Professional Documents
Culture Documents
Todays Roadmap
Introduction (1)
Introduction (2)
11
12
13
Instances of presence or absence of implied authority: invitation to tender contains specification, plans, drawings and
BQ
no implied warranty that those documents are accurate
Engineer has no implied authority to warrant their accuracy
14
15
17
18
19
20
21
22
By Clause 6(3) of the Government Civil Engineering Works:The Engineer shall issue to the Contractor from time to time
during the progress of the Works such other Drawings and
Specification as in the opinion of the Engineer shall be
necessary for the purpose of the execution of the Works and
the Contractor shall be bound by the same.
24
25
27
Supervision - three principal areas: prevention, detection and correction of any defective work
intervention in the contractors working methods or temporary works
correction of original design errors
The Engineer is required to exercise due care during construction to
ensure that the materials and workmanship conform to the contractual
requirements
A higher degree of supervision will be required where inferior work by the
contractor has already been seen or reported:I think that the degree of supervision required of an architect must be
governed to some extent by his confidence in the contractor. If and
when something occurs which should indicate to him a lack of
confidence in the contractor, then, in the interest of his employer, the
standard of his supervision should be higher. (Sutcliffe v
Chippendale and Edmondson (a firm) (1971))
Apart from being the employers agent, there will be certain circumstances in
which the Engineer will act as a certifier
Many matters may arise in the course of the execution of a building contract
where a decision has to be made which will affect the amount of money which the
contractor gets. Under the RIBA contract many such decisions have to be made
by the architect and the parties agree to accept his decisions. For example, he
decides whether the contractor should be reimbursed for loss under Clause 11
(variation), Clause 24 (disturbance) or Clause 34 (antiquities); whether he should
be allowed extra time (Clause 23); or when work ought reasonably to have been
completed (Clause 22). And, perhaps most important, he has to decide whether
work is defective. These decisions will be reflected in the amounts contained in
certificates issued by the architect.
The building owner and the contractor make their contract on the understanding
that in all such matters the architect will act in a fair and unbiased manner and it
must therefore be implicit in the employer's contract with the architect that he shall
not only exercise due care and skill but also reach such decisions fairly, holding
the balance between his client and the contractor (Sutcliffe v Thackrah (1974))
As between the employer and the contractor, the employer does not warrant that
the certifier will be skilful or confident
the employer only warrants that the certifier will be honest and independent in
exercising his function as a certifier
28
29
the work was delayed and Pacific may claims for EoT and additional expenses
which were rejected by the Engineer. The claims were ultimately referred to
arbitration and the Employer paid 10 million in settlement of Pacifics claim
then Pacific commenced legal proceedings against the Engineer for 45 million
being the balance unrecovered from the Employer alleging negligence and/or
breach of duty by the Engineer to act fairly and impartially in administrating the
contract
the Engineer sought to strike out the Statement of Claim on the ground that it did
not disclose a reasonable cause of action and was an abuse of the Courts
process
30
31
33
Physical damage
Economic loss
sufficient proximity between the parties and that it is
just and reasonable to impose liability
assumption of responsibility
34
35
36
The Bolam test:- whether the defendant has acted in accordance with
practices that are regarded as acceptable by a respectable body of
opinion in the same profession
Bolam v Friern Hospital Management Committee (1957)
Where you get a situation which involves the use of some special
skill or competence the test is the standard of the ordinary
skilled man exercising and professing to have that special skill. A
man need not possess the highest expert skill it is sufficient if
he exercises the ordinary skill of the ordinary competent man
exercising that particular art.
The law does not require a professional man that he be a paragon,
combining the qualities of polymath and prophet
To be liable, the Engineer must have failed to exercise the standard of
care required of him
37
38
39
Any Questions?