electrical machines
EEM/F
Student workbook
SH5002-3P
2nd edition
Author: Ralf Linnertz
Table of contents
Equipment
Basic experiment without fault simulator
Fault switch 2 actuated
Fault switch 5 actuated
Fault switch 11 actuated
Fault switches 1 and 4 actuated
Fault switches 3 and 6 actuated
Fault switches 4 and 5 actuated
Fault switches 5 and 8 actuated
All fault switches actuated
1
3
9
15
21
27
33
39
45
51
..............................................................................................................................................
..........................................................................................
........................................................................................................................
......................................................................................................................
....................................................................................................................
.......................................................................................................
.......................................................................................................
.......................................................................................................
.......................................................................................................
.................................................................................................................
Equipment
SE2662-9D
LM8501
SE2662-3G, SE2672-3G
SE2663-1k, SE2673-1k
SE2662-5G, SE2672-5G
SE2663-1H, SE2673-1H
EEM/F EQUIPMENT
Device
Fault simulator
Metriso C insulation tester
Three-phase motor with squirrel-cage rotor,
0.3 kW/1 kW
Quantity
1
1
1
EEM/F EQUIPMENT
Circuit
U1
V1
W1
W2
U2
V2
Terminal panel
Screen terminal
Housing (frame)
Stator coil U
Stator coil W
Stator coil V
M
3~
Sample measurements
Winding-to-winding insulation resistance
measurement
U1
V1
W1
W2
U2
V2
Winding-to-housing insulation
resistance measurement
Equipment/components
Note:
The winding resistances (coil U, coil V, coil W) of a three-phase induction motor must be
identical in order to generate a symmetrical rotating field in the stator. However, even if the
winding resistances are identical, it is still possible for insulation faults to occur (winding-towinding or winding-to-frame).
A winding-to-winding insulation fault can result in a short circuit (triggering the circuit breaker)
or overcurrent which is then shut off by the motor protection relay or a general motor
protection mechanism (NTC, PTC).
A winding-to-frame insulation fault can pose a contact hazard since a potential difference
arises between the housing or frame and earth.
In this case, it is important to install a dependable protective mechanism which disconnects
the motor from the mains when hazardous contact voltages (> 50 V) occur.
The measured winding resistances should be approximately equal to the following values:
270 (0.1 kW), 100 (0.3 kW), 20 (1 kW).
The insulation resistances must be at least 1 k/V according to VDE specifications. This
means that no insulation fault should be present as long as the winding-to-winding resistance
is at least 400k and the resistance between windings and the grounded frame or housing
is at least 230k.
Measurement procedure
Select a suitable measuring instrument, measure the winding resistance for each of the coils
U, V, W and enter the values in the table provided.
Winding resistance can be measured with a universal multimeter (or an ohmmeter).
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
Coil U (U1-U2)
Coil V (V1-V2)
Coil W (W1-W2)
Select a suitable measuring instrument, measure the winding-to-winding insulation
resistance values and enter the values in the table provided.
Winding-to-winding insulation resistance can be measured with an
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1 V1
U1 W1
V1 W1
U2 V2
U2 W2
V2- W2
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1
V1
W1
U2
V2
W2-
Experiment objectives
Exercises:
Open the fault simulator and actuate fault switch 2 without simulating any other faults.
Close the fault simulator again.
Circuit
U1
V1
W1
Terminal panel
W2
U2
V2
Screen terminal
Housing (frame)
M
3~
Sample measurements
Winding resistance
10
U1
V1
W1
W2
U2
V2
Winding-to-frame
insulation resistance
measurement
Equipment/components
Note:
The winding resistances (coil U, coil V, coil W) of a three-phase induction motor must be
identical in order to generate a symmetrical rotating field in the stator. However, even if the
winding resistances are identical, it is still possible for insulation faults to occur (winding-towinding or winding-to-frame).
A winding-to-winding insulation fault can result in a short circuit (triggering the circuit breaker)
or overcurrent which is then shut off by the motor protection relay or a general motor
protection mechanism (NTC, PTC).
A winding-to-frame insulation fault can pose a contact hazard since a potential difference
arises between the housing or frame and earth.
In this case, it is important to install a dependable protective mechanism which disconnects
the motor from the mains when hazardous contact voltages (> 50 V) occur.
The measured winding resistances should be approximately equal to the following values:
270 (0.1 kW), 100 (0.3 kW), 20 (1 kW).
The insulation resistances must be at least 1 k/V according to VDE specifications. This
means that no insulation fault should be present as long as the winding-to-winding resistance
is at least 400k and the resistance between windings and the grounded frame or housing
is at least 230k.
11
Measurement procedure
Select a suitable measuring instrument, measure the winding resistance for each of the coils
U, V, W and enter the values in the table provided.
Winding resistance can be measured with a
___________________________________________________..
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
Coil U (U1-U2)
Coil V (V1-V2)
Coil W (W1-W2)
Select a suitable measuring instrument, measure the winding-to-winding insulation
resistance values and enter the values in the table provided.
Winding-to-winding insulation resistance can be measured with an
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1 V1
U1 W1
V1 W1
U2 V2
U2 W2
V2- W2
12
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1
V1
W1
U2
V2
W2-
13
14
Experiment objectives
Exercises:
Open the fault simulator and actuate fault switch 5 without simulating any other faults.
Close the fault simulator again.
15
Circuit
U1
V1
W1
W2
U2
V2
Terminal panel
Screen terminal
Housing (frame)
M
3~
Sample measurements
Winding-to-winding insulation
resistance measurement
16
U1
V1
W1
W2
U2
V2
Winding-to-frame insulation
resistance measurement
Equipment/components
Note:
The winding resistances (coil U, coil V, coil W) of a three-phase induction motor must be
identical in order to generate a symmetrical rotating field in the stator. However, even if the
winding resistances are identical, it is still possible for insulation faults to occur (winding-towinding or winding-to-frame).
A winding-to-winding insulation fault can result in a short circuit (triggering the circuit breaker)
or overcurrent which is then shut off by the motor protection relay or a general motor
protection mechanism (NTC, PTC).
A winding-to-frame insulation fault can pose a contact hazard since a potential difference
arises between the housing or frame and earth.
In this case, it is important to install a dependable protective mechanism which disconnects
the motor from the mains when hazardous contact voltages (> 50 V) occur.
The measured winding resistances should be approximately equal to the following values:
270 (0.1 kW), 100 (0.3 kW), 20 (1 kW).
The insulation resistances must be at least 1 k/V according to VDE specifications. This
means that no insulation fault should be present as long as the winding-to-winding resistance
is at least 400k and the resistance between windings and the grounded frame or housing
is at least 230k.
17
Measurement procedure
Select a suitable measuring instrument, measure the winding resistance for each of the coils
U, V, W and enter the values in the table provided.
Winding resistance can be measured with a
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
Coil U (U1-U2)
Coil V (V1-V2)
Coil W (W1-W2)
Select a suitable measuring instrument, measure the winding-to-winding insulation
resistance values and enter the values in the table provided.
Winding-to-winding insulation resistance can be measured with an
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1 V1
U1 W1
V1 W1
U2 V2
U2 W2
V2- W2
18
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1
V1
W1
U2
V2
W2-
19
20
Experiment objectives
Exercises:
Open the fault simulator and actuate fault switch 11 without simulating any other
faults.
Close the fault simulator again.
21
Circuit
U1
V1
W1
W2
U2
V2
Terminal panel
Screen terminal
Housing (frame)
M
3~
Sample measurements
Winding-to-winding insulation
resistance measurement
22
U1
V1
W1
W2
U2
V2
Winding-to-frame insulation
resistance measurement
Equipment/components
Note:
The winding resistances (coil U, coil V, coil W) of a three-phase induction motor must be
identical in order to generate a symmetrical rotating field in the stator. However, even if the
winding resistances are identical, it is still possible for insulation faults to occur (winding-towinding or winding-to-frame).
A winding-to-winding insulation fault can result in a short circuit (triggering the circuit breaker)
or overcurrent which is then shut off by the motor protection relay or a general motor
protection mechanism (NTC, PTC).
A winding-to-frame insulation fault can pose a contact hazard since a potential difference
arises between the housing or frame and earth.
In this case, it is important to install a dependable protective mechanism which disconnects
the motor from the mains when hazardous contact voltages (> 50 V) occur.
The measured winding resistances should be approximately equal to the following values:
270 (0.1 kW), 100 (0.3 kW), 20 (1 kW).
The insulation resistances must be at least 1 k/V according to VDE specifications. This
means that no insulation fault should be present as long as the winding-to-winding resistance
is at least 400k and the resistance between windings and the grounded frame or housing
is at least 230k.
23
Measurement procedure
Select a suitable measuring instrument, measure the winding resistance for each of the coils
U, V, W and enter the values in the table provided.
Winding resistance can be measured with a
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
Coil U (U1-U2)
Coil V (V1-V2)
Coil W (W1-W2)
Select a suitable measuring instrument, measure the winding-to-winding insulation
resistance values and enter the values in the table provided.
Winding-to-winding insulation resistance can be measured with an
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1 V1
U1 W1
V1 W1
U2 V2
U2 W2
V2- W2
24
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1
V1
W1
U2
V2
W2-
25
26
Experiment objectives
Exercises:
Open the fault simulator and actuate fault switches 1 and 4 without simulating any
other faults.
Close the fault simulator again.
27
Circuit
U1
V1
W1
W2
U2
V2
Terminal panel
Screen terminal
Housing (frame)
M
3~
Sample measurements
Winding-to-winding insulation
resistance measurement
28
U1
V1
W1
W2
U2
V2
Winding-to-frame insulation
resistance measurement
Equipment/components
Note:
The winding resistances (coil U, coil V, coil W) of a three-phase induction motor must be
identical in order to generate a symmetrical rotating field in the stator. However, even if the
winding resistances are identical, it is still possible for insulation faults to occur (winding-towinding or winding-to-frame).
A winding-to-winding insulation fault can result in a short circuit (triggering the circuit breaker)
or overcurrent which is then shut off by the motor protection relay or a general motor
protection mechanism (NTC, PTC).
A winding-to-frame insulation fault can pose a contact hazard since a potential difference
arises between the housing or frame and earth.
In this case, it is important to install a dependable protective mechanism which disconnects
the motor from the mains when hazardous contact voltages (> 50 V) occur.
The measured winding resistances should be approximately equal to the following values:
270 (0.1 kW), 100 (0.3 kW), 20 (1 kW).
The insulation resistances must be at least 1 k/V according to VDE specifications. This
means that no insulation fault should be present as long as the winding-to-winding resistance
is at least 400k and the resistance between windings and the grounded frame or housing
is at least 230k.
29
Measurement procedure
Select a suitable measuring instrument, measure the winding resistance for each of the coils
U, V, W and enter the values in the table provided.
Winding resistance can be measured with a
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
Coil U (U1-U2)
Coil V (V1-V2)
Coil W (W1-W2)
Select a suitable measuring instrument, measure the winding-to-winding insulation
resistance values and enter the values in the table provided.
Winding-to-winding insulation resistance can be measured with an
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1 V1
U1 W1
V1 W1
U2 V2
U2 W2
V2- W2
30
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1
V1
W1
U2
V2
W2-
31
32
Experiment objectives
Exercises:
Open the fault simulator and actuate fault switches 3 and 6 without simulating any
other faults.
Close the fault simulator again.
33
Circuit
U1
V1
W1
W2
U2
V2
Terminal panel
Screen terminal
Housing (frame)
M
3~
Sample measurements
Winding-to-winding insulation
resistance measurement
34
U1
V1
W1
W2
U2
V2
Winding-to-frame insulation
resistance measurement
Equipment/components
Note:
The winding resistances (coil U, coil V, coil W) of a three-phase induction motor must be
identical in order to generate a symmetrical rotating field in the stator. However, even if the
winding resistances are identical, it is still possible for insulation faults to occur (winding-towinding or winding-to-frame).
A winding-to-winding insulation fault can result in a short circuit (triggering the circuit breaker)
or overcurrent which is then shut off by the motor protection relay or a general motor
protection mechanism (NTC, PTC).
A winding-to-frame insulation fault can pose a contact hazard since a potential difference
arises between the housing or frame and earth.
In this case, it is important to install a dependable protective mechanism which disconnects
the motor from the mains when hazardous contact voltages (> 50 V) occur.
The measured winding resistances should be approximately equal to the following values:
270 (0.1 kW), 100 (0.3 kW), 20 (1 kW).
The insulation resistances must be at least 1 k/V according to VDE specifications. This
means that no insulation fault should be present as long as the winding-to-winding resistance
is at least 400k and the resistance between windings and the grounded frame or housing
is at least 230k.
35
Measurement procedure
Select a suitable measuring instrument, measure the winding resistance for each of the coils
U, V, W and enter the values in the table provided.
Winding resistance can be measured with a
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
Coil U (U1-U2)
Coil V (V1-V2)
Coil W (W1-W2)
Select a suitable measuring instrument, measure the winding-to-winding insulation
resistance values and enter the values in the table provided.
Winding-to-winding insulation resistance can be measured with an
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1 V1
U1 W1
V1 W1
U2 V2
U2 W2
V2- W2
36
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1
V1
W1
U2
V2
W2-
37
38
Experiment objectives
Exercises:
Open the fault simulator and actuate fault switches 4 and 5 without simulating any
other faults.
Close the fault simulator again.
39
Circuit
U1
V1
W1
W2
U2
V2
Terminal panel
Screen terminal
Housing (frame)
M
3~
Sample measurements
Winding-to-winding insulation
resistance measurement
40
U1
V1
W1
W2
U2
V2
Winding-to-frame insulation
resistance measurement
Equipment/components
Note:
The winding resistances (coil U, coil V, coil W) of a three-phase induction motor must be
identical in order to generate a symmetrical rotating field in the stator. However, even if the
winding resistances are identical, it is still possible for insulation faults to occur (winding-towinding or winding-to-frame).
A winding-to-winding insulation fault can result in a short circuit (triggering the circuit breaker)
or overcurrent which is then shut off by the motor protection relay or a general motor
protection mechanism (NTC, PTC).
A winding-to-frame insulation fault can pose a contact hazard since a potential difference
arises between the housing or frame and earth.
In this case, it is important to install a dependable protective mechanism which disconnects
the motor from the mains when hazardous contact voltages (> 50 V) occur.
The measured winding resistances should be approximately equal to the following values:
270 (0.1 kW), 100 (0.3 kW), 20 (1 kW).
The insulation resistances must be at least 1 k/V according to VDE specifications. This
means that no insulation fault should be present as long as the winding-to-winding resistance
is at least 400k and the resistance between windings and the grounded frame or housing
is at least 230k.
41
Measurement procedure
Select a suitable measuring instrument, measure the winding resistance for each of the coils
U, V, W and enter the values in the table provided.
Winding resistance can be measured with a
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
Coil U (U1-U2)
Coil V (V1-V2)
Coil W (W1-W2)
Select a suitable measuring instrument, measure the winding-to-winding insulation
resistance values and enter the values in the table provided.
Winding-to-winding insulation resistance can be measured with an
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1 V1
U1 W1
V1 W1
U2 V2
U2 W2
V2- W2
42
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1
V1
W1
U2
V2
W2-
43
44
Experiment objectives
Exercises:
Open the fault simulator and actuate fault switches 5 and 8 without simulating any
other faults.
Close the fault simulator again.
45
Circuit
U1
V1
W1
W2
U2
V2
Terminal panel
Screen terminal
Housing (frame)
M
3~
Sample measurements
Winding-to-winding insulation
resistance measurement
46
U1
V1
W1
W2
U2
V2
Winding-to-frame insulation
resistance measurement
Equipment/components
Note:
The winding resistances (coil U, coil V, coil W) of a three-phase induction motor must be
identical in order to generate a symmetrical rotating field in the stator. However, even if the
winding resistances are identical, it is still possible for insulation faults to occur (winding-towinding or winding-to-frame).
A winding-to-winding insulation fault can result in a short circuit (triggering the circuit breaker)
or overcurrent which is then shut off by the motor protection relay or a general motor
protection mechanism (NTC, PTC).
A winding-to-frame insulation fault can pose a contact hazard since a potential difference
arises between the housing or frame and earth.
In this case, it is important to install a dependable protective mechanism which disconnects
the motor from the mains when hazardous contact voltages (> 50 V) occur.
The measured winding resistances should be approximately equal to the following values:
270 (0.1 kW), 100 (0.3 kW), 20 (1 kW).
The insulation resistances must be at least 1 k/V according to VDE specifications. This
means that no insulation fault should be present as long as the winding-to-winding resistance
is at least 400k and the resistance between windings and the grounded frame or housing
is at least 230k.
47
Measurement procedure
Select a suitable measuring instrument, measure the winding resistance for each of the coils
U, V, W and enter the values in the table provided.
Winding resistance can be measured with a
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
Coil U (U1-U2)
Coil V (V1-V2)
Coil W (W1-W2)
Select a suitable measuring instrument, measure the winding-to-winding insulation
resistance values and enter the values in the table provided.
Winding-to-winding insulation resistance can be measured with an
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1 V1
U1 W1
V1 W1
U2 V2
U2 W2
V2- W2
48
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1
V1
W1
U2
V2
W2-
49
50
51
Circuit
U1
V1
W1
W2
U2
V2
Terminal panel
Screen terminal
Housing (frame)
M
3~
Sample measurements
Winding-to-winding insulation
resistance measurement
52
U1
V1
W1
W2
U2
V2
Winding-to-frame insulation
resistance measurement
Equipment/components
Note:
The winding resistances (coil U, coil V, coil W) of a three-phase induction motor must be
identical to generate a symmetric rotary field in the stator. However, even if the winding
resistances are identical, it is still possible for insulation faults to occur (winding-to-winding or
winding-to-frame).
A winding-to-winding insulation fault can result in a short circuit (triggering the circuit breaker)
or overcurrent which is then shut off by the motor protection relay or a general motor
protection mechanism (NTC, PTC).
A winding-to-frame insulation fault can pose a contact hazard since a potential difference
arises between the housing or frame and earth.
In this case, it is important to install a dependable protective mechanism which disconnects
the motor from the mains when hazardous contact voltages (> 50 V) occur.
The measured winding resistances should be approximately equal to the following values:
270 (0.1 kW), 100 (0.3 kW), 20 (1 kW).
The insulation resistances must be at least 1 k/V according to VDE specifications. This
means that no insulation fault should be present as long as the winding-to-winding resistance
is at least 400k and the resistance between windings and the grounded frame or housing
is at least 230k.
53
Measurement procedure
Select a suitable measuring instrument, measure the winding resistance for each of the coils
U, V, W and enter the values in the table provided.
Winding resistance can be measured with a
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
Coil U (U1-U2)
Coil V (V1-V2)
Coil W (W1-W2)
Select a suitable measuring instrument, measure the winding-to-winding insulation
resistance values and enter the values in the table provided.
Winding-to-winding insulation resistance can be measured with an
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1 V1
U1 W1
V1 W1
U2 V2
U2 W2
V2- W2
54
___________________________________________________.
Resistance
Measurement
0.1 kW
0.3 kW
1 kW
U1
V1
W1
U2
V2
W2-
55
56
Your personal experience and observations can contribute to improvements to this product
and the elimination of any errors. Your comments will be of considerable importance to us in
future revisions of our manuals.
We wish to thank you for your interest and your
cooperation.