Professional Documents
Culture Documents
FRANCIS DAM
FAILURE
worst American civil engineering
disaster of the 20th Century
J. David Rogers, Ph.D., P.E., P.G., C.E.G., C.HG.
Karl F. Hasselmann Chair in Geological Engineering
Missouri University of Science & Technology
for the
Minimal Abutment
Excavation 1924-25
64 victims at Powerhouse 2
PATH OF DESTRUCTION
Post-failure survey
of displaced blocks
FIXING BLAME
The Commission met
on March 19th and
issued their report 5
days later
They concluded that the
red conglomerate
underling the dams
right abutment was
unsuitable for a dam
foundation, and that the
failure began in that
area, along the old San
Francisquito fault
Original (1923) design concept for the St. Francis Dam by the
LA BWWS, shown at left
The cross section given to the Governors Commission by
BWWS is presented on the right. It extends down to Elevation
1620. The red line approximates the actual limits of the dam.
Political promises
Grunskys Ladder
Prominent
shrinkage
crack
observed
cutting
through
Block 5 after
the failure
Proctor, Gardett and Arledge identified two candidates for Block 35.
The one located furthest downstream is shown at right. Block 35
came from the base of the dams missing section, at the bottom of
the dams left abutment. Blocks 27, 28 and 35 were identified by
adhesions of schist on their base relative to original horizontality of
the concrete cold pour joints (pillows), which are easily discerned.
Keyblock Theory
Malpasset Dam
The Malpasset arch dam
in France failed on its
initial filling in 1959
The dam was designed
by Dr. Andre Coyne, the
worlds foremost expert
in arch dam engineering
Dr. Pierre Londe spent
8 years unraveling the
failure mechanism
It was caused by
hydraulic uplift of a large
rock wedge lying beneath
the dams left abutment
Evaluation of
East Abutment Slide
Discontinuous Deformation
Analysis was used to evaluate
the East Abutment Landslide
This illustrates the destabilizing
effects of lateral loss of restraint
that may have triggered upward
migration of the slide mass
Large pore pressures may have
developed along the basal
detachment surface due to
entrapment in the mica schist,
greatly reducing inter-particle
friction
The reservoir extended about
halfway up the slope shown here
After the failure thousands of dead fish were observed floating in deep
plunge pools excavated downstream of the failed dam. Some
suggested they must have been killed by dynamite
Autopsies of the dead fish revealed that they succumbed to silt
ingestion of their gills; suggesting a very turbid outflow
Based on later tests performed during the Second World War, it would
have taken more than 12,000 lbs of dynamite beneath 30 feet of water
on the dams upstream side to sabotage the structure
A casual
observation
The Ray Silvey family was driving up San Francisquito Road past the
dam around 8:30 PM on March 12th
They had gone about 100 feet past the dams left abutment when they
were forced to stop by a 12-inch high scarp cutting across the road, in
the Pelona Schist!
High velocity orifice flow may have sprung from the base of the right
abutment, shortly before the failure.
A light was observed in the canyon below the dam by passersby in
the 45 minutes preceding the failure.
The damkeeper wifes body was found fully clothed, wedged
between two blocks near the base of the structure, mile upstream
from where she lived. This suggests the couple was up at the dam
looking at something.
Landslideinduced seich
Sheared face
of Block 1
Another photo,
showing the final
position of Block 7,
wedged between
Blocks 1 and 5.
Block 7 came from
the dams upper left
abutment, which slid
in behind Block 5.
Note the man at
bottom left for scale.
As the left side of the main dam was undercut, the dam
tilted slightly and rotated to that side, allowing water to
enter the shrinkage crack on the west side of Block 1
This triggered a chain-reaction failure of the right
abutment , but only after the reservoir had dropped
between 70 to 80 feet.
DESIGN DEFICIENCIES #1
The dam was unknowingly built against a
paleolandslide
Hydraulic uplift ignored in the design, leading to a
lower factor of safety than designers realized
Hydraulic uplift not relieved on sloping abutments (a
common problem until the 1960s)
Rather scant system of seepage interception
Cement heat of hydration effects ignored
Low strength laitance layer between successive
concrete lifts, creating low tensile strength horizons
Aggregate separation using trough placement
DESIGN DEFICIENCIES #2
The upstream heel of dam not battered 3.5:10 below
elevation 1645 ft
Dam heightened 20 feet without increasing base width
Downstream face chopped off at elevation 1650 ft, giving
a thinner cross section than it actually required, to
overcome the effects of uplift
Absence of grouted contraction joints
Plugging the dams expansion cracks with oakum on the
downstream face was the absolute WORST thing they
could have done to destabilize the dam
Gypsiferous Vasquez conglomerate subject to slaking
under submersion
No instruments placed within the dam structure to
monitor its actual performance
CONCLUSION No. 1
For every complex problem, there is a solution
that is simple, neat, and wrong
H. L. Menken
CONCLUSION No. 2
#2) We will not identify those
geologic features or structures for
which we are not specifically
looking for. We have to have in
mind what we are seeking,
realizing that we will seldom be
able to recognize those features
with which weve had little prior
experience
CONCLUSION No. 3
Engineering geology, by its nature, is a
very subjective science, built upon
each persons unique pedigree of
experience. The simple inclusion of a
geologist on a project, will not, in of
itself, insulate such projects from
disaster. Consider the fact that we now
know there are over 153 dams currently
existing in the United States which
were unknowingly built against ancient
landslides.