford the public an Auditorium of South Florence High jurisdictional wetlands and 5.10 acres of
opportunity to comment on the School located at 3200 South Irby Street fill in non-jurisdictional wetlands, 8.14
proposed Interim Goals Agreement prior in Florence, South Carolina. acres of mechanized land clearing in
to its approval and notice in the Federal Federal and State Agency Scoping jurisdictional wetlands, 2.32 acres
Register when the agreement has been Meeting: A Federal and State Agency mechanized land clearing in non-
finalized. The draft final of the Scoping Meeting is planned to be held jurisdictional wetlands, and 0.67 acres
Intergovernmental agreement was on Thursday, September 20, 2007 in of excavation in waters of the United
published in the Federal Register on Charleston, South Carolina. States. Construction/upgrade of the rail
November 3, 2006 (71 FR 64686). Public line extension may require filling of
FOR FURTHER INFORMATION CONTACT: For
comments on the draft 4.49 acres of jurisdictional wetlands and
further information and/or questions
intergovernmental agreements 4.90 acres of mechanized clearing.
about the proposed project and EIS,
establishing interim goals were accepted Construction of the transmission line
please contact Dr. Richard Darden, may involve converting an estimated
through December 4, 2006. The final Project Manager, by telephone: 843–
intergovernmental agreement 58.68 acres of jurisdictional wetlands
329–8043 or toll free 1–866–329–8187, from forested wetlands to scrub shrub
establishing the interim goals was or by mail: CESAC–RE–P, 69A Hagood
signed on April 27, 2007. An electronic wetlands.
Avenue, Charleston, SC 29403. For 2. Alternatives. The following
copy of the document is available at: inquiries from the media, please contact
http://ww.evergladesplan.org/pm/ alternatives have been identified as
the Corps, Charleston District Public reasonable alternatives that will be fully
progr_regs_igit_agreements.aspx. Affairs Officer (PAO), Ms. Connie evaluated in the EIS: No Action; the
Brenda S. Bowen, Gillette by telephone: (843) 329–8123. modification of existing Santee Cooper
Army Federal Register Liaison Officer. SUPPLEMENTARY INFORMATION: An facilities to meet the purpose and need
[FR Doc. 07–4377 Filed 9–6–07; 8:45 am] application for a Department of the of and for the proposed project;
BILLING CODE 3710–AJ–M
Army permit was submitted by Santee alternative locations within the
Cooper pursuant to section 10 of the jurisdictional authority of Santee
Rivers and Harbors Act of 1899 (33 Cooper where the proposed project
DEPARTMENT OF DEFENSE U.S.C. 403) and section 404 of the Clean might be developed; alternative facility
Water Act (33 U.S.C. 1344) on December layouts for the proposed Pee Dee
Department of the Army; Corps of 11, 2006 and was advertised in a local Station; alternatives for energy
Engineers public notice, P/N # SAC 2006–3574– generation, and mitigation measures.
SIB, on December 22, 2006. The public However, this list is not exclusive and
Intent To Prepare an Environmental notice is available on Charleston additional alternatives may be
Impact Statement for the Pee Dee District’s public Web site at http:// considered for inclusion as reasonable
Electrical Generating Station in www.sac.usace.army.mil/ alternatives.
Florence County, SC ?action=publicnotices.pn2006. Santee 3. Scoping and Public Involvement
mstockstill on PROD1PC66 with NOTICES

AGENCY: Department of the Army, U.S. Cooper agreed that based on the Process. Scoping meetings will be
Army Corps of Engineers. potential social, economic, and conducted to gather information on the
ACTION: Notice of Intent. environmental effects associated with scope of the project and the alternatives
the construction of the proposed Pee to be addressed in detail in the EIS.
SUMMARY: The U.S. Army Corps of Dee Electrical Generating Station in There will be three (3) sessions: One (1)
Engineers, Charleston District intends to Florence County, an EIS should be Specifically for the Federal and State

VerDate Aug<31>2005 18:34 Sep 06, 2007 Jkt 211001 PO 00000 Frm 00017 Fmt 4703 Sfmt 4703 E:\FR\FM\07SEN1.SGM 07SEN1
Federal Register / Vol. 72, No. 173 / Friday, September 7, 2007 / Notices 51421

agencies with regulatory responsibilities DEPARTMENT OF DEFENSE consider all comments for the scope of
and two (2) for the general public that the SEIS received by October 16, 2007.
are being planned. Additional public Department of the Army; Corps of
Brenda S. Bowen,
and agency involvement will be gained Engineers
Army Federal Register Liaison Officer.
through the implementation of a public
Notice of Intent To Hold a Public [FR Doc. 07–4378 Filed 9–6–07; 8:45 am]
outreach plan and agency coordination
Meeting To Take Public Comments on BILLING CODE 3710–AJ–M
team.
the Draft Supplemental Environmental
4. Significant Issues. Issues associated Impact Statement on Rock Mining in
with the proposed project to be given Wetlands in the Lake Belt Region of DEPARTMENT OF EDUCATION
significant analysis in the EIS are likely Miami-Dade County, FL
to include, but may not be limited to, Submission for OMB Review;
the potential impacts of the proposed AGENCY:Department of the Army, U.S. Comment Request
Pee Dee Station on: Air quality, wetland Army Corps of Engineers, DoD.
AGENCY: Department of Education.
quality, conservation, economics, ACTION: Notice of meeting. SUMMARY: The IC Clearance Official,
aesthetics, general environmental Regulatory Information Management
concerns, wetlands, historic properties, SUMMARY: The U.S. Army Corps of Services, Office of Management invites
fish and wildlife values, flood hazards, Engineers (Corps) Jacksonville District comments on the submission for OMB
flood plain values, land use, navigation, issued a draft Supplemental review as required by the Paperwork
shore erosion and accretion, recreation, Environmental Impact Statement (SEIS) Reduction Act of 1995.
water supply and conservation, energy on August 17, 2007 to evaluate potential DATES: Interested persons are invited to
needs, public health and safety, impacts of further rock mining within submit comments on or before October
hazardous wastes and materials, food wetlands in western Miami-Dade 9, 2007.
and fiber production, mineral needs, County, FL. In order to accept public ADDRESSES: Written comments should
considerations of property ownership, comments on the Draft SEIS, the Corps be addressed to the Office of
environmental justice and, in general, has scheduled a public meeting. The Information and Regulatory Affairs,
the needs and welfare of the people. Corps invites Federal agencies, Attention: Education Desk Officer,
American Indian Tribal Nations, state Office of Management and Budget, 725
5. Cooperating Agencies. S.C.
and local governments, and other 17th Street, NW., Room 10222,
Department of Health and
interested private organizations and Washington, DC 20503. Commenters are
Environmental Control, S.C. Department encouraged to submit responses
parties to attend the public meeting and
of Archives and History, U.S. Fish and to comment on the draft SEIS. electronically by e-mail to
Wildlife Service, National Oceanic and oira_submission@omb.eop.gov or via fax
Atmospheric Administration, National DATES: The Corps plans to hold a public to (202) 395–6974. Commenters should
Marine Fisheries Service, and U.S. meeting on September 18, 2007 at 6:30 include the following subject line in
Environmental Protection Agency will p.m. EST. their response ‘‘Comment: [insert OMB
be asked to participate as cooperating ADDRESSES: The meeting will be held at number], [insert abbreviated collection
agencies. the Miami Dade Fire Rescue name, e.g., ‘‘Upward Bound
6. Additional Review and Headquarters, 9300 NW 41st Street, Evaluation’’]. Persons submitting
Consultation. Additional review and Doral, FL 33178. (786) 331–5000. comments electronically should not
consultation which will be incorporated submit paper copies.
FOR FURTHER INFORMATION CONTACT: Ms.
into the preparation of this EIS will SUPPLEMENTARY INFORMATION: Section
Leah Oberlin, (561) 472–3506.
include, but shall not be limited to: 3506 of the Paperwork Reduction Act of
Section 401 of Clean Water Act, the SUPPLEMENTARY INFORMATION: The Corps 1995 (44 U.S.C. Chapter 35) requires
Magnuson-Stevens Fishery will provide additional notification of that the Office of Management and
Conservation and Management Act, the the meeting time and location through Budget (OMB) provide interested
National Environmental Policy Act, the newspaper advertisements and other Federal agencies and the public an early
National Historic Preservation Act; the means. Following a short presentation opportunity to comment on information
on the draft SEIS, verbal and written collection requests. OMB may amend or
Endangered Species Act, and the Clean
comments on the draft SEIS will be waive the requirement for public
Air Act.
accepted. A transcript of verbal consultation to the extent that public
7. Availability of the Draft comments will be generated to ensure participation in the approval process
Environmental Impact Statement. The accuracy. A spanish language translator would defeat the purpose of the
Draft Environmental Impact Statement will be available. To submit comments information collection, violate State or
(DEIS) is anticipated to be available late on the draft SEIS or to request copies of Federal law, or substantially interfere
in 2008. A Public Hearing will be materials related to this effort as they with any agency’s ability to perform its
conducted following the release of the become available to the public, contact: statutory obligations. The IC Clearance
DEIS. Ms. Leah Oberlin, U.S. Army Corps of Official, Regulatory Information
Engineers, Regulatory Division, Palm Management Services, Office of
Lieutenant Colonel J. Richard Jordan, III, Beach Gardens Regulatory Office, 4400 Management, publishes that notice
Commander, U.S. Army Corps of Engineers, PGA Boulevard, Suite 500, Palm Beach containing proposed information
Charleston District. Gardens, FL, 33410, by e-mail at collection requests prior to submission
mstockstill on PROD1PC66 with NOTICES

[FR Doc. E7–17685 Filed 9–6–07; 8:45 am] Leah.A.Oberlin@saj02.usace.army.mil, of these requests to OMB. Each
BILLING CODE 3710–CH–P or by telephone at (561) 472–3506. proposed information collection,
Comments or requests for information grouped by office, contains the
can also be submitted on the Lake Belt following: (1) Type of review requested,
SEIS Web site at http:// e.g., new, revision, extension, existing