Minimum Separation Distance Between High

Voltage Transmission Lines


Presented to:
Environment, Energy Security & Sustainability Symposium

June 17, 2010


Denver, Colorado

icfi.com

Introduction
Public company on NASDAQ with symbol ICFI
Founded in 1969; more than 3,500 employees
End-to-end management, technology, and policy
services advise, implement, improve

Diverse client base 78% U.S. federal, state, and local


agencies; 17% U.S. commercial; and 5% international
Global presence with more than 50 offices, headquartered
in the Washington, D.C. area

icfi.com

Presentation Content
Background for Study
Connecting Supply and Demand
Relevance to Conference

Study Goals and Limitations


Transmission Export Lines and Hubs
Conclusions

icfi.com

Background for Study

Wyoming has abundant supply of wind

Other States have demand (RPS) for renewable energy

Wyomings transmission system is limited

Multiple transmission export lines are proposed

No prescribed minimum separation distance between


transmission lines leads to questions about reliability,
energy security, and environmental impacts

.
4

icfi.com

Abundant Wind Resources = Supply

5 5

icfi.com

Wyoming: 1st in Wind Speed (Class 6 &7)

icfi.com

Renewable Portfolio Standards Drive Demand

icfi.com

Load Centers and Projected Peak Growth with Existing


Transmission Capacity

Source: Renewable Energy Atlas of the West.

icfi.com

Transmission Projects Proposed in Wyoming to


Transfer Abundant Supply to Distant Load Centers

4
icfi.com

Proposed Transmission Export Lines Capacity


Transmission Project

Capacity
(Megawatts)

Gateway South (PacifiCorp)

1,500

Gateway West (PacifiCorp)

1,500

Overland Intertie (LS Power Development, LLC)

2,000

Wyoming-Colorado Intertie (LS Power Development, LLC)

900

Trans West Express (Anschutz Corporation)

3,000

Zephyr (TransCanada)

3,000
Total

11,900

NOTE: Capacities are based on thermal ratings and do not represent simultaneous system rating. Capacity for each project
provided by transmission proponents. Capacities are representative values which may change based on final path rating.

10

icfi.com

Separation Distance How Much is


Enough?

11

8
icfi.com

Separation Distance and Reliability Example


Dependent Factors (19-24%)
Lightning
High Winds
Tornadoes
Storms (ice/hail/snow)
Fire
Independent Factors (75-81%)
Human error
Equipment failure
Sabotage
Vegetation
Other Misc.
Unknown

Photo credit: Darrell Gerrard, PacifiCorp

WECC 2006-2007 outages for 500600-kV


12

9
icfi.com

Separation Distance: Reliability Vs.


Costs/Impacts

Line de-rating risk

Installation/Maintenance Cost

Future need for new


transmission

Environmental Permitting Time

Ease of adherence to
environmental and
land-use constraints

Visual Impact Concern

Public Opposition

Need for Remedial


Action Scheme

Line Separation Distance


13

7
icfi.com

Example Minimum Separation Distances1 (feet)


for Typical 500-kV Transmission Lines

Invalid without application of associated assumptions and mitigation


14

10
icfi.com

Thank You
Study funded by: Wyoming Infrastructure
Authority, Steve Ellenbecker Executive Director
(www.wyia.org)
Report available online: www.icfi.com/collector
Authors: Robert J. Henke, Judah Rose, Ken Collison, Venkat Banunarayanan,
Kiran Kumaraswamy, Casey Jacobson, Nishit Pande

Point of Contact: Robert J. Henke


ICF International
303-792-7810
rhenke@icfi.com
15