6470 Federal Register / Vol. 71, No.

26 / Wednesday, February 8, 2006 / Notices

individual or entity interested in Directions: Arriving from Interstate 5, review and discuss existing information
submitting study requests, commenting southbound: Take Martin Way Exit 109, and identify preliminary information
on the PAD or SD1, and any agency turn left onto Martin Way. At the third and study needs; (4) review and discuss
requesting cooperating status must do so traffic light turn right onto Desmond the process plan and schedule for pre-
by March 31, 2006. Drive. Head uphill and at the filing activity that incorporates the time
Comments on the PAD and SD1, intersection turn left and proceed along frames provided for in Part 5 of the
study requests, requests for cooperating the front of the Headquarters building. Commission’s regulations and, to the
agency status, and other permissible Proceed past a stop sign at the main extent possible, maximizes coordination
forms of communications with the entrance and find the visitors parking of federal, state, and tribal permitting
Commission may be filed electronically lot on the left. and certification processes; and (5)
via the Internet in lieu of paper. The Arriving from Interstate 5, discuss requests by any Federal or state
Commission strongly encourages northbound: Take Martin Way Exit 109, agency or Indian tribe acting as a
electronic filings. See 18 CFR turn right onto Martin Way. At the cooperating agency for development of
385.2001(a)(1)(iii) and the instructions second traffic light turn right onto an environmental document.
on the Commission’s Web site (http:// Desmond Drive. Head uphill and at the Meeting participants should come
www.ferc.gov) under the ‘‘e-filing’’ link. intersection turn left and proceed along prepared to discuss their issues and/or
o. At this time, Commission staff the front of the Headquarters building. concerns. Please review the Pre-
intends to prepare an Environmental Proceed past a stop sign at the main Application Document in preparation
Assessment (EA) for the project, in entrance and find the visitors parking for the scoping meetings. Directions on
accordance with the National lot on the left. how to obtain a copy of the PAD and
Environmental Policy Act (NEPA). Please note that parking is limited and SD1 are included in paragraph m of this
carpools are encouraged. If the visitors document.
Scoping Meetings parking lots are full, retrace your route
We will hold two scoping meetings at to Desmond Drive and take a left at the Scoping Meeting Procedures
the times and places noted below. The stop sign onto Desmond Drive. Continue The scoping meetings will be
daytime meeting will focus on resource around and park at the U.S. Fish and recorded by a stenographer and will
agency, Indian tribes, and non- Wildlife Service building (510 Desmond become part of the formal Commission
governmental organization concerns, Drive) and walk across the field to the record on the project.
while the evening meeting is primarily Washington State Department of
Magalie R. Salas,
for receiving input from the public. We Ecology building.
invite all interested individuals, Please check in at the front desk upon Secretary.
organizations, and agencies to attend arriving at the Washington State [FR Doc. E6–1657 Filed 2–7–06; 8:45 am]
one or both of the meetings, and to Department of Ecology office building. BILLING CODE 6717–01–P
assist staff in identifying particular SD1, which outlines the subject areas
study needs, as well as the scope of to be addressed in the environmental
environmental issues to be addressed in document, has been mailed to the DEPARTMENT OF ENERGY
the environmental document. The times individuals and entities on the
Commission’s mailing list. Copies of Federal Energy Regulatory
and locations of these meetings are as
SD1 will be available at the scoping Commission
follows:
meetings, or may be viewed on the web Notice of Application Accepted for
Evening Scoping Meeting at http://www.ferc.gov, using the Filing and Soliciting Motions To
Date and Time: Monday, February 27, ‘‘eLibrary’’ link. Follow the directions Intervene, Protests, and Comments
2006, 7 p.m. (p.s.t.). for accessing information in paragraph
Location: PUD Electric Building m. Depending on the extent of February 1, 2006.
Headquarters, 2320 California Street, comments received, a Scoping Take notice that the following
Everett, Washington. Document 2 (SD2) may or may not be hydroelectric application has been filed
Directions: Arriving from Interstate 5, issued. with the Commission and is available
southbound: Take Exit 194, follow City for public inspection:
Center signs onto Everett Avenue, Site Visit
a. Type of Application: Preliminary
westbound (right). Turn left at Virginia A site visit is typically held in Permit.
Avenue. Turn right at California Street. conjunction with the scoping meeting. b. Project No.: 12630–000.
Arriving from Interstate 5, However, anticipating that access to c. Date filed: December 8, 2005.
northbound: Take Exit 193, turn left some project facilities would be limited d. Applicant: Arizona Independent
onto Pacific Avenue. Turn right at by winter weather, the co-licensees Power, Inc.
Cedar, and then left onto Hewitt hosted a project site visit on October 17, e. Name of Project: Ford Canyon
Avenue. Turn right at Virginia Avenue. 2005. The site visit was noticed by the Pumped Storage Project.
For additional information: Please Commission on September 20, 2005 and f. Location: The project would be
contact Ms. Dawn Presler, Relicensing attended by Commission staff on located in White Tank Mountain
Information Coordinator, Snohomish October 17, 2005. For these reasons, the Regional Park, in Maricopa County,
County PUD No. 1, (425) 783–1709 or Commission will not host its own site Arizona. The project will utilize water
DJPresler@SNOPUD.com. visit in conjunction with its NEPA from the Colorado River System.
scoping meeting. g. Filed Pursuant to: Federal Power
Daytime Scoping Meeting Act, 16 U.S.C. 791(a)–825(r).
Scoping Meeting Objectives
rmajette on PROD1PC67 with NOTICES1

Date and Time: Tuesday, February 28, h. Applicant Contact: Mr. Frank L.
2006, 10 a.m. (p.s.t.). At the scoping meetings, staff will: (1) Mazzone, Arizona Independent Power,
Location: Washington State Present the proposed list of issues to be Inc., 957 Fairway Drive, Sonoma, CA
Department of Ecology, Headquarters/ addressed in the EA; (2) review and 95476, Phone (707) 996–2573.
Southwest Regional Office, 300 discuss existing conditions and resource i. FERC Contact: Robert Bell, (202)
Desmond Drive, Lacey, Washington. agency management objectives; (3) 502–6062.

VerDate Aug<31>2005 15:26 Feb 07, 2006 Jkt 208001 PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 E:\FR\FM\08FEN1.SGM 08FEN1
Federal Register / Vol. 71, No. 26 / Wednesday, February 8, 2006 / Notices 6471

j. Deadline for filing comments, application for preliminary permit for a to intervene in accordance with the
protests, and motions to intervene: 60 proposed project must submit the Commission’s Rules may become a
days from the issuance date of this competing application itself, or a notice party to the proceeding. Any comments,
notice. of intent to file such an application, to protests, or motions to intervene must
The Commission’s Rules of Practice the Commission on or before the be received on or before the specified
and Procedure require all intervenors specified comment date for the comment date for the particular
filing documents with the Commission particular application (see 18 CFR 4.36). application.
to serve a copy of that document on Submission of a timely notice of intent Comments, protests and interventions
each person in the official service list allows an interested person to file the may be filed electronically via the
for the project. Further, if an intervener competing preliminary permit Internet in lieu of paper. See 18 CFR
files comments or documents with the application no later than 30 days after 385.2001 (a)(1)(iii) and the instructions
Commission relating to the merits of an the specified comment date for the on the Commission’s Web site under ‘‘e-
issue that may affect the responsibilities particular application. A competing filing’’ link. The Commission strongly
of a particular resource agency, they preliminary permit application must encourages electronic filing.
must also serve a copy of the document conform with 18 CFR 4.30(b) and 4.36. s. Filing and Service of Responsive
on that resource agency. o. Competing Development Documents: Any filings must bear in all
k. Description of Project: The Application: Any qualified development capital letters the title ‘‘COMMENTS’’,
proposed project would consist of: (1) A applicant desiring to file a competing ‘‘COMPETING APPLICATION’’,
proposed 1,970-foot-long, 250-foot-high development application must submit to ‘‘RECOMMENDATIONS FOR TERMS
earth and rock filled with impervious the Commission, on or before a AND CONDITIONS’’, ‘‘PROTEST’’, or
core upper reservoir dam, (2) a proposed specified comment date for the ‘‘MOTION TO INTERVENE’’, as
upper reservoir with surface area of 150 particular application, either a applicable, and the Project Number of
acres, with a storage capacity of 12,500 competing development application or a the particular application to which the
acre-feet and a normal water surface notice of intent to file such an filing refers. Any of the above-named
elevation of 3,040 feet mean sea level, application. Submission of a timely documents must be filed by providing
(3) a proposed 2,160-foot-long, 210-foot- notice of intent to file a development the original and the number of copies
high earth and rock filled with application allows an interested person provided by the Commission’s
impervious core lower reservoir dam, to file the competing application no regulations to: The Secretary, Federal
(4) a proposed lower reservoir having a later than 120 days after the specified Energy Regulatory Commission, 888
surface area of 140 acres, with a storage comment date for the particular First Street, NE., Washington, DC 20426.
capacity of 12,500 acre-feet and a application. A competing license A copy of any motion to intervene must
normal water surface elevation of 1,840 application must conform with18 CFR also be served upon each representative
feet mean sea level, (5) two proposed 4.30(b) and 4.36. of the Applicant specified in the
14,070-foot-long, 25-foot-diameter p. Notice of Intent: A notice of intent particular application.
penstocks, (6) a proposed powerhouse must specify the exact name, business t. Agency Comments: Federal, state,
containing five generating units having address, and telephone number of the and local agencies are invited to file
a total installed capacity of 1,250, (7) prospective applicant, and must include comments on the described application.
two proposed 28-foot-diameter tailraces, an unequivocal statement of intent to A copy of the application may be
(8) a proposed 40-mile-long, 500 submit, if such an application may be obtained by agencies directly from the
kilovolt transmission line; and (9) filed, either a preliminary permit Applicant. If an agency does not file
appurtenant facilities. The project application or a development comments within the time specified for
would have an annual generation of application (specify which type of filing comments, it will be presumed to
1,682 gigawatt hours that would be sold application). A notice of intent must be have no comments. One copy of an
to a local utility. served on the applicant(s) named in this agency’s comments must also be sent to
l. Locations of Applications: A copy of public notice. the Applicant’s representatives.
the application is available for q. Proposed Scope of Studies under
inspection and reproduction at the Permit: A preliminary permit, if issued, Magalie R. Salas,
Commission in the Public Reference does not authorize construction. The Secretary.
Room, located at 888 First Street NE., term of the proposed preliminary permit [FR Doc. E6–1668 Filed 2–7–06; 8:45 am]
Room 2A, Washington DC 20426, or by would be 36 months. The work BILLING CODE 6717–01–P
calling (202) 502–8371. This filing may proposed under the preliminary permit
also be viewed on the Commission’s would include economic analysis,
Web site at http://www.ferc.gov using preparation of preliminary engineering DEPARTMENT OF ENERGY
the ‘‘eLibrary’’ link. Enter the docket plans, and a study of environmental
number excluding the last three digits in impacts. Based on the results of these Federal Energy Regulatory
the docket number field to access the studies, the Applicant would decide Commission
document. For assistance, call toll-free whether to proceed with the preparation
of a development application to Notice of Application Accepted for
1–866–208–3676 or e-mail
construct and operate the project. Filing and Soliciting Motions To
FERCOnlineSupport@ferc.gov. For TTY,
r. Comments, Protests, or Motions to Intervene, Protests, and Comments
call (202) 502–8659. A copy is also
available for inspection and Intervene: Anyone may submit February 1, 2006.
reproduction at the address in item h. comments, a protest, or a motion to Take notice that the following
above. intervene in accordance with the hydroelectric application has been filed
rmajette on PROD1PC67 with NOTICES1

m. Individuals desiring to be included requirements of Rules of Practice and with the Commission and is available
on the Commission’s mailing list should Procedure, 18 CFR 385.210, 385.211, for public inspection:
so indicate by writing to the Secretary 385.214. In determining the appropriate a. Type of Application: Preliminary
of the Commission. action to take, the Commission will Permit.
n. Competing Preliminary Permit: consider all protests or other comments b. Project No.: 12631–000.
Anyone desiring to file a competing filed, but only those who file a motion c. Date filed: December 20, 2005.