ASAS BINA ENT. SDN. BHD.

METHOD STATEMENT - ERECTION OF TEMPORARY


HOARDING
Rev. No: 0
Project Doc. No. : MS/TH/01
Page : 1
Contents
1. OBJECTIVE...........................................................................................................2
2. SCOPE...................................................................................................................2
3. MATERIAL.............................................................................................................2
4. EQUIPMENTS & MACHINERIES REQUIRED.....................................................2
5. SITE PREPARATION WORK................................................................................2
6. METHOD OF WORK.............................................................................................2
7. QUALITY ISSUES.................................................................................................2
8. SAFETY ISSUES...................................................................................................2
9. ENVIRONMENTAL ISSUES..................................................................................2

ASAS BINA ENT. SDN. BHD.


METHOD STATEMENT - ERECTION OF TEMPORARY
HOARDING
Rev. No: 0
Project Doc. No. : MS/TH/01
Page : 2

1.
OBJECTIVE
To outline the sequence of activities, method and resources needed for the
operation of erecting temporary hoarding.

2.
SCOPE
The work shall include all labour, material, equipment, safety requirement and
services necessary for the execution erecting temporary hoarding.

3.
MATERIAL
Material to be used is as follows:3.1
50 x 50 x 1.6mm thick SHS M.S Posts
3.2
50 x 25 x 1.2mm thick RHS M.S Nogging
3.3
50 x 25 x 1.6mm thick SHS M.S Braces
3.4
0.3mm thick metal decking
3.5
Nail
3.6
Cement
3.7
Sand
3.8
Water

4.
EQUIPMENTS & MACHINERIES REQUIRED
Equipment and machineries to be used are as follows:4.1
Minimum: One (1) number of JCB Backhoe (if required)
4.2
Minimum: One (1) set of hand excavating equipment
4.3
Minimum: One (1) set of steel work equipment
4.4
Minimum: One (1) set of water levelling
4.5
Minimum: One (1) number of spirit level

5.
SITE PREPARATION WORK
Setting out boundaries of ground in the proposed perimeter.

ASAS BINA ENT. SDN. BHD.


METHOD STATEMENT - ERECTION OF TEMPORARY
HOARDING
Rev. No: 0
Project Doc. No. : MS/TH/01
Page : 3
6.

METHOD OF WORK
6.1
Determine the location of the temporary hoarding will be
established with confirmation from the surveyor.
6.2
After getting confirmation, using the given point and mark the main
pole as per alignment. Center to center of the main column is
3000mm.
6.3
Preparation of the main pillars started by using hand digging to the
depth 400mm.
6.4
Pole-sized 50X50X1.6mm thk SHS M.S constructed using
equipment such as spirit level, water level, and tape measure. Two
workers used to establish the main pillars.
6.5
Pillars need to ensure accurate position along the fence line at
3.0m (panel width) intervals and make sure the base are sitting on
an even level surface.
6.6
Erect the remaining pillars along the line as noted previously until
the hoarding line is complete.
6.7
50x25x1.2mm thk nogging need to install three (3) lines to support
metal deck panels.
6.8
Metal deck panels will be installed with the frame hoarding (spacing
4 for every panels).
6.9
This work will be repeated until completion.
6.10
Entrance gate will be erected at remaining area (refer item no.3)
with support at both side (left and right) using welded angles.

7.
QUALITY ISSUES
Boundaries demarcation required to ensure no double handling or trespassing
to others people land.
View inspection required during the process of erection hoarding.
Regular inspection to be carried out by weekly basis to ensure the hoarding in
good condition.
8.

SAFETY ISSUES
Safety helmets and safety footwear should always be worn.
All soft spots or holes shall be identified and barricade if necessary.
The site shall be kept clear of unnecessary obstruction.
First aid kit boxes will be provided at site office.
During raining, no erection hoarding activities are allowed to work.

ASAS BINA ENT. SDN. BHD.


METHOD STATEMENT - ERECTION OF TEMPORARY
HOARDING
Rev. No: 0
Project Doc. No. : MS/TH/01
Page : 4

9.
ENVIRONMENTAL ISSUES
All workers shall ensure that tools and machinery are in a good condition to
avoid any oil leakage that could harm to environment.
Construction waste from construction area must be collected into centralized
garbage bin and disposed at the designated area.