You are on page 1of 10

Federal Register / Vol. 71, No.

154 / Thursday, August 10, 2006 / Notices 45821

DEPARTMENT OF ENERGY Support. This rate adjustment will believes that both Federal generators
remove the VAR Support (also known as and non-Federal generators should be
Western Area Power Administration reactive power) costs from the TRR. The treated comparably when they provide
Western Area Power Administration VAR Support.
The Central Valley Project-Rate Order (Western) will collect the revenue To mitigate the current comparability
No. WAPA–128 requirement for CVP VAR Support costs discrepancy between Federal and non-
AGENCY: Western Area Power in the power revenue requirement (PRR) Federal generators, SNR asked for
Administration, DOE. under power rate schedule CV–F12. comments from interested parties on
ACTION: Notice of Order Concerning
The Deputy Secretary of Energy whether SNR should:
approved existing Rate Schedules CV– (1) Take no action and continue with
Reactive Power and Voltage Control
T1, CV–NWT3, PACI–T1, and COTP–T1 the existing rate, (2) roll all VAR
Revenue Requirement Component.
for transmission service and CV–F11 for Support costs from both types of
SUMMARY: The Deputy Secretary of Base Resource and First Preference generators into SNR’s TRR, or (3)
Energy confirmed and approved Rate Power on November 18, 2004 (Rate exclude all VAR Support from both
Order No. WAPA–128 and Rate Order No. WAPA–115, 69 FR 70510, types of generators from SNR’s TRR.
Schedules CV–F12, CV–T2, CV–NWT4, December 6, 2004), and the Commission SNR proposed to exclude all VAR
PACI–T2, and COTP–T2 that revise the confirmed and approved the rate Support costs from SNR’s TRR (71 FR
Transmission Revenue Requirement schedules on October 11, 2005, under 10666, March 2, 2006). After
(TRR) associated with Reactive Power FERC Docket No. EF0–5011–000 (113 considering comments received, SNR
and Voltage Control from the Central FERC ¶ 61,026). The existing rate recommended implementation of the
Valley Project (CVP) and other non- schedules are effective from January 1, third option to the Deputy Secretary of
Federal Generation Sources Service 2005, through September 30, 2009. the Department of Energy (DOE).
(VAR Support) and place new formula The April 1, 2006, update of the As part of a settlement agreement
rates into effect on an interim basis. The approved transmission rates resulted in approved by the Commission on
provisional formula rates will be in annual CVP VAR Support costs of February 29, 2006, in FERC Docket No.
effect until the Federal Energy $358,374. Western’s Sierra Nevada ER05–912–000, Calpine Construction
Regulatory Commission (Commission) Region (SNR) currently estimates its Finance Company, L.P. (114 FERC ¶
confirms, approves, and places them annual costs associated with the CVP 61,217), SNR agreed to pay the Calpine
into effect on a final basis or until and other non-Federal generator VAR Construction Finance Company (CCFC)
replaced by other rates. The provisional Support to be $1,221,240. This increase for reactive power subject to the
rates will provide sufficient revenue to in cost is attributable to the inclusion of outcome of this rate proceeding.
pay all annual costs, including interest non-Federal generator VAR Support Currently, CCFC is the only non-
expense, and repay power investment costs that SNR began paying in Federal, interconnected generator being
and irrigation aid, within the allowable December 2005. VAR Support costs are compensated by SNR for VAR Support
periods. assigned pro rata to the respective under the settlement agreement. SNR
DATES: Rate Schedules CV–F12, CV–T2, transmission systems on a capacity basis intends to mitigate this disparity and
CV–NWT4, PACI–T2, and COTP–T2 and are one of the cost components treat every generator directly connected
will be placed into effect on an interim contained in Component 1 of the CVP, to SNR’s transmission system in a
basis on the first day of the first full PACI, and COTP formula rates. comparable fashion. One reason for this
billing period beginning on or after In implementing Western’s Open decision is that SNR cannot determine
September 1, 2006, and will be in effect Access Transmission Tariff (OATT), the cost that SNR would be required to
until the Commission confirms, Western separated its merchant function pay in the future for all the costs
approves, and places the rate schedules from Western’s reliability function. All associated with all such facilities. The
in effect on a final basis through generators connected to Western’s obligation to provide such payments
September 30, 2009, or until the rate transmission system have an obligation could create an open, indefinite, and
schedules are superseded. to provide reactive power within the undefined future liability for SNR.
bandwidth (commonly referred to as the Under the Anti-Deficiency Act, 31
FOR FURTHER INFORMATION CONTACT: Mr.
deadband) as a part of their obligation U.S.C. 1341, Western cannot commit to
James D. Keselburg, Regional Manager, to maintain interconnected transmission paying an open, indefinite future
Sierra Nevada Customer Service Region, system reliability. By including CVP obligation. On the other hand, if SNR
Western Area Power Administration, reactive power and voltage control costs excludes both the Federal and non-
114 Parkshore Drive, Folsom, CA in SNR’s TRR, SNR in certain Federal generator costs for VAR Support
95630–4710, (916) 353–4418, or Mr. circumstances, may be treating its in the TRR, it would ultimately fall to
Sean Sanderson, Rates Manager, Sierra merchant in a manner not comparable the customers who purchase power
Nevada Customer Service Region, with other transmission customers. from the generator to pay for such costs.
Western Area Power Administration, Under SNR’s current rates, all Customers who receive power from
114 Parkshore Drive, Folsom, CA transmission customers, including a SNR, through Rate Schedule CV–F11,
95630–4710, (916) 353–4466, e-mail: transmission customer with a generator currently pay VAR Support costs in the
sander@wapa.gov. directly connected to SNR’s system, are PRR including the VAR Support
SUPPLEMENTARY INFORMATION: The obligated to pay SNR for the cost of VAR associated with network service. Also
current formula rates for transmission Support. As a result, a transmission included are VAR Support costs
service on the CVP (CV–T1 and CV– customer with a generation associated with the Rate Schedules
NWT3), the Pacific Alternating Current interconnection with SNR that provides PACI–T1 and COTP–T1 if not recovered
Intertie (PACI) (PACI–T1), and the VAR Support according to the Western from contracted sales. By excluding the
rwilkins on PROD1PC61 with NOTICES

California-Oregon Transmission Project Electric Coordinating Council reliability VAR Support component from the TRR,
(COTP) (COTP–T1) transmission requirements would also be paying SNR SNR can accurately determine the costs
systems are based on a TRR that for CVP VAR Support; however, SNR associated with transmission service.
includes CVP and other non-Federal would not be paying such a Furthermore, Western has a statutory
generator costs for providing VAR transmission customer. Western duty to ensure that its rates are the

VerDate Aug<31>2005 21:27 Aug 09, 2006 Jkt 208001 PO 00000 Frm 00057 Fmt 4703 Sfmt 4703 E:\FR\FM\10AUN1.SGM 10AUN1
45822 Federal Register / Vol. 71, No. 154 / Thursday, August 10, 2006 / Notices

lowest cost possible consistent with approved in the rate schedule (CV–F11), Dated: July 26, 2006.
sound business principles under includes operations and maintenance Clay Sell,
Delegation Order No. 00–037.00. While (O&M), purchased power for project use Deputy Secretary.
SNR’s power customers would be and First Preference Customer loads,
obligated to pay SNR for all costs Department of Energy, Deputy
interest expense, annual expenses Secretary
associated with reactive power from the (including any other statutorily required
generators in its power rates, the overall costs or charges), investment repayment In the matter of: Western Area Power
cost to SNR’s power customers would for the CVP, and the Washoe Project Administration; Rate Adjustment for the
be lower and more predictable since annual PRR that remains after project Central Valley Project, the California
they are paying for only the costs Oregon Transmission Project, and the
use loads are met. Revenues from
associated with the Federal generators. Pacific Alternating Current Intertie
project use, transmission, ancillary
Excluding all reactive power costs for
SNR’s TRR is consistent with Western’s services, and other services are applied [Rate Order No. WAPA–128]
statutory duties, therefore, SNR has to the total PRR and the remainder is
Order Confirming, Approving, and
adopted option 3. SNR has compensated collected from Base Resource and First
Placing the Central Valley Project
CCFC beginning in December 2005 for Preference Customers. Power Rates, the Central Valley Project,
reactive power costs within the The provisional rate formula change the California-Oregon Transmission
deadband. This rate action will for CV–F12 for the Base Resource and Project, and the Pacific Alternating
terminate these payments. First Preference PRR results in a .04 Current Intertie Transmission Rates
This rate action is consistent with a percent decrease when compared to the Into Effect on an Interim Basis
recent Commission order denying fiscal year (FY) 2006 PRR.
rehearing in Entergy Services, Inc., This rate was established in
Docket No. EL05–149–001 (114 FERC ¶ By Delegation Order No. 00–037.00, accordance with section 302 of the
61,303). This order articulated the effective December 6, 2001, the Department of Energy (DOE)
Commission’s position that Secretary of Energy delegated: (1) The Organization Act, (42 U.S.C. 7152). This
compensation for reactive power is authority to develop power and Act transferred to and vested in the
based on comparability principles. The transmission rates to Western’s Secretary of Energy the power marketing
Commission emphasized that an Administrator, (2) the authority to functions of the Secretary of the U.S.
interconnecting generator should not be confirm, approve, and place such rates Department of the Interior, Bureau of
compensated for reactive power when into effect on an interim basis to the Reclamation (Reclamation) under the
operating its generating facility within Deputy Secretary of Energy, and (3) the Reclamation Act of 1902 (ch. 1093, 32
the specified deadband (+/¥95 percent) authority to confirm, approve, and place Stat. 388), as amended and
since it is only meeting its reliability into effect on a final basis to remand or supplemented by subsequent laws,
and interconnection obligations. The particularly section 9(c) of the
to disapprove such rates to the
transmission owner would be violating Reclamation Project Act of 1939 (43
Commission. Existing DOE procedures
the comparability standard only if it U.S.C. 485h(c)), and other Acts that
for public participation in power rate
compensated its own generating units specifically apply to the project
adjustments (10 CFR part 903) were involved.
for providing reactive power and did published on September 18, 1985.
not compensate the third-party By Delegation Order No. 00–037.00,
generators. By excluding VAR Support Under Delegation Order Nos. 00– effective December 6, 2001, the
from the TRR, no transmission 037.00 and 00–001.00B, and in Secretary of Energy delegated: (1) The
customers, including third-party compliance with 10 CFR part 903, and authority to develop power and
generators, are required to pay for VAR 18 CFR part 300, I hereby confirm, transmission rates to Western’s
Support. Therefore, SNR does not plan approve, and place Rate Order No. Administrator, (2) the authority to
to compensate third-party generators WAPA–128, the CVP power, and CVP, confirm, approve, and place such rates
interconnected with its transmission PACI, and COTP transmission service into effect on an interim basis to the
system for VAR Support. This outcome formula rates into effect on an interim Deputy Secretary of Energy, and (3) the
is both consistent with Western’s basis. The new Rate Schedules CV–T2, authority to confirm, approve, and place
statutory duties and with the CV–NWT4, PACI–T2, COTP–T2, and into effect on a final basis to remand or
Commission’s comparability standard. CV–F12 will be promptly submitted to to disapprove such rates to the
CCFC and/or other generators that are or the Commission for confirmation and Commission. Existing DOE procedures
may be interconnected with Western’s for public participation in power rate
approval on a final basis.
transmission system will continue to adjustments (10 CFR part 903) were
recover their costs (real and reactive) as published on September 18, 1985.
a bundled product or market-based rate Acronyms and Definitions
as CCFC did prior to its comparability
filing at the Commission. As used in this Rate Order, the
Under the 2004 Power Marketing following acronyms and definitions
Plan, Base Resource and First Preference apply:
power is primarily CVP hydrogeneration 2004 Power Marketing Plan: The 2004
available subject to water conditions CVP Power Marketing Plan (64 FR
and operating constraints. The Base 34417) effective January 1, 2005.
Resource and First Preference power Administrator: The Administrator of the
formula rates recover a PRR through an Western Area Power Administration.
rwilkins on PROD1PC61 with NOTICES

allocation of percentages of costs to First Ancillary Services: Those services


Preference and Base Resource necessary to support the transfer of
Customers. electricity while maintaining reliable
Component 1 of the PRR for Base operation of the transmission
Resource and First Preference Power, as provider’s transmission system in

VerDate Aug<31>2005 21:27 Aug 09, 2006 Jkt 208001 PO 00000 Frm 00058 Fmt 4703 Sfmt 4703 E:\FR\FM\10AUN1.SGM 10AUN1
Federal Register / Vol. 71, No. 154 / Thursday, August 10, 2006 / Notices 45823

accordance with standard utility Stat. 719) and the Flood Control Act Revenue Requirement: The revenue
practice. of 1962 (76 Stat. 1173, 1191–1192). required to recover annual expenses
Base Resource: The Central Valley and FRN: Federal Register notice. (such as O&M, purchase power,
Washoe Project power output and FY: Fiscal Year—October 1 to transmission service expenses,
existing power purchase contracts September 30. interest, deferred expenses) and repay
extending beyond 2004 as determined kV: Kilovolt—The electrical unit of Federal investments and other
by Western to be available for measure of electric potential that assigned costs.
marketing after meeting the equals 1,000 volts. SNR: The Sierra Nevada Customer
requirements of Project Use and First kW: Kilowatt—The electrical unit of Service Region of Western.
Preference Customers and any capacity that equals 1,000 watts. TRR: Transmission Revenue
adjustments for maintenance, kWh: Kilowatthour—The electrical unit Requirement.
reserves, transformation losses, and of energy that equals 1,000 watts in 1 VAR Support: Reactive power and
certain ancillary services. hour. voltage control from the CVP and
Load: The amount of electric power or other non-Federal Generation Sources
CCFC: Calpine Construction Finance
energy delivered or required at any Service.
Company.
specified point(s) on a transmission or Washoe Project: A Reclamation project
COI: The California-Oregon Intertie—
distribution system. located in the Lahontan Basin in west-
Consists of three 500-kilovolt lines Mill: A monetary denomination of the
linking California and Oregon, the central Nevada and east-central
United States that equals one-tenth of California.
California-Oregon Transmission a cent or one-thousandth of a dollar.
Project, and the Pacific Alternating WECC: Western Electricity Coordinating
Mills/kWh: Mills per kilowatthour—The Council.
Current Intertie. The Western unit of charge for energy.
Electricity Coordinating Council Western: United States Department of
MW: Megawatt—The electrical unit of Energy, Western Area Power
establishes the seasonal transfer capacity that equals 1 million watts or
capability for the California-Oregon Administration.
1,000 kilowatts.
Intertie. NEPA: National Environmental Policy Effective Date
COI Rating Seasons: COI rating seasons Act of 1969 (42 U.S.C. 4321, et seq.). The new provisional rates will take
are: summer, June through October; Net Revenue: Revenue remaining after effect on the first day of the first full
winter, November through March; and paying all annual expenses. billing period beginning on or after
spring, April through May. NITS: Network Integrated Transmission September 1, 2006, and will remain in
COTP: The California-Oregon Service. effect until September 30, 2009, pending
Transmission Project—A 500-kilovolt Non-firm: A type of product and/or
approval by the Commission on a final
transmission project in which service not always available at the
basis.
Western has part ownership. time requested by the customer.
CVP: The Central Valley Project is a O&M: Operation and Maintenance. Public Notice and Comment
multipurpose Federal water OATT: Open Access Transmission Western followed the Procedures for
development project extending from Tariff. Public Participation in Power and
the Cascade Range in northern PACI: Pacific Alternating Current
Transmission Rate Adjustments and
California to the plains along the Kern Intertie—A 500-kV transmission
Extensions (10 CFR part 903) in
River south of Bakersfield, California. project of which Western owns a
developing these rates. The steps
Capacity: The electric capability of a portion of the facilities.
Power: Capacity and Energy. Western took to involve interested
generator, transformer, transmission parties in the rate process were:
circuit, or other equipment expressed Preference: The provisions of
Reclamation Law which require 1. A Federal Register notice
in kilowatts. published on March 2, 2006 (71 FR
Commission: The Federal Energy Western to first make Federal power
available to certain non-profit entities. 10666), announced the proposed change
Regulatory Commission. of the reactive power and voltage
Project Use: Power used to operate CVP
Component 1: Part of a formula rate control revenue requirement
facilities under Reclamation Law.
which is used to recover the costs for Provisional Rate: A rate which has been component. This notice began the
a specific service or product. confirmed, approved, and placed into public consultation and comment
Customer: An entity with a contract that effect on an interim basis by the period.
receives service from Western’s Sierra Deputy Secretary. 2. On March 2, 2006, Western e-
Nevada Customer Service Region. PRR: Power Revenue Requirement—The mailed the Federal Register notice (71
Deficits: Unpaid or deferred annual annual revenue that must be collected FR 10666) to the SNR Preference
expenses. to recover annual expenses such as Customers and interested parties
DOE: United States Department of O&M, purchase power, transmission explaining the fact that this was a minor
Energy. service expenses, interest, deferred rate adjustment. Therefore, there was no
DOE Order RA 6120.2: A DOE order expenses, and repay Federal public information or comment forum
outlining power marketing investments and other assigned costs. for this rate process. Western also
administration financial reporting and PRS: Power Repayment Study. reiterated its availability to meet with
ratemaking procedures. Rate Brochure: A document dated interested parties to explain the
FERC: The Commission (to be used February 2006 explaining the rationale for the rate adjustment and to
when referencing Commission rationale and background for the rate discuss the studies that support the
Orders). proposal contained in this Rate Order. proposal for the change to the revenue
First Preference: A Customer or entity Reclamation: United States Department requirement.
rwilkins on PROD1PC61 with NOTICES

qualified to use Preference power of the Interior, Bureau of Reclamation. 3. On March 2, 2006, Western also
within a county of origin (Trinity, Reclamation Law: A series of Federal mailed letters to the SNR Preference
Calaveras, and Tuolumne) as laws. Viewed as a whole, these laws Customers and interested parties
specified under the Trinity River create the originating framework transmitting the Web site address to
Division Act of August 12, 1955 (69 under which Western markets power. obtain a copy of the FRN and providing

VerDate Aug<31>2005 21:27 Aug 09, 2006 Jkt 208001 PO 00000 Frm 00059 Fmt 4703 Sfmt 4703 E:\FR\FM\10AUN1.SGM 10AUN1
45824 Federal Register / Vol. 71, No. 154 / Thursday, August 10, 2006 / Notices

instructions on how to receive a copy of Additional CVP facilities were Customer (other than First Preference
the Rate Brochure. authorized by Congress through a series Customers) signed a contract with
4. Western communicated clarifying of laws. The American River Division Western that specifies how Base
information on the proposed rate was authorized in 1944 and includes the Resource power will be made available
adjustment with the following Folsom Dam and Powerplant and the under the 2004 Power Marketing Plan.
Customers and/or interested parties. Nimbus Dam and Powerplant on the Power generated from the CVP is first
This information is included in the American River. The Trinity Dam and dedicated to project use. The remaining
record. Powerplant, Judge Francis Carr power is allocated to various Preference
Northern California Power Agency, Powerplant, and Whiskeytown Dam and Customers in California. Types of
California, Port of Oakland, Spring Creek Powerplant were Preference Customers include: (1)
California, Redding Electric Utility, authorized as part of the Trinity River Irrigation and water districts, (2) public
California, Sacramento Municipal Division in 1955 and allocated up to 25 utility districts, (3) municipalities, (4)
Utility District, California. percent of the resulting energy to Trinity Federal agencies, (5) state agencies, (6)
5. Western received three comment County for use within Trinity County. rural electric cooperatives, and (7)
letters during the consultation and The San Luis Unit, authorized in 1960, Native American tribes.
comment period, which ended on April includes the B.F. Sisk San Luis Dam, In 1964, Congress authorized
3, 2006. All formally submitted San Luis Reservoir and William R. construction of the 500-kV Pacific
comments have been considered in Gianelli Pump-Generating Plant, O’Neill Northwest-Pacific Southwest
preparing this Rate Order. Pump-Generating Plant, and Dos Alternating Current Intertie. On July 31,
Comments: Written comments were Amigos Pumping Plant. The Rivers and 1967, Reclamation (Western’s power
received from the following Harbors Act of 1962 authorized the New marketing predecessor), PG&E, the
organizations: Calpine Construction Melones Project and allocated up to 25 Southern California Edison Company,
Finance Company, L.P., California. percent of the resulting energy to and the San Diego Gas and Electric
Redding Electric Utility, California. Calaveras and Tuolumne Counties for Company entered into Contract 14–06–
Sacramento Municipal Utility District, use within the counties. 200–2947A (Contract 2947A), an extra
California. Western’s SNR markets the surplus high-voltage transmission service and
hydropower generation of the CVP and exchange agreement for the northern
Project Description Washoe Project. Between 1967 and portion of the PACI. Western, the
Initially authorized by Congress in 2004, under the terms of Contract 14– California Independent System Operator
1935, the CVP is a large water and 06–200–2948A (Contract 2948A) with Corporation, and PG&E initiated a
power system that covers about one- the Pacific Gas and Electric Company Transmission Exchange Agreement
third of the state of California. (PG&E), CVP resources, along with other (Contract No. 04–SNR–00788–A)
Legislation set the purposes of the CVP Western resources, were integrated with effective January 1, 2005, that provides
in priority order as: (1) Improvement of PG&E resources. PG&E served the Western with a 400–MW entitlement of
navigation, (2) river regulation, (3) flood combined PG&E/Western loads with the transmission capacity on the PACI.
control, (4) irrigation, and (5) power. integrated resources. When PG&E The COTP is a jointly owned 342-
The CVP Improvement Act of 1992 informed Western that it planned to mile, 500-kV transmission line that
added fish and wildlife mitigation as a terminate Contract 2948A on December connects the Captain Jack Substation in
priority above power and added fish 31, 2004, Western began working with southern Oregon to Tracy/Tesla
and wildlife enhancement as a priority its Customers to develop and implement Substation in central California.
equal to power. the 2004 Power Marketing Plan. The Operational since March 1993, COTP
The CVP is within the Central Valley 2004 Power Marketing Plan was provides a third high-voltage intertie
and Trinity River Basins of California. It published in the Federal Register (64 between the Pacific Northwest and
includes 18 dams and reservoirs with a FR 34417) on June 25, 1999. It California. COTP owners other than
total storage capacity of 13 million acre- established the criteria for marketing Western are non-Federal participants.
feet. The system includes 615 miles of CVP and Washoe Project power output
canals, 7 pumping facilities, 11 for 20 years beginning on January 1, Power Repayment Study
powerplants with a maximum operating 2005, and ending on December 31, 2024. Western prepares a PRS each FY to
capability of about 2,074 MW, about 852 The Base Resource is a fundamental determine if revenues will be sufficient
circuit-miles of high voltage component and the primary power to repay, within the required time, all
transmission lines, 15 substations, and product marketed through the 2004 costs assigned to the power function.
16 communication sites. Reclamation Power Marketing Plan. Under previous Repayment criteria are based on law,
operates the water control and delivery marketing plans, Preference Customers applicable policies, including DOE
system and all of the powerplants received a fixed capacity and load factor Order RA 6120.2, and authorizing
except the San Luis Unit, which the energy allocation. Under the 2004 legislation.
state of California operates for Power Marketing Plan, Preference
Reclamation. Customers (other than First Preference) Existing and Provisional Formula Rates
The Rivers and Harbors Act of 1937 receive an allocated percentage of the and Revenue Requirement
authorized Reclamation to build the Base Resource. The Base Resource is Under the 2004 Power Marketing
CVP, including Shasta and Keswick defined as the CVP and Washoe Project Plan, the PRR for First Preference and
Dams on the Sacramento River. The power output and any existing power Base Resource power includes O&M,
initial authorization included purchase contracts extending beyond purchased power for project use and
powerplants at Shasta and Keswick 2004, determined by Western to be First Preference Customer loads, interest
Dams along with high-voltage available for marketing after meeting the expense, annual expenses (including
rwilkins on PROD1PC61 with NOTICES

transmission lines to transmit power requirements of project use and First any other statutorily required costs or
from Shasta and Keswick Powerplants Preference Customers, and any charges), investment repayment for the
to the Tracy Pumping Plant and to adjustments for maintenance, reserves, CVP, and the Washoe Project annual
integrate Federal hydropower into other transformation losses, and certain PRR that remains after project use loads
electric systems. ancillary services. In 2000, each CVP are met. Revenues from project use,

VerDate Aug<31>2005 21:27 Aug 09, 2006 Jkt 208001 PO 00000 Frm 00060 Fmt 4703 Sfmt 4703 E:\FR\FM\10AUN1.SGM 10AUN1
Federal Register / Vol. 71, No. 154 / Thursday, August 10, 2006 / Notices 45825

transmission, ancillary services, and rates recover a PRR through percentages Customers’ percentages to be used for
other services are applied to the total for First Preference and Base Resource billing purposes were developed as part
PRR, and the remainder is collected Customers. Base Resource Customer of the rate process for the existing rates.
from Base Resource and First Preference percentages were established through A comparison of the power revenue
Customers. the public process for the 2004 Power requirement for existing and provisional
The Base Resource and First Marketing Plan. The First Preference formula rates follows:
Preference power provisional formula

COMPARISON OF POWER REVENUE REQUIREMENTS FOR EXISTING AND PROVISIONAL FORMULA RATES
Existing rates Provisional rates Percent
(as of 4/1/06) (effective 9/1/06) change
($000) ($000)

Rate Schedule ........................................................................................................................... CV–F11 CV–F12 ................


Base Resource and First Preference PRR ............................................................................... $53,003 $52,983 ¥.04%

Certification of Rates Support in Component 1 of the Base comparable treatment to manipulate the
Resource and First Preference PRR. rate structure to deprive non-affiliate
Western’s Administrator certified that (non-Federal) generators of
the provisional CVP power and CVP, Comments
compensation while assuring affiliate
PACI, and COTP transmission service The comments and responses (Federal) generators of compensation.’’
formula rates are the lowest possible regarding change of VAR Support Response: Western understands that
rates consistent with sound business revenue requirement component, the Commission’s policy for
principles. The provisional formula paraphrased for brevity when not compensation is one of comparability.
rates were developed following affecting the meaning of the In Order No. 2003 (68 FR 49,845), the
administrative policies and applicable statement(s), are discussed below. Direct Commission emphasized that an
laws. quotes from comment letters are used interconnecting utility should not be
PRR and CVP, PACI, and COTP for clarification where necessary. compensated for providing reactive
A. Comment: A Customer supported power within the established power
Transmission Service Formula Rates
Western’s recommendation to remove factor range since it is only meeting its
Discussion
all VAR Support costs from Western’s contractual obligation. Generators need
According to Reclamation Law, TRR and recover CVP Western generator only be compensated where they are
Western must establish rates sufficient VAR Support costs from the PRR. The directed to operate outside the
to recover O&M, other annual and customer indicated that this action will deadband (68 FR 49891). In Order No.
interest expenses, and repay power ‘‘allocate costs associated with CVP 2003A (69 FR 15,932), the Commission
investment and irrigation aid. generation to the CVP power rate base,
addressed comparability. It added that if
which is much more appropriate and
Statement of Revenue and Related a transmission provider pays its own or
consistent with cost causation than
Expenses affiliated generator for reactive power
allocating these generator costs to the
within the established range, then it
This rate adjustment constitutes a TRR.’’
Response: Western appreciates the must also pay interconnected customers
minor rate adjustment in accordance (69 FR 15935).
supportive comment.
with 10 CFR part 903 because it B. Comment: A Customer supported Western notes that in the Entergy
produces less than a 1 percent change Western’s proposal to revise Component Services, Inc. case cited above, Entergy
in the annual revenues of the power 1 of its TRR to exclude the costs Services, Inc., established a rate
system. The summary of projected associated with VAR Support. The schedule for reactive power. Entergy
revenue and expense data from the PRS, Customer indicated that ‘‘Western’s included its revenue requirement for
as well as the cost-of-service study that proposal will ensure that VAR support reactive power in the rate schedule. As
supported the existing rates and the rate costs from CVP generation are paid by part of the Commission proceeding,
design and rate methodology were those entities that are benefiting from Entergy sought to zero out the Rate
approved when the existing rates were the associated generation.’’ Schedule and thus Entergy maintained
put into effect on November 18, 2004 Response: Western appreciates the that it met the comparability
(Rate Order No. WAPA–115, 69 FR supportive comment. requirements of Order No. 2003A, and
70510, December 6, 2004). The C. Comment: A Customer referenced the Commission agreed (114 FERC
Commission confirmed and approved an open FERC docket (114 FERC ¶ 61,303) (2006).
the rate schedules on October 11, 2005, ¶ 61,303, issued March 23, 2006) Western’s rate actions are reviewed by
under FERC Docket No. EF05–5011–000 regarding Entergy Services, Inc., and the Commission under the provisions of
(113 FERC 61,026). expressed concern over Western’s 18 CFR part 300 and Delegation Order
Basis for Rate Development intentions to transfer VAR Support costs No. 00–037.00. Western strives to abide
from the TRR to the PRR; thereby, by Commission precedent, consistent
This rate adjustment does not change avoiding additional VAR Support costs with our mission and statutory
the rate design or methodology of the from non-Federal generators. The authorities, and, as such, has voluntarily
existing rates. This rate adjustment Customer indicated that ‘‘while there published an OATT and initiated this
rwilkins on PROD1PC61 with NOTICES

removes the VAR Support revenue may be an argument that comparability rate adjustment in an effort to maintain
requirement from the TRRs associated would permit Western to ‘‘zero out’’ the comparability. Like Entergy, Western is
with Component 1 of the CVP, PACI, VAR Support component of the TRR removing the costs from the TRR to
and COTP transmission service. These and not compensate either Federal or meet the comparability test established
provisional rates include the CVP VAR non-Federal generators, it is not by the Commission. By law, Western

VerDate Aug<31>2005 21:27 Aug 09, 2006 Jkt 208001 PO 00000 Frm 00061 Fmt 4703 Sfmt 4703 E:\FR\FM\10AUN1.SGM 10AUN1
45826 Federal Register / Vol. 71, No. 154 / Thursday, August 10, 2006 / Notices

must recover all of its costs. To meet its Federal generators. Western rectified Submission to the Federal Energy
statutory obligations and remain this situation with this rate process. As Regulatory Commission
consistent with Western’s OATT, discussed above, Western’s final The provisional rates herein
Western must recover its costs from decision is consistent with its statutory confirmed, approved, and placed into
either transmission users or power duties and with the comparability effect, together with supporting
users. Western may not forgo recovery. provisions of the Commission. documents, will be submitted to the
As described above, the removal of the
Availability of Information Commission for confirmation and final
reactive power component is the option
approval.
which is most consistent with Western’s Information about this rate
statutory duties. Based on Western’s rate adjustment, including power repayment Order
design all transmission customers are studies, comments, letters, In view of the foregoing and under the
treated comparably since no memorandums, and other supporting authority delegated to me, I confirm and
transmission customer pays for reactive material made and kept by Western and approve on an interim basis, effective
power within the deadband. In other used to develop the provisional rates, is September 1, 2006, Rate Schedules CV–
words, all transmission customers, available for public review in the Sierra F12, CV–T2, CV–NWT4, PACI–T2 and
including Western and interconnected Nevada Regional Office, Western Area COTP–T2 for the Central Valley and the
utilities, pay the same transmission Power Administration, 114 Parkshore California-Oregon Transmission Projects
rates. Given Western’s position as a Drive, Folsom, California. and the Pacific Alternating Current
Federal agency, Western believes this is
Regulatory Procedure Requirements Intertie of the Western Area Power
consistent with the Commission’s
Administration. The rate schedules
position that compensation within the Regulatory Flexibility Analysis shall remain in effect on an interim
deadband is based solely on the
basis, pending the Commission’s
comparability provision in Order No. The Regulatory Flexibility Act of 1980
confirmation and approval of them or
2003A (114 FERC ¶ 61,303, slip op 5–6) (5 U.S.C. 601, et seq.) requires Federal
substitute rates on a final basis through
(2006). agencies to perform a regulatory
Comment: A Customer expressed September 30, 2009.
flexibility analysis if a final rule is likely
concern that Western is shifting a cost to have a significant economic impact Dated: July 26, 2006.
component that has traditionally been on a substantial number of small entities Clay Sell,
associated with transmission service to and there is a legal requirement to issue Deputy Secretary.
its power rate and believes that this shift a general notice of proposed
‘‘obfuscates the costs associated with Rate Schedule CV–F12 (Supersedes
rulemaking. Western has determined
providing transmission service by Schedule CV–F11)
that this action does not require a
allocating costs traditionally allocated regulatory flexibility analysis since it is Central Valley Project; Schedule of
in transmission rates to other rates.’’ a rulemaking of particular applicability Rates for Base Resource and First
This Customer believes that Western’s involving rates or services applicable to Preference Power
proposal ‘‘did not meet the principle of public property.
comparability and is therefore Effective: September 1, 2006, through
discriminatory and inconsistent with Environmental Compliance September 30, 2009.
Western’s reciprocity obligations under Available: Within the marketing area
In compliance with the National served by the Sierra Nevada Customer
its tariff.’’ Environmental Policy Act (NEPA) of
Response: Prior to FERC Order No. Service Region.
1969, 42 U.S.C. 4321, et seq.; the Applicable: To the Base Resource (BR)
888 (61 FR 21,540), Western
Council on Environmental Quality and First Preference (FP) power
traditionally bundled the costs for
Regulations for implementing NEPA (40 Customers.
power, transmission, and ancillary
CFR parts 1500–1508); and DOE NEPA Character and Conditions of Service:
services. Western did not maintain a
Implementing Procedures and Alternating current, 60 hertz, three-
separate rate component for an ancillary
Guidelines (10 CFR part 1021), Western phase, delivered and metered at the
service such as reactive power. FERC
has determined that this action is voltages and points established by
Order No. 888 unbundled power,
categorically excluded from preparing contract. This service includes the
transmission, and ancillary services.
an environmental assessment or an Central Valley Project (CVP)
After FERC Order No. 888, ancillary
services were seen as a new commodity environmental impact statement. transmission (to include reactive supply
with a different pricing mechanism. Determination Under Executive Order and voltage control from Federal
Within the confines of Western’s 12866 generation sources needed to support
statutory requirements, Western the transmission service), spinning, and
voluntarily promulgated an OATT and Western has an exemption from non-spinning reserve services.
unbundled some of its power, centralized regulatory review under Power Revenue Requirement: Western
transmission, and ancillary services. Executive Order 12866; accordingly, no will develop the Power Revenue
When Western became aware of a clearance of this notice by the Office of Requirement (PRR) prior to the start of
possible non-comparability issue Management and Budget is required. each fiscal year (FY). The PRR will be
regarding compensation for reactive Small Business Regulatory Enforcement divided into two 6-month periods,
power, Western initiated this rate Fairness Act October through March and April
process to remedy that problem. through September. A monthly PRR will
Western was concerned that Western has determined that this rule be calculated by dividing each 6-month
compensating non-Federal generators is exempt from congressional PRR by six. The PRR for the April
rwilkins on PROD1PC61 with NOTICES

under its existing rates and requiring notification requirements under 5 U.S.C. through September period will be
these same generators to pay for VAR 801 because the action is a rulemaking reviewed in March of each year. The
Support in Western transmission service of particular applicability relating to review will analyze financial data from
rates created duplicative charges and rates or services and involves matters of the October through February period, to
unequal treatment for Federal and non- procedure. the extent information is available, as

VerDate Aug<31>2005 21:27 Aug 09, 2006 Jkt 208001 PO 00000 Frm 00062 Fmt 4703 Sfmt 4703 E:\FR\FM\10AUN1.SGM 10AUN1
Federal Register / Vol. 71, No. 154 / Thursday, August 10, 2006 / Notices 45827

well as forecasted data for the March for the April through September period Component 1:
through September period. If there is a will be recalculated.
change of $5 million or more, the PRR First Preference Power Formula Rate:

FP Customer Load
FP Customer Percentage =
Gen + Power Purchases − Pr oject Use

FP Customer Charge = FP Customer FP CUSTOMERS’ MAXIMUM When possible, Western will pass
Percentage × MRR. PERCENTAGES through directly to the appropriate
Where:
Customer, the Commission or other
Maximum FP regulatory body accepted or approved
FP Customer Load = An FP Customer’s customer’s charges or credits in the same manner
forecasted annual load in megawatthours FP customers percentage Western is charged or credited. If the
(MWh). applied to the
MRR Commission or other regulatory body
Gen = The forecasted annual CVP and
accepted or approved charges or credits
Washoe generation (MWh).
Sierra Conservation Center .... 1.39 cannot be passed through directly to the
Power Purchases = Power purchases for
Calaveras Public Power Agen- appropriate Customer, the charges or
project use and FP loads (MWh). cy ......................................... 3.49 credits will be passed through using
Project Use = The forecasted annual project Trinity Public Utility District ..... 9.21
use loads (MWh).
Component 1 of the FP power formula
Tuolumne Public Power Agen- rate.
MRR = Monthly Power Revenue cy ......................................... 3.42
Requirement.
Component 3: Any charges or credits
Total ................................. 17.51% from the Host Control Area (HCA)
Western will develop the FP applied to Western for providing this
Customer percentage prior to the start of service will be passed through directly
Below is a sample calculation for an
each FY. During March of each FY, each to the appropriate Customer in the same
FP Customer monthly charge for power.
FP Customer’s percentage will be manner Western is charged or credited,
reviewed. If, as a result of the review, to the extent possible. If the HCA costs
FP CUSTOMER MONTHLY CHARGE or credits cannot be passed through to
there is a change in the FP Customer’s SAMPLE CALCULATION
percentage of more than one-half of 1 the appropriate Customer in the same
percent, the percentage will be revised manner Western is charged or credited,
Example: First Preference
for the April through September period. Customer Charge Calculation the charges or credits will be passed
through using Component 1 of the FP
The percentages in the table below are FP Customer Load—MWh ... 10,000 power formula rate.
the maximum percentages for each FP Washoe generation—MWh .. 2,500 BR Formula Rate:
Customer that will be applied to the CVP generation—MWh ........ 3,700,000 Component 1:
MRR. The maximum percentages were Project Use Load—MWh ...... 1,200,000
Project Use purchase—MWh 47,000
BR Customer Charges = (BR RR × BR %)
determined based on a critically dry
FP Customer percentage ..... 0.39% Where:
year where there are hydrologic
MRR ...................................... $3,333,333 BR RR = BR Monthly Revenue Requirement
conditions that result in low CVP FP Customer monthly charge $13,000 BR % = BR percentage for each Customer as
generation and, consequently, low indicated in the BR contract after
levels of BR. These maximum adjustments for hourly exchange energy.
Component 2: Any charges or credits
percentages are not used in instances
associated with the creation, BR Customers will pay for exchange
where individual FP Customer termination, or modification to any energy by adjusting the BR percentage
percentages increase due to load growth. tariff, contract, or schedule accepted or that is applied to the BR RR.
If these maximum percentages are used approved by the Federal Energy Adjustments to a Customer’s BR
for determining the FP Customer’s Regulatory Commission (Commission) percentage for seasonal exchanges will
charges for more than 1 year, Western or other regulatory body will be passed be reflected in the Customer’s BR
will evaluate their percentage from the on to each appropriate Customer. The contract.
formula rate versus the maximum Commission or other regulatory body An illustration of the adjustment to a
percentage and make adjustments as accepted or approved charges or credits Customer’s BR percentage for hourly
appropriate. apply to the service to which this rate Exchange Energy (EE) is shown in the
methodology applies. table below.

EXAMPLE OF BASE RESOURCE PERCENTAGE ADJUSTMENTS FOR EXCHANGE ENERGY


BR Hourly Customer’s BR delivered
Customers Revised BR
BR customer percentage BR = 30 BR in excess (adjusting for
receiving EE percentage
from contract MWh of load EE)

Customer A ................................................................ 20 6 3 0 3 10
rwilkins on PROD1PC61 with NOTICES

Customer B ................................................................ 10 3 0 1 4 13.33


Customer C ................................................................ 70 21 0 2 23 76.67

Total 100 ............................................................. 30 3 3 30 100


EN10AU06.013</MATH>

VerDate Aug<31>2005 21:27 Aug 09, 2006 Jkt 208001 PO 00000 Frm 00063 Fmt 4703 Sfmt 4703 E:\FR\FM\10AUN1.SGM 10AUN1
45828 Federal Register / Vol. 71, No. 154 / Thursday, August 10, 2006 / Notices

After the FP Customers’ share of the Rate Schedule CV–T2 (Supersedes regulatory body accepted or approved
annual PRR has been determined, the Schedule CV–T1) charges or credits apply to the service to
remainder of the annual PRR is which this rate methodology applies.
Central Valley Project; Schedule of Rate
recovered from the BR Customers. The When possible, Western will pass
for Transmission Service
BR RR will be collected in two 6-month through directly to the appropriate
periods. For October through March, 25 Effective: September 1, 2006, through Customer, the Commission or other
percent of the BR RR will be collected. September 30, 2009. regulatory body accepted or approved
For April through September, 75 Available: Within the marketing area charges or credits in the same manner
served by the Sierra Nevada Customer Western is charged or credited. If the
percent of the BR RR will be collected.
Service Region. Commission or other regulatory body
A BR RR is calculated by dividing the Applicable: To Customers receiving accepted or approved charges or credits
BR 6-month revenue requirement by six. Central Valley Project (CVP) firm and/or cannot be passed through directly to the
The revenues from the sale of surplus non-firm transmission service. appropriate Customer in the same
BR will be applied to the annual BR RR Character and Conditions of Service: manner Western is charged or credited,
for the following FY. Transmission service for three-phase, the charges or credits will be passed
Component 2: Any charges or credits alternating current at 60 hertz, delivered through using Component 1 of the CVP
associated with the creation, and metered at the voltages and points transmission service formula rate.
termination, or modification to any of delivery or receipt, adjusted for Component 3: Any charges or credits
tariff, contract, or schedule accepted or losses, and delivered to points of from the Host Control Area (HCA)
approved by the Commission or other delivery. This service includes applied to Western for providing this
scheduling and system control and service will be passed through directly
regulatory body will be passed on to
dispatch service needed to support the to the appropriate Customer in the same
each appropriate Customer. The
transmission service. manner Western is charged or credited,
Commission or other regulatory body Formula Rate: The formula rate for to the extent possible. If the HCA costs
accepted or approved charges or credits CVP firm and non-firm transmission or credits cannot be passed through to
apply to the service to which this rate service includes three components: the appropriate Customer in the same
methodology applies. Component 1: manner Western is charged or credited,
When possible, Western will pass the charges or credits will be passed
through directly to the appropriate CVP TRR through using Component 1 of the CVP
Customer, the Commission or other TTc + NITSc transmission service formula rate.
regulatory body accepted or approved Billing: The formula rate above
Where:
charges or credits in the same manner applies to the maximum amount of
CVP TRR = Transmission Revenue capacity reserved for periods ranging
Western is charged or credited. If the
Requirement is the costs associated with
Commission or other regulatory body from 1 hour to 1 month, payable
facilities that support the transfer
accepted or approved charges or credits capability of the CVP transmission whether used or not. Billing will occur
cannot be passed through directly to the system, excluding generation facilities monthly.
appropriate Customer, the charges or and radial lines. Adjustment for Losses: Losses
credits will be passed through using TTc = Total Transmission Capacity is the incurred for service under this rate
Component 1 of the BR formula rate. total transmission capacity under long- schedule will be accounted for as agreed
term contract between the Western Area to by the parties in accordance with the
Component 3: Any charges or credits Power Administration (Western) and service agreement.
from the HCA applied to Western for other parties. Adjustment for Audit Adjustments:
providing this service will be passed NITSc = Average 12-month coincident peaks Financial audit adjustments that apply
through directly to the appropriate of network integrated transmission
service (NITS) Customers at the time of
to the revenue requirement under this
Customer in the same manner Western rate schedule will be evaluated on a
the monthly CVP transmission system
is charged or credited, to the extent peak. For rate design purposes, case-by-case basis to determine the
possible. If the HCA costs or credits Western’s use of the transmission system appropriate treatment for repayment
cannot be passed through to the to meet its statutory obligations is treated and cash flow management.
appropriate Customer in the same as NITS.
Rate Schedule CV–NWT4 (Supersedes
manner Western is charged or credited, Western will revise the rate from Schedule CV–NWT3)
the charges or credits will be passed Component 1 based on either of the
through using Component 1 of the BR following two conditions: (a) Updated Central Valley Project; Schedule of Rate
formula rate. financial data available in March of each for Network Integration Transmission
year and (b) a change in the numerator Service
Billing: Billing for BR and FP power
will occur monthly using the respective or denominator that results in a rate Effective: September 1, 2006, through
formula rate. change of at least $0.05 per September 30, 2009.
kilowattmonth. Rate change Available: Within the marketing area
Adjustment for Losses: Losses will be notifications will be posted on the Open served by the Sierra Nevada Customer
accounted for under this rate schedule Access Same-Time Information System. Service Region.
as stated in the service agreement. Component 2: Any charges or credits Applicable: To Customers who
Adjustment for Audit Adjustments: associated with the creation, receive Central Valley Project (CVP)
Financial audit adjustments that apply termination, or modification to any Network Integration Transmission
to the revenue requirement under this tariff, contract, or rate schedule Service (NITS), to points of delivery and
rwilkins on PROD1PC61 with NOTICES

rate schedule will be evaluated on a accepted or approved by the Federal receipt as specified in the service
case-by-case basis to determine the Energy Regulatory Commission agreement.
appropriate treatment for repayment (Commission) or other regulatory body Character and Conditions of Service:
and cash flow management. will be passed on to each appropriate Transmission service for three-phase,
EN10AU06.014</MATH>

Customer. The Commission or other alternating current at 60 hertz, delivered

VerDate Aug<31>2005 21:27 Aug 09, 2006 Jkt 208001 PO 00000 Frm 00064 Fmt 4703 Sfmt 4703 E:\FR\FM\10AUN1.SGM 10AUN1
Federal Register / Vol. 71, No. 154 / Thursday, August 10, 2006 / Notices 45829

and metered at the voltages and points through to the appropriate Customer in Western will update the rate from
of delivery or receipt, adjusted for the same manner Western is charged or Component 1 of the formula rate for
losses, and delivered to points of credited, the charges or credits will be COTP firm transmission service at least
delivery. This service includes passed through using Component 1 of 15 days before the start of each COI
scheduling and system control and the CVP NITS formula rate. rating season. Rate change notifications
dispatch service needed to support the Billing: NITS will be billed monthly will be posted on the Open Access
transmission service. under the formula rate. Same-Time Information System.
Formula Rate: The formula rate for Adjustment for Losses: Losses Component 2: Any charges or credits
CVP NITS includes three components: incurred for service under this rate associated with the creation,
Component 1: schedule will be accounted for as agreed termination, or modification to any
NITS Customer’s monthly demand to by the parties in accordance with the tariff, contract, or rate schedule
charge = NITS Customer’s load ratio service agreement. accepted or approved by the Federal
share times one-twelfth (1/12) of the Adjustment for Audit Adjustments: Energy Regulatory Commission
Annual Network TRR. Financial audit adjustments that apply (Commission) or other regulatory body
Where: to the revenue requirement under this will be passed on to each appropriate
NITS Customer’s load ratio share = The NITS rate schedule will be evaluated on a Customer. The Commission accepted or
Customer’s hourly load (including case-by-case basis to determine the approved charges or credits apply to the
behind the meter generation minus the appropriate treatment for repayment service to which this rate methodology
NITS Customer’s hourly Base Resource) and cash flow management. applies.
coincident with the monthly CVP
transmission system peak minus the Rate Schedule COTP–T2 (Supersedes When possible, Western will pass
coincident peak for all firm CVP Schedule COTP–T1) through directly to the appropriate
(including reserved transmission Customer, the Commission or other
capacity) transmission service, expressed California-Oregon Transmission Project;
regulatory body accepted or approved
as a ratio. Schedule of Rate for Transmission
charges or credits in the same manner
Annual Network TRR = Total CVP Service
Western is charged or credited. If the
transmission revenue requirement, less
Effective: September 1, 2006, through Commission or other regulatory body
revenues from long-term contracts for
CVP transmission between the Western September 30, 2009. accepted or approved charges or credits
Area Power Administration (Western) Available: Within the marketing area cannot be passed through directly to the
and other parties. served by the Sierra Nevada Customer appropriate Customer in the same
Service Region. manner Western is charged or credited,
The Annual Network TRR will be the charges or credits will be passed
revised when the rate from Component Applicable: To Customers receiving
California-Oregon Transmission Project through using Component 1 of the
1 of the CVP transmission rate under COTP transmission service formula rate.
Rate Schedule CV-T1 is revised. (COTP) firm and/or non-firm
Component 2: Any charges or credits transmission service. Component 3: Any charges or credits
associated with the creation, Character and Conditions of Service: from the Host Control Area (HCA)
termination, or modification to any Transmission service for three-phase, applied to Western for providing this
tariff, contract, or rate schedule alternating current at 60 hertz, delivered service will be passed through directly
accepted or approved by the and metered at the voltages and points to the appropriate Customer in the same
Commission or other regulatory body of delivery or receipt, adjusted for manner Western is charged or credited,
will be passed on to each appropriate losses, and delivered to points of to the extent possible. If the HCA
Customer. The Commission accepted or delivery. This service includes charges or credits cannot be passed
approved charges or credits apply to the scheduling and system control and through to the appropriate Customer in
service to which this rate methodology dispatch service needed to support the the same manner Western is charged or
applies. transmission service. credited, the charges or credits will be
When possible, Western will pass Formula Rate: The formula rate for passed through using Component 1 of
through directly to the appropriate COTP firm and non-firm transmission the COTP transmission service formula
Customer, the Commission or other service includes three components: rate.
regulatory body accepted or approved Component 1: Billing: The formula rate above
charges or credits in the same manner applies to the maximum amount of
Western is charged or credited. If the COTP TRR capacity reserved for periods ranging
Commission or other regulatory body from 1 hour to 1 month, payable
accepted or approved charges or credits Western’s COTP Seasonal Capacity
whether used or not. Billing will occur
cannot be passed through directly to the Where: monthly.
appropriate Customer in the same COTP TRR = COTP Seasonal Transmission
manner Western is charged or credited, Adjustment for Losses: Losses
Revenue Requirement (the Western Area
the charges or credits will be passed Power Administration’s (Western) costs incurred for service under this rate
through using Component 1 of the CVP associated with facilities that support the schedule will be accounted for as agreed
NITS formula rate. transfer capability of the COTP). to by the parties in accordance with the
Component 3: Any charges or credits Western’s share of COTP Seasonal Capacity service agreement.
from the Host Control Area (HCA) = Western’s share of COTP capacity Adjustment for Audit Adjustments:
(subject to curtailment) under the then
applied to Western for providing this Financial audit adjustments that apply
rwilkins on PROD1PC61 with NOTICES

current California-Oregon Intertie (COI)


service will be passed through directly transfer capability for the season. to the revenue requirement under this
to the appropriate Customer in the same Seasonal definitions for summer, winter, rate schedule will be evaluated on a
manner Western is charged or credited, and spring are June through October, case-by-case basis to determine the
to the extent possible. If the HCA November through March, and April appropriate treatment for repayment
EN10AU06.015</MATH>

charges or credits cannot be passed through May, respectively. and cash flow management.

VerDate Aug<31>2005 00:08 Aug 10, 2006 Jkt 208001 PO 00000 Frm 00065 Fmt 4703 Sfmt 4703 E:\FR\FM\10AUN1.SGM 10AUN1
45830 Federal Register / Vol. 71, No. 154 / Thursday, August 10, 2006 / Notices

Rate Schedule PACI–T2 (Supersedes regulatory body accepted or approved on the conference call. Each individual
Schedule PACI–T1) charges or credits in the same manner or organization wishing to address the
Western is charged or credited. If the LGAC meeting on the conference call
Pacific Alternating Current Intertie
Commission or other regulatory body will be allowed a maximum of five
Project; Schedule of Rate for
accepted or approved charges or credits minutes to present their point of view.
Transmission Service
cannot be passed through directly to the Please contact the Designated Federal
Effective: September 1, 2006, through appropriate Customer in the same Officer (DFO) at the number listed
September 30, 2009. manner Western is charged or credited, below to schedule agenda time. Time
Available: Within the marketing area the charges or credits will be passed will be allotted on a first come, first
served by the Sierra Nevada Customer through using Component 1 of the PACI serve basis, and the total period for
Service Region. transmission service formula rate. comments may be extended, if the
Applicable: To Customers receiving Component 3: Any charges or credits number of requests requires it.
the Pacific Alternating Current Intertie from the Host Control Area (HCA) This is an open meeting and all
(PACI) firm and/or non-firm applied to Western for providing this interested persons are invited to
transmission service. service will be passed through directly participate in the conference call. LGAC
Character and Conditions of Service: to the appropriate Customer in the same meeting minutes will be available after
Transmission service for three-phase, manner Western is charged or credited, the meeting and can be obtained by an
alternating current at 60 hertz, delivered to the extent possible. If the HCA costs E-mail or written request to the DFO.
and metered at the voltages and points or credits cannot be passed through to Members of the public are requested to
of delivery or receipt, adjusted for the appropriate Customer, the charges or call the DFO at the number listed below
losses, and delivered to points of credits will be passed through using if planning to participate.
delivery. This service includes Component 1 of the PACI transmission
scheduling and system control and DATES: The Local Government Advisory
service formula rate.
dispatch service needed to support the Billing: The formula rate above Committee will meet on September 14,
transmission service. applies to the maximum amount of 2006, by conference call from 1–3
Formula Rate: The formula rate for capacity reserved for periods ranging eastern daylight time. The conference
PACI firm and non-firm transmission from 1 hour to 1 month, payable call in number is (866) 299–3188 and
service includes three components: whether used or not. Billing will occur the conference code, when prompted, is
Component 1: monthly. ‘‘2025642791.’’
Adjustment for Losses: Losses ADDRESSES: Additional information can
PACI TRR incurred for service under this rate be obtained by writing the DFO at 1200
schedule will be accounted for as agreed Pennsylvania Avenue, NW., (1301A),
Western’s PACI Seasonal Capacity
to by the parties in accordance with the Washington, DC 20460.
Where: service agreement. FOR FURTHER INFORMATION CONTACT:
PACI TRR = PACI Seasonal Transmission Adjustment for Audit Adjustments: Contact Roy Simon, Designated Federal
Revenue Requirement, the Western Area Financial audit adjustments that apply Officer for the Local Government
Power Administration’s (Western) costs to the revenue requirement under this Advisory Committee (LGAC) at (202)
associated with facilities that support the rate schedule will be evaluated on a
transfer capability of the PACI. 564–3868, or by E-mail at
case-by-case basis to determine the Simon.Roy@epa.gov.
Western’s PACI Seasonal Capacity =
Western’s share of PACI capacity (subject
appropriate treatment for repayment Information on Services for the
to curtailment) under the then current and cash flow management. Disability: For information on access or
California-Oregon Intertie (COI) transfer [FR Doc. E6–13031 Filed 8–9–06; 8:45 am] services for individuals with disability,
capability for the season. Seasonal BILLING CODE 6450–01–P or to request accommodation for a
definitions for summer, winter, and disability, please contact Roy Simon at
spring are June through October, (202) 564–3868. Please place requests at
November through March, and April
through May, respectively. ENVIRONMENTAL PROTECTION least 5 days prior to the meeting, to give
AGENCY EPA as much time as possible to process
Western will update the rate from your request.
Component 1 of the formula rate for [FRL–8207–8]
Dated: August 1, 2006.
PACI firm transmission service at least
15 days before the start of each COI Meeting of the Local Government Roy Simon,
rating season. Rate change notifications Advisory Committee Designated Federal Officer, Local Government
will be posted on the Open Access Advisory Committee.
AGENCY: Environmental Protection
Same-Time Information System. [FR Doc. E6–13034 Filed 8–9–06; 8:45 am]
Agency (EPA).
Component 2: Any charges or credits ACTION: Notice.
BILLING CODE 6560–50–P
associated with the creation,
termination, or modification to any SUMMARY: The Local Government
tariff, contract, or rate schedule Advisory Committee (LGAC) will meet ENVIRONMENTAL PROTECTION
accepted or approved by the Federal on Thursday, September 14, 2006, by AGENCY
Energy Regulatory Commission conference call from 1–3 eastern
[FRL–8207–7]
(Commission) or other regulatory body daylight time. The conference call in
will be passed on to each appropriate number is (866) 299–3188 and the Tentative Approval and Solicitation of
Customer. The Commission accepted or conference code, when prompted, is Request for a Public Hearing for Public
approved charges or credits apply to the ‘‘2025642791.’’ The Committee will be
rwilkins on PROD1PC61 with NOTICES

Water Supply Supervision Program


service to which this rate methodology discussing the agenda for the full LGAC Revision for the Commonwealth of
applies. meeting on October 31–November 2, Puerto Rico
When possible, Western will pass 2006.
through directly to the appropriate The Committee will hear comments AGENCY: Environmental Protection
EN10AU06.016</MATH>

Customer, the Commission or other from the public between 2:15–2:30 p.m. Agency (EPA).

VerDate Aug<31>2005 21:27 Aug 09, 2006 Jkt 208001 PO 00000 Frm 00066 Fmt 4703 Sfmt 4703 E:\FR\FM\10AUN1.SGM 10AUN1

You might also like