Professional Documents
Culture Documents
The stones in stone steps are held in place by gravity. To have enough weight to be effective, each stone should have
more than enough height to create a step of the needed height, should be at least twice as deep as the height of the
step, and should be firmly anchored in undisturbed soil (or highly compacted fill). The best stones for steps have a fairly
flat top and a reasonably flat face, and are heavy enough that two or more people are needed to lift or move them.
When more than one stone is needed to make one step, the stones should abut each other firmly so that crusher fines
cannot wash out through cracks between the stones.
Use pressure-treated landscape timbers, which have a rough-sawn finish – for aesthetics, avoid pressure
treatments that perforate the wood with hundreds of small slits. Typically, the timber used for each step
should be at least 2’ wider than the trail so that the timber can fully retain the crusher fines above the step.
Since timber is not heavy enough to hold itself in place, they are held in place by 2’ long sections of rebar
driven straight into the ground, one at each end. Driving the rebar can be difficult or impossible in rocky soil.
If the rebar bends after it is significantly in the ground, saw off the undriven part rather than bend it over.
The Contractor is responsible for disposing of excavated materials that are considered unsuitable and of any
surplus excavated material not required for embankments or backfill.
Flooding
None of the crusher fines specifications are designed to withstand a flood of moving water (although they can
withstand temporary standing water). A crusher fines trail impacted by a concentrated flow of moving water
will have to be extensively repaired or rebuilt.
Key: The numbers 1 through 6 refer to construction methods. If the site or subgrade conditions fit into more
than one category, use the higher-numbered specification.
• After several heavy rains and several months of user traffic, the County is responsible for adjusting
the path surface (with a Bobcat and/or hand labor) to eliminate unplanned high and low spots.
Adjustments and recompaction will be easier if the top several inches of the crusher fines are damp
from a recent rain. Fines may need to be added where compaction was inadequate. Any washouts
should be filled at this time and the sources of the washouts corrected.
Crusher fines cannot be used on sites which are often or permanently wet, or which are subjected to
concentrated water flows. Other materials and methods can be used instead, some of which are listed here.
Side swales
If altering the water table on the site is acceptable, swales on both sides of the trail may be able to lower the
water table just enough for crusher fines to be used (see “Side Swales and Culverts” in Crusher Fines Trail
Drainage, p. 3-28).
Boardwalk
A short section of boardwalk can cross a wet area and create a feature along the trail (see Boardwalk, p. 2-
88).
Stepping stones
On a low-traffic pedestrian-only trail, stepping stones can be used to cross an area that is sometimes wet or
damp (see “Stepping Stones” in Crusher Fines Trail Drainage).
Bridge
A low bridge can be considered across a wet or boggy area. The bridge can be a desirable feature along the
trail (see Bridges, p. 2-56).
Stone pavement
On a pedestrian-only trail, a short pavement of fitted stones can cross an intermittent channel or an
occasionally wet area (see “Swale Crossings” in Crusher Fines Trail Drainage).
Wood decking
A ground-level boardwalk can rest on the ground and provide a dry crossing of a damp area without piers or
railings (see Boardwalk, p. 2-88).
Causeway
In some conditions, a causeway can elevate the crusher fines trail above ground level (see “Causeway and
Channelization” in Crusher Fines Trail Drainage).
Channelization
On a pedestrian-only trail, a causeway with a short section of stone paving at ground level can channel
occasional surface water across the stone pavement (see “Causeway and Channelization” in Crusher Fines
Trail Drainage).
By building to the highest specification for the combination of subgrade and site conditions for crusher fines
and for the selected hard surface, a crusher surface can become the foundation for a hard surface to be
constructed later.
Several steps must be taken to prepare the crusher fines surface, foundations, subgrade, and excavation for
a future (potential) hard surface. These are listed below and partially illustrated on the next page.
The sub grade preparation and base courses must meet or exceed the specifications in this Handbook for
both the crusher fines trail and the eventual hard surface. Choose the appropriate foundation method for
crusher fines from Methods 1-5 given above, choose the appropriate foundation method for the hard surface,
then combine the features of both to produce a foundation which meets or exceeds the specifications in this
Handbook for both trail types.
5. Consider the location of an adjacent soft surface trail for the hard surface
During the planning phase for the crusher fines trail, determine the likely location for an adjacent soft surface
trail once the hard surface is installed. A corridor should be planned and reserved for the adjacent soft
surface trail in initial planning and construction. If crusher fines are excavated and replaced with the hard
surface, some of these fines may be usable in the new soft surface trail.
The following are specific for crusher fines. For additional general guidelines, see Features for the Physically
Challenged, p. 2-107.
3. Consider using a concrete surface on steep sections. Where a trail has to be steep for a short time
but it is desirable to minimize barriers, consider surfacing the steep sections with concrete. This provides
a smooth maintenance-free surface for wheelchair users both during climbing and braking. (Concrete is
considered more accessible than asphalt.)
4. Design for slow-moving users at a pedestrian scale. Crusher fines trails have the potential to be
much more intimate with their site than hard surface trails. If at all possible, design the trail to be rich in
trailside detail. By the concept of intermediate path goals (see Section 1 Part E), interesting features on
or visible from the trail should occur as often as possible - this makes a short trail rich in experience.
5. Vary the width of the trail. While the trail should be at least 5’ wide to allow two wheelchairs to
comfortably pass, the width of the trail should vary with the site and site features. Pullouts can be
constructed to encourage stopping, but widening the trail in logical locations serves the same purpose in
a more naturalistic and less obvious way.
6. Consider using cuts and fills, bridges, and/or boardwalk sections to cross uneven terrain.
Even on a crusher fines trail, boardwalk sections and bridges can be used as needed to span terrain that
might ordinarily be crossed on the ground in a series of grades.
These basic drainage mechanisms tend to cause wheelchair users to roll toward the sides of the trail.
For wheelchair users, the surface pitch for drainage should not exceed 2%, and less or no pitch is
preferred as practical. At locations where a surface pitch could divert a wheelchair into a dangerous
place, such as off a steep cross slope or into a retaining wall or railing, the pitch should be as close to
0% as practical.
Overlooks, pullouts, and other stopping points should be as level as practical, not exceeding 2% pitch or
grade in any direction.
Minimizing or eliminating surface pitch makes it more difficult to drain the trail surface. This requires
more effort to keeping site runoff from reaching the trail in the first place. If trail grades are 4% or above
and the site has significant runoff, consider using side swales to keep site runoff from reaching the trail.
Another technique is to raise the crusher fines surface at least 5/8” to 1” above the adjacent ground level.
(Consistently raising the trail surface more than I” tends to make trail users feel detached from the site
and is hence not advised.) The raised surface has to be maintained in order to be effective.
While grade breaks are OK for wheelchairs, the standard drainage dip is a wheelchair trap. Use the
guidelines below to create small grade breaks to replace drainage dips and to also double as a rest stop
along the trail. In the absence of outslope and crowning, these small grade breaks need to be used at
frequent intervals in order to drain the trail. Small grade breaks should be used at 2-3 times the specified
frequency of drainage dips. Because their shape is subtle, they also need simple but more frequent
maintenance to maintain their shape and drainage characteristics.
An example of typical trail maintenance equipment. Bush-hog used for trimming maint. Swath as well as
cutting grassed trails. Capable of cutting small shrubs as well.
The Aquacide Unit offers an alternative method of killing weeds embedded in soft surface trails by using
steam to boil weed root systems. Excellent for areas near playgrounds and pet trails where pesticides should
not be used.
Check the entire trail surface for any signs of washouts or water damage - no matter how small. Look for
signs of concentrated water having flowed down the trail or across the trail. If any problem is found,
identify the source of the excess water and add appropriate drainage features. For instance, it may be
necessary to adjust the outslope or crown, add another drainage dip uphill, or install an inside swale.
(Although difficult, the best way to thoroughly understand the problem is to watch the trail while water is
actively flowing).
Regrade any parts of the trail surface with incorrect outslope, crown, or superelevation. The stockpile of
extra fines ordered when each trail was built can be used to add fines to a trail as needed.
If the water source cannot be diverted or kept off the trail surface, it may be necessary to rebuild that part
of the trail with a hard surface.
Except for exceptional downpours (such as an inch per hour), drainage dips and grade breaks should
show no signs of erosion. If the bottoms of drainage dips or grade breaks show any signs of scouring or
erosion, too much water is being concentrated at those points:
• If an alluvial fan of crusher fines is deposited in the outlet of a dip, the problem is potentially serious.
Monitor the dip after each subsequent heavy rain to see if the erosion was a one-time occurrence. If fines
continue to be washed out, install additional drainage dips uphill of the eroded dip or grade break, install an
inside swale to keep water off the trail, or otherwise catch and divert some of the water at a higher point. If
the concentration of water cannot be diverted, consider adding a hard surface in this part of the trail.
• If a dip begins to fill with crusher fines sediments, the problem is already serious - a few rains will fill the dip
and render it ineffective, possibly causing a large washout further down the trail in a domino effect of failed
dips. Immediately fix the problem as described in the previous paragraph.
Inspect for the effects of too much water, too much sediment, or poor drainage:
If the bottoms of side swales show erosion (other than erosion of bare soil before the vegetation cover is
restored), an intermediate culvert or other means of draining the swale at more intervals should be
installed. In extreme cases, riprap can also be added to the bottom of the swale to harden the swale
channel against erosion.
Inspect culvert headwalls and tailwalls for settling and water damage. If settling, erosion, or water
damage is occurring to these structures, identify the source of the problem and repair it.
If the outlet below a culvert is eroding, add riprap beneath the outlet. Use all sizes of rocks in the riprap
to try to create a more naturalistic appearance.
If a swale or culvert is beginning to fill with leaves or sediment, clean it out long before it fills. If sediment
is the cause, find the source of the sediment and, if possible, reduce the amount of sediment flowing into
the swale or culvert. If the sediment is crusher fines from the trail, the source of the trail washout should
be corrected.
4. Inspect and repair all trail structures:
Carefully inspect all trail and trailside structures (including retaining walls, bridges, drainage crossings,
railings, signs, fences, etc.) for any damage caused by humans or the elements. Any damage that
compromises the functionality or aesthetics of these structures should be repaired, as should any minor
damage that will become worse in time if not repaired now.
Carefully inspect all revegetation efforts. All plantings should be at the appropriate stage of growth
depending on the season and when they were planted. Any areas that are stunted or behind schedule
should be monitored.
Any erosion in revegetated areas should be stopped through the use of erosion control blankets, bales of
hay or straw, diverting site drainage, or other appropriate means. The eroded areas should be reseeded
or replanted (if the time of year is appropriate), then protected by mulch or erosion control blankets as
necessary. See Site Preservation, Restoration, and Revegetation, p.2-103, for details.
In maintenance during the spring, replace plantings that did not survive the winter unless site or growing
conditions indicates otherwise.
For future reference, keep records of which plants do best and worst under their site conditions.
The high-quality public image of the trails and county property must be maintained. All litter, no matter
how small, should be picked up and hauled off the site. Any vandalism or graffiti should be fixed or
removed.
Any fallen branches or trees on trails should be removed, as should any live or dead trees that are likely
to fall on the trail. In ecologically sensitive or pristine areas, removed wood can be scattered close to
where it fell in order to preserve the local chain of growth and decay. In less sensitive or developed
areas, removed woody material should either be hauled off, mulched in a chipper and reused onsite, or
broken into smaller pieces and left to decay in widely scattered spots on the site - do not form piles or
obvious dumping places.
“Social” trails are unplanned, unofficial trails created by users, usually by shortcutting. Any social trails,
which have begun to emerge, should be noted and monitored. Find the reason why people are creating
the social trail, and if there is good reason for a trail to be there, consider making the trail official now or
in the future. Making the trail official means that the trail will need to be designed, constructed,
maintained, and managed according to the standards in this Handbook.
If the social trail is damaging the site, could damage it in the future; or if a trail is inappropriate in that
location, close the trail and post the closure (see Signs, p. 2-68). The closure will have to be enforced,
and that enforcement will need to become part of the management plan for the main trail and/or the
County property.
First Year
Inspection and maintenance are more frequent during the first year in order to find and correct problems
early. Some of the following inspections can be combined (i.e., performed at the same time) if they would be
scheduled separately within the same 6-week period. In scheduling first year maintenance, adhere more to
the purpose of frequent and timely inspections than to strict dates.
As soon as possible after the first good rain falls on a new trail, perform the entire maintenance checklist,
paying special attention to water damage on the trail surface, in drainage dips and grade breaks, and in
swale crossings, side swales, and culverts. If any damage occurs after only one rain, the problem will be
major very soon. Some reconstruction may be necessary, including the substantial modification or addition of
new drainage features. One qualified person can perform the inspection and note the problems, and a crew
of 1-4 should be able to repair them.
This inspection should again concentrate on repair of all drainage features. Trail structures and revegetation
should also receive special attention. Any social trails, which have begun to appear, should be evaluated and
handled as described in the maintenance checklist.
This maintenance can be combined with another scheduled maintenance if both would be scheduled within
the same 6-week period.
In the spring
Once the snow has largely melted but before vegetation emerges, perform the maintenance checklist again.
A small maintenance crew of 1-4 workers should be able to fix most of whatever problems may have
occurred. Special attention should be given to preventive maintenance and to all aspects of trail drainage.
Swales and culverts should be checked to make sure they are not clogged or are becoming clogged with
leaves or sediments. The source of any erosion of crusher fines or soil should be diverted and the erosion
repaired. Regrade any parts of the trail surface with incorrect outslope, crown, or superelevation.
In the third year and after, routine maintenance should become easier and less extensive. The troublesome
spots along the trail will be known (and hopefully already corrected). Most problems with the trail surface
should have been corrected by now. Maintenance of side swales and culverts will always be ongoing. Plants
introduced through revegetation should be firmly established.
Over a period of years, the surfaces of trails tend to level with use - outslope and crowning level out, dips fill
in, and high spots are worn down. Continual minor readjustments of the trail surface will help keep the trail
surface in its original condition. More crusher fines may need to be added to the trail surface in spots. Barring
washouts, however, only minor adjustments should need to be made to the trail surface for decades once the
drainage is under control.
Trail structures may begin to need more extensive maintenance as they age and settle, particularly fences,
retaining walls, culvert headwalls, railings, signs, and bridges. This maintenance should be done as needed
to maintain the high-quality public image of the trail system. The goal of this maintenance, however, is not to
keep everything shiny and new without signs of age. The natural aging of materials is highly valued as long
as that aging does not become an eyesore or compromise the physical integrity of the structure. As
structures age gracefully, repairs should attempt to preserve and enhance the positive aspects of age.
The creation of new social trails will diminish if consistent efforts were made earlier to close or make social
trails official. If usage of the main trail greatly increases, however, user pressure will likely create new social
trails.
In general, if trail usage increases over time or exceeds the usage level for which the trail was built,
maintenance will increase. Some reconstruction or widening of the trail may be necessary.
A competent inspector as needed should inspect major structures, which affect user safety such as bridges,
large retaining walls, and railings. Generally, this will not be necessary for the first 15 years, and possibly
every 5-10 years after that depending on the structure. Unless a bridge or retaining wall was not designed or
constructed correctly, there should be no need for replacement for 50 years.
If a structure is extensively damaged (flood, landslide, foundation failure, overload, structural failure), it
should be inspected and repaired or rebuilt as necessary.
Specialized Trail grader is perfect for most straight trails but does not grade well on winding pathways and in tight
spaces.
Signs
Signs may need to be replaced every 10 years depending on their condition. Signs should be replaced if they
become dilapidated to the point that their aging is seen as an eyesore instead of as an interesting character.