Table of contacts:

1. Introduction
2. Construction Management
2.1 Purpose
2.2 Elements
2.3 Plans Necessary
2.4 Permits and approvals
3. Bar charts And Mile Stone Charts.
3.1 PERT
3.2 CPM
3.3 General Comparison Between PERT and CPM
4

MS Project.
4.1 Details
4.2 Bar Chart / Gantt chart.
4.3 Network Diagram.

Specifications

Plans
6.1 Calculation Details

Conclusions.

TASK WORK OR OUT- TURN


The measurement of capacity of doing work by an artisan or a skilled labour in the form
of quantity of work per day is called ask-work or out-turn of labour. There can be
variations in out-turn from man to man Depending upon experience etc. out-turn of work
for average artisan per day is given in a table below.
Particulars of items

Quantity per day per craftsman


(mason/painter/carpenter etc)

1. Brick work in lime or cement mortar


a) In foundation and plinth
cu.m
b) In super structure
2. Brick work in mud mortar
a) In foundation and plinth
cu.m
b) In super structure
3. Brick in cement or lime mortar in aches
cu.m
4. Half brick wall in part ion
5. Coursed rubble stone in lime or cement mortar
Including dressing
6. Random rubble stone masonry in lime or cement Mortar
1.00 cu.m
7. Ashlars masonry in lime or cement mortar
cu.m
8. Lime concrete in foundations or floor
9. Lime concrete in roof terracing
10.Cement concrete 1:2:4
11.R.B. Work
12.R.C.C Work
13.12mm plastering with cement or lime mortar
cu.m
14.Pointing with cement or lime mortar
sq.m
15.White washing or colour washing three coats
sq .m
16.White washing or colour washing one coat
200.00 sq.m

1.25
1.00 cu.m
1.50
1.25 cu.m
0.55
5.00 sq.m
0.80 cu.m

0.40
8.50
6.00
5.00
1.00
3.00

cu.m
cu.m
cu.m
cu.m
cu.m
8.00
10.00
70.00

17.Painting or varnishing doors windows one coat


25.00
sq.m
18.Distempering one coat
35.00 sq.m
19.2.5 cm C.C floor laying
7.50 sq.m
20.Brick-on-edge in floor lime or cement mortar excluding L.C.
7.00 sq.m
21.Brick flat floor as above
8.00 sq.m
22.Timber farming sal or teak wood
0.07
cu.m
23.Country wood timber farming
0.15 sq.m
24.Door and window shutters paneled or glazed
0.15
sq.m
25.Battened door and window
0.80
sq.m
26.Single Allah bad tiling or Mangalore tiling
6.00
sq.m
27.Double Allah bad tiling
4.00 sq.m
28.Breaking of brick ballast 40mm size
0.75
cu.m
29.Breaking of brick ballast 25mm size
0.55
cu.m
30.Breaking of stone ballast 40mm size
0.40
cu.m
31.Ashlor stone dressing
0.70 cu.m
32.Flag stone dressing
1.50
sq.m
33.Earth work in excavation in ordinary soil
3.00
cu.m
34.Excavation in rock
1.00 cu.m

MAJOR QUANTITIES
FOR CONSTRUCTION
CONCRETE (CUM)
STEEL (Mton)
BRICKS (CU.M)
CEMENT (BAGS)
SAND (UNITS)
TOTAL
LABOUR CHARGES
FORM WORK
MATERIALS
(TILES,FLOORING,WIRI
NG)

QUANTITY
115
11
300
300
225

RATE/CU.M(RS)
5000
40000
2000
250
2750

TOTAL
575000
440000
600000
75000
618750
2308750

30%
40%
40%

581325
775100
923500

TOTAL
MISSLANEOUS

4588675
2%

155020

TOTAL G + 2

4743695

TOTAL

4750000/-

Gantt. The bar represents the actual project status.


11. The project manager must now keep the project plan up to date through Microsoft
Project. Choose the task to be updated, then choose Tools | Tracking | Update tasks. In
the dialog box, enter progress data, either in the form percentage complete, actual
dates, actual durations, or actual work.
12. To view project progress in Microsoft Project, choose Report | Visual Reports.
13. To close the project, create a final report by the means in step 12. If the project
plan was useful to the management of the project, the project manager may wish to
create a template plan to use in the future. Choose File | Save As | Template.
The Advantages of Microsoft Project:

Using MS-Project we can estimate the project completion time, and can estimate
the man hours required to each individual tasks.

We can predict the delay at any stage of the project.

Estimating the recourses like 3Ms (money, man powers and materials).

Delay can also be adjusted when and where ever possibility available.

Day to day budget can be known which will help to avoid the financial problems.

Bar-chart prepared using MS-Project will give the complete idea about the
project.

Any adjustments can be done using software at any point of time.

About MS-project
"A project is a finite endeavor - having specific start and completion dates undertaken to create a unique product or service which brings about beneficial change
or added value. This finite characteristic of projects stands in sharp contrast to

processes, or operations, which are permanent or semi-permanent functional work to


repetitively produce the same product or service."