Implementation Solution for Change

Implementation
Solution for SRB over
HSDPA Activation

Prepared by:

Date:

Reviewed by:

Date:

Approved by:

Date:

Technical support website:


http://support.huawei.com

Technical support hotline:


Fax:

28/01/2015

Page 1 of 13

Implementation Solution for Change

Contents
1

Description of Change........................................................................................................4
1.1

Description of Sites.................................................................................................4

1.2

Purpose and Requirements.....................................................................................4

1.3

Description of Change and Change Influence........................................................4

1.3.1

Software Version..........................................................................................................4

1.3.2

Monitoring and Maintenance Switches.....................................................................5

1.3.3

Feature Related Parameters.......................................................................................5

1.4

Change Period.........................................................................................................8

1.5

Composition of Change Team and Responsibility of Team Members...................8

1.5.1

Change Team of Optus......................................................................................8

1.5.2

Huawei On-site Change Team.........................................................................9

1.5.3

Huawei Support & Guarantee Team...............................................................9

1.6

Check of Equipment Running................................................................................9

1.7

Change Risks and Countermeasures.......................................................................9

1.8

Issue terminals......................................................................................................10

1.9

Check Before Change...........................................................................................10

Operation Steps for Change..............................................................................................11


2.1

Change Steps.........................................................................................................11

2.1.1

Overall Description..............................................................................................11

2.1.2

Operation Steps for Change...........................................................................11

2.1.3

Script for Change..............................................................................................12

2.2

Test and Verification.............................................................................................12

2.3

Solution for Rollback In the Case of Failure........................................................13

2.3.1

Definition of Change Failure..........................................................................13

2.3.2

Information Collection Before Rollback.....................................................13

2.3.3

Overall Description of Rollback....................................................................13

2.3.4

Rollback Steps...................................................................................................13

2.3.5

Script for Rollback............................................................................................14

2.3.6

Equipment Status Check................................................................................14

Technical support website:


http://support.huawei.com

Technical support hotline:


Fax:

Page 2 of 13

Implementation Solution for Change

2.3.7

2.4

Rollback Risk Analysis....................................................................................14

Change of Spare Parts and Emergency Workstation............................................14

1.1

Technical support website:


http://support.huawei.com

Technical support hotline:


Fax:

Page 3 of 13

Implementation Solution for Change

1 Description of Change
1.2

Description of Sites
The target sites of activating feature WRFD-010652 SRB over HSDPA are
HSDPA enabled site.
The current SRB is setup on DCH while HSDPA service is setup, the transmit
power control (TPC) command is transmitted to the UE on an A-DPCH. After
feature WRFD-010652 SRB over HSDPA is activated, downlink SRB of a support
UE are carried on HSDPA, and the A-DPCH is replaced with the F-DPCH.

1.3

Purpose and Requirements


F-DPCH binding with SRB over HSDPA can make full use of the downlink codes
and power due to replacing many DPCHs. As a result, it make more codes and
power available for HSDPA to improve the downlink capacity. (eg., if A-DPCH using
code SF=256, F-DPCH can be shared by 10 UEs, which means max 9 SF=256
codes and power resource can be saved). Moreover, the SRB over HSDPA is
prerequisite of another feature WRFD-010686 CPC-DTX/DRX which is planned to
be introduced to production network.
This feature requires both network and handsets to support.

1.4

Description of Change and Change Influence


To enable this feature, the network performance optimization parameters and
function switches are going to be tuned to ensure the user experiences.

1.4.1

Software Version
The WRFD-010652 SRB over HSDPA feature will be enabled on SRAN9.0
software RNC and NodeBs
Technology

Technical support website:


http://support.huawei.com

Testing Performed Against

UMTS-RNC

MBSC V900R016C00SPC620

UMTS-NodeB

MBTS V100R009C00SPC120

Technical support hotline:


Fax:

Page 4 of 13

Implementation Solution for Change

1.4.2

Monitoring and Maintenance Switches


After WRFD-010652 SRB over HSDPA being enabled on production network,
there are risks that PS call drop rate will increase. The following switches will be
set to recommended value to facilitate the investigation and troubleshooting
process.

1.4.3

Current Setting

Parameter ID

Recommend
Setting

Process Control Switch 2

PROCESSSWITCH2

RNC_PCHR_OU PCHR_OUTPUT
TPUT_CTRL_S _CTRL_SWITC
WITCH-0
H-0

Flow Type

FlowType

DCCC-1

DCCC-0

Flow Type

FlowType

SRB2_STAT-1

SRB2_STAT-0

Parameter Name

Feature Related Parameters


The following parameters and switches strongly related to feature performance, which will
be set to recommended value.
Parameter Name

Parameter ID

Type of Channel
Preferably Carrying
Signaling RB
Effective Flag of
Signaling RB Channel
Type
Cell Hspa Enhanced
function switch
Extra Power For Srb

SrbChlType

Dynamic Resource
Allocation Switch 2

DraSwitch2

RSCP Upper Thld for


SRB over HS-DSCH

Technical support website:


http://support.huawei.com

Current Setting

HSPA(UL_EDC HSUPA
H,DL_HSDSCH)
.
SrbChlTypeRrcEffectFla FALSE.
FALSE
g
HspaEnhSwitch
ExtraPowerForSrb

DL Non-HSPA Power
Initial Load State for SRB
H2D
RSCP Lower Thld for
SRB over HS-DSCH

Recommend
Setting

E_F_DPCH_ON. E_F_DPCH_OF
F
2
N/A

DRA_BASE_CO DRA_BASE_CO
VER_LOAD_SR VER_LOAD_SR
B_H2D_SWITC B_H2D_SWITC
H-1
H-0
SrbH2DNonHLoadState DL_OVERLOA DL_LOADED_S
DED_STATE
TATE
-88

-90

-80

-80

SrbOverHsdpaRscpDow
nThd

SrbOverHsdpaRscpUpT
hd

Technical support hotline:


Fax:

Page 5 of 13

Implementation Solution for Change

Parameter Name

Parameter ID

Recommend
Setting

Current Setting

SrbOverHsdpaEcn0Dow 25 (-12dB)
nThd

29(-10dB)

Ec/N0 Upper Thld for


SRB over HS-DSCH
HSPA Technologies
Retried by UEs
Fake EcNo

SrbOverHsdpaEcn0UpT 31(-9dB)
hd
RetryCapability
SRB_OVER_HS
DPA-1
FakeEcNo
25 (-12dB)

35(-7dB)

Process Control Switch 2

PROCESSSWITCH2

Ec/N0 Lower Thld for


SRB over HS-DSCH

Special User Function


Switch3

SRB_OVER_HS
DPA-1
50(0.5dB)

RNC_PS_QUER RNC_PS_QUER
Y_UE_IMEI_S Y_UE_IMEI_S
WITCH-1
WITCH-0
SpecUserFunctionSwitc SPECUSER_SR N/A
h3
B_OVER_HSDP
A_DISABLED_
SWITCH-1

Dynamic Resource
Allocation Switch 2

DraSwitch2

FDPCH Maximum
Reference Power

FDPCH Maximum
Reference Power

DRA_PCPICH_ DRA_PCPICH_
ECN0_ON_RAC ECN0_ON_RAC
H_UPDATE_SW H_UPDATE_SW
ITCH-1
ITCH-0
-30(-3dB)
30(3dB)

-200 (-20dB)

FDPCH Minimum
Reference Power

FdpchMinRefPwr

-150(-15dB)

Cell Capability Container

CellCapContainerFdd

FDPCH_SUPPO FDPCH_SUPPO
RT-0
RT-0

Compatibility Switch

CmpSwitch

CMP_UU_FDPC CMP_UU_FDPC
H_COMPAT_S H_COMPAT_S
WITCH-0
WITCH-0

UALGORSVPARA
Reserved swtich

RsvSwitch11

RESERVED_SW RESERVED_SW
ITCH_11_BIT5- ITCH_11_BIT50
1

UALGORSVPARA
Reserved swtich

RsvSwitch7

RESERVED_SW RESERVED_SW
ITCH_7_BIT14- ITCH_7_BIT141
0

UALGORSVPARA
Reserved swtich

RsvSwitch11

RESERVED_SW RESERVED_SW
ITCH_11_BIT12 ITCH_11_BIT12
-1
-1

Technical support website:


http://support.huawei.com

Technical support hotline:


Fax:

Page 6 of 13

Implementation Solution for Change

Current Setting

Parameter Name

Parameter ID

Recommend
Setting

Optimization Switch

Optimization Switch

PS_RL_SETUP_ PS_RL_SETUP_
SWITCH-1
SWITCH-1

Process Control Switch 4

PROCESSSWITCH4

IUR_RL_REEST IUR_RL_REEST
_SWITCH-1
_SWITCH-1

Process Control Switch 4

PROCESSSWITCH4

TRB_RESET_R TRB_RESET_R
L_REEST_SWIT L_REEST_SWIT
CH-1
CH-1

Optimization Switch

OptimizationSwitch

SRB_RESET_R SRB_RESET_R
L_SETUP_SWIT L_SETUP_SWIT
CH-1
CH-1

Optimization Switch

OptimizationSwitch

RLFAIL_RL_SE RLFAIL_RL_SE
TUP_SWITCH-1 TUP_SWITCH-1

Optimization Switch

OptimizationSwitch

RL_RESTORE_ RL_RESTORE_
SWITCH-1
SWITCH-1

Optimization Switch

OptimizationSwitch

ASU_RL_RESE ASU_RL_RESE
T_SWITCH-1 T_SWITCH-1

Optimization Switch

OptimizationSwitch

MC_RL_RESET MC_RL_RESET
_SWITCH-1
_SWITCH-1

Process Control Switch 4

PROCESSSWITCH4

PHY_RECFG_R PHY_RECFG_R
EEST_SWITCH- EEST_SWITCH1
1

Process Control Switch 4

PROCESSSWITCH4

PHYCHRECFG_ PHYCHRECFG_
ENH_RL_REES ENH_RL_REES
T_SWITCH-1 T_SWITCH-0

Process Control Switch 4

PROCESSSWITCH4

RB_SETUP_EN RB_SETUP_EN
HANCE_RL_RE HANCE_RL_RE
EST_SWITCH-1 EST_SWITCH-1

Process Control Switch 4

PROCESSSWITCH4

RBRECFG_ENH RBRECFG_ENH
_RL_REEST_S _RL_REEST_S
WITCH-1
WITCH-1

Optimization Switch

OptimizationSwitch

RB_RECFG_RL RB_RECFG_RL
_REEST_SWIT _REEST_SWIT
CH-1
CH-1

Improvement Switch

Improvement Switch

NON_DCCC_R NON_DCCC_R
BRECFG_RL_R BRECFG_RL_R
EEST_SWITCH- EEST_SWITCH1
1

Improvement Switch

Improvement Switch

SMC_RL_REES SMC_RL_REES
T_SWITCH-1 T_SWITCH-1

Technical support website:


http://support.huawei.com

Technical support hotline:


Fax:

Page 7 of 13

Implementation Solution for Change

1.5

Current Setting

Parameter Name

Parameter ID

Recommend
Setting

Process Control Switch 4

PROCESSSWITCH4

IRATHO_HOCA IRATHO_HOCA
NCEL_RL_REE NCEL_RL_REE
ST_SWITCH-1 ST_SWITCH-0

Optimization Switch

OptimizationSwitch

Process Control Switch 2

PROCESSSWITCH2

Performance
Enhancement Switch 3

PerfEnhanceSwitch3

Optimization Switch6

OptimizationSwitch6

ASU_RSP_FAIL ASU_RSP_FAIL
_REL_UE-0
_REL_UE-1

Process Control Switch 2

PROCESSSWITCH2

ASU_RSP_TIM ASU_RSP_TIM
EOUT_HANDL EOUT_HANDL
E_SWITCH-1 E_SWITCH-1

UE_SRB_RESE UE_SRB_RESE
T_SWITCH-1 T_SWITCH-1
CELLUPT_RLF
AILURE_SRBR
EESTAB_SWIT
CH-1

CELLUPT_RLF
AILURE_SRBR
EESTAB_SWIT
CH-1

PERFENH_RLR PERFENH_RLR
ESETUP_GUAR ESETUP_GUAR
ANTEE_SWITC ANTEE_SWITC
H-1
H-0

Change Period
The change period is from 23:00, 16/02/2015 to 06:00 17/02/2015.

1.6

Composition of Change Team and Responsibility of Team Members


Feature Activation: Fan Bai
Drive test: Huawei DT team

1.6.1

Change Team of Optus


Name
Wance Shand
Ruth Foo
Rainier Collantes
Marcin Wierzbicki
Alan Loo
Gabriel Prasad
Shift Duty

Technical support website:


http://support.huawei.com

Responsibility
Project Manager
RNC platform Owner
Capacity Manager
RAE Prime
Mobile Tier2
Mobile Tier2
Tier I, GMS Pro Active

Technical support hotline:


Fax:

Telephone No.
0431 501 880
0402 974 738
0433 788 081
0434 739 988
0434 763 295
0402 792 982
1800 505 777 * 3

Page 8 of 13

Implementation Solution for Change

1.6.2

Huawei On-site Change Team


Name
Joyce Yu
Fan Bai
Mac Chin
Bill Li

1.6.3

Huawei Support & Guarantee Team


Name

Responsibility
Supporting overall

Cherry Li

coordination as the

Telephone No.
0452 625 158

technical expert
Product support contact

Bill Li

1.7

Telephone No.
0432 329 858
0423 715 506
0434 679 157
0425 510 050

Responsibility
Project Manager
RAN Engineer
Technical Specialist
CSSD Manager

0425 510 050

person

Check of Equipment Running


It is required to check the health of the trial RNC and NodeB before feature
activation.

1.8

Change Risks and Countermeasures


Risk existing in change duration: the PS call drop rate may increase after
feature activation.
No.

1
2
3

1.9

Risk Description

Data backup
Impact on NEs
Risk in change

Possibility

Impact

(High/Middle/

(High/Middl

Low)
Low
Low
Middle

e/Low)
Low
Low
Middle

Countermeasure

N/A
RSSR, DCR, HO SSR
RSSR, DCR, HO SSR

duration

Issue terminals
To our best knowledge, the following terminals are not compatible with SRB over HSDPA.
It is required to block these terminals to use SRB over HSDPA. The following table lists
the blacklisted terminals know by HUAWEI.

Technical support website:


http://support.huawei.com

Technical support hotline:


Fax:

Page 9 of 13

Implementation Solution for Change

2
3
4
5
6
7

1.10

Check Before Change


No.

Preparations Before Change

Owner

1
2
3

Solution for rollback in the case of failure


Test solution
Confirming change risks and emergency

Fan Bai
Mac. Chin
Fan Bai

4
5
6

measures
Readiness of mobile phone test card
Readiness of change test personnel
Readiness of relevant equipment

Mac. Chin
Mac. Chin
N/A

7
8
9
10

maintenance personnel
Readiness of support & guarantee team
Readiness of remote log-in environment
Readiness of emergency spare parts
Readiness of boards, tools, and

Mac. Chin
Fan Bai
N/A
N/A

Completion
Date

instruments

2 Operation Steps for Change


2.1
2.1.1

Change Steps
Overall Description
The whole procedure of change is composed of following sub-tasks

Pre- Drive test


Data Backup(Configuration, Alarm .etc)
Check the path for transmitting SRBs has been configured.
Run Script to activate SRB over HSDPA
Turn on License Control item of SRB over HSDPA
System Verification

Technical support website:


http://support.huawei.com

Technical support hotline:


Fax:

Page 10 of 13

Implementation Solution for Change

2.1.2

Post- Drive test

Operation Steps for Change


No.
1

Change Step
Pre-Drive
test

Data backup

Time

Person
DT team

12:00

Backup Configuration file ,

Fan Bai

23:00

Drive test for benchmark

Check the

Active Alarm, License file


Check the path for transmitting

Fan Bai

23:30

configuration
Feature

SRBs has been configured


Turn On Feature Switches and

Fan Bai

0:00

Activation
System

License Control
Alarm check

Fan Bai

1:30

verification
KPI report
Post-Drive

KPI monitoring

6
7

Fan Bai
DT team

3:00
12:00

Drive test

Script for Change

RNC Feature
Activation.txt

2.2

Implementation

test

2.1.3

Operation

NodeB Feature
Activation.txt

Test and Verification

No.

1
2
3

Operation Item

Operation Method

Alarm Check

Clear new Alarm caused by

Owner
Fan
Bai

KPI monitoring

feature activation if applicable


Confirm Major KPI

Bai

Drive test

performance is no degradation
Post Drive Test

Fan
DT

Time

0:00
2:00
12:00

team

Technical support website:


http://support.huawei.com

Technical support hotline:


Fax:

Page 11 of 13

Implementation Solution for Change

2.3
2.3.1

Solution for Rollback In the Case of Failure


Definition of Change Failure
A change failure shall be recognized if the major KPI degradation
could not be resolved before 4:00 am.
Upon the suiation of change failure, rollback operation shall be taken
and finished before 6:00 am.

2.3.2

Information Collection Before Rollback

Configuration file
Operation Log
Performance Data
CHR, PCHR

2.3.3 Overall Description of Rollback

2.3.4

Data Backup(Configuration, Alarm .etc)


Run Script to rollback the configuration
System Verification
Post- Drive test

Rollback Steps
No.
1

2.3.5

Change Step

Data backup

Operation

Implementation

Time

Backup Configuratio file ,

Person
Fan Bai

4:00

Feature

Active Alarm, License file


Run roll back scripts to turn

Fan Bai

4:30

deactivation
System

Off Feature Swicthes


Alarm check

Fan Bai

5:30

verification
KPI report

KPI monitoring

Fan Bai

6:00

Script for Rollback

RNC Feature
Rollback.txt
Technical support website:
http://support.huawei.com

Technical support hotline:


Fax:

Page 12 of 13

Implementation Solution for Change

2.3.6

Equipment Status Check


N/A

2.3.7

Rollback Risk Analysis


N/A

2.4

Change of Spare Parts and Emergency Workstation

N/A

Technical support website:


http://support.huawei.com

Technical support hotline:


Fax:

Page 13 of 13