You are on page 1of 26

Consulting Engineers Group Ltd, Deesa.

Name of Work :- Estimate of RCC Box Structure for Crossing of Various Minors of Narmanda Canal System on NH- 15

Name of Work :- Estimate of RCC Box Structure for Crossing of Various Minors of Narmanda Canal System on NH- 15
DETAILS OF QUANTITY & THEIR ABSTRACT (2X1.5)
Item No.

Description

Qty

Excavation for Structures (Earth


work in excavation of foundation of
structures as per drawing and
technical specification,
including
setting out, construction of shoring
and bracing, removal of stumps
and other deleterious matter,
dressing of sides and bottom and
backfilling with approved material.)
In all types of Soil
Box section
Retrun Wall
Man hole

Nos

1
4
2

60.300
3.650
6.400

2.400
1.800
5.900

0.530
1.030
1.530
Total

(2X1.5 Single Cell)

1
4
2
2

60.300
3.650
6.400
3.650

2.400
1.800
5.900
22.500

0.150
0.150
0.150
0.150
Total

Unit

Rate

Amount

219.32

Cum

40

8,773

61.62

Cum

3,985

245,538

76.702
27.068
115.546
219.316

Providing and laying in position


Plain Cement Concrete of Grade M
15 in levelling course below
foundations complete as per
drawings
and
Technical
Specifications
Box section
Retrun Wall
Man hole (PCC)
Approach slab

Total Qty.

21.708
3.942
11.328
24.638
61.616

Consulting Engineers Group Ltd, Deesa.


Item No.

Description

Name of Work :- Estimate of RCC Box Structure for Crossing of Various Minors of Narmanda Canal System on NH- 15
Nos

1
4
2
1
2
2
2
2
2
-1
2
2

60.000
60.000
60.000
60.000
59.000
59.000
5.400
4.500
5.400
3.800
3.800
3.000

Qty

0.380

0.440
4.500
4.500
0.350
1.000
1.000

70.680
2.700
72.000
44.100
10.620
5.310
25.661
16.200
19.440
-4.389
3.040
2.400

Total

267.762

Total Qty.

Unit

Rate

Amount

267.76

Cum

4,420

1,183,507

20.76

Cum

4,432

91,986

Providing and laying in position


Reinforced Cement Concrete in box
cell structures and slab culverts,
Wing walls, Retaining walls for
culverts complete as per drawings
and Technical Specifications

RCC M 25 Grade
Box section
i) Base slab
ii) haunches
iii) wall
iv) Deck slab
v) Bracket
vi) Man hole bottam raft
vii) wall
Deduction of Median Opening
Median opening Man hole

3.100
0.011
0.300
2.100
0.300
0.045
5.400
0.400
0.400
3.300
0.400
0.400

2.000
0.350
0.300

RCC M30 Return wall


4

Return wall raft

3.500

1.500

0.300

6.300

wall

3.500

0.350

2.950

14.455

Total

20.755

(2X1.5 Single Cell)

Consulting Engineers Group Ltd, Deesa.


Item No.

Description

Nos

Qty

Providing weep holes in Brick


masonry/Plain/Reinforced concrete
abutment,wing wall / return wall with
100 mm dia AC pipe,extending
through the full width of the
structure with slope of 1V :20H
towards drawing foce. Complete as
per
drawing
and
Technical
Specifications
Return wall

Name of Work :- Estimate of RCC Box Structure for Crossing of Various Minors of Narmanda Canal System on NH- 15

Total

8.000
8.000

0.300

37.800

Approach slab M 30 (RCC)


4

9.000

3.500

Providing and laying of Filter media


with
granular
materials/stone
crushed aggregates satisfying the
requirements laid down in clause
2504.2.2. of MoRTH specifications
to a thickness of not less than 600
mm with smaller size towards the
soil and bigger size towards the wall
and provided over the entire surface
behind abutment, wing wall and
return wall to the full height
compacted to a firm condition
complete as per drawing and
technical specification.

Behind web
Behind return wall

2
2

60.000
7.600

0.600
0.600

Wearing Coat CC M 30 (PCC)

8.600

9.000

(2X1.5 Single Cell)

2.000
2.500
Total
0.165

144.000
22.800
166.800
25.542

Total Qty.

Unit

Rate

Amount

8.00

Nos.

200

1,600

37.80

Cum

4,432

167,530

166.80

Cum

839

139,945

25.54

Cum

4219

107,762

Consulting Engineers Group Ltd, Deesa.


Item No.

Description

Name of Work :- Estimate of RCC Box Structure for Crossing of Various Minors of Narmanda Canal System on NH- 15
Nos

Qty

Supplying, Fitting and Placing uncoated Fe 500 TMT -HYSD bar


Reinforcement
in
Box
cells,
Retaining
walls,
Wing
walls
complete as per Drawing and
Technical Specifications
Box section

100

kg/Cum

26.776

Return wall

100

kg/Cum

2.076

Approach slab M 30 (RCC)

100

kg/Cum

3.780
Total

Total Qty.

Unit

Rate

Amount

32.63

MT

60,679

1,980,059

32.632

10

Providing & fixing Compressible


fibre board in expansion joint
complete as per drawing &
Technical Specification.

11

Crash Barriear

10.00

0.25

5.000

5.00

Cum 4,460.00

22300

12

Kerb

3.20

6.400

6.40

Rmt

1971.2

13

Road Sign Board

Lumsum

11000

14

Enamel Paint

Lumsum

4000

Lumsum

Total Amount

(2X1.5 Single Cell)

5,000

308.00

3970970.33

Consulting Engineers Group Ltd, Deesa.


Item No.

Description

Name of Work :- Estimate of RCC Box Structure for Crossing of Various Minors of Narmanda Canal System on NH- 15
Nos

Qty

1.00

200.00

11.75

0.50

1175

2.00

200.00

0.85

0.64

217.6

Estimate For Narmada Canal Crossing Diversion

Embankment construction with


material obtained from borrow pits
(contruction of embankment with
approved material obtained from
borrow pits with all lifts and leads,
transporting to site, spreading,
Grading to required slope and
compacting to meet requirement of
table 300-2 )
For Side Shoulders Above Sub
Grade

Total Quantity

Plant Mix Method (Construction of


granular sub-base by providing
close graded material, mixing in a
mechanical mix plant at OMC,
carriage of mixed material to work
site, spreading in uniform layers with
motor grader on prepared surface
and compacting with vibratory power
rolled to achievethe desired density,
complete as per clause 401)

wet mix macadam (Providing,


Laying, Spreading and compacting
grade stone aggregate to wet mix
macadam specification including
premixing the material with water at
Omc in mechenical mix plant
carriage of mixed material by tipper
to site, laying in uniform layers with
paver in sub-base / base course on
well prepared surface and
compacting with vibratory roller to
achieve the desire density)

(2X1.5 Single Cell)

Total Qty.

Unit

Rate

Amount

1392.6

1392.60

Cum

171.00

238134.6

958.00

358292

1.00

200.00

9.35

0.20

374.00

374.00

Cum

1.00

200.00

9.05

0.30

543.00

543.00

Cum 1,428.00

775404

Consulting Engineers Group Ltd, Deesa.


Item No.

Nos

Qty

Total Qty.

Unit

Rate

Amount

Prime coat (Providing and applying


primer coat with bitumen emulsion
on prepared surface of granular
base including clearing of road
surface an spraying primer at the
rate of 0.60 kg/sqm using
mechanical means.)

1.00

200.00

9.05

0.00

1810.00

1810.00

sqm

25.00

45250

Tack coat (Providing and applying


tack coat with bitumen emulsion
using emulsion pressure distributor
at the rate of 0.20 kg per sqm on the
prepared bituminous/granular
surface cleaned with mechanical
broom.)

1.00

200.00

8.75

0.00

1750.00

1750.00

sqm

9.00

15750

1.00

200.00

8.75

0.10

175.00

175.00

Cum 7,264.00

Description

Name of Work :- Estimate of RCC Box Structure for Crossing of Various Minors of Narmanda Canal System on NH- 15

Dense bituminous macadam


(Providing and laying dence
bituminous macadam with 100 -120
TPH batch type HMP/Drummix plant
60 to 90 TPH capacity producing an
average output of 75 tonnes per
hour using crushed aggregates of
specified grading, premixed with
bituminous binder @ 4.0 to 4.5 % by
weight of toatal mix of mix and filler,
transporting the hot mix to work site,
laying with a hydrostatic paver
finisher with sensor control to the
required grade, level and alignment,
rolling with smooth wheeled,
vibratory and tandem rollers to
achieve the desired compaction as
per MoRTH specification clause No.
507 complete in all respects.)

(2X1.5 Single Cell)

1271200

Consulting Engineers Group Ltd, Deesa.


Item No.

Description
Bituminous concrete (Providing and
laying bituminous concrete with 100
-120 TPH batch type HMP/Drum
mix plant 60 to 90 TPH capacity
producing an average output of 75
tonnes per hour using crushed
aggregates of specified grading,
premixed with bituminous binder @
5.4 to 5.6 % of mix and filler,
transporting the hot mix to work site,
laying with a hydrostatic paver
finisher with sensor control to the
required grade, level and alignment,
rolling with smooth wheeled,
vibratory and tandem rollers to
achieve the desired compaction as
per MoRTH specification clause No.
509 complete in all respects.)

(2X1.5 Single Cell)

Name of Work :- Estimate of RCC Box Structure for Crossing of Various Minors of Narmanda Canal System on NH- 15
Nos

Qty

Total Qty.

1.00

200.00

8.75

0.04

70.00

70.00

Unit

Rate

Cum 8,177.00

Amount

572390

Total Amount in Rs. Including diversion cost.

7247390.93

Say -

7247391.00

Name of Work :- Estimate of RCC Chamber and M.S. Pipe laying by Pushing Method
for crossing of Kalayanpura Distributory on NH-15

ABSTRACT
(A) Estimated Cost as per details of Quantity and Abstract (I+II)

#REF!

(B) Add for Contingency & Supervision charges @ 3.125%

#REF!

(C ) Add 1% for Quality Control

#REF!

(D) Add 2% for Planning & Estimation

#REF!

Total (A+B+C+D)

#REF!
Say (Rs.)

#REF!

Name of Work :- Estimate of RCC Chamber and M.S. Pipe laying by Pushing Method
for crossing of Garamadi Minor (i) on NH-15
ABSTRACT
(A) Estimated Cost as per details of Quantity and Abstract (I+II)

9,443,667.71

(B) Add for Contingency & Supervision charges @ 3.125%

295,114.62

(C ) Add 1% for Quality Control

94,436.68

(D) Add 2% for Planning & Estimation

188,873.35

Total (A+B+C+D)

10,022,092.36
Say (Rs.)

10,022,092.36

Name of Work :- Estimate of RCC Chamber and M.S. Pipe laying by Pushing Method
for crossing of Piparala Minor on NH-15
ABSTRACT
(A) Estimated Cost as per details of Quantity and Abstract (I+II)

#REF!

(B) Add for Contingency & Supervision charges @ 3.125%

#REF!

(C ) Add 1% for Quality Control

#REF!

(D) Add 2% for Planning & Estimation

#REF!

Total (A+B+C+D)

#REF!
Say (Rs.)

#REF!

Name of Work :- Estimate of RCC Chamber and M.S. Pipe laying by Pushing Method
for crossing of Sidhada Minor (iii) on NH-15
ABSTRACT
(A) Estimated Cost as per details of Quantity and Abstract (I+II)
(B) Add for Contingency & Supervision charges @ 3.125%
(C ) Add 1% for Quality Control

9,219,271.06
288,102.22
92,192.71

(D) Add 2% for Planning & Estimation


Total (A+B+C+D)

184,385.42
9,783,951.41

Say (Rs.)

9,783,951.41

Name of Work :- Estimate of RCC Chamber and M.S. Pipe laying by Pushing Method
for crossing of Parsund Distributory on NH-15
ABSTRACT
(A) Estimated Cost as per details of Quantity and Abstract (I+II)

#REF!

(B) Add for Contingency & Supervision charges @ 3.125%

#REF!

(C ) Add 1% for Quality Control

#REF!

(D) Add 2% for Planning & Estimation

#REF!

Total (A+B+C+D)

#REF!
Say (Rs.)

#REF!

Name of Work :- Estimate of RCC Chamber and M.S. Pipe laying by Pushing Method
for crossing of Bamroli Minor on NH-15
ABSTRACT
(A) Estimated Cost as per details of Quantity and Abstract (I+II)

#REF!

(B) Add for Contingency & Supervision charges @ 3.125%

#REF!

(C ) Add 1% for Quality Control

#REF!

(D) Add 2% for Planning & Estimation

#REF!

Total (A+B+C+D)

#REF!
Say (Rs.)

#REF!

Name of Work :- Estimate of RCC Chamber and M.S. Pipe laying by Pushing Method
for crossing of Garamadi Distibutory on NH-15
ABSTRACT
(A) Estimated Cost as per details of Quantity and Abstract (I+II)

#REF!

(B) Add for Contingency & Supervision charges @ 3.125%

#REF!

(C ) Add 1% for Quality Control

#REF!

(D) Add 2% for Planning & Estimation

#REF!

Total (A+B+C+D)

#REF!
Say (Rs.)

#REF!

Name of Work :- Estimate of RCC Chamber and M.S. Pipe laying by Pushing Method
for crossing of Par Minor (i) on NH-15
ABSTRACT
(A) Estimated Cost as per details of Quantity and Abstract (I+II)

#REF!

(B) Add for Contingency & Supervision charges @ 3.125%

#REF!

(C ) Add 1% for Quality Control

#REF!

(D) Add 2% for Planning & Estimation

#REF!

Total (A+B+C+D)

#REF!
Say (Rs.)

#REF!

Name of Work :- Estimate of RCC Chamber and M.S. Pipe laying by Pushing Method
for crossing of Par Distributory on NH-15
ABSTRACT
(A) Estimated Cost as per details of Quantity and Abstract (I+II)

#REF!

(B) Add for Contingency & Supervision charges @ 3.125%

#REF!

(C ) Add 1% for Quality Control

#REF!

(D) Add 2% for Planning & Estimation

#REF!

Total (A+B+C+D)

#REF!
Say (Rs.)

#REF!

Name of Work :- Estimate of RCC Chamber and M.S. Pipe laying by Pushing Method
for crossing of Bavarda Minor on NH-15
ABSTRACT
(A) Estimated Cost as per details of Quantity and Abstract (I+II)

#REF!

(B) Add for Contingency & Supervision charges @ 3.125%

#REF!

(C ) Add 1% for Quality Control

#REF!

(D) Add 2% for Planning & Estimation

#REF!

Total (A+B+C+D)

#REF!
Say (Rs.)

#REF!

Name of Work :- Estimate for RCC Chamber and RCC Box laying by pushing method
for crossing of Manpura Sub Branch Canal on NH-14
ABSTRACT
(A) Estimated Cost as per details of Quantity and Abstract (I+II)

13,311,885.48

(B) Add for Contingency & Supervision charges @ 3.125%

415,996.42

(C ) Add 1% for Quality Control

133,118.85

(D) Add 2% for Planning & Estimation

266,237.71

Total (A+B+C+D)

14,127,238.46
Say (Rs.)

14,127,238.46

Name of Work :- Estimate for RCC Chamber and RCC Box laying by pushing method
for crossing of Radhanpur Sub Branch Canal on NH-14
ABSTRACT
(A) Estimated Cost as per details of Quantity and Abstract (I+II)

24,815,478.77

(B) Add for Contingency & Supervision charges @ 3.125%

775,483.71

(C ) Add 1% for Quality Control

248,154.79

(D) Add 2% for Planning & Estimation

496,309.58

Total (A+B+C+D)

26,335,426.84
Say (Rs.)

26,335,426.84

Consulting Engineers Group Ltd, Deesa.


Name of Work :- Quatation of RCC Chamber and M.S. Pipe laying by Pushing Method for crossing of
Garamadi Minor (i) on NH-15
DETAILS OF QUANTITIES & ABSTRACT
Item
No.

Description
Excavation for Structures (Earth work
in excavation of foundation of structures as
per drawing and technical specification,
including setting out,
construction of
shoring and bracing, removal of stumps
and other deleterious matter, dressing of
sides and bottom and backfilling with
approved material.)

Total
Qty.

Unit

Rate

225.76

Cum

71.00

16,029

As per Sor
P.42/12.1

18.22

Cum

1,479.42

26,949

As per SOR
P.68/15.5

9.11

Cum

5,060.42

46,090

As per SOR
P.43/12.8 (A)

104.32

Cum

6,536.42

681,902

Amount

Rate As per
SOR 2012-13

In all types of Soil


Man hole U/S side
Man hole D/S side

Providing and laying Filter material


complete as per drawing and Technical
specification.
Man hole

Providing and laying in position Plain


Cement Concrete of Grade M 15 in leveling
course below foundations complete as per
drawings and Technical Specifications.
Man hole (PCC)
Providing and laying in position Reinforced
Cement Concrete in box cell structures and
slab culverts, Wing walls, Retaining walls
for culverts complete as per drawings and
Technical Specifications.
RCC M 30 Grade U/S SIDE
Box section
i)Man hole bottom raft
ii) wall
long wall
Short Wall
iii) Slab
Deduction of Canal Opening

Deduction for carring pipe


RCC M 30 Grade D/S SIDE
Box section
i)Man hole bottom raft
ii) Wall
long wall
Short Wall
iii) Slab
Deduction of Canal Opening
Deduction for carring pipe
Total Qty. of RCC M-30

As per SOR
P.44/12.11 (vii) (i)

Consulting Engineers Group Ltd, Deesa.


Item
Description
No.

Supplying, Fitting and Placing un-coated Fe


500 TMT -HYSD bar Reinforcement in Box
cells, Retaining walls, Wing walls complete
as
per
Drawing
and
Technical
Specifications.

Total
Qty.

Unit

Rate

10.43

MT

71,828.00

Amount

749,166

Rate As per
SOR 2012-13

As per SOR
P.58/13.6

For Man hole raft and wall @ 100kg / cum

(I) Total Amount of Main hole chamber

1520136.59

Supply and laying MS Pipe including epoxy coating (by pushing method) for Garamdi

Supplying of Casing pipe manufacured


from M.S. Plates confirming to IS: 2062,
Fe410 tested 10% of Pipes at factory upto
25 kg/cm2 for leakage of 1500 mm dia, 20 37287.50
mm thick at site between Radhanpur &
Piparala on NH-15 (Now NH-27) excluding
coating.

Kg.

76.16

Coal Tar Epoxy High Build Epoxy coating of


1500 mm dia pipe,260 micron
thick,internal and external as per technical
specifications.

50.00

Mtr.

7,000.00

Erection, laying and jointing by boring and


pushing method as per technical
specifications and directions of engineer
in-charge at designed angle. (1500 mm
dia, 20mm thick) including Feild weld
testing 100% by U.T.

40.00

Mtr.

Erection, laying and jointing of casing pipe


1500mm dia, 20mm thick as directed by
engineer in-charge in open area.

10.00

2,839,816

As per SOR
P.26/8.7 (A)

350,000

As per
Quotation

30,337.20

1,213,488

As per
Quotation

Mtr.

25,881.00

258,810

As per
Quotation

Supplying of Carrier pipe manufacured


from M.S. Plates confirming to IS: 2062,
Fe410 tested 20% of Pipes at factory
tested upto 25 kg/cm2 for leakage of 1200 29594.50
mm dia 16 mm thick at site between
Radhanpur & Piparala on NH-15 (Now NH27) excluding coating.

Kg.

76.16

Coal Tar Epoxy High Build coating of 1200


mm, dia pipe 260 micron thick internal and
external as per technical specifications.

62.00

Mtr.

6,500.00

403,000

As per
Quotation

Erection, laying and jointing of carrier pipe


including providing spacers, end seals as
per technical specifications and directions
of engineer incharge at designed angle.
(1200 mm dia, 16 mm thick)

62.00

Mtr.

9,750.00

604,500

As per
Quotation

(II) Total Cost for Supplying and laying


Total Cost including pipe pushing and main hole Chamber (I+II)

2,253,917

7923531
9443668

As per SOR
P.26/8.7 (A)

ESTIMATE

Division

Kutch Branch Canal Dn. No. 1/1, Radhanpur.

Unit / Group

4701-Capital Outlay on Major & Medium Irrigation (Plan)

Major Head

Narmada Project

Minor Head

04 Branch canal and distributaries

Detail Head

Estimate is framed in the office of the Executive Engineer, Kutch Branch Canal Dn. No. 1/1,
Radhanpur for the probable expenses that will be incurred for the work of RCC Chamber and
MS Pipe laying by Pushing Method for crossing GAIL Pipe Line by Manpura Sub-Branch canal
@ Ch. 8.730 KM.

Estimated Cost= Rs. 1,27,78,628=00

Estimate prepared by:

Assistant Engineer, KBC Sub Div. No. 1/1 C

Estimate checked by :

Deputy Executive Engineer


K.B.C. Sub Dn. No. 1/1 C
Radhanpur

Consulting Engineers Group Ltd, Deesa.


Name of Work :- Quatation of RCC Chamber and M.S. Pipe laying by Pushing Method for crossing of
Sidhada Minor (iii) on NH-15
DETAILS OF QUANTITIES & ABSTRACT
Item
No.

Description

Total
Qty.

Unit

Rate

256.36

Cum

71.00

18,202

As per Sor
P.42/12.1

18.22

Cum

1,609.20

29,313

As per SOR
P.68/15.5

9.11

Cum

5,190.20

47,272

As per SOR
P.43/12.8 (A)

86.74

Cum

6,666.20

Amount

Rate as per
SOR 2012-13

Excavation for Structures (Earth work in


excavation of foundation of structures as per
drawing and technical specification,
including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with
approved material.)
1
In all types of Soil
Man hole U/S side
Man hole D/S side

Providing and laying Filter material complete


as per drawing and Technical specification.
Man hole

Providing and laying in position Plain Cement


Concrete of Grade M 15 in levelling course below
foundations complete as per drawings and
Technical Specifications
Man hole (PCC)

Providing and laying in position Reinforced


Cement Concrete in box cell structures and slab
culverts, Wing walls, Retaining walls for culverts
complete as per drawings and Technical
Specifications
RCC M 30 Grade U/S SIDE
Box section
i)Man hole bottam raft
ii) wall
long wall
Short Wall
iii) Slab
Deduction of Canal Opening
4

Deduction for carring pipe


RCC M 30 Grade D/S SIDE
Box section
i)Man hole bottam raft
ii) wall
long wall
Short Wall

As per SOR
578,204 P.44/12.11 (vii)
(i)

Consulting Engineers Group Ltd, Deesa.


Item
Description
No.
iii) Slab

Total
Qty.

Unit

Rate

8.67

MT

71,828.00

Amount

Rate as per
SOR 2012-13

Deduction of Canal Opening


Deduction for carring pipe

Total Qty. of RCC M-30

Supplying, Fitting and Placing un-coated Fe 500


TMT -HYSD bar Reinforcement in Box cells,
Retaining walls, Wing walls complete as per
Drawing and Technical Specifications

622,749

As per SOR
P.58/13.6

For Man hole raft and wall @ 100kg / cum


(I) Total Amount of Main hole chamber 1295739.94
Supply and laying MS Pipe including epoxy coating (by pushing method)for Sidhada

Supplying of Casing pipe manufacured from M.S.


Plates confirming to IS: 2062, Fe410 tested 10%
of Pipes at factory upto 25 kg/cm2 for leakage of
1500 mm dia, 20 mm thick at site between
Radhanpur & Piparala on NH-15 (Now NH-27)
excluding coating.

37287.50

Kg.

76.16

Coal Tar Epoxy High Build Epoxy coating of 1500


mm dia pipe,260 micron thick,internal and
external as per technical specifications.

50.00

Mtr.

7,000.00

Erection, laying and jointing by boring and


pushing method as per technical specifications
and directions of engineer in-charge at designed
angle. (1500 mm dia, 20mm thick) including Feild
weld testing 100% by U.T.

40.00

Erection, laying and jointing of casing pipe


1500mm dia, 20mm thick as directed by engineer
in-charge in open area.

10.00

Supplying of Carrier pipe manufacured from M.S.


Plates confirming to IS: 2062, Fe410 tested 20%
of Pipes at factory tested upto 25 kg/cm2 for
leakage of 1200 mm dia 16 mm thick at site
between Radhanpur & Piparala on NH-15 (Now
NH-27) excluding coating.

29594.50

Kg.

76.16

Coal Tar Epoxy High Build coating of 1200 mm,


dia pipe 260 micron thick internal and external as
per technical specifications.

62.00

Mtr.

6,500.00

403,000

As per
Quotation

Erection, laying and jointing of carrier pipe


including providing spacers, end seals as per
technical specifications and directions of engineer
incharge at designed angle. (1200 mm dia, 16
mm thick)

62.00

Mtr.

9,750.00

604,500

As per
Quotation

2,839,816

As per SOR
P.26/8.7 (A)

350,000

As per
Quotation

Mtr. 30,337.20

1,213,488

As per
Quotation

Mtr. 25,881.00

258,810

As per
Quotation

(II) Total Cost for Supplying and laying


Total Cost including pipe pushing and main hole Chamber (I+II)

2,253,917

7923531
9219271

As per SOR
P.26/8.7 (A)

Consulting Engineers Group Ltd, Deesa.

Name of Work :- Estimate of RCC Chamber and M.S. Pipe laying by Pushing Method for crossing of Manpura Sub- Branch on NH-15
DETAILS OF QUANTITIES & ABSTRACT
Item No.

Description

Qty

1
1

5.100
5.100

10.100
10.100

3.018
5.633

5.100

10.100

0.300

5.100

10.100

0.150

Unit

Rate

Amount

Remarks

445.61

Cum

66

29,410

As per Sor
P.44/12.1

30.91

Cum

553

17,091

As per SOR
2011.12
P.70/15.5

15.45

Cum

3,711

57,346

As per SOR
2011.12
P.45/12.8 (A)

30.906

Providing and laying in position


Plain Cement Concrete of Grade M
15 in levelling course below
foundations complete as per
drawings
and
Technical
Specifications
Man hole (PCC)

Total Qty.

155.457
290.156
445.613

Providing and laying Filter


material complete as per drawing
and Technical specification.
Man hole

Excavation for Structures (Earth


work in excavation of foundation of
structures as per drawing and
technical specification,
including
setting out, construction of shoring
and bracing, removal of stumps
and other deleterious matter,
dressing of sides and bottom and
backfilling with approved material.)

In all types of Soil


Man hole U/S side
Man hole D/S side

Nos

15.453
15.453

Consulting Engineers Group Ltd, Deesa.


Item No.

Description

Nos

Qty

4.800

9.800

0.400

18.816

2
2
1

4.800
9.000
4.8

0.400
0.400
9.8

3.225
3.225
0.15

12.384
23.220
7.056

Total Qty.

Unit

Rate

Amount

Remarks

134.84

Cum

5,089

686,219

As per SOR
2011.12
P.46/12.11
(vii) (i)

13.48

MT

60,679

818,217

As per SOR
P.60/13.6

Providing and laying in position


Reinforced Cement Concrete in box
cell structures and slab culverts,
Wing walls, Retaining walls for
culverts complete as per drawings
and Technical Specifications
RCC M 30 Grade U/S SIDE
Box section
i)Man hole bottam raft
ii) wall
long wall
Short Wall
iii) Slab
Deduction of Canal Opening
4

(6.350+0.35)/2X2.0X0.4 (-)

Deduction for carring pipe

(3.14X1.232X1.232X0.4)/4X4 (-)

2.680
1.906
56.890

RCC M 30 Grade D/S SIDE


Box section
i)Man hole bottam raft

4.800

9.800

0.400

18.816

ii) wall
long wall
Short Wall
iii) Slab

2
2
1

4.800
9.000
4.8

0.400
0.400
9.8

5.133
5.133
0.15

19.711
36.958
7.056

Deduction of Canal Opening


Deduction for carring pipe

(6.350+0.35)/2X2.0X0.4 (-)

2.680

(3.14X1.232X1.232X0.4)/4X4 (-)

1.906
77.954

Total Qty. of RCC M-30

134.844

Supplying, Fitting and Placing uncoated Fe 500 TMT -HYSD bar


Reinforcement
in
Box
cells,
Retaining
walls,
Wing
walls
complete as per Drawing and
Technical Specifications
For Man hole raft and wall @
100kg / cum

134.844
134.844

(I) Total Amount of Main hole chamber

1608283.52

Consulting Engineers Group Ltd, Deesa.


Item No.

Description

Nos

Qty

Total Qty.

Unit

Rate

Amount

Remarks

Supply and laying MS Pipe including epoxy coating (by pushing method)

Supplying of Casing pipe


API 5L tested upto25 kg/cm2
for leakage of 1500 mm dia ,20
mm thick at site between
Radhanpur & Piparala on NH-15
(Now NH-27) excluding coating.

50

4.75

0.02

19

149150.00

Kg.

68.77

Epoxy coating of 1500 mm dia


pipe,1000 micron thick,internal
and external as per technical
specifications.

50

200

200.00

Mtr.

7,000.00

1,400,000 For in casing

Erection, laying and jointing by


boring and pushing method or
by micro tunneling including
providing spacers, end seals as
per technical specifications and
directions of engineer
incharge at designed angle.
(1500 mm dia, 20mm thick)

40

160

160.00

Mtr.

24,157.40

3,865,184

As Per
Quotation

Erection, laying and jointing of


casing pipe 1500mm dia, 20mm
thick as directed by engineer
in-charge in open area.

10

40

40.00

Mtr.

23,034.00

921,360

As Per
Quotation

Supplying of Carrier pipe


API 5L tested upto 25 kg/cm2
for leakage of 1200 mm dia 16
mm thick at site between
Radhanpur & Piparala on NH-15
(Now NH-27) excluding coating.

62

3.796

0.016

15.06

29594.50

Kg.

68.77

2,035,214

As per SOR
2011.12
P.28/8.7 (A)

Epoxy coating of 1200 mm, dia


pipe 1000 micron thick internal
and external as per technical
specifications.

62

248

248.00

Mtr.

6,000.00

1,488,000

for caring
pipe

10,257,046

As per SOR
2011.12
P.28/8.7 (A)

Consulting Engineers Group Ltd, Deesa.


Item No.

Description
Erection, laying and jointing of
carrier pipe including providing
spacers, as per technical
specifications and directions of
engineer incharge at designed
angle. (1200 mm dia, 16 mm
thick)

Nos

Qty

Total Qty.

Unit

Rate

62

248

248.00

Mtr.

9,551.00

Amount

2,368,648

(II) Total Cost for Supplying and laying

22335451

Total Cost including pipe pushing and main hole Chamber (I+II)

23943735

Remarks

As Per
Quotation

Consulting Engineers Group Ltd, Deesa.

Name of Work :- Estimate of RCC Chamber and M.S. Pipe laying by Pushing Method for crossing of Khirai Minor (D-28) on NH-8A
DETAILS OF QUANTITIES & ABSTRACT
Item No.

Description

Qty.

1
1

4.600
4.600

6.600
6.600

3.290
4.963

4.600

6.600

0.300

4.600

6.600

0.150

Unit

Rate

Amount

Remarks

250.56

Cum

66

16,537

As per Sor
P.44/12.1

18.22

Cum

553

10,073

As per SOR
2011.12
P.70/15.5

9.11

Cum

3,711

33,800

As per SOR
2011.12
P.45/12.8 (A)

18.216

Providing and laying in position


Plain Cement Concrete of Grade M
15 in levelling course below
foundations complete as per
drawings
and
Technical
Specifications
Man hole (PCC)

Total Qty.

99.884
150.677
250.561

Providing and laying Filter


material complete as per drawing
and Technical specification.
Man hole

Excavation for Structures (Earth


work in excavation of foundation of
structures as per drawing and
technical specification,
including
setting out, construction of shoring
and bracing, removal of stumps
and other deleterious matter,
dressing of sides and bottom and
backfilling with approved material.)

In all types of Soil


Man hole U/S side
Man hole D/S side

Nos

9.108
9.108

Consulting Engineers Group Ltd, Deesa.


Item No.

Description

Nos

Qty.

4.300

6.300

0.400

10.836

2
2
1

4.300
5.500
4.3

0.400
0.400
6.3

3.447
3.447
0.15

11.858
15.167
4.064

Total Qty.

Unit

Rate

Amount

Remarks

82.42

Cum

5,089

419,459

As per SOR
2011.12
P.46/12.11
(vii) (i)

8.24

MT

60,679

500,145

As per SOR
P.60/13.6

Providing and laying in position


Reinforced Cement Concrete in box
cell structures and slab culverts,
Wing walls, Retaining walls for
culverts complete as per drawings
and Technical Specifications
RCC M 30 Grade U/S SIDE
Box section
i) Man hole bottam raft
ii) wall
long wall
Short Wall
iii) Slab
Deduction of Canal Opening
4

(1.910+0.35)/2X0.520X0.4 (-)

Deduction for carring pipe

(3.14X1.232X1.232X0.4)/4 (-)

0.235
0.477
41.212

RCC M 30 Grade D/S SIDE


Box section
i)Man hole bottam raft

4.300

6.300

0.400

10.836

ii) wall
long wall
Short Wall
iii) Slab

2
2
1

4.300
5.500
4.3

0.400
0.400
6.3

3.447
3.447
0.15

11.858
15.167
4.064

Deduction of Canal Opening

(1.910+0.35)/2X0.520X0.4 (-)

0.235

Deduction for carring pipe

(3.14X1.232X1.232X0.4)/4 (-)

0.477
41.212

Total Qty. of RCC M-30

82.425

Supplying, Fitting and Placing uncoated Fe 500 TMT -HYSD bar


Reinforcement
in
Box
cells,
Retaining
walls,
Wing
walls
complete as per Drawing and
Technical Specifications
For Man hole raft and wall @
100kg / cum

82.425
82.425
(I) Total Amount of Main hole chamber

980014.25

Consulting Engineers Group Ltd, Deesa.


Item No.

Description

Nos

Qty.

Total Qty.

Unit

Rate

Amount

Remarks

Supply and laying MS Pipe including epoxy coating (by pushing method)

Supplying of Casing pipe


API 5L tested upto25 kg/cm2
for leakage of 1500 mm dia ,20
mm thick at site between
Radhanpur & Piparala on NH-15
(Now NH-27) including. 1000
micron thick (including &
external) epoxy coating.

50

4.75

0.02

4.75

37287.50

Kg.

68.77

Epoxy coating of 1500 mm dia


pipe,1000 micron thick,internal
and external as per technical
specifications.

50

50

50.00

Mtr.

7,000.00

350,000 For in casing

Erection, laying and jointing by


boring and pushing method or
by micro tunneling including
providing spacers, end seals as
per technical specifications and
directions of engineer
incharge at designed angle.
(1500 mm dia, 20mm thick)

40

40

40.00

Mtr.

24,157.40

966,296

As per
Quotation

Erection, laying and jointing of


casing pipe 1500mm dia, 20mm
thick as directed by engineer
in-charge in open area.

10

10

10.00

Mtr.

23,034.00

230,340

As per
Quotation

Supplying of Carrier pipe


API 5L tested upto 25 kg/cm2
for leakage of 1200 mm dia 16
mm thick at site between
Radhanpur & Piparala on NH-15
(Now NH-27) excluding coating.

62

3.796

0.016

3.77

29594.50

Kg.

68.77

Epoxy coating of 1200 mm, dia


pipe 1000 micron thick internal
and external as per technical
specifications.

62

62

62.00

Mtr.

6,000.00

2,564,261

2,035,214

372,000

As per SOR
2011.12
P.28/8.7 (A)

As per SOR
2011.12
P.28/8.7 (A)

for caring
pipe

Consulting Engineers Group Ltd, Deesa.


Item No.

Description
Erection, laying and jointing of
carrier pipe including providing
spacers, as per technical
specifications and directions of
engineer incharge at designed
angle. (1200 mm dia, 16 mm
thick)

Nos

Qty.

Total Qty.

Unit

Rate

62

62

62.00

Mtr.

9,551.00

Amount

592,162

(II) Total Amount

7110273.14

Total Amount I+II

8090287.39

Remarks

As per
Quotation

You might also like