1.
Tax code
2.
Placing of Orders
Orders are normally placed after PEB Steel submits a written
proposal (also known as quotation or offer) (hereinafter "the
Proposal") to its customer.
Quotations may be revised one or more times until both the
customer and PEB Steel agree upon all technical and commercial
matters.
Once all matters are agreed upon, and are included in a final
revised and typed PEB Steel proposal, the customer and PEB Steel
shall sign a standard contract of which these standard terms and
conditions shall form an integral Part. A blank form of this contract
is attached to the Proposal.
2.
Swift Code
: BIDVVNVX310
Beneficiary
Address
A/C No.
Tax code
3500684522
4.
Approval of Drawings
4.1
4.2
4.3
4.4
4.5
4.6
4.7
iii. 15% of Building value not later than 7 days from the date of
the buildings sheeting delivery at job site
4.8
iv. 05% of Building value not later than 7 days from the erection
date of the building.
4.9
Acceptance of Orders
Only signed and dated contracts are accepted at the PEB Steel
Head Office in Ho Chi Minh City, Vietnam. Accepted orders are
entered in a Sales Register maintained by the Finance Department.
An order will be placed "ON HOLD" by PEB Steel, when it is
considered to be incomplete. Such an order will remain on hold
until corrective action is taken.
3.
: 3500684522
5.
Bank Details:
1.
5.2
5.3
: HSBCVNVX
Beneficiary
Address
A/C No.
: (VND) 001-217058-001
5.4
6.
(USD) 001-217058-101
LSD (E) R07/ 19-01-10
5.3.1
5.3.2
5.3.3
5.3.4
Column reactions.
Design Certificates
7.
7.1
Change Orders
Changes in requirements after a contract is signed and
accepted requires the client to sign a Change Order letter
(which shall be prepared by PEB) which describes the
change(s) and the impact that the changes may have on price
and/or delivery.
No action shall be taken by PEB Steel on the changes until the
Change Order is signed as accepted by the client.
7.2
8.
Jobs On Hold
8.1
All costs incurred due to a job placed "On Hold" after start of
manufacturing will be to the Customer's account.
8.2
Jobs that have been entered but have not been released for
production within 30 days from the date of signing contract for
whatever reason (including lack of technical clarification) will be
put "On Hold". If such jobs are subsequently reactivated, they
are subject to the pricing schedule in effect at the time of their
release from the "On Hold" status.
9.
9.1
Material Dispatch
The material dispatch commitment is measured (in weeks) from
the date of the latest receipt and acceptance by PEB Steel Head
Office of the following:
Signed Contract.
Acceptable Letter of Credit / acceptable Bank Guarantee.
Down Payment.
Final Change Order including amendment to L/C price / Letter of
Guarantee price.
Signed final "approved as noted" Approval Drawings.
9.2
12.3 PEB Steel does not supply nor does it accept responsibility
for plumbing services, painting, electrical services, air
conditioning services, or any other material or service not
specified in the final accepted proposal, contract, or change
order.
23. Storage
23.1 PEB Steel shall store, free of charge at PEB Steel open stock
yards, any or all materials for a contract for a period not
exceeding 10 days from the scheduled dispatch date.
23.2 Should a customer delay dispatch of goods for a period
exceeding 10 days after the originally scheduled dispatch
date, STORAGE CHARGES shall be levied by PEB, at the rate
of 0.1% of the ex-works selling price (of the unshipped
material) per day.
23.3 PEB Steel will not be held responsible for damage caused to
the exposed steel after it has been stored longer than 10
days. Such damage may include deterioration of the
structure paint coating and discoloration of roof/wall panels.
2.
3.
4.
34.2
32. Warranty
32.1 PEB Steel warrants materials for one year from the date of
dispatch from PEB Steel Factory. This warranty extends only to
materials manufactured by PEB Steel in that such materials
shall not fail due to defective materials or workmanship, when
utilized in the intended manner.
32.2 PEB Steel warrants that the structure shall support the loads
described in PEB Steel drawings and Contract, if properly
erected as part of a complete structural system designed by
PEB Steel and comprising only of parts made by PEB and the
structure issued for which it was designed.
32.3 No warranties are expressed or implied other than those
described in these Terms and Conditions
LSD (E) R07/ 19-01-10