Professional Documents
Culture Documents
M IEmam
Organization for Energy Pianning
Cairo,Egypt
M.Ei-Shibini
M.El-Marsafawy
Electrical Engineering Department,Faculty
of Engineering,Cairo University,Cairo,Egypt
0-7803-1462-x/93$03.00
01993IEEE
1384
d-Check electric supply reliability and determine contracting demand.Considering that utilities capabilities
can ensure the power supply for contracting demand ,it is
required to check system reliabilbty, which should fulfill
the following constrains: duration of any outage should be
less than maximum allowable outage time for critical
loads,and a minimum power supply should be avallable for
critical 1oads.The process conditions determine these two
1imits.In general critical demand ZC is the sum of the
main loads which are supposed to be in operation or ready
to operate any time.In case that critical demand was less
than after-shaving maximum demand,contracting demand ZN
would be chosen equal to that after-shaving maximum demand
as shown in following equation
I I I . PROPOSED METHODOLOGY
If
3.1. Technical Considerations:The calculation of
cogeneration capacity which is equivalent to the difference between peak demand and the shaving level is made
based on the steam paths pressures,rates,constrains and
electric load profile, taking into consideration required
reliability as shown below.
H(i))*EFF(i)/36OO
MW
MW
(1)
where: H(1) is boiler house output steam enthalpy,Q(i),and H(i) are input steam rate and enthalpy,EFF(i) is
efficiency and conversion factor,GT is total generation
capacity,and i is the generation unit number.
b-Determine the required power shaving:starting with
initial value of shaving power which is a fraction of the
available generation,the initial value of after shaving
maximum demand will be given as shown below:
ZR = ZM AF*GT
(2)
where: ZR is after shaving maximum demand,ZM is maximum
load demandland AF is fraction.
The initial value of after shaving maximum demand will
be modified according to other constrains calculationB.The
required power shaving(DZ) will be in general the difference betweenmaxiaum load demand and after shaving maximum
demand as shown by the following equation
DZ
= ZM
GT
(4)
DZ
ZN =
take
ZR
(7)
The occurrence of different outage levels of cogeneration and each demand level time should be checked.If this
time exceeds the allowable outage time ,the difference
between critical demand and cogeneration output power
should be supplied through utility network.The contracting
demand should ensure the supply of critical load during
cogeneration outages.This can be done using the following
formula:
TST(i,j)
= OZi
(8)
where: TST( i,j) is time of coincident cogeneration capacity(j) outage and load demand level (i)in minutes,HRS is
operating hours,qi is outage of (j)cogeneration capacity
per unit time, and OZi is per unit time occurrence of load
demand level(i).
(3)
ZR
ZR
ZC <
H(i))*EFF(i))
(5)
where: Gj is output power of unit (j), and GT cogeneraThe steam rate flow through that path has to be calcu- tion total rated output power.
lated again as shown below :
These calculations should be repeated for simultaneously
Q(i) = Q(i) - DQ
(6) different generation outage levels and load demand levels.
The results of previous test will be a group of recomThat unit capacity should be calculated again according mended contracting demands and the maximum value will be
to the new steam flow through it.
the suitable one.
1385
14
price(Theywere51.8,48,8,42.5,36.5,27.7,23.7respectively
(12)
LC
BCR= B
((R(k)-C(k))/(ltFLT)
K = l
)/c.c.
(16)
EC(2,K)
(17)
1386
CGT =
c'?R(K)-
k= 1
C(K)
DCG -BCG(K))
(23)
where: L is the payback period ,and BCG(K) is the facility book value banking interest for year (k)and is calculated by the following equation
BCG(K)= (CGT-K*DCG)*R
(24)
V. CASE STUDY
The industrial company tor coke and chemicals is one of
the major industrial enterprises in Egypt.The production
of this company includes the following products:industrial
and laboratory chemicals, tar and Electrode pitch,anmonium
sulfate fertilizer,and coke oven gas.
1387
lo5
II __
95
__
/--
-.- .. ..-
..- .
- - ... . .. .. . .. - .
/
20. ___
. -.__I
2000
07
3ooo
5000
4000
6000
h
"
P1q.I
Y.I.U.
7000
8000
55
9000
M IT
OEEYI~IIC~
D...nd
Probability
Flq.2
hv.1
Load Factor V e r s u s
shaved Power
XT
riP.4
The use of cogeneration for peak shnvirtg has the advantages of improving load factor and decreasing contracting
demand,but it has the disadvantage of less operating time
and uneconomic use of the facility.The utility factor(defined by generated energy to available energy ratio)will
be low.To improve the this economy application'it is
required to increase the amount of shaving.Fig.3 shows
generated and purchased electric energy corresponding to
shaving amount.It is clear that using cogeneration for
peak shaving decreases the purchased energy but it doesn't
use all possible generation capability. Fig 4 shows the
load factor and generators utility factor for different
possible generators rating,which are equal to the shaving
amount.It is clear that load factor and generators utility
factors are improved as the shaving amount increase.Although Fig 3 shows that purchased electricity decreases but
this doesn't mean that electricity cost decreases as the
investment in cogeneration project has t o be recovered in
certain period of years.That cost should be considered as
a portion of yearly electricity cost.Fig 5 shows the
purchased electricity cost and total cost including
capital cost of equipment assuming a payback period of
five years at different shaving arnounts.It is clear that
increasing shaving amount improves the economy of the
facility,except that portion near to the peak where occurrence probability is very low for concerned application.It
is clear in Fig.1 that base load is about 4 MW,while peak
demand is semi-sharp and starts from 6.3 MW and reaches 9
MW.This type of loading requires the increase of shaving
to improve the application economy.Fig 6 shows generators
rating and corresponding payback period.This curve shows
that payback period decreases by increasing generators
ratings
Load a n d G e n e r a t o r u t i l i t y
n c t o r m V ~ ~ D Y~ e. n c r a t o r s R ~ L ~ , , ~
shaved power
K/G"
where : K = 340
(25)
and
n= 0.333
1388
110
TlP.5 V a r l o t l o a of Purehas*d L l . e t r l e l t y c o s t
ond 'Sotol E h c t r i c l t y C o s t Ylth A m o u n t of shmvlnq
3 50
3 50
350
350
350
30
50
I
4LD
G1
G2
d1->06
Existing boilers
87->88
new boilers
Fig.7
1389
20-
01992 1994 1996 1998 2000 2002 2004 2006 2006 2010 2
1 ra
, I
0.1
I l q . 1 0 P e a k shivins Cost a n d B a n e Load Cost
\rer.u.
coqcneration P O Y e l ( 1 9 9 1
FIG
Price.)
0.2
0.3
IDZJ, F.4TOR
0.4
0.5
0.6
WADFACTOR&ELE.AIERAGE PRICES
AC.191 PIKES H1M D.CH.4RGE=bO/lfl
.I1
..
98&0.6
__
0.85
LOM FACTDR
019
0.95
1
riq.13
1390
- Contracting demand
Payback period
Actual benefit to cost ratio
Relative benefit to cost ratio
(This ratio take into consideration
banking interest )
- Total levelized benefit
- Total capital cost
= 3.67 MW
= 2.53 MW
= 3.0 years
=
8.63
21.35
inflation rate and
= 41.22 M.L.E.
1.447 M US$
= 4.2
M.L.E.
This suggestion leads to an increase in per unit electricity prices for low load factor up to more than 120LE/KWH for load factor less than 0.1 as shown in Fig.11,while it will be less than 0.1 LE/KWH for load factors
higher than 0.85 as shown in Fig.12.The test of this
suggestion to the studied Company for Coke and Chemicals
indicated that the total cost of electricity decreased by
using cogeneration facility either in supplying base load
or in shaving peak demand.Fig.13 shows that the decrease
of cost is steeper in the first case than in the second
applicationland overall electricity cost is higher in the
second application.The electricity cost for first application starts to incrense sharply at about 4500 KW generating power,while cost for peak shaving continues its
decrease as generation rating increases,and starts to be
less than first application electricity cost in the range
5000 KW and higher,where peak shaving by cogeneration will
be more economic than supplying the base loading
VI. CONCLUSIONS
Fig.8 shows the expected evolution of factory purchased
electricity without and with cogeneration project in
addition to yearly profit.It is clear that these values
are increasing along the life of the project while Fig.9
shows that even that yearly profit and benefit are increasing but levelized benefits are slightly decreasing
near the end of the project life.
(26)
1391